Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Jayaprakashan P. vs State Of Kerala
2021 Latest Caselaw 9647 Ker

Citation : 2021 Latest Caselaw 9647 Ker
Judgement Date : 23 March, 2021

Kerala High Court
Jayaprakashan P. vs State Of Kerala on 23 March, 2021
W.P(c).No.3011/2021-B              1

               IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                PRESENT

                 THE HONOURABLE SMT. JUSTICE P.V.ASHA

     TUESDAY, THE 23RD DAY OF MARCH 2021 / 2ND CHAITHRA, 1943

                        WP(C).No.3011 OF 2021(B)

PETITIONER:

               JAYAPRAKASHAN P., AGED 47 YEARS
               S/O.P.KELU MASTER, PONNARATH CONSTRUCTIONS,
               P.K.HOUSE, KUTTIYATTOOR.P.O, MAYYIL, KANNUR-670602.

               BY ADV. SMT.TESSY JOSE

RESPONDENTS:

       1       STATE OF KERALA
               REPRESENTED BY CHIEF SECRETARY,
               SECRETARIAT,THIRUVANANTHAPURAM-695001.

       2       THE SUPERINTENDING ENGINEER,
               MINOR IRRIGATION CIRCLE,WEST HILL,CHUNGAM,
               KAVERI HOUSE,KOZHIKODE-673005.

       3       THE EXECUTIVE ENGINEER,
               MINOR IRRIGATION DIVISION,SULTHAN BATHERI,
               WAYANAD-673592.

       4       THE DISTRICT COLLECTOR,
               COLLECTORATE,WAYANAD-673121.

       5       THE ASSISTANT ENGINEER,
               MINOR IRRIGATION SECTION, PANAMARAM-670721.

       6       ASSISTANT EXECUTIVE ENGINEER,
               MANANTHAVADY, WAYANAD, MINOR IRRIGATION SUB
               DIVISION, MANANTHAVADY, WAYANAD-670645.

       7       THE CHIEF GENERAL MANAGER,
               NABARD, KERALA REGIONAL OFFICE,
               PONNAN ROAD, THIRUVANANTHAPURAM-695001.

       8       THE CHIEF ENGINEER,
               IRRIGATION AND ADMINISTRATION, PUBLIC OFFICE
               BUILDING,THIRUVANANTHAPURAM-695033.

               R1-6, R8 BY GOVERNMENT PLEADER SMT.PRINCY XAVIER

     THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON
17.03.2021, THE COURT ON 23.03.2021 DAY DELIVERED THE FOLLOWING:
 W.P(c).No.3011/2021-B                      2




                                     P.V.ASHA, J.
                  -----------------------------------------------------
                             W.P(c) No.3011 of 2021-B
                   ----------------------------------------------------
                      Dated this the 23rd day of March, 2021

                                 JUDGMENT

Petitioner is an A class Government Contractor, who was awarded the work

'NABARD RIDF XX-construction of neervaram kalluvayal L1 scheme in

Panamaram Panchayat Wayanad district'. Termination of contract as per Ext.P8

order is under challenge in this Writ Petition.

2. The petitioner executed Ext.P1 agreement on 4.3.2016. It is stated

that on account of the protest of the owners of landed property and the nearby

residents, the work got delayed. On the request of farmers the 6 th respondent

requested for a revised estimate as per Ext.P2 letter addressed to the 3 rd

respondent. The revised estimate was sanctioned only on 18.4.2018, after a period

of 20 months. It is stated that in August, 2018, the area was affected with heavy

flood and the work had to be stopped. Except the pipeline work, the petitioner

could proceed with the work of transformer yard, other cable works and concrete

works after the rain subsided. In the meanwhile, extension of time was granted till

3.6.2019 without imposing any fine. Even though the petitioner submitted Ext.P3

application for extension of time for the period from 3.6.19 to 31.3.2021, there was

no response. The work relating to laying of 1.50 km PVC pipe and 350mm

diameter D1 pipe was remaining. According to the petitioner, pipe manufacturing

factory remained closed on account of Covid 19 pandemic and there was shortage

of materials. The petitioner thereupon submitted Ext.P4 representation again

requesting for time for the period from 3.6.19 to 31.3.2021. It was followed by

Ext.P5 representation dt.8.1.2021. The petitioner further states that a meeting was

convened by the District Collector on 13.1.2021 when it was decided to fix the

time for completion of the work as 31.3.2021 and that the Department would co-

operate with the extension of time in case the pipes were brought to the site before

