Citation : 2021 Latest Caselaw 10252 Ker
Judgement Date : 26 March, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE SMT. JUSTICE P.V.ASHA
FRIDAY, THE 26TH DAY OF MARCH 2021 / 5TH CHAITHRA, 1943
WP(C).No.862 OF 2021(G)
PETITIONER:
T.SHAJI
AGED 49 YEARS
S/O NARAYANAN T.K., THOTTUNGAL HOUSE, KUMBIDI P.O.,
PALAKKAD DISTRICT
BY ADVS.
SRI.JACOB SEBASTIAN
SRI.K.V.WINSTON
SMT.ANU JACOB
RESPONDENTS:
1 STATE OF KERALA
REPRESENTED BY SECRETARY TO GOVERNMENT, IRRIGATION
DEPARTMENT, SECRETARIAT, THIRUVANANTHAPURAM,PIN-695
001
2 THE SUPERINTENDING ENGINEER (ROADS DIVISION),
OFFICE OF THE SUPERINTENDING ENGINEER, PUBLIC WORKS
DEPARTMENT, NORTH ZONE, KOZHIKODE,PIN-673 001
3 THE EXECUTIVE ENGINEER,
PWD ROADS DIVISION, PALAKKAD,PIN-678 001
4 THE ADDITIONAL CHIEF SECRETARY,
FINANCE DEPARTMENT, GOVERNMENT SECRETARIAT,
THIRUVANANTHAPURAM,PIN-695 001
5 THE CHIEF SECRETARY,
GOVERNMENT SECRETARIAT, THIRUVANANTHAPURAM,
PIN-695 001
SMT.VINITHA.B, GP
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
26.03.2021, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
WP(C).No.862 OF 2021(G)
2
JUDGMENT
Dated this the 26th day of March 2021
The petitioner is an A class Contractor,
who wants substitution of bills which were
pledged in respect of 5 items of work towards
performance guarantee by the bill covered by
Ext.P1 certificate. Even though the petitioner
had submitted Ext.P2 application for
substituting the same, as per Exts.P4 to P8
letters the 3rd respondent informed that it can
be made only through indemnity certificate
through EMLI. The EMLI software is not so far
modified. Though petitioner submitted Ext.P10
representation to 2nd respondent it is not so
far considered. The petitioner relies on
Ext.P11 judgment in W.P.(C) No.17718 of 2020
and submits that in the light of the Government
Order Ext.P3 dated 23.06.2020, the performance
guarantee can be substituted. WP(C).No.862 OF 2021(G)
2. I have already considered a similar
issue in the common judgment dated 05.03.2021
in W.P.(C)No.23018 of 2021 and connected cases
and has held that in the light of the G.O.(Rt)
No.5989/2020 dated 16.10.2020 in modification
of Ext.P3 order dated 23.06.2020 the amount
under audited and passed bills can be accepted
as performance guarantee/additional performance
guarantee not only to new works but also to
ongoing works. It was held that performance
guarantee, which was already furnished in
whatever form, can be substituted by adjusting
the amount under an audited and passed bill. In
the present case the petitioner's application
for substitution was rejected as per Exts.P4 to
P8 letters on the ground that the pledging
procedure through EMLI is not possible since
the software is not updated. The said issue was
also considered in that judgment and directions
were issued to grant the benefit manually.
3. Though the Government ordered WP(C).No.862 OF 2021(G)
modification of the EMLI software to enable the
adjustment ordered on 23.06.2020 as per Ext.P3
order, so far no such modification is made.
Hence, the adjustment of bill amount towards
performance guarantee permitted under the order
dated 23.06.2020 is being made manually, on
directions from this Court in a series of
cases. The position continues to be the same
even now. Therefore, in order to extend the
benefit of Ext.P3 order and its modification by
order dated 16.10.2020, to the petitioner the
competent authorities would have to do the
adjustment/substitution manually till the
software is updated.
4. The respondents 2 and 3 shall
therefore, re-consider the request made by the
petitioner in Ext.P2 application and in case
the bill covered by Ext.P1 would be admissible
as against the performance guarantee furnished
by the petitioner towards the work mentioned in
Ext.P2 application, by way of the bills already WP(C).No.862 OF 2021(G)
pledged, appropriate action shall be taken in
accordance with law for substituting the
pending bill covered by Ext.P1, manually,
without any further delay and at any rate
within a period of one month from the date of
receipt of a copy of the judgment.
The writ petition is accordingly disposed
of.
Sd/-
P.V.ASHA JUDGE DM WP(C).No.862 OF 2021(G)
APPENDIX PETITIONER'S EXHIBITS:
EXHIBIT P1 A TRUE COPY OF THE CERTIFICATE DATED 7 JANUARY 2021 ISSUED BY THE THIRD RESPONDENT
EXHIBIT P2 A TRUE COPY OF THE APPLICATION SUBMITTED BY THE PETITIONER BEFORE THE 2ND RESPONDENT FOR SUBSTITUTION OF SECURITY DEPOSIT DATED DECEMBER 28,2020
EXHIBIT P3 A TRUE COPY OF G.O(RT) NO.3834/2020 DATED 23.06.2020
EXHIBIT P4 A TRUE COPY OF THE LETTER DATED 7 JANUARY 2021 ISSUED BY THE THIRD RESPONDENT IN RELATION TO WORK NUMBER ONE
EXHIBIT P5 A TRUE COPY OF THE LETTER DATED 7 JANUARY 2021 ISSUED BY THE THIRD RESPONDENT IN RELATION TO WORK NUMBER TWO
EXHIBIT P6 A TRUE COPY OF THE LETTER DATED 7 JANUARY 2021 ISSUED BY THE THIRD RESPONDENT IN RELATION TO WORK NUMBER THREE
EXHIBIT P7 A TRUE COPY OF THE LETTER DATED 7 JANUARY 2021 ISSUED BY THE THIRD RESPONDENT IN RELATION TO WORK NUMBER FOUR
EXHIBIT P8 A TRUE COPY OF THE LETTER DATED 7 JANUARY 2021 ISSUED BY THE THIRD RESPONDENT IN RELATION TO WORK NUMBER FIVE
EXHIBIT P9 A TRUE COPY OF THE LETTER DATED 28.07.2020 ISSUED BY THE SECOND RESPONDENT
EXHIBIT P10 A TRUE COPY OF THE REPRESENTATION DATED JANUARY 9,2021 SUBMITTED BY THE PETITIONER BEFORE THE SECOND WP(C).No.862 OF 2021(G)
RESPONDENT
EXHIBIT P11 A TRUE COPY OF THE JUDGMENT DATED AUGUST 25,2020 IN WPC NO.17718/2020 AND CONNECTED CASES
RESPONDENTS EXHIBITS: NIL
//TRUE COPY//
PA TO JUDGE
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!