Citation : 2021 Latest Caselaw 9620 Ker
Judgement Date : 23 March, 2021
WP(C).No.16002 OF 2020(A)
1
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE SMT. JUSTICE P.V.ASHA
TUESDAY, THE 23RD DAY OF MARCH 2021 / 2ND CHAITHRA, 1943
WP(C).No.16002 OF 2020(A)
PETITIONER/S:
RAHMATHULLA K.K.
AGED 56 YEARS
KANICHADI KUZHIYIL HOUSE, CHERUVADI.P.O., MAVOOR,
KOZHIKODE-673661, KERALA.
BY ADVS.
SRI.V.K.PRASAD
SRI.M.PRAVEESH
RESPONDENT/S:
1 STATE OF KERALA,
REPRESENTED BY THE SECRETARY, IRRIGATION
DEPARTMENT, GOVERNMENT SECRETARIAT,
THIRUVANANTHAPURAM-695001.
2 SUPERINTENDING ENGINEER,
MINOR IRRIGATION CIRCLE, KAVERI HOUSE, WEST
HILL.P.O., KOZHIKODE-673005.
3 THE EXECUTIVE ENGINEER,
MINOR IRRIGATION DIVISION, OFFICE OF THE EXECUTIVE
ENGINEER, MINOR IRRIGATION DIVISION, CIVIL STATION,
KOZHIKODE-673020.
4 M.M.BALAKRISHNAN,
CHERIYAMADATHIL HOUSE, KALPATHOOR, MEPPAYYUR,
PINCODE-673524, KOZHIKODE.
R4 BY ADV. SRI.K.B.ARUNKUMAR
OTHER PRESENT:
SMT.VINITHA.B, GP
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
23.03.2021, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
WP(C).No.16002 OF 2020(A)
2
JUDGMENT
Dated this the 23rd day of March 2021
The petitioner challenges finalisation of the tender in
favour of the 4th respondent.
2. Ext.P1 notice inviting tender was issued on 06.03.2020
by the Minor Irrigation Department under the Kerala State
Irrigation Department for construction of the check dam across
Vencheri river at Chambanmuzhi Kaipram in Puthuppadi Panchayath
under Thiruvambady Legislative Assembly of Kozhikkode District.
The time for completion fixed was ten months. It is stated that
4 bidders participated in the tender and petitioner came out
successful as per Ext.P2 proceedings. Three remaining bidders
did not qualify since they failed to pay GST under reverse
mechanism. It was under those circumstances, the petitioner was
declared as L-1. It is stated that despite this petitioner was
not awarded the work and he submitted Ext.P3 representation and
2nd respondent as per Ext.P4 letter informed the petitioner that
files were returned to the office of the 3 rd respondent. It is
stated that the petitioner thereafter approached this Court in
WP(C) No.14413 of 2020 and this Court directed the respondents
to take a decision. As per Ext.P5 letter the 3rd respondent
informed that after the petitioner was declared as L-1, the
matter was considered and it was found that there was a
difference of Rs.8,30,485/-. It was stated that the tender WP(C).No.16002 OF 2020(A)
submitted by other three persons were rejected on the ground
that they did not remit the sum of Rs.502/- towards GST and the
entire documents of the petitioner were forwarded to the
Superintending Engineer as per letter dated 18.05.2020. Seeing
that there was a difference of Rs.8,30,485/- between the amount
quoted by the petitioner and the 4th respondent, respondents
called for clarification from the Commercial Taxes Department
and it was informed that the tenders for which tender fee is
less than Rs.5,000/- are exempted from realization of GST and
therefore it was decided that the 4th respondent who quoted the
lowest amount be awarded the work. The petitioner is challenging
Ext.P5 letter. According to the petitioner tender conditions
cannot be varied.
3. The 3rd respondent has filed a counter affidavit
reiterating the contents of Ext.P5 letter. It is stated that as
per the GST S.11(1) of the GST Rules 2017, if the tender fee
amount is less than Rs.5,000/- it is exempted from the GST and
in the present case the tender fee is only Rs.2,790/- and all
the bidders are eligible for exemption from paying GST @ 18%. It
is stated that the Technical Evaluation Committee which met on
23.06.2020 considered the tenders in the light of the
clarification and the petitioner became L-4. The 2nd respondent
directed to take a suitable decision in the matter in order to
see that no loss is sustained by the Government. Thereafter the
3rd respondent approved the lowest tender and issued selection WP(C).No.16002 OF 2020(A)
notice to the 4th respondent. He signed the agreement with the 3rd
respondent on 09.07.2020. The site of the said work has been
handed over to the contractor on 15.07.2020 and he has started
the work from 15.07.2020. It is stated that the petitioner was
informed about all these in the letter dated 13.07.2020.
4. The 4th respondent also filed a counter affidavit stating
that he is eligible for exemption from payment of GST and being
L-1 he is entitled to be awarded the work.
5. The petitioner has filed a reply affidavit pointing out
that the work is not started and he is entitled to be awarded
the work.
6. Admittedly the bid amount quoted by the petitioner is
Rs.69,97,656.8. It is only because the tender evaluation
committee initially did not consider the relevant rules under
the GST which provides for exemption from payment of GST where
the tender fee is below Rs.5,000/- that petitioner was treated
as L-1 though he quoted the highest amount and was actually L-4
among the 4 bidders. In the aforesaid circumstances, respondents
have awarded the work in public interest in order to see that
the Government does not sustain any loss in the process of
tender and also to see that the selection is made in accordance
with the rules. What the respondents have done is in accordance
with law.
7. Just because the respondents have issued a selection
notice and the petitioner was treated as L-1 without noticing WP(C).No.16002 OF 2020(A)
the relevant provisions under the GST Rules, petitioner cannot
have any right to insist that he should be given the work and
the person who would be quoted at the lowest amount should be
given the work. It is settled law that even if there are certain
minor variations from the tender conditions, interference by
courts under Article 226 of the Constitution of India is
uncalled for except in cases of arbitrariness and malafides. No
such allegation is raised in this Writ Petition. Therefore,
petitioner does not deserve any relief.
The Writ Petition is accordingly dismissed.
Sd/-
P.V.ASHA
rkc JUDGE
WP(C).No.16002 OF 2020(A)
APPENDIX
PETITIONER'S/S EXHIBITS:
EXHIBIT P1 A TRUE COPY OF THE TENDER NOTICE BEARING
NO.EE MI/ET-42/2019-20 DATED 6.3.2020
INVITING TENDERS ISSUED BY 2ND RESPONDENT MINOR IRRIGATION DEPARTMENT UNDER 1ST RESPONDENT STATE IRRIGATION DEPARTMENT.
EXHIBIT P2 A TRUE COPY OF THE TECHNICAL EVALUATION REPORT DATED 16.6.2020 DOWNLOADED FROM THE WEBSITE OF 1ST RESPONDENT SHOWING PETITIONER AS L1.
EXHIBIT P3 A TRUE COPY OF THE REPRESENTATION DATED 17.6.2020 SUBMITTED BY PETITIONER AT THE OFFICE OF 2ND RESPONDENT.
EXHIBIT P4 A TRUE COPY OF THE COMMUNICATION FROM THE OFFICE OF THE 2ND RESPONDENT BEARING NO.DB10-2019/7212/1A DATED 23.6.2020.
EXHIBIT P5 A TRUE COPY OF LETTER BEARING NO.D2/2019/7212/1A DATED 13.7.2020 SENT BY 3RD RESPONDENT THAT WAS RECEIVED BY THE PETITIONER ON 18.7.2020.
EXHIBIT P6 A TRUE COPY OF THE LETTER DATED 5.10.2018
SENT BY DEPUTY COMMISSIONER SGST
DEPARTMENT, PALAKKAD, PALAAKKD DISTRICT COMMITTEE OF ALL KEARALA GOVERNMENT CONTRACTORS ASSOCIATION STATED IN EXHIBIT P5 COMMUNICATION.
EXHIBIT P7 A TRUE COPY OF THE TENDER NOTICE DATED 27/07/2020 ISSUED BY RESPONDENT 3.
EXHIBIT P8 TRUE COPY OF THE PHOTOGRAPHS OF THE TENDER SITE TAKEN ON 24/02/2021.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!