20.2.2021. The petitioner states that the said decision was without ascertaining the

factual circumstances because the pipes were to be obtained from Gujarat where

the factories were remaining closed due to the scarcity of workers on account of

the pandemic. Apart from that, in the absence of a valid agreement, the petitioner

would not be able to take the risk of purchasing pipes spending such huge amount

of about Rs.70 lakhs. Thereupon, the petitioner submitted Ext.P7 representation

on 15.1.2021 before the 2nd respondent. Ext.P8 order of termination was passed

thereupon on 25.01.2021, without considering her request.

3. The 2nd respondent has filed a statement. It is stated that the site was

handed over to the contractor on 4.3.2016 fixing the date of completion as

3.3.2017; time was extended 5 times upto 3.6.2019 at the request of the contractor

without imposing fine; the contractor did not turn up to complete the work despite

several attempts from the part of the departmental officers; notices were given to

contractor on 24.08.2020, 7.9.2020 and 6.11.2020 directing to resume the work; on

receipt of the notice dt.6.11.2020, the petitioner attended the office and assured to

complete the work before 28.2.2021; as per Ext.R2(a) letter the petitioner was

informed that the NABARD XX tranche would be closed by 31.3.2021 and the

contract would be terminated at his risk and cost, in the event of non-completion of

the work; thereafter a meeting was held in the chamber of District Collector,

Wayanad with the petitioner, NABARD officials and officials from the

department; in that meeting it was unanimously decided that the work could be

finished without any further extension; the petitioner instead of resuming the work

submitted Ext.P7 letter on 15.1.2021 demanding further time and rate escalation;

after consultation with the District Collector, who authorised the agreement

authority to take a decision, the Department was forced to terminate the work at

the risk and cost of the petitioner; petitioner has completed only 28% of the work;

the rest of the work has to be rearranged through another agency and the loss

sustained by the Government is to be recovered from the petitioner; extension of

time was granted 5 times considering the request of the petitioner till 3.6.2019;

sanctioning of revised estimate on 18.04.2018 did not stand in the way of carrying

out the work of laying of DI pipes, since the length of DI pipes in the sanctioned

revised estimate is less than that of the original agreement; departmental officials

had not directed the petitioner to stop the work pending revision; on the other

hand, the petitioner failed to arrange men and machinery to complete the work in

time. Pointing out the conditions in Annexure R2(b) conditions of contract, it is

stated that there is no provision for escalation of rates or extension of time beyond

what is provided in the agreement. There was no response from the petitioner's

side to resume or complete the work despite reciept of notices. Even after the

meeting convened on 13.1.2021, in which the petitioner had participated, he did

not turn up to resume the work. It is stated that the petitioner's request for further

time extension was not forwarded to higher authorities as the petitioner did not

respond to the repeated notices issued to him. The demand for price escalation of

pipe items and also for the extension of time was contrary to the decision taken in

the meeting and the conditions of contract. It is stated that it is the result of

inaction on the part of the petitioner in arranging and completing the work within

the agreed period. The petitioner was responsible for executing the works of

pumphouse, culvert, concrete canals and D1 and PVC pipeline works, out of which

he had completed the works only to the tune of Rs.64,26,127/- as against the

revised estimate of Rs.3,15,75,121/- which comes to 28% of the work financially.

It is stated that even after the site conditions became favourable, the petitioner had

not turned up to complete the work. It is stated that after 2018 flood, he had

executed only the work of transformer yard and duct cable during the period of

December, 2018 to 30.1.2019, cost of which was only Rs.1.5 lakhs. It is stated

that even though extension of time upto 03.06.2019 was granted from the offices

of the respondent on 27.11.2019, the petitioner had attended their office only on

10.12.2020, after one year, for executing supplementary agreement, that too, after

several reminders. It is submitted that several works using DI pipes are going on

and therefore non availability of pipes is not at all a genuine reason. It is further

stated that the petitioner had furnished a photocopy of the order dated 15.09.2020

claiming that advance payment was made for pipe, which was found not genuine.

It is stated that the NABARD XX tranche will expire on 31.3.2021 and therefore

the work has to be completed before that date.

4. The petitioner has filed a reply affidavit producing various

communications in Exts.P10 to P12 and stating that request for extension from

03.06.2019 to 31.03.2020 was submitted on 02.08.2019 and there was no response

even after subsequent requests. It is stated that the notices Exts.P10 and P11

notices dated 24.08.2020 and 07.09.2020 respectively were issued to him directing

him to resume work when extension application of the petitioner was pending. It

is stated that the petitioner could not have resumed the work in the absence of a

valid agreement. Though he had submitted Ext.P4 representation for extension of

time till 31.3.2021 in response to Ext.P12 communication, the respondents did not

issue any orders for extension and therefore there was no question of resuming the

work in the absence of a valid agreement. It is stated that though he had pointed

out the same in the meeting, his submission was not considered. It is also stated

that he made enquiries as to the cost of pipes immediately on the very next day of

the meeting held on 30.1.2021 when he came to know that there was 40%

escalation in price. Thereupon he submitted Ext.P7 representation on 15.1.2021

stating that he would not be able to resume the work in the absence of any

extension from 03.06.2019 as a sum of Rs.70 lakhs is necessary towards the cost

of the pipes. The petitioner stated that he had completed 56% of the work, relying

on Ext.P13 progress report issued by the Minor Irrigation Sub Division. Without

revising the estimate and getting it sanctioned, it was not possible to resume the

work. It is stated that even in the absence of a stop memo when a revised estimate

is pending, work could not have been continued as measurement has to be entered

on each day. According to the petitioner, the decision taken on 13.01.2021 was

without considering the practical difficulties and without considering the expiry of

the agreement. It is stated that 20 months' time was taken for getting the revised

estimate and that the Department alone is responsible for the delay of that much

period. According to him, the fact that the 5 extensions were granted without

penalty, would show that the default was not on the part of the contractor. It is

stated that the 2nd respondent, who refused to forward the applications submitted

by the petitioner, committed dereliction of duty; the 20 months' time for revised

sanction and thereafter the refusal to extend the agreement has resulted in delay in

completing the work . It is stated that even during the time when the area was

affected by the flood, the petitioner completed the work of transformer yard and

duct cable, even when the Revenue Department had to remove tonnes of sand from

the field on account of the flood and it became impossible for the petitioner to do

the pipeline work in the field. When there is 40% escalation in price on account of

the delay of 5 years caused by the Department, the petitioner cannot be asked to

carry out the work at the pre-revised rates. According to the petitioner, the order of

termination with risk and cost is illegal.

5. I heard the learned Counsel for the petitioner and the learned

Government Pleader.

6. Ext.P8 order of termination is issued for non-completion of work.

The work is to be executed in terms of the contract entered. In the present case,

both sides agree that the time for completion was extended several times and that

there was no extension of time after 03.06.2019.

7. The materials on record would show that the petitioner continued to

seek for extension of time by submitting petitions after petitions and the

respondents continued to issue orders after orders directing the petitioner to

resume the work. There was neither extension nor resumption. Petitioner's

demand is not only for extension but for escalation of rates also. But it is stated

that the conditions of contract did not provide for any escalation of rate. It would

appear that the petitioner is not inclined to continue the work at the original rates

even if extension is granted. This Court would not be in a position to determine

whether the petitioner deserves escalation of rate or to direct the respondents to

revise the rates, as the petitioner was awarded the work on contract.

8. Regarding the contention of the petitioner that he lost 20 months' time

on account of sanctioning of revised estimates and the delay was not at his

instance, the admitted facts would show that the original time for completion of

work was one year. The petitioner admits that time was granted till 03.06.2019 as

against the scheduled date of completion of 03.03.2017. The petitioner admits

that he received the notices directing resumption of work. But according to him,

when his applications for extension of time was pending and there was no

extension of agreement or any response to his applications, it was not necessary to

act upon those notices.

9. The pleadings would show that there is absolutely no co-operation

between the agreement authority and the contractor. The learned Government

Pleader argued that the respondents lost confidence in the petitioner. In such

circumstances, it woud not be proper for this Court even to direct the respondents

to re-consider the issue.

