Citation : 2021 Latest Caselaw 9227 Ker
Judgement Date : 19 March, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE N.NAGARESH
FRIDAY, THE 19TH DAY OF MARCH 2021/28TH PHALGUNA, 1942
WP(C).No.10921 OF 2017(M)
PETITIONER:
K.M.SALIM, AGED 60 YEARS,
S/O. LATE MARAKKAR, ERUMAMUNDA P.O.,
CHUNGANTHARA, NILAMBUR
BY ADVS.
SRI.BABU KARUKAPADATH
SMT.AMRIN FATHIMA
SRI.K.M.FAISAL (KALAMASSERY)
SRI.MITHUN BABY JOHN
SRI.J.RAMKUMAR
SMT.M.A.VAHEEDA BABU
SHRI.P.U.VINOD KUMAR
RESPONDENTS:
1 STATE OF KERALA REPRESENTED BY
ITS SECRETARY, PUBLIC WORKS DEPARTMENT,
GOVERNMENT SECRETARIAT,
THIRUVANANTHAPURAM 695 001.
2 CHIEF ENGINEER, P.W.D. ROADS AND BRIDGES,
NEAR MUSEUM, THIRUVANANTHAPURAM-695 001.
3 THE SUPERINTENDING ENGINEER,
ROADS AND BRIDGES, P.W.D., NORTH CIRCLE,
KOZHIKODE-673 001.
4 ASSISTANT EXECUTIVE ENGINEER,
P.W.D. ROADS DIVISION, MANJERI 676 121.
5 THE EXECUTIVE ENGINEER,
ROADS DIVISION, MANJERI 676 121.
W.P.(C) No.10921/2017
:2:
6 THE SECRETARY, DEPARTMENT OF FINANCE,
GOVERNMENT SECRETARIAT,
THIRUVANANTHAPURAM - 695 001.
ADDL. 7 THE CHIEF TECHNICAL EXAMINER,
FINANCE (INSPECTION WING -TECHNICAL)
DEPARTMENT, SBTEU BUILDING, 3RD FLOOR,
PULIMOODU, THIRUVANANTHAPURAM-695 001.
IS IMPLEADED AS ADDITIONAL R7 AS PER ORDER
DATED 03.02.2021 IN I.A.1/2021 IN WPC
10921/2017.
BY GOVERNMENT PLEADER SMT.RASHMI K.M.
THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY
HEARD ON 19-03-2021, THE COURT ON THE SAME DAY DELIVERED
THE FOLLOWING:
W.P.(C) No.10921/2017
:3:
N. NAGARESH, J.
`````````````````````````````````````````````````````````````
W.P.(C) No.10921 of 2017
`````````````````````````````````````````````````````````````
Dated this the 19th day of March, 2021
JUDGMENT
~~~~~~~~~
The petitioner, who is a Government Contractor,
seeks to direct the respondents to pay the whole balance
amount due to the petitioner to the tune of `27,41,030/-
covered by Bill No.595 dated 27.12.2015 in respect of the
contract work "the construction of Chethukadavu Bridge
across Kalikavu River in Malappuram District", completed
and executed as per Ext.P2 agreement, by sanctioning the
revised estimate, along with interest at a reasonable rate
thereon, within such time as this Court deems just and
proper. The petitioner further seeks to direct the
respondents not to recover the DLR amount given to the
petitioner, which was approved by the 2 nd respondent as per
Ext.P3.
W.P.(C) No.10921/2017
2. The petitioner states that in response to a
notification, the petitioner was awarded the work of the
construction of Chethukadavu bridge across Kalikavu River
in Malappuram District. The probable amount of contract
was ₹3,35,55,123/-. The petitioner quoted 13% below the
PAC. The petitioner agreed to complete the work for
`2,91,92,957/-. The petitioner entered into Ext.P2 Agreement
with the respondents on 01.05.2012. The petitioner had to
complete the work within 18 months. The site was handed
over to the petitioner on 15.05.2012.
3. The petitioner would submit that during the
inception of well for the construction of the Bridge, existence
of massive rock boulders were found beneath the water.
These rock boulders could not have been removed by
explosion using gunpowder. The massive rock boulders had
to be chiselled and removed by skilled labourers who are
experienced to work under water. In view of the urgency and
importance of the work, the petitioner engaged skilled
labourers, providing them with oxygen masks for doing the W.P.(C) No.10921/2017
under-water work. The work was done by such skilled
workers under the direct supervision of the Departmental
Authorities. The wages for the skilled workers for doing this
particular work had to be paid by the Department. However,
the petitioner paid them initially. These amounts should be
paid back to the petitioner as hand receipts.
4. As the massive rock formation was not
contemplated in the work, the Department was bound to
prepare a revised estimate, with the required additional
quantity of work. The Chief Engineer approved the additional
work of boulder removal and made part payment also. The
skilled workers had to be paid `69,08,919/-. The said
amount was approved by the Chief Engineer as per Ext.P3.
After removing the massive boulders, the construction was
carried out and the bridge was handed over on 17.09.2014.
5. However, the Department did not honour the final
bill of `27,41,030/-, as the revised estimate was not
sanctioned by the 1st and 6th respondents. The petitioner
submitted repeated representations for sanctioning this W.P.(C) No.10921/2017
amount. By Ext.P8, the 2 nd respondent-Chief Engineer
recommended to revise the estimate so as to include the
additional work. To the shock and surprise of the petitioner,
Ext.P9 order was issued by the 1st respondent rejecting the
recommendation for sanction of the revised estimate.
6. The counsel for the petitioner argued that during
the execution of the work, unexpected issues arose and
huge rock boulder formations had to be removed from the
well foundation. This work was not included in the estimate.
This work had to be carried out engaging highly skilled
workers. The work was done under the supervision of the
officials of the Department. The skilled workers had to be
paid an amount of `69,08,919/-. This amount was approved
by the Chief Engineer as per Ext.P3 and, in fact, part
payments were made also. The petitioner has completed the
construction of the bridge and the public are using the
bridge. There is no complaint whatsoever regarding the
quality of construction made by the petitioner. W.P.(C) No.10921/2017
7. After getting the work done, the respondents
cannot now contend that they will not revise the estimates.
There is no dispute that huge rock boulders had to be
removed. The work was carried out in the presence of the
Departmental Officials. They do not have any doubt
regarding the work carried out by the petitioner. Therefore,
the 1st respondent cannot now take an arbitrary stand that
the amount cannot be paid.
8. The 1st respondent filed a counter affidavit. The 1 st
respondent admitted the existence of hard rock strata. The
1st respondent stated that a detailed estimate of the work
was prepared in respect of this additional work adopting
PWD standard data. The rate of cutting down obstacles of
size above 40 dm3, wooden blocks of size above 100 dm3
and sinking wells in rocks, have not been included in item
Nos.701 to 706 of well sinking. The 1st respondent stated
that breaking down of obstacles of size more than 40 dm3
and the sinking wells through rock, if any, encountered
during well sinking operation, is to be done by the W.P.(C) No.10921/2017
Department separately by means of some other
arrangements simultaneously together with well sinking
operation.
9. The 1st respondent examined the proposals of the
2nd respondent. The 1st respondent noted that the size of
boulders is not specified in the soil log. There is no evidence
to establish that boulders removed were more than 40 dm3
size. The payment was made based on DLR without
assessing the quantity of boulders removed and without
arriving rate analysis of the above item, which is not in order.
The Chief Engineer was directed to resubmit the revised
estimate. Exts.P9 and P10 are not final orders or
instructions.
10. The 1st respondent stated that the Government
received a revised estimate proposal from the 2 nd
respondent. And no amount found to be eligible to the
petitioner, would be withheld. The amount eligible to the
petitioner will be sanctioned after examination of revised
estimate in consultation with Finance Department of the W.P.(C) No.10921/2017
Government of Kerala.
11. The 1st respondent subsequently filed an
additional counter affidavit dated 24.08.2019. In the
additional counter affidavit, it has been stated that the
Finance Department of Government of Kerala examined the
proposal for additional work and opined that the details
submitted by the Chief Engineer pertaining to the admissible
amount for breaking the boulders comes to `1,09,296/- only
as against the revised estimate provision of `69,08,919/-.
Though the Chief Engineer again submitted the same
proposal, the proposal did not mention the quantum of 40
dm3 boulders broken and the split up details of rate analysis
to substantiate the claim made on the said head. Therefore,
it was once again requested to provide revised estimate. The
revised estimate was accordingly submitted and it is under
the examination by the Government. The 1 st respondent
reiterated that amount will be sanctioned to the petitioner
soon.
W.P.(C) No.10921/2017
12. The additional 7th respondent, who is the Chief
Technical Examiner, Finance (Inspection Wing - Technical)
Department has filed a counter affidavit dated 24.02.2021.
The Chief Technical Examiner in his counter affidavit stated
that:
1. The size of boulders is not specified in the soil log. Payment was seen made based on Daily Labour Report without assessing the quantity of boulders removed.
2. The revised estimate ought to have been prepared much earlier. Revised estimate should not be kept waiting till the work is completed. The Chief Engineer has not submitted the revised estimate to the Government during the course of execution of work. Revised estimate was forwarded only after completion of the work.
3. Field Officers could not quantify the boulders claimed to be broken and produce the materials at site or its disposal details for verification by the officials from the Technical Wing.
4. In this case, records of daily labourers engaged by the contractor for the particular item is available with PWD. The DLR submitted by the Chief Engineer, total man-days taken for cutting and breaking boulders and wooden logs more than 40 dm3 size comes to 216 numbers only. Therefore, admissible cost for cutting and breaking boulders as per the documents submitted by PWD would come to `1,09,296/- at the rate of `506/- each for 216 numbers of man-days.
W.P.(C) No.10921/2017
13. I have heard the counsel on either side.
14. The dispute involved is in a narrow compass.
While executing the work of bridge construction, it was noted
that there were rock boulder formations beneath the water,
which ought to have been removed for sinking well. The
agreement entered into between the petitioner and the
respondents did not contemplate this situation. The item of
removing boulders above 40 dm3 size was not covered in
the scope of agreement. It is the firm statement of the Chief
Engineer, as contained in Ext.P3, that actual expenditure for
cutting and breaking into small pieces of boulders of more
than 40 dm3 size during sinking and seating of wells, would
come to `69,08,919/-.
15. The case of the 7th respondent is that there was
no material to verify the quantity of rock boulders removed.
The size of boulders is not specified in the soil log. The Field
Officers from the Technical Wing were not in a position to
quantify the boulders claimed to be broken and to produce
the materials at the site or its disposal details for verification. W.P.(C) No.10921/2017
This objection, it seems, is without appreciating the issue at
hand.
16. In Ext.P11, the Assistant Engineer has specifically
stated that to remove the huge rock boulders, the well
sinkers/divers had to go down up to 12 metres in the river
wearing oxygen mask helmets. Compressors, chisels and
hammers had to be used by 5 to 6 sinkers/divers at a time.
To assist them Serang, Man mazdoors, Compressor
Operators, Cleaners and Blacksmiths had to be engaged as
standbys.
17. The size of rock boulders could not have been
assessed in advance. According to the Executive Engineer,
no equipment or technology is presently available for
determining the exact size and quantity of an invisible object
laying beneath the earth. Though the presence of an object
coming at the path of a core bore can be noticed, the size
and quantity of the object cannot be assessed in core boring.
According to the Engineers, who were in charge of the work,
it was practically unviable to collect the crushed boulder W.P.(C) No.10921/2017
pieces from the river bed and bring them ashore to assess
the quantum of rock boulders.
18. As the size of massive rock boulders could not
have been assessed in advance, the work also could not
have been estimated in advance. Every day, Overseers
used to prepare DLR and submit to higher officers. When
the work was carried out in the presence of departmental
officials and in such difficult situation, it would be harsh and
unrealistic on the part of the 7th respondent to submit that
their field officers could not quantify the boulders broken as
the broken boulders were not produced at site for verification
by the official from the Technical Wing.
19. The further contention of the respondents that
revised estimates ought to have been prepared in advance,
is also seen ignoring the stark reality. It is an admitted
position that the size and the quantity of rock boulders
beneath the river bed to be removed, could not have been
quantified in advance. For the very same reason,
preparation of revised estimate in advance was impractical. W.P.(C) No.10921/2017
At any rate, the petitioner cannot be found fault with for not
forwarding revised estimate in advance.
20. In Ext.P11, the Assistant Executive Engineer and
Executive Engineer have informed that 5 to 6 sinkers have
worked using compressor, chisel and hammer taking
considerable time to remove the boulders. These workers
were highly skilled and were using oxygen supply masks
during the work under water. To facilitate the work and also
for safety reasons, Serang, Man mazdoor, Compressor
Operator, Cleaner and Blacksmiths were engaged every day.
The Executive Engineer in Ext.P6 has stated that the said
work took nearly six months.
21. There is a further anomaly in the stand taken by
the respondents. The Assistant Executive Engineer and the
Executive Engineer would submit that 5 to 6 sinkers/divers
did work for nearly six months to remove the crop boulder
formations. Supporting staff like Serang, Man mazdoors,
Blacksmiths and Compressor Operators had to be deployed
when sinkers and divers were doing the work at the river W.P.(C) No.10921/2017
bed. These deployments were not provided for in the
agreement.
22. The 7th respondent has stated that the total man-
days taken for cutting and breaking boulders more than 40
dm3 size comes to 216 numbers only. Therefore, the
admissible cost for cutting and breaking boulders more than
40 dm3 size as per the document submitted by PWD at the
estimate rate based on PWD revised SoR 2010 comes to
`1,09,296/- (@ `460/- + 10% contractors profit = @ `506/-
per each for 216 numbers man-days). The figure of 216
man-days has been arrived at on the basis of the DLR
submitted by the Chief Engineer.
23. Obviously, there appears to be some error in
calculating man-days. When 5 to 6 sinkers/divers have
worked from beneath the river and when equal number of
specialised staff had to be deployed ashore during the work,
and when the rock boulder removal work lasted for more
than 200 days, the total man-days cannot be 216. Similarly,
the wage payable for such skilled workers is taken as `506/- W.P.(C) No.10921/2017
per worker per day. The daily wage payable even to
unskilled labourer in Kerala in the open market is much
higher. Assuming that the PWD Manual prescribes a lower
rate of `506/- per worker per day, there is no explanation as
to why the said rate should be made applicable to highly
skilled workers doing hazardous job beneath the waters and
at the river bed. These important aspects are not seen taken
note of.
24. In the afore circumstances of the case, this Court
is of the considered opinion that the respondents will have to
reconsider the entire issue afresh taking note of the peculiar
circumstances under which the bridge was constructed,
deploying highly skilled workers to execute the work of
removal of rock boulders formations in the river bed. The
omissions, if any, on the part of the officers of the
respondents in making technical compliances in the matter of
preparation of revised estimates etc., cannot be a reason to
deny dues to the petitioner, if he is otherwise eligible for the
same.
W.P.(C) No.10921/2017
In the circumstances of the case, the writ petition
is disposed of directing the 1 st respondent to reconsider the
revised estimate proposal submitted by the Chief Engineer in
the light of the observations made hereinabove and take a
decision afresh after giving an opportunity of hearing to the
petitioner and after consulting the officers who were in
charge of the work, if necessary. Fresh orders in this regard
shall be passed within a period of four months. To enable the
1st respondent to take a reasoned decision afresh, Ext.P9 is
set aside.
Sd/-
N. NAGARESH, JUDGE aks/15.03.2021 W.P.(C) No.10921/2017
APPENDIX PETITIONER'S EXHIBITS:
EXHIBIT P1 A TRUE COPY OF THE ORDER DATED 11.05.2012 OF THE 3RD RESPONDENT PERMITTINGTHE PETITIONER TO ADJUST THE AMOUNT DUE TO THE CONTRACTOR UNDER COMPLETED WORKS TOWARDS SECURITY DEPOSIT OF THE NEW WORK
EXHIBIT P2 A TRUE COPY OF THE RELEVANT PAGES OF THE AGREEMENT NO.SE(K) 31/2012-13 DATED 01.05.2012 EXECUTED BETWEEN THE PETITIONER AND THE 3RD RESPONDENT
EXHIBIT P3 A TRUE COPY OF THE ORDER OF APPROVAL OF DAILY LABOUR REPORT TO THE TUNE OF RS.
69,08,919 DATED 27.06.2014 OF THE 2ND RESPONDENT CHIEF ENGINEER
EXHIBITP4 A TRUE COPYOF THE FORWARDING LETTER DATED 30.01.2015 OF THE 3RD RESPONDENT ALONG WITH THE COMPLETION CERTIFICATE, SEND TO THE 5TH RESPONDENT
EXHIBIT P5 A TRUE COPY OF THE REPRESENTATION DATED 01.06.2015 SUBMITTED BY THE PETITIONER BEFORE THE 5TH RESPONDENT
EXHIBIT P6 A TRUE COPY OF THE REQUEST DATED 14.03.2016 SUBMITTE DBY THE 5TH RESPONDENT BEFORE THE 3RD RESPONDENT
EXHIBIT P7 A TRUE COPY OF THE REPRESENTATION DATED 25.07.2016SUBMITTED BY THE PETITIONER BEFORE THE 5TH RESPONDENT
EXHIBIT P8 A TRUE COPY OF THE REPRESENTATION DATED 25.07.2016 SUBMITTED BY THE PETITIONER BEFORE THE 5TH RESPONDENT
EXHIBIT P9 A TRUE COPY OF THE ORDER DATED 15.02.2016 OF THE 1ST RESPONDENT REJECTING THE RECOMMENDATION FOR SANCTION OF THE REVISED ESTIMATE.
W.P.(C) No.10921/2017
EXHIBIT P10 A TRUE COPY OF THE ORDER DATED 02.02.2017 OF THE 1ST RESPONDENT ADDRESSED TO THE 2ND RESPONDENT
EXHIBIT P11 A TRUE COPY OF THE REPORT DATED 9/5/2017 SUBMITTED BY THE ASSISTANT ENGINEER BEFORE THE 4TH RESPONDENT
EXHIBIT P12 A TRUE COPY OF THE REPORT DATED 9/1/2020 SUBMITTED BY THE ASSISTANT ENGINEER TO THE 4TH RESPONDENT
EXHIBIT P13 A TRUE COPY OF THE REPORT DATED 10/1/2020 SUBMITTED BY THE 3RD RESPONDENT TO THE 2ND RESPONDENT BASED ON P12
EXHIBIT P14 A TRUE COPY OF THE REPORT DATED 17/2/2020 SUBMITTED BY THE 5TH RESPONDENT TO THE 3RD RESPONDENT
EXHIBIT P15 A TRUE COPY OF THE LETTER DATED 2/6/2020 OF THE 1ST RESPONDENT ADDRESSED TO THE 2ND RESPONDENT
EXHIBIT P16 A TRUE COPY OF THE REPORT DATED 5/6/2020 SUBMITTED BEFORE THE 2ND RESPONDENT
EXHIBIT P17 A TRUE COPY OF THE REPORT DATED 8/6/2020 SUBMITTED BY THE 3RD RESPONDENT 2ND RESPONDENT
RESPONDENTS' EXHIBITS
ANNEXURE R1(a) TRUE COPY OF THE ORDER DATED 06.01.2021.
ncd
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!