Citation : 2021 Latest Caselaw 8802 Ker
Judgement Date : 17 March, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE RAJA VIJAYARAGHAVAN V
WEDNESDAY, THE 17TH DAY OF MARCH 2021 / 26TH PHALGUNA, 1942
WP(C).No.732 OF 2020(N)
PETITIONER:
BINU AND COMPANY,
PEZHUMTHURUTH, PERUMON P.O., KOLLAM - 691 601,
REPRESENTED BY ITS PROPRIETOR S.S.BINU.
BY ADVS.
SRI.S.SREEKUMAR (SR.)
SRI.P.MARTIN JOSE
SRI.P.PRIJITH
SRI.THOMAS P.KURUVILLA
SRI.AJAY BEN JOSE
SRI.MANJUNATH MENON
SHRI.HARIKRISHNAN S.
RESPONDENTS:
1 THE DISTRICT COLLECTOR,
KOLLAM, DISTRICT COLLECTOR OFFICE, CIVIL STATION,
KOLLAM - 691 013.
2 TAHASILDAR/AUTHORIZED OFFICER (REVENUE RECOVERY),
TALUK KACHERY, KOLLAM - 691 001.
3 KERALA STATE ROAD TRANSPORT CORPORATION,
TRANSPORT BHAVAN, FORT, THIRUVANANTHAPURAM,
PIN - 695 023, REP. BY ITS CHAIRMAN
AND MANAGING DIRECTOR.
4 THE CHAIRMAN AND MANAGING DIRECTOR,
KERALA STATE ROAD TRANSPORT CORPORATION, TRANSPORT
BHAVAN, FORT, THIRUVANANTHAPURAM, PIN - 695 023.
R3 & R4 BY ADV. SRI.P.C.CHACKO(PARATHANAM)
SMT MABLE C KURIAN, GP
THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON
17.03.2021, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
WP(C).No.732 OF 2020(N) 2
JUDGMENT
Instant petition is filed challenging Exts P12 and P13 notices issued
under Section 7 and 34 of the Revenue Recovery Act,1968 and also for a
further direction to quash Ext.P19 notice issued by the 4th respondent calling
upon the petitioner to make payment of a sum of Rs.38,79,447/- towards
loss sustained to the 3rd respondent, the Kerala State Road Transport
Corporation (KSRTC).
2. The facts which led to the challenge raised as aforesaid can be
briefly stated at the outset itself.
In the year 2013, the 3rd respondent invited a tender for the supply
of ER WCR tubes of different dimensions and sizes. The petitioner submitted
his tender which was accepted by the 4th respondent and Ext.P1 supply
order was issued. Ext.R3(c) is the agreement entered into between the
petitioner and the 3rd respondent on the basis of which, 8520 tubes
weighing a total of 55,640 kgs was supplied to the 3rd respondent.
Immediately thereafter, Ext.P3 notice was issued informing the petitioner
that out of the total number of 4034 pipes supplied by him weighing about
27230 kgs, 225 pipes were found to be damaged. The petitioner was called
upon to replace 225 pipes or to refund the value. On receipt of the said
communication, Ext.P4 letter was issued by the petitioner informing of his
willingness to refund the value of 225 pipes. However, without responding
to the said letter, Ext.P5 letter was issued calling upon the petitioner herein
to replace 40,279 Kgs of tubes. In response, the petitioner issued Ext.P6
informing that his liability was limited to the value of 725 pipes weighing
about 4865 kgs and worth Rs.2,85,040/-. However, the 4th respondent by
Ext.P7 notice called upon the petitioner to pay a sum of Rs.20,64,946/-
being the value of damaged pipes. He submitted Ext.P8 explanation and
offered his willingness to return a sum of Rs.71,046/- being the balance
amount after adjusting the loss suffered to respondent Nos.3 and 4 from the
security amount deposited by the petitioner. Thereafter, Ext.P10 notice was
issued on 31.12.2014 warning the petitioner that he would be blacklisted if
he failed to pay the amount detailed in Ext.P7. In response, Ext.P11 notice
was issued by the petitioner requesting that he may not be blacklisted and
seeking to reconsider the entire disputes. Immediately thereafter, contending
that the respondents have failed to consider the petitioner's explanation
before blacklisting the concern, W.P.(C) No.7909 of 2015 was preferred
before this Court. While the Writ Petition was pending, proceedings under
the Revenue Recovery Act was initiated and the impugned notices were
issued. When this matter was brought to the notice of the learned Single
Judge, by Ext.P15 judgment dated 13.12.2019, the matter was disposed of
ordering a joint inspection with the hope that the parties would be able to
amicably resolve the dispute. Pursuant to the judgment, a joint inspection
was conducted and Ext. R3(i) is the report. On the side of the petitioner, an
expert Engineer was also present. The expert Engineer prepared Ext.P18,
consolidated report, a copy of which was forwarded to the respondents. The
expert Engineer had opined that the unilateral act on the part of the
respondents in rejecting the quality of pipes supplied by the petitioner was
not governed by their quality or usefulness but rather was a result of the
selective whims and fancies of certain officials who were swayed by
extraneous considerations and instigations. The expert also opined that
rejection of pipes was done with the sole aim to harass, discredit and to
cause pecuniary loss to the petitioner. The petitioner states that the 4th
respondent without considering the consolidated report submitted by the
expert Engineer, issued Ext.P19 demand notice demanding a sum of
Rs.38,79,447/- being the alleged loss sustained by the Corporation. The
initiation of revenue recovery proceedings and also the issuance of Ext.P19
time barred notice pursuant to the joint inspection conducted by the parties
are under challenge in this writ petition.
3. In the counter affidavit filed by the respondents 3 and 4, it is
contended that the petitioner had agreed while executing Ext.R3(c)
agreement that the goods supplied by him shall be of the best quality and
workmanship. However, on inspection, it was found that the goods supplied
did not match the assurance given by the petitioner. It is stated that if
during the period of 12 months from the date of supply of the goods, it was
found that the goods did not conform to the description and quality, the
Corporation was entitled to reject the goods. It is further stated that the
work managers from various depots had reported that the goods did not
conform to the specifications and it was in the said circumstances that the
petitioner was asked to take back the goods or to pay the value. The split up
details of the damaged pipes were given to the petitioner and he had also
agreed to reimburse the value of a certain quantity. According to the
respondents 3 and 4, pursuant to the joint inspection ordered by this Court,
an inspection was conducted and it was found that the total value of
defective materials together with interest after deducting the amounts paid
by way of security was Rs.39,79,447/- as on 28.1.2020. It is contended that
the petitioner cannot claim that Ext.P19 notice is time barred as it was issued
pursuant to the joint inspection ordered by this Court.
4. I have considered the submissions advanced.
5. The dispute between the parties is with regard to the quality of
pipes supplied by the petitioner pursuant to Ext.P1 supply order and
Ext.R3(c) agreement entered into between the parties on 10.12.2013. The
sole question is whether one of the contracting parties can say that the other
party is a defaulter and quantify the damages and recover the same by
recourse to proceedings under the Revenue Recovery Act. The petitioner
has seriously disputed that he is a defaulter. He disputes the very liability to
pay the amount determined by the respondents 3 and 4. It has to be borne
in mind that during the earlier round of litigation, this Court after taking note
of the nature of dispute, and the initiation of revenue recovery proceedings,
had ordered a joint inspection of the materials to make an attempt to resolve
the dispute. However, it appears that the rift has widened and the
respondents 3 and 4 have come up with Ext.P19 demand notice wherein
their demand was for a sum of Rs.38,79,447/- being the loss sustained to
the Corporation due to the supply of low quality of materials by the
petitioner herein. The petitioner relies on a report of the expert Engineer,
whose services were sought by him during the joint inspection. In the
report, some scathing remarks are made by the expert Engineer.
6. It is by now settled that it is not within the province of one of
the contracting parties to decide as to who is in breach and fix the quantum.
This is not one of those cases where the defaulting party admits that he is in
default and agrees to pay a liquidated sum by way of damages to the party
who is not in breach.
7. In the case on hand, the 3rd respondent is one of the
contracting parties and by issuing Ext.P19, they are seeking to realize a sum
of Rs. 38,79,447/- towards the alleged loss sustained to the 3rd respondent.
When the petitioner disputes the liability and when he contends that he is
being victimized by the officers of the Corporation, the 4th respondent
cannot be a Judge on his own cause and cannot be its own arbiter to
determine the liability and quantum of damages.
8. The Apex Court in State of Karnataka v. Rameshwara Rice
Mills, Thirthahalli1 had occasion to lay down the principles in the following
lines:
"The terms of Clause.12 do not afford scope for a liberal construction being made regarding the powers of the Deputy Commissioner to adjudicate upon a disputed question of breach as well as to assess the damages arising from the breach. The crucial words in Clause.12 are and for any breach of conditions set forth hereinbefore, the first party shall be liable to pay damages to the second party as may be assessed by the second party". On a plain reading of the words it is clear that the right of the second party to assess damages would arise only if the breach of conditions is admitted or if no issue is made of it. If it was the intention of the parties that the officer acting on behalf of
1 (AIR 1987 SC 1359)
the State was also entitled to adjudicate upon a dispute regarding the breach of conditions the wording of Clause.12 would have been entirely different. It cannot also be argued that a right to adjudicate upon an issue relating to a breach of conditions of the contract would flow from or is inhered in the right conferred to assess the damages arising from a breach of conditions. The power to assess damages, as painted out by the Full Bench, is a subsidiary and consequential power and not the primary power. Even assuming for argument's sake that the terms of Clause.12 afford scope for being construed as empowering the officer of the state to decide upon the question of breach as well as assess the quantum of damages, we do not think that adjudication by the officer regarding the breach of the contract can be sustained under law because a party to the agreement cannot be an arbiter in his own cause. Interests of justice and equity require that where a party to a contract disputes the committing of any breach of conditions the adjudication should be by an independent person or body and not by the other party to the contract. The position will, however, be different where there is no dispute or there is consensus between the contracting parties regarding the breach of conditions. In such a case the Officer of the State, even though a party to the contract will be well within his rights in assessing the damages occasioned by the breach in view of the specific terms of Clause.12
9. As held by the Apex Court, interest of justice and equity require
that where a party to a contract disputes his liability, the adjudication should
be by an independent person or body and not by the other party to the
contract. The only exception is when there is a consensus between the
contracting parties with regard to breach of conditions.
10. In that view of the matter, I quash Exts.P12 and P13 as
premature. The petitioner shall reply to Ext.P19 notice. If the dispute is not
resolved to the satisfaction of the respondents 3 and 4, the matter is
required to be adjudicated in accordance with law in a court of law or by an
independent adjudicatory body in full compliance with the principles of
natural justice.
This writ petition is disposed of.
Sd/-
RAJA VIJAYARAGHAVAN V
JUDGE NS
APPENDIX PETITIONER'S EXHIBITS:
EXHIBIT P1 TRUE COPY OF SUPPLY ORDER DATED
11/10/2013 ISSUED BY THE 4TH RESPONDENT
TO THE PETITIONER.
EXHIBIT P2 TRUE COPY OF NOTE DATED 21/01/2014
PREPARED BY ASSISTANT CONTROLLER, CHIEF
STORES, PAPPANAMCODE.
EXHIBIT P3 TRUE COPY OF LETTER DATED 27/01/2014
ISSUED BY THE 3RD RESPONDENT TO THE
PETITIONER.
EXHIBIT P4 TRUE COPY OF REPLY DATED 10/02/2014
ISSUED BY THE PETITIONER TO THE 3RD
RESPONDENT.
EXHIBIT P5 TRUE COPY OF LETTER DATED 04/03/2014
ISSUED BY THE 4TH RESPONDENT TO THE
PETITIONER.
EXHIBIT P6 TRUE COPY OF EXPLANATION DATED 14/03/2014
ISSUED BY THE PETITIONER.
EXHIBIT P7 TRUE COPY OF NOTICE DATED 13/05/2014
ISSUED BY THE 4TH RESPONDENT.
EXHIBIT P8 TRUE COPY OF EXPLANATION DATED 29/05/2014
TO EXHIBIT P7 SUBMITTED BY THE
PETITIONER.
EXHIBIT P9 TRUE COPY OF LETTER DATED 20/06/2014
ISSUED BY THE REGIONAL WORKSHOP, EDAPPAL
OF RESPONDENTS 3 AND 4 TO THE PETITIONER.
EXHIBIT P10 TRUE COPY OF FINAL NOTICE DATED
31/12/2014 ISSUED BY THE 4TH RESPONDENT
TO THE PETITIONER.
EXHIBIT P11 TRUE COPY OF DETAILED EXPLANATION DATED
10/01/15 SUBMITTED BY THE PETITIONER TO
THE 4TH RESPONDENT.
EXHIBIT P12 TRUE COPY OF DEMAND NOTICE DATED
30/11/2019 UNDER SECTION 7 OF THE REVENUE
RECOVERY ACT.
EXHIBIT P13 TRUE COPY OF DEMAND NOTICE DATED
30/11/2019 UNDER 42 SECTION 34 OF THE
REVENUE RECOVERY ACT.
EXHIBIT P14 TRUE COPY OF REPLY DATED 05/12/2019 TO
EXHIBIT P12 AND P13 NOTICES.
EXHIBIT P15 TRUE COPY OF JUDGMENT DATED 13/12/2019 IN
W.P.(C) NO.7909 OF 2015 OF THIS HON'BLE
COURT.
EXHIBIT P16 TRUE COPY OF LETTER DATED 01/01/2020
ISSUED BY THE 3RD RESPONDENT TO THE
PETITIONER.
EXHIBIT P17 TRUE COPY OF LETTER DATED 06/01/2020
ISSUED BY THE PETITIONER TO EXHIBIT P16.
EXHIBIT P18 TRUE COPY OF THE CONSOLIDATED REPORT
DATED 31/01/2020 ALONG WITH COVERING
LETTER DATED 3/2/2020 ISSUED BY THE
PETITIONER
EXHIBIT P19 TRUE COPY OF THE DEMAND NOTICE DATED
28/1/2020 ISSUED BY THE 4TH RESPONDENT
RESPONDENTS EXHIBITS:
EXHIBIT R3 A TRUE COPY OF THE SHORT TENDER NOTICE
DATED 25.7.2013 ISSUED BY THE 3RD
RESPONDENT
EXHIBIT R3 B TRUE COPY OF THE PURCHASE ORDER DATED
11.10.2013 ISSUED BY THE 3RD RESPONDENT
EXHIBIT R3 C TRUE COPY OF THE AGREEMENT EXECUTED DATED
10.12.2013 BETWEEN THE PETITIONER AND 3RD
RESPONDENT
EXHIBIT R3 D TRUE COPY OF THE COMMUNICATION DATED
17.2.2014 ISSUED BY THE MECHANICAL
ENGINEER, KSRTC REGIONAL WORKS SHOP
EDAPPAL TO THE CONTROLLER OF PURCHASE AND
STORES, KSRTC THRIUVANANTHAPURAM.
EXHIBIT R3 E TRUE COPY OF THE REPORT DATED 18.2.2014
ISSUED BY THE WORKS MANAGER, REGIONAL
WORKSHOP, MAVELIKKARA TO THE CONTROLLER
OF PURCHASE AND STORES
THIRUVANANTHAPURAM.
EXHIBIT R3 F TRUE COPY OF THE REPORT DATED 17.2.2014
ISSUED BY THE WORKS MANAGER, ALUVA TO THE
EXECUTIVE DIRECTOR, VIGILANCE CHIEF
OFFICE, THIRUVANANTHAPURAM
EXHIBIT R3 G TRUE COPY OF THE REPORT DATED 15.2.2014
SENT BY THE WORKS MANAGER, REGIONAL
WORKSHOP, KOZHIKODE TO THE EXECUTIVE
DIRECTOR, VIGILANCE.
EXHIBIT R3 H TRUE COPY OF THE NOTE DATED 21.2.2014
ISSUED BY THE ASSISTANT CONTROLLER (S AND
CI) TO THE CONTROLLER OF PURCHASE AND
STORES.
EXHIBIT R3 I TRUE COPY OF THE JOINT INSPECTION REPORT
SIGNED BY THE PETITIONER AS WELL AS THE
REPRESENTATIVES OF THE 3RD RESPONDENT
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!