Citation : 2021 Latest Caselaw 9699 Ker
Judgement Date : 23 March, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE SATHISH NINAN
TUESDAY, THE 23RD DAY OF MARCH 2021 / 2ND CHAITHRA, 1943
WP(C).No.3535 OF 2021(N)
PETITIONER:
SATHYAJITH,AGED 47 YEARS
S/O.PACHUNNI, PUTHIYAMPARAMBIL HOUSE,
KOTTAKKAL, MALAPPURAM DISTRICT-676503.
BY ADVS.
SRI.ABDUL JAWAD K.
SMT.A.GRANCY JOSE
RESPONDENTS:
1 THE MALAPPURAM MUNICIPALITY
REPRESENTED BY ITS SECRETARY, MALAPPURAM-676505.
2 THE SECRETARY,
MALAPPURAM MUNICIPALITY, MALAPPURAM-676505.
R1 & R2 BY ADV. SRI.E.S.M.KABEER
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
23.03.2021, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
WP(C).No.3535 OF 2021(N)
2
JUDGMENT
Dated this the 23rd day of March 2021
The application submitted by the petitioner for
building permit, for construction of a building in his
property having an extent of 6.50 cents was rejected by
the municipality relying upon the master plan, in which, a
portion of the land of the petitioner is required for the
municipality for the purpose of 'widening road and drain'.
The petitioner is aggrieved by the order.
2. Heard the learned counsel for the petitioner and
also learned standing counsel for the municipality.
3. As evidenced by Ext P2 and P2(a), the petitioner
has issued a purchase notice in terms of Section 67(1) of
the Kerala Town and Country Planning Act, 2016 calling
upon the Municipality that necessary steps be taken for
purchase/acquisition of the required extent of property
for the purpose of widening the road and drain in terms of
the master plan. Ext P2 purchase notice was issued on WP(C).No.3535 OF 2021(N)
09.12.2020.
4. It is now trite that when an area becomes
compulsorily acquirable under the Development Plan, the
owner of the land gets a corresponding right to issue a
purchase notice under Section 67 of the Kerala Town and
Country Planning Act and that if the same is rejected or
not considered by the Municipality within 60 days, then
the party gets a right to make use of the property, and
the Municipality cannot thereafter refuse the building
permit applied for by the party on the premise that the
land is proposed to be acquired for any purpose [see
Thalassery Municipality v. Puthalath Balakrishnan,
(2019(3) KLT 154) and Abul Hakeem v. Manjeri Municipality,
(2018(1) KLT 1026)]
5. More than 60 days have elapsed since the
submission of the purchase notice. No steps have been
taken for purchase/acquisition of the property. The
municipality is not entitled to refuse building permit
relying on the master plan.
WP(C).No.3535 OF 2021(N)
In the result, the writ petition is disposed of
directing the 2nd respondent to reconsider and pass fresh
orders on the building permit application submitted by the
petitioner dated 28.10.2020 without reference to Ext P1
decision which was based on the master plan. The
application shall be considered and orders passed within a
period of one month from the date of receipt of a copy of
this judgment.
Sd/-
SATHISH NINAN
JUDGE vdv WP(C).No.3535 OF 2021(N)
APPENDIX PETITIONER'S/S EXHIBITS:
EXHIBIT P1 TRUE COPY OF THE ORDER NO.B.A-160/20-
21 DATED 09.12.2020, ISSUED BY THE 2ND RESPONDENT.
EXHIBIT P2 TRUE COPY OF THE PURCHASE NOTICE DATED 09.12.2020 BY THE PETITIONER BEFORE THE 2ND RESPONDENT.
EXHIBIT P2(a) TRUE COPY OF THE RECEIPT OF ACCEPTANCE ON 09.12.2020 ISSUED BY THE RESPONDENT MUNICIPALITY IN WARD NO.16978.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!