10. When there is contract entered into between the petitioner and the

respondents and the respondents have terminated the contract in accordance with

the conditions of contract, this Court is not expected to interfere with it. Whether

there was breach of conditions or not would be a matter to be adjudicated after

adducing evidence. Even regarding the quantum of work executed, there is

dispute between the parties.

Therefore, I am of the view that a Writ Petition under Article 226 of the

Constitution of India would not be the proper remedy available to the petitioner.

Hence, I dismiss the Writ Petition. The petitioner would be free to agitate the

matter before the appropriate forum.

Sd/- (P.V.ASHA, JUDGE)

rtr/

APPENDIX PETITIONER'S EXHIBITS:

EXHIBIT P1              TRUE COPY OF THE AGREEMENT NO.SE(MI)-
                        76/2015-16 DATED 4.3.2016 BETWEEN THE
                        PETITIONER AND THE 2ND RESPONDENT.

EXHIBIT P2              TRUE COPY OF THE COMMUNICATION DATED
                        2.8.2016 SENT BY THE 6TH RESPONDENT TO THE
                        3RD RESPONDENT.

EXHIBIT P3              TRUE COPY OF THE REQUEST MADE BY THE
                        PETITIONER TO THE 3RD RESPONDENT DATED
                        2.8.2019.

EXHIBIT P4              TRUE COPY OF THE REPRESENTATION DATED
                        10.12.2020 SENT BY THE PETITIONER TO THE
                        2ND AND 5TH RESPONDENTS.

EXHIBIT P5              A TRUE COPY OF THE REQUEST DATED 8.1.2021
                        SENT TO THE 5TH RESPONDENT BY THE
                        PETITIONER

EXHIBIT P6              TRUE COPY OF THE MINUTES OF THE MEETING
                        DATED 13.1.2021 HELD BY 4TH RESPONDENT.

EXHIBIT P7              TRUE COPY OF THE REPRESENTATION DATED
                        15.1.2021 SENT BY THE PETITIONER TO THE 2ND
                        RESPONDENT.

EXHIBIT P8              TRUE COPY OF THE ORDER DATED 25.1.2021
                        ISSUED BY THE 2ND RESPONDENT.

EXHIBIT P9              TRUE COPY OF THE ORDER NO DB5-4188/14 DATED
                        27.11.2019 ISSUED BY THE 2ND RESPONDENT.

EXHIBIT P10             TRUE COPY OF THE COMMUNICATION DATED
                        24.8.2020 SENT BY THE 2ND RESPONDENT TO THE
                        PETITIONER.

EXHIBIT P11             TRUE COPY OF THE COMMUNICATION DATED
                        7.9.2020 SENT BY THE 2ND RESPONDENT TO THE
                        PETITIONER.

EXHIBIT P12             TRUE COPY OF THE COMMUNICATION DATED
                        6.11.2020 SENT BY THE 2ND RESPONDENT TO THE
                        PETITIONER.

EXHIBIT P13             TRUE COPY OF THE PROGRESS REPORT OF THE
                        WORK SHOWING COMPLETION OF 56% OF THE WORK
                        ISSUED BY THE MINOR IRRIGATIOB SUB DIVISION
                        FOR THE MONTH OF JULY.


EXHIBIT P14             TRUE COPY OF THE BANK STATEMENT SHOWING
                        PAYMENT OF RS.3,00,000/- ON 8.11.2016 AS
                        ADVANCE PAYMENT TO M/S.MERCURY ENTERPRISES.

EXHIBIT P15             TRUE COPY OF THE BANK STATEMENT SHOWING
                        RECEIPT OF RS.3,00,000/- ON 15.5.2017
                        SHOWING RETURN OF ADVANCE PAYMENT.

EXHIBIT P16             TRUE COPY OF COMMUNICATION DATED NIL ISSUED
                        BY M/S MERCURY ENTERPRISES, PIPE SUPPLIER
                        TO THE PETITIONER STATING THE REASONS FOR
                        RETURNING THE AMOUNT.


RESPONDENTS' EXHIBITS

ANNEXURE R2(a)          TRUE COPY OF THE LETTER DT.7.12.2020.

ANNEXURE R2(b)          TRUE COPY OF RELEVANT PAGE OF THE
                        AGREEMENT.
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter