Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Abg Engineering India Pvt. ... vs State Of Kerala
2021 Latest Caselaw 10342 Ker

Citation : 2021 Latest Caselaw 10342 Ker
Judgement Date : 26 March, 2021

Kerala High Court
Abg Engineering India Pvt. ... vs State Of Kerala on 26 March, 2021
               IN THE HIGH COURT OF KERALA AT ERNAKULAM

                               PRESENT

                 THE HONOURABLE SMT. JUSTICE P.V.ASHA

     FRIDAY, THE 26TH DAY OF MARCH 2021 / 5TH CHAITHRA, 1943

                       WP(C).No.7956 OF 2021(T)


PETITIONER:

               ABG ENGINEERING INDIA PVT. LIMITED,
               CORPORATE TOWERS, ST.MARYS GROUP, MUTHOOR,
               THIRUVALLA, PATHANAMTHITTA DISTRICT, PIN-689 107,
               REPRESENTED BY ITS MANAGING DIRECTOR, MR.T.O.ALEYAS.

               BY ADVS.
               SRI.R.BINDU (SASTHAMANGALAM)
               SRI.PRASANTH M.P

RESPONDENTS:

      1        STATE OF KERALA,
               REPRESENTED BY THE ADDITIONAL CHIEF SECRETARY, WATER
               RESOURCE DEPARTMENT OF LOCAL SELF GOVERNMENT,
               GOVERNMENT OF KERALA,
               THIRUVANANTHAPURAM, PIN-695 001.

      2        THE MANAGING DIRECTOR,
               KERALA WATER AUTHORITY,
               THIRUVANANTHAPURAM, PIN-695 001.

      3        THE SUPERINTENDING ENGINEER,
               P.H.CIRCLE, KERALA WATER AUTHORITY,
               ALAPPUZHA, PIN-688 001.

      4        THE PROJECT MANAGER,
               UIDSSMT, KERALA WATER AUTHORITY,
               ALAPPUZHA, PIN-688 001.

               BY ADVS. SMT.VINITHA.B, GOVERNMENT PLEADER
                        SRI.P.BENJAMIN PAUL, SC, KWA

THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION           ON
26.03.2021, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
 WP(C).No.7956 of 2021(T)
                                  2


                             JUDGMENT

The petitioner claims that the work

of 'Replacing the old/damaged pipe line-JICA

Assisted water supply project to Cherthala

Municipality and adjoining villages-

Replacing existing GRP Raw Water

Transmission line with MS pipe at

Maravanthuruthu Panchayath and allied works

in time bound manner', was awarded to it

based on which Ext.P3 agreement was executed

on 07.02.2017.

2. It is stated that even though

petitioner started all the preliminary works

including collection of MS pipes, the

respondents were unable to get road cutting

permission and there had been heavy public

protest. Because of all these, petitioner

could not commence the work in November, WP(C).No.7956 of 2021(T)

2017, and complete the work in time.

3. It is stated that in view of the

delay, petitioner requested for hike in the

rates and as there was no fruitful results,

petitioner decided to give up the work and

submitted Ext.P10 representation for

foreclosure on 18.11.2020. It is stated that

Ext.P10 was followed by Ext.P11

representation. According to the petitioner,

it will not be possible for him to complete

the work at the same rates.

As the learned counsel for the

petitioner submitted that petitioner would

be satisfied with a direction to the 3 rd

respondent to consider Ext.P10

representation, the writ petition is

disposed of with a direction to the 3rd

respondent to consider and pass orders on

Ext.P10 representation, after affording an WP(C).No.7956 of 2021(T)

opportunity of hearing to petitioner, within

a period of two months from the date of

receipt of a copy of the judgment.

Sd/-

P.V.ASHA JUDGE ww WP(C).No.7956 of 2021(T)

APPENDIX PETITIONER'S EXHIBITS:

EXHIBIT P1 TRUE COPY OF THE ARTICLES AND MEMORANDUM OF ASSOCIATION DATED 28/05/2003.

EXHIBIT P2 TRUE COPY OF THE TENDER SANCTION ORDER DATED 30/01/2017.

EXHIBIT P3 TRUE COPY OF THE CONTRACT AGREEMENT DATED 07/02/2017.

EXHIBIT P4 TRUE COPY OF THE LETTER ISSUED TO THE PETITIONER DATED 31/05/2018.

EXHIBIT P5 TRUE COPY OF LETTER DATED 26/05/2017 ALONG WITH THE MINUTES OF THE MEETING DATED 06/04/2017.

EXHIBIT P6 TRUE COPY OF THE LETTER ISSUED BY THE 4TH RESPONDENT DATED 17/01/2019.

EXHIBIT P7 TRUE COPY OF THE REPORT DATED 22/01/2019 OF THE 4TH RESPONDENT.

EXHIBIT P8 TRUE COPY OF THE LETTER DATED 09/05/2019 SUBMITTED BY THE PETITIONER TO THE 3RD RESPONDENT.

EXHIBIT P9 TRUE COPY OF THE LETTER DATED 12/02/2020 ADDRESSED TO THE 4TH RESPONDENT.

EXHIBIT P10 TRUE COPY OF THE FORECLOSURE APPLICATION SUBMITTED BY THE PETITIONER DATED 18/11/2020.

EXHIBIT P11 TRUE COPY OF THE REPRESENTATION DATED 11/02/2021.

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter