Citation : 2021 Latest Caselaw 8827 Ker
Judgement Date : 17 March, 2021
WP(C).No.28805 OF 2019(A)
1
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE SMT. JUSTICE P.V.ASHA
WEDNESDAY, THE 17TH DAY OF MARCH 2021 / 26TH PHALGUNA, 1942
WP(C).No.28805 OF 2019(A)
PETITIONER/S:
KERALA STATE INDUSTRIAL ENTERPRISES LTD.
ST.JOSEPH'S PRESS BUILDING COTTON HILL,
THIRUVANANTHAPURAM-695014, KERALA, REPRESENTED BY
ITS GENERAL MANAGER, MR.JAYARAJ.P.V.
BY ADVS.
SRI.M.GOPIKRISHNAN NAMBIAR
SRI.K.JOHN MATHAI
SRI.JOSON MANAVALAN
SRI.KURYAN THOMAS
SRI.PAULOSE C. ABRAHAM
JAIMOHAN
RESPONDENT/S:
1 AIRPORTS AUTHORITY OF INDIA,
REPRESENTED BY ITS AIRPORT DIRECTOR, TRIVANDRUM
INTERNATIONAL AIRPORT, THIRUVANANTHAPURAM-695008,
KERALA.
2 AIRPORT DIRECTOR,
AIRPORTS AUTHORITY OF INDIA, TRIVANDRUM
INTERNATIONAL AIRPORT, THIRUVANANTHAPURAM-695008,
KERALA.
R1-2 BY ADV. SRI.V.SANTHARAM
R1-2 BY ADV. SRI.LAKSHMEESH.S.KAMATH
THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON
03.03.2021, THE COURT ON 17.03.2021 DELIVERED THE FOLLOWING:
W.P.(C) No.28805 of 2019
P.V.ASHA, J.
---------------------------------
W.P.(C) No.28805 of 2019
----------------------------------
Dated this the 17th day of March, 2021.
JUDGMENT
The Kerala State Industrial Enterprises Limited has
filed this Writ Petition aggrieved by the enhancement of
license fee for the Air Cargo Complex ordered by the
respondents.
2. As per Ext.P1 Government Order dated 30.04.1979
Government of Kerala declared that the petitioner would be
the agency for running the Air Cargo Complex in the State.
The said order was issued in implementation of the policy
decision of the Govt. of India to set up "Integrated Air
Cargo Complexes" in each State. The Government decided to
establish the same at Thiruvananthapuram. It is stated that
thereafter the petitioner extended its operation to the
Airports at Kochi and Kozhikkode in 1985 and 1998
respectively. Pursuant to Ext.P1 order petitioner and 2nd
respondent entered into Ext.P2 agreement on 01.10.1997 and
license was granted to the petitioner for using the plot of
land having an extent of 3505 sq.mtr referred to therein
for a period of 5 years from 06.03.1997 to 05.03.2002 for W.P.(C) No.28805 of 2019
the purpose of cargo activities. The license fee payable
was fixed as Rs.1,99,785/- in each year which should be
paid in advance. The said fee was subject to revision by
the authority at an interval of every three years or as
approved by the board of International Airports Authority
of India from time to time. The license agreement continued
to be extended from time to time. As per Ext.P3 agreement,
the period of license was extended from 07.10.2010 to
31.03.2012 and the license fee was enhanced to Rs.173.50 sq
mtr and thereafter as per Ext.P4 communication dated
01.04.2014 to Rs.243/- per sq.mtr per annum for the period
from 01.04.2014.Immediately thereafter the license fee was
again enhanced to Rs.1,360/- per sq.mtr per annum as per
Ext.P5 letter dt.27.01.2015. It is stated that as per
Ext.P6 letter dated 25.03.2019 the Minister for Industries
and Information Technology, Govt. of Kerala wrote to the
Minister for Civil Aviation, Govt. of India requesting its
intervention in the matter and seeking exemption from
paying the enhanced license fee for unpaved land occupied
by it. But as per Ext.P7 letter dated 19.06.2015 the
petitioner was informed by the respondents that they have
adopted a transparent process and methodology and revised
land license fee base rate based on the current Government W.P.(C) No.28805 of 2019
circle rate/ready reckoner rate applicable at various
airports. The Government circle rate/ready reckoner rates
all over the country have increased manifold due to
revaluation/reassessment of land cost by the Government in
view of steep hike of rental value in open market and after
considering various aspects. It is further stated that the
revision of base rate was worked out and decided for
implementation after a period of 6 years. It was stated
that the revised license fee with effect from 01.10.2014 is
uniformly applicable to all concessioners at the airports.
