Citation : 2021 Latest Caselaw 7283 Ker
Judgement Date : 2 March, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE SMT. JUSTICE P.V.ASHA
TUESDAY, THE 02ND DAY OF MARCH 2021 / 11TH PHALGUNA, 1942
WP(C).No.531 OF 2021(N)
PETITIONER:
K.V. PAULOSE
AGED 67 YEARS
KUNNEL HOUSE, KARUNAGAPPALLI P.O,
KOLENCHERRY, ERNAKULAM-682311.
BY ADV. SRI.BASANT BALAJI
RESPONDENTS:
1 STATE OF KERALA
REPRESENTED BY SECRETARY TO GOVERNMENT,
WATER RESOURCES DEPARTMENT,
GOVERNMENT SECRETARIAT,
THIRUVANANTHAPURAM-695001.
2 THE CHIEF ENGINEER,
IRRIGATION DEPARTMENT, PROJECT II,
THIRUVANANTHAPURAM-695003.
3 THE SUPERINTENDING ENGINEER,
IRRIGATION DEPARTMENT, PROJECT CIRCLE,
PIRAVAM, 1ST FLOOR, IRRIGATION COMPLEX,
KOLLICKAL, MUVATUPUZHA ROAD, ERNAKULAM-686664.
4 THE EXECUTIVE ENGINEER,
IRRIGATION DEPARTMENT II P DIVISION NO I,
ANGAMALY-683573.
OTHER PRESENT:
SMT.PRINCY XAVIER, GP
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
02.03.2021, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
WP(C).No.531 OF 2021(N)
2
J U D G M E N T
Petitioner is a Contractor who had undertaken
the work of construction of main canal from ch.1000
m to 1350 m after executing an agreement on
09.09.2010. It is stated that the work was completed
2 days prior to the actual date of completion which
was fixed as 17.09.2012. It is further pointed out
that on direction of the respondents he had to
execute a supplementary agreement for certain extra
items on 28.09.2013. Even after completion of the
said work based on the supplementary agreement,
sanction is not accorded for the revised estimate
and the payment due to petitioner even on the basis
of original agreement is not made. Petitioner has
therefore filed this writ petition seeking a
direction to the respondents to obtain the sanction
for revised estimate from the Technical Sanction
Committee and for releasing the amount due to him
along with interest at the rate 12% per annum.
2. When the writ petition came up for WP(C).No.531 OF 2021(N)
consideration on 11.02.2021, seeing that the work
was completed in the year 2012, an interim order was
passed directing the Chief Engineer to place the
bill submitted by the petitioner before the
Technical Sanction Committee for taking further
action for releasing the payment due to the
petitioner.
3. Learned Government Pleader on instructions
submits that pursuant to the direction in the
interim order, the bill was placed before the
Technical Sanction Committee. It is also stated that
the proceedings for administrative sanction for
revised estimate was also submitted before the
Government. It is stated that the Executive Engineer
has already been asked to release the payment based
on the original agreement and that further payment
would be made on receipt of administrative sanction
on the revised estimate.
Therefore there shall be a direction to the
Executive Engineer-the 4 th respondent to release the WP(C).No.531 OF 2021(N)
payment due to the petitioner in accordance with the
original agreement in tune with the decision
referred to by the learned Government Pleader,
within a period of 'three weeks' from the date of
receipt of a copy of the judgment. Respondents shall
see that administrative sanction is accorded for the
revised estimate at the earliest within a period of
'one month' and to make payment due to the
petitioner based on that, without any further delay.
Though the learned counsel for the petitioner
points out that the work was executed in 2012 ahead
of time for which he is entitled even for incentive
and payment has been delayed by more than 7 years,
the said claim for interest is left open.
The writ petition is disposed of accordingly.
Sd/-
P.V.ASHA, JUDGE AS WP(C).No.531 OF 2021(N)
APPENDIX PETITIONER'S EXHIBITS:
EXHIBIT P1 TRUE COPY OF THE AGREEMENT DTD 09/09/2010 WITH THE SCHEDULE
EXHIBIT P2 TRUE COPY OF THE ACKNOWLEDGEMENT FROM OF HANDING OVER THE RIGHT TO THE PETITIONER DTD 18.9.2010
EXHIBIT P3 TRUE COPY OF THE COMPLETION CERTIFICATE ISSUED BY THE 3RD RESPONDENT DTD 28/09/2013
EXHIBIT P4 TRUE COPY OF THE INSPECTION REPORT DTD 19/07/2011 OF THE 1ST RESPONDENT
EXHIBIT P5 TRUE COPY OF THE SUPPLEMENTARY AGREEMENT WITH SCHEDULE DTD 28/09/2013 EXECUTED BETWEEN PETITIONER AND THE 3RD RESPONDENT
EXHIBIT P6 TRUE COPY OF THE LETTER DTD 28/09/2013 SEND BY THE 3RD RESPONDENT TO THE 4TH RESPONDENT ALONG WITH THE DEVIATION SANCTION STATEMENT IN FORM NO.42
EXHIBIT P7 TRUE COPY OF THE PROCEEDING ISSUED BY THE 3RD RESPONDENT DTD 12/03/2013
EXHIBIT P8 TRUE COPY OF THE LETTER DATED 25/03/2014 BY THE PUBLIC INFORMATION OFFICE TO THE PETITIONER
EXHIBIT P9 TRUE COPY OF THE LETTER DTD 29/08/2019 SEND BY THE 3RD RESPONDENT TO THE PETITIONER.
EXHIBIT P10 TRUE COPY OF THE LETTER DTD 23/10/2019 SEND BY THE 3RD RESPONDENT TO THE 2ND RESPONDENT
EXHIBIT P11 TRUE COPY OF THE JUDGMENT DTD 26/09/2014 IN WP(C)NO.18757/2014.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!