Correspondence between the Ministers of the State and
Centre continued even thereafter as seen from Ext.P8
letter. As per Ext.P9 letter the petitioner had taken up
the matter with the Government requesting for intervention
in the matter for waiver of the enhanced license fee. In
Ext.P10 letter dated 05.07.2018 the respondents again
enhanced the license fee to Rs.1,575/- per sq.mtr. per
annum. In this letter it was stated that the normal
applicable license fee would be the base for considering
any concession to Government agencies or other agencies as
per policy of AAI irrespective of the location of allotted
site and 50% of the normal rate of license fee/land rent
for the years from 2018-19 to 2021-22 are applicable for W.P.(C) No.28805 of 2019
the land allotted to Government agencies including Defence
at Trivandrum Airport. Thereupon the petitioner requested
for 50% concession applicable to Government agency as per
Ext.P11 letter dated 10.08.2018. In Ext.P7 letter the
petitioner stated that in the light of Ext.P1 Govt. order
it is a Government agency and hence eligible for 50%
concession. Petitioner had also taken up the matter with
the Govt. as per Ext.P12 letter requesting to take up the
matter with the respondents for reduction in license fee
pointing out that it is a 100% Govt. agency to look after
the cargo operations. But as per Ext.P13 letter dated
26.10.2018 the respondents rejected the request stating
that concession is not extended to PSUs of Central
Government or State Government. Though the matter was
taken up by the Government in Ext.P14 letter stating that
petitioner is the Kerala Government Agency running the Air
Cargo Operations and requesting to extend 50% reduction in
the license fee, as per Ext.P14(a) letter dated 17.01.2019
that request was also rejected stating that the concession
is not extended to PSUs of Central Govt. as well as State
Govt. and stating that petitioner is a Limited company, an
agency appointed by the Govt. of Kerala for running the Air
Cargoes which are not eligible for reduction in lease W.P.(C) No.28805 of 2019
rentals. It was stated that as per AAI Policy Guidelines
AAI allots land to Central Government Departments/State
Government(wholly owned by Central/State Government) for
performing their mandatory/regulatory functions who are
charged 50% of the normal license fee rate. The respondents
started issuing demand notices Ext.P15, P16, P16(a) and P17
requesting to clear the arrears. The Writ Petition was
filed thereafter at this stage challenging Ext.P5 order
dated 27.01.2015, Ext.P13, Ext.P15 and P17 letters and for
a direction to the respondents to reinstate the rate of
lease rate at Rs.243/- per sq.mtr with periodic escalation
at 7.5% and also for a direction to extent the benefit of
concessional license fee as available to Govt. agencies to
the petitioner.
3. According to the petitioner the license fee was
enhanced unilaterally as per Ext.P5 order dated 27.01.2015.
It is alleged that the respondents ought to have enhanced
the fee only in case it was accepted by the petitioner and
unilateral increase of license fee is not contemplated in
the agreement executed between the parties. Petitioner also
pointed out that the charges at various airports for cargo
handling are different and the revenue handled by the
airports are not comparable. It is also alleged that the W.P.(C) No.28805 of 2019
denial of 50% concession to the petitioner is arbitrary and
petitioner is entitled to the concession as it is a
Government agency.
4. The respondents have filed a counter affidavit. They
have raised a preliminary objection as to the
maintainability of the Writ Petition stating that it is
highly belated. It is stated that Ext.P5 enhancement was
made as early as in January 2015 and the same was given
effect from 01.10.2014. Their further contention is that the
challenge in the Writ Petition is against contractual
obligations and there is no statutory contract between the
petitioner and the respondents. It is pointed out that as
far as there is no allegation as to the violation of
statutory provisions the remedy under Article 226 would not
be available to the petitioner, even if there is any
violation of any contractual terms. It is further stated
that the license agreement itself, the full text of which is
produced as per Ext.R2(a) provides for a mechanism when
there is breach of any contractual obligations. It is stated
that the allotment letter and license agreement provide for
the license fee payable and also that the same would be
subject to revision by the authority at an interval of every
three years or at such intervals as may be approved by the W.P.(C) No.28805 of 2019
Board of AAI from time to time. It is stated that the
licensee agreed to pay revised license fee without any
protest on the basis of the agreements executed and
extended. It is stated that the area given in license is
having an extent of 3185 sq.mtr as found in the joint
measurement. It is stated that the license fee for the year
2010-11 to 2013-14 was Rs.180, Rs.195, Rs.210 and Rs.226 per
sq.mtr per annum. It was enhanced to Rs.243/- per sq.mtr per
annum from 01.04.2014 to 30.09.2014 in 2014-15. It was
revised to Rs.1,360 per sq.mtr per annum w.e.f. 01.10.2014
to 31.03.2015. It is stated that the petitioner has not been
paying the land rent as per the revised rates of license fee
w.e.f. 01.10.2014, revised as per Ext.R2(f) circular dated
20.10.2014 and R2(g) circular dt.04.12.2017. It is stated
that the present rate of license fee for unpaved land
allotted to the petitioner was Rs.1,575/- from 01.04.2017
onwards and it is frozen for the next 5 years from
01.04.2017 to 31.03.2022. It is stated that the rates are
fixed by the CHQ of AAI after consideration of various
aspects and it cannot be fixed on mutual agreements between
the parties. The Chairman of AAI had already informed the
Government Secretary that the revision of license fee was in
order. The AAI had adopted transparent process and W.P.(C) No.28805 of 2019
methodology on the basis of the current Government circle
rate/ready reckonable rates applicable at various airports.
The rates had increased manifold due to re-
valuable/reassessment of land cost by the Government in view
of steep hike in rental value in open market and after
considering factors like inflation, devaluation of currency,
more demand of land due to commercialization, expansion of
cities etc which necessitated revision in base rate and the
rate was worked out and decided for implementation after a
period of six years and said rate is uniformly applicable to
all.
5. It is stated that the petitioner has to pay
licence fee at normal rates plus service tax as applicable
at Trivandrum Airport. The licence fees raised are subject
to revision and yearly escalation as decided by the Airport
Authority of India from time to time. According to the
respondents, it is not necessary to obtain the acceptance
of licencee for implementation of revision of licence fee
as it is covered by the allotment letters as well as the
agreement between the two parties. It is stated that all
other PSUs across the country are paying the licence fee at
the revised rates implemented w.e.f 01.10.2014 in Ext.R2(f)
and as revised subsequently as per Ext.R2(g) w.e.f W.P.(C) No.28805 of 2019
01.04.2017. The land allotted to the Central Govt./State
Govt. alone would be granted 50% concession and the same is
not extended to PSUs.
6. Heard the learned counsel on either side.
7. The learned counsel for the petitioner argued that
even in contractual matters if the respondents are acting
arbitrarily, this Court under Article 226 can interfere
relying on the judgment dt.20.12.2019 in W.P.
(c).No.19414/2008 and the judgment of the Delhi High Court
reported in C.P.Mittal v. Union of India & Anr. [2007 SCC
OnLine Del 1185]. The learned counsel for the petitioner
argued that there is no automatic ban against entertaining
Writ Petitions under Article 226 of the Constitution of
India in case substantial elements of public law are
available.
8. The learned counsel for the respondents, relying on
the judgments of the Apex Court in Delhi Science Forum v.
Union of India [(1996) 2 SCC 405], Peerless General Finance
and Investment Co. Limited v. Reserve Bank of India [(1992)
2 SCC 343], Kerala State Electricity Board v. Kurien E.
Kalathil [(2000) 6 SCC 293], Pimpri Chinchwad Municipal
Corpn. v. Gayatri Construction Co. [(2008) 8 SCC 172],
Joshi Technologies International Inc. v. Union of India & W.P.(C) No.28805 of 2019
Ors. [(2015) 7 SCC 728], Rajasthan State Industrial
Development & Investment Corpn. v. Diamond & Gem
Development Corpn. Ltd. [(2013) 5 SCC 470] and Gujarat
Maritime Board v. Larsen and Toubro Infrastructure
Development Projects Limited & Anr. [(2016) 10 SCC 46]
argued that policy decisions of the Government including
economic policy are not liable to be interfered with under
Article 226 of the Constitution of India as also the
dispute relating to the terms of the contract with
statutory body are not liable to be interfered with.
9. One of the contentions raised by the respondent is
that there is huge delay on the part of the respondents in
challenging the orders against the petitioner, pointing out
the date on which Ext.P5 was issued. It is relevant to note
that immediately after the escalation as per Ext.P5 order,
there had been correspondence between the Ministers of the
State and Centre; petitioner and respondents; State and
Centre; State and respondents. Petitioner is an agency
under the State Government and 1st respondent is an agency
under the Central Government. The delay occurred in filing
the writ petition by and between such parties cannot
therefore non-suit the petitioner when it is seen that
there was an attempt going on for an amicable solution. W.P.(C) No.28805 of 2019
Therefore, I find that the objection raised by the
respondents with respect to delay is unsustainable.
10. The next contention of the respondents is on
judicial review in matters of contract. It is true that
Clause 3 of Ext.P2 provides for revision of licence fee at
an interval of 3 years or at such intervals as may be
approved by the Board of International Airports Authority
of India from time to time. It also provides for payment of
such license fee by the licensee without protest. According
to the respondents, when there is any such dispute, the
petitioner has to resort to arbitration, as provided in
Clause 35 of Ext.P2 agreement. But according to the
petitioner when the escalation by way of revision is by
500%, the same amounts to arbitrariness and in such
circumstances this court can interfere even in contractual
matters. In this context it is necessary to have a look at
the judgments relied on by the learned Counsel for the
petitioner. In the judgment of the Madras High Court in V.
Krishnamoorthi V AAI in W.P.No.19414 of 2008 the issue
considered was one and the same. There the respondent
granted license to petitioner therein for running a coach
service/car service. There the challenge was against
circular issued in 2008, by which the license fee was W.P.(C) No.28805 of 2019
enhanced by 5 times. Despite the availability of a
provision for arbitration, the contention of the petitioner
that the enhancement was arbitrary and violative of
principles of natural justice was accepted. The contentions
raised by respondents as to the availability of a clause
for arbitration; writ will lie in contractual matters, etc
as raised in this writ petition were repelled. Relying on
the judgment in (2004) 3 SCC 214, it was held that the
respondents being instrumentalities of State, ought to have
acted fairly and reasonably. It is the very same respondent
which has enhanced the license fee in this case also.
11. Similar was the finding in the judgment of the
Delhi High Court in C.P.Mittal's case (supra) where the
allottees of Public Call Offices challenged the action of
the Northern Railway in demanded enhancement of commission
from 10% to 102 to 150%, under the guise of policy
decision. It was found that the action of a public utility
service provider has caused immense injury to the licensees
who were allotted PCOs in furtherance of welfare policies
and therefore writ petition will lie under Article 226 of
the Constitution of India and the enhancement was set
aside.
12. In this context it is relevant to have a look at W.P.(C) No.28805 of 2019
the judgments relied on by the learned Counsel for the
respondent. In the judgment in Kurien E. Kalathil's case
the apex court held that disputes arising out of contracts
have to be settled in accordance with the contract and that
contractual activities of a statutory body need not involve
issues of public law. In Diamond & Gem Development &
Investment Companies' case (supra) the dispute was with a
private company and Rajastan State Industrial Development &
Invest Corporation, which had allotted land to the Diamond
& Gem Corporation for establishment of Gem Industrial
estate and executed lease deed for completing the project
within 5 years. Cancellation of allotment was challenged.
The Apex Court found that cancellation was under the Rules
as well as in terms of the lease and found that it could
have resorted to arbitration clause. In that judgment also
the apex court held that court should not exercise its writ
jurisdiction to enforce contractual obligations. It was
also held that discretion must be exercised by the court on
grounds of public policy, public interest and public good.
In Joshy Technologies case(supra) the Apex Court summarised
the circumstances under which the High Court should not
normally exercise its discretion, in para 69 of the
judgment as follows:
W.P.(C) No.28805 of 2019
69.1. The Court may not examine the issue unless the action has some public law character attached to it. 69.2. Whenever a particular mode of settlement of dispute is provided in the contract, the High Court would refuse to exercise its discretion under Article 226 of the Constitution and relegate the party to the said mode of settlement, particularly when settlement of disputes is to be resorted to through the means of arbitration.
69.3. If there are very serious disputed questions of fact which are of complex nature and require oral evidence for their determination.
69.4. Money claims per se particularly arising out of contractual obligations are normally not to be entertained except in exceptional circumstances.
13. The very same principles were reiterated in the
judgment in Gujarat Maritime Board v. Larsen and Toubro
Infrastructure Development Projects Limited & Anr: [(2016)
10 SCC 46] also.
14. Thus it is well settled that whenever there is a
provision for arbitration the parties shall resort to it.
However it is pertinent to note that there is no factual
disputes and the petitioner does not want to enforce any
provision in the contract. In this case parties on either
side are agencies under State Government and Central
Government. There is a provision for 50% concession. It
appears that the said concession is not referred to in the
agreement executed between the petitioner and 1st
respondent. The request of petitioner is rejected saying
that the enhancement is based on policy decision. In the
judgments in Peerless's case or in Delhi Science Forum's W.P.(C) No.28805 of 2019
case, relied on by the learned Counsel for the respondents
it is held that the courts are not supposed to sit in
judgment over matters of economic policy and that it should
be left to the experts in the field. Both those judgments
do not appear to have been rendered in a case where the
dispute was between the agencies under the two Governments.
Therefore the question whether the petitioner would be
eligible for concession @ 50% as mentioned in Ext.P10
requires emergent consideration/reconsideration.
15. The respondents have stated that the concession is
admissible only for those Government agencies, directly and
fully controlled by the Government. Ext.P1 order would
show that the petitioner was appointed as the agency of the
Government of Kerala for running Air Cargo Complex. The
said decision is taken pursuant to the policy decision of
the Government of India to set up integrated Air cargo
complexes in each State. Based on the said policy decision,
the State Government has after undertaking a traffic survey
and on a finding that Air cargo potential of the State is
promising, declared that the petitioner would be the agency
for running the complex. In Ext.P10 the respondents have
stated as follows :
"xxxx xxxx xxxx xxxx xxxx xxxx
W.P.(C) No.28805 of 2019
xxxx xxxx
As per point No.2d) of the AAI, CHQ's letter
mentioned as above, normal applicable licence fee will be the BASE for considering any concession to Govt. Agencies and/or other agencies as per policy of AAI, irrespective of the location of allotted sites. Hence, 50% of the normal rate of licence fee/land rent for the years from 2018-19 to 2021-22 (i.e 50% of Rs.1,895/- per sqm/annum for paved land and 50% of Rs.1,575/- per sqm/annum for unpaved land) are applicable for the land allotted to Govt. Agencies including Defence at Trivandrum Airport.
xxxx xxxx xxxx"
Thus the 50% concession was ordered for the land allotted
to Government agencies. That would mean that if the air
cargo is under a government department 50% concession would
be available. In the present case there is no separate
claim for State Government. It is evident from Ext.P1 that
the the petitioner is acting on behalf of the Government of
Kerala in implementation of the policy decision of the
Government of India to set up integrated cargo complexes,
which could only be a public purpose. Therefore whatever
benefit is admissible to the Government of Kerala should be
granted to the petitioner. Correspondence had been going on
between the Ministers of the State of Kerala and the Centre
on the enhanced rate of license fee ever since its W.P.(C) No.28805 of 2019
enhancement. Though the respondents have stated that Govt.
agency means agency which is fully controlled by the
Government and that PSUs would not come within the said
definition, nothing is seen in the orders to that effect.
Therefore, to that extent I am of the view that the matter
requires reconsideration by the respondents. Therefore,
even without going into the arbitrariness in the escalation
or the agreement executed between the parties, it is seen
that a reconsideration is required at the end of the
respondents as to the admissibility of concession to the
extent of 50% to the petitioner. A decision shall be taken
afresh in this matter after affording an opportunity of
hearing to the petitioner as well as the State Government
within a period of three months from the date of receipt of
a copy of the judgment. Till a decision is taken the
respondents shall not initiate any coercive action against
the petitioner.
The Writ Petition is disposed as above.
Sd/-
P.V.ASHA
rkc JUDGE
WP(C).No.28805 OF 2019(A)
APPENDIX
PETITIONER'S/S EXHIBITS:
EXHIBIT P1 TRUE COPY OF THE ORDER DATED 30.4.1979
ISSUED BY THE GOVT. OF KERALA BEARING
NO.GO.MS.NO.215/79/ID TO THE PETITIONER.
EXHIBIT P2 TRUE COPY AGREEMENT DATED 1.10.1997 EXECUTED BETWEEN THE PETITIONER AND THE 1ST RESPONDENT.
EXHIBIT P3 TRUE COPY OF THE AGREEMENT DATED 26.3.2012 EXECUTED BETWEEN THE PETITIONER AND THE 1ST RESPONDENT.
EXHIBIT P4 TRUE COPY OF THE COMMUNICATION ISSUED BY THE 1ST RESPONDENT DATED 1.4.2014 TO ALL AIRLINES.
EXHIBIT P5 TRUE COPY OF THE LETTER DATED 27.1.2015 ISSUED BY THE 1ST RESPONDENT TO THE PETITIONER.
EXHIBIT P6 TRUE COPY OF THE LETTER DATED 25.3.2015 BEARING NO.20/15/M(IND.&IT) SENT BY THE HON'BLE MINISTER FOR INDUSTRIES AND INFORMATION TECHNOLOGY, GOVT. OF KERALA TO THE HON'BLE MINISTER FOR CIVIL AVIATION, GOVT. OF INDIA.
EXHIBIT P7 TRUE COPY OF THE LETTER DATED 19.6.2015 SENT BY THE CHAIRMAN OF THE 1ST RESPONDENT WROTE TO THE PRINCIPAL SECRETARY TO THE GOVERNMENT.
EXHIBIT P8 TRUE COPY OF THE LETTER DATED 2.7.2015 SENT BY THE HON'BLE CHIEF MINISTER, GOVT. OF KERALA TO THE HON'BLE MINISTER FOR CIVIL AVIATION, GOVT. OF INDIA.
EXHIBIT P9 TRUE COPY OF THE LETTER DATED 18.12.2017 ISSUED BY THE PETITIONER TO THE ADDITIONAL CHIEF SECRETARY, INDUSTRIES DEPARTMENT, GOVT. OF KERALA.
EXHIBIT P10 TRUE COPY OF THE LETTER DATED 5.7.2018
ISSUED BY THE 1ST RESPONDENT TO THE
PETITIONER.
EXHIBIT P11 TRUE COPY OF THE LETTER DATED 10.8.2018
WP(C).No.28805 OF 2019(A)
ISSUED BY THE PETITIONER TO THE CHAIRMAN OF THE 1ST RESPONDENT.
EXHIBIT P12 TRUE COPY OF THE LETTER DATED 17.9.2018 ISSUED BY THE PETITIONER TO THE PRINCIPAL SECRETARY TO THE GOVT., INDUSTRIES DEPARTMENT, GOVT. OF KERALA.
EXHIBIT P13 TRUE COPY OF THE LETTER DATED 26.10.2018 ISSUED BY THE 1ST RESPONDENT TO THE PETITIONER.
EXHIBIT P14 TRUE COPY OF THE LETTER BEARING DO NO.123/PS/IND, GAD & NORKA DATED 15.11.2018 ISSUED BY THE PRINCIPAL SECRETARY TO THE GOVT., INDUSTRIES DEPARTMENT, GOVT. OF KERALA TO THE CHAIRMAN OF THE 1ST RESPONDENT.
EXHIBIT P14A TRUE COPY OF THE LETTER DATED 17.1.2019 BEARING NO.ED/CARGO/1360/TRV/CUDCT/2018 ISSUED BY AAI CARGO LOGISTICS & ALLIED SERVICES COMPANY LTD. TO THE PRINCIPAL SECRETARY, GOVT. OF KERALA.
EXHIBIT P15 TRUE COPY OF THE LETTER DATED 7.2.2019
ISSUED BY THE 1ST RESPONDENT TO THE
PETITIONER.
EXHIBIT P16 TRUE COPY OF THE LETTER DATED 19.2.2019
ISSUED BY THE CHIEF EXECUTIVE OFFICER OF AAI CARGO LOGISTICS & ALLIED SERVICES COMPANY LTD., A SUBSIDIARY OF THE 1ST RESPONDENT, TO THE PRINCIPAL SECRETARY TO THE GOVT., INDUSTRIES DEPARTMENT, GOVT. OF KERALA.
EXHIBIT P16A TRUE COPY OF THE LETTER DATED 13.3.2019 ISSUED BY THE 1ST RESPONDENT TO THE PETITIONER.
EXHIBIT P17 TRUE COPY OF THE LETTER DATED 13.3.2019 ISSUED BY THE 1ST RESPONDENT TO THE PETITIONER.
RESPONDENT'S/S EXHIBITS:
EXHIBIT R2 A TRUE COPY OF THE LICENCE AGREEMENT DATED 26.3.2012, ALONG WITH ANNEXURE A1 AND AWARD LETTER DATED 16.2.2012.
EXHIBIT R2 B TRUE COPY OF THE LETTER NO-
WP(C).No.28805 OF 2019(A)
AAT/COM/6(21)/96/933/9590 DATED 12.8.1996
EXHIBIT R2 C TRUE COPY OF THE LETTER NO-AAT/LM/KSIE DATED 16.2.2012.
EXHIBIT R2 D TRUE COPY OF THE LETTER NO-AAT/LM-
35/LA/KSIE 2012 DATED 16.11.2012.
EXHIBIT R2 E TRUE COPY OF THE LETTER NO-AAT/LM-
35/LA/KSIE/2012/577 DATED 13.12.2012.
EXHIBIT R2 F TRUE COPY OF THE CIRCULAR NO-
AV.21012/20/2014-LM DATED 20.10.2014 ISSUED BY THE CHQ OF AAI.
EXHIBIT R2 G TRUE COPY OF THE CIRCULAR NO-
AV.21012/58/2016-LM/710 DATED 4.12.2017 ISSUED BY THE CHQ OF AAI.
EXHIBIT R2 H TRUE COPY OF THE LICENCE AGREEMENT DATED 1.10.1997 EXECUTED BETWEEN THE AAI AND KSIE.
EXHIBIT R2 I TRUE COPY OF THE LETTER D.O.NO-
ED/CARGO/1360/TRV/2019 482 DATED 4.4.2019
EXHIBIT R2 J TRUE COPY OF THE LETTER NO-AAI/F&A/ CARGO/2018-19/F&A/6186 DATED 18.9.2018
EXHIBIT R2 K TRUE COPY OF THE LETTER NO-
AAI/F&A/CARGO/2018-19 DATED 7.8.2018
EXHIBIT R2 I TRUE COPY OF THE LETTER NO-
AAI/F&A/CARGO/2018-19 19/1819/445 DATED 7.8.2018.
EXHIBIT R2 M TRUE COPY OF THE INTERIM ORDER DATED 28.5.2015 PASSED BY THE HON'BLE HIGH COURT IN WPC NO-2491 OF 2015.
EXHIBIT R2 N TRUE COPY OF THE LETTER NO-
AAT/LM/CIRCULAR/2018/180 DATED 5.7.2018 ADDRESSED TO AII AIRLINES /AGENCIES/OIL COMPANIES/GOVERNMENT DEPARTMENTS.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!