Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Green Vistas Infrastructure ... vs Union Of India
2021 Latest Caselaw 12865 Ker

Citation : 2021 Latest Caselaw 12865 Ker
Judgement Date : 11 June, 2021

Kerala High Court
Green Vistas Infrastructure ... vs Union Of India on 11 June, 2021
         IN THE HIGH COURT OF KERALA AT ERNAKULAM
                          PRESENT
        THE HONOURABLE MR. JUSTICE P.B.SURESH KUMAR
 FRIDAY, THE 11TH DAY OF JUNE 2021 / 21ST JYAISHTA, 1943
                  WP(C) NO. 3870 OF 2020


PETITIONER/S:

          GREEN VISTAS INFRASTRUCTURE PROJECTS,
          G-159, PANAMPILLY NAGAR, ERNAKULAM - 682 036,
          REPRESENTED BY ITS AUTHORISED SIGNATORY,
          MR.SAURABH GULECHHA.
          BY ADVS.
          K.P.DANDAPANI (SR.)
          SRI.MILLU DANDAPANI


RESPONDENT/S:

    1     UNION OF INDIA,
          REPRESENTED BY MINISTRY OF ENVIRONMENT, FORESTS
          AND CLIMATE CHANGE, CGO COMPLEX, LODHI ROAD,
          NEW DELHI - 110 003, REPRESENTED BY ITS
          SECRETARY.
    2     STATE OF KERALA,
          REPRESENTED BY PRINCIPAL SECRETARY TO
          GOVERNMENT, GOVERNMENT
          SECRETARIAT,THIRUVANANTHAPURAM - 695 001.
    3     STATE ENVIRONMENT IMPACT ASSESSMENT AUTHORITY
          (SEIAA),
          KSRTC BUS TERMINAL COMPLEX, 4TH FLOOR,
          THAMPANOOR, THIRUVANANTHAPURAM - 695 001,
          REPRESENTED BY ITS MEMBER SECRETARY.
    4     STATE ENVIRONMENT ASSESSMENT COMMITTEE (SEAC),
          KSRTC BUS TERMINAL COMPLEX, 4TH FLOOR,
          THAMPANOOR, THIRUVANANTHAPURAM - 695 001,
          REPRESENTED BY ITS SECRETARY.
    5     THE DISTRICT COLLECTOR,
          COLLECTORATE, CIVIL STATION, KAKKANAD,
          KOCHI,ERNAKULAM - 682 030.
 W.P.(C) No.3870 of 2020
                            ..2..




     6     THRIKKAKARA MUNICIPALITY,
           KAKKANAD P.O., KOCHI - 682 030, REPRESENTED BY
           ITS SECRETARY.
     7     ADDL.R7. THE KERALA STATE REMOTE SENSING AND
           ENVIRONMENTAL CENTRE,
           VIKAS BHAVAN, C-BLOCK, THIRUVANANTHAPURAM,
           KERALA-695033, REPRESENTED BY ITS DIRECTOR.
           (IS SUO MOTU IMPLEADED AS PER ORDER DATED 18-6-
           2020).
     8     ADDL.R8. THE VILLAGE OFFICER
           VILLAGE OFFICE,THRIKKAKKARA, KAKKANAD, PIN-682
           030.

           IS SUO MOTU IMPLEADED AS PER ORDER DATED 24-06-
           2020.
           BY ADVS.
           SRI.HARIDAS P.NAIR, CGC
           SRI.M.P.SREEKRISHNAN, STANDING COUNSEL
           SHRI.G.G.MANOJ, SC, THRIKKAKARA MUNICIPALITY
           SRI.S.VISHNU SRI.K.J.MANURAJ, GOVERNMENT
           PLEADER




THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION
ON 11.06.2021, THE COURT ON THE SAME DAY DELIVERED THE
FOLLOWING:
 W.P.(C) No.3870 of 2020
                                   ..3..




                     P.B.SURESH KUMAR, J.
                  -------------------------------------
                    W.P.(C) No.3870 of 2020
                  --------------------------------------
            Dated this the 11th day of June, 2021



                               JUDGMENT

Petitioner is a joint venture constructing a

residential complex within the limits of the sixth respondent

Municipality. When the petitioner proposed to develop the

lands belonging to them for the said purpose during early

2006, the Kerala Municipality Building Rules, 1999, was not

implemented in Thrikkakkara Grama Panchayat, which was

later upgraded as the sixth respondent Municipality. The

proposal of the petitioner was for construction of 500

residential apartments in 5 blocks. The practice prevailing

then in Thrikkakkara Grama Panchayat for construction of

buildings in the nature of one proposed by the petitioner was

to obtain a No-objection Certificate from the Panchayat for the

purpose of construction. The petitioner, therefore obtained W.P.(C) No.3870 of 2020 ..4..

Ext.P1 certificate from Thrikkakkara Grama Panchayat on

04.02.2006 to the effect that permission of the Panchayat is

not necessary for the construction proposed by them. In

Ext.P1 certificate, it was however mentioned by the panchayat

that there shall not be any construction within three meters

from the boundaries of the adjacent public roads and that the

petitioner shall provide adequate drainage facility for the

building. On the strength of Ext.P1 certificate, the petitioner

commenced construction of the first two blocks.

2. While the construction of the first two blocks

was proceeding, on 14.09.2006, the Central Government

issued Environmental Impact Assessment Notification, 2006

(EIA Notification) under the Environment (Protection) Act,

1986. As per the EIA Notification, prior environmental

clearance is required for building projects involving built up

area exceeding 20,000 square meters. According to the

petitioner, the requirement in the EIA Notification does not

apply to their project since they have commenced the

construction of the project before 14.09.2006. It is also

alleged by the petitioner that EIA Notification has been

subsequently clarified to that effect by the Central W.P.(C) No.3870 of 2020 ..5..

Government by issuing a circular on 21.11.2006. It is stated

that nevertheless, with a view to give confidence to the

investors and potential buyers of residential apartments in the

project, the petitioner preferred an application before the

State Environment Impact Assessment Authority (SEIAA) for

environmental clearance for their project in terms of the EIA

Notification. Ext.P6 is the application preferred by the

petitioner in this regard on 31.07.2012.

3. Ext.P6 application was forwarded by the

SEIAA to the State Level Expert Appraisal Committee (SEAC).

The SEAC took the view that the petitioner has commenced

the construction of the project without obtaining building

permit from the local authority and they are therefore not

entitled to the environmental clearance sought for. A

recommendation was made by the SEAC in the circumstances

for rejection of the application without prejudice to the right

of the petitioner to prefer a fresh application after regularizing

the construction. When the matter was taken up by the SEIAA

thereupon, petitioner made Ext.P8 submission pointing out

that the construction was on the strength of Ext.P1 certificate

issued by the local authority and the same cannot therefore W.P.(C) No.3870 of 2020 ..6..

be considered as unauthorised. It is stated that in the light of

Ext.P8 submission, the recommendation made by the SEAC

was not accepted by the SEIAA and the application was

consequently remitted to the SEAC for fresh consideration.

Thereupon, the SEAC took the view that the petitioner should

have obtained environmental clearance before commencing

the construction of the project in terms of the EIA Notification,

and directed the petitioner to file an affidavit to the effect that

violation of EIA Notification has occurred and they will not

repeat the same.

4. It is stated by the petitioner that though the

question of violation of the EIA Notification does not arise in

the case of the petitioner as they have commenced the

construction of the project prior to the EIA Notification, with a

view to avoid further legal complications concerning the

project, the petitioner has submitted an affidavit before the

SEAC as directed by them with the hope that on filing the

same, the application preferred by the petitioner for

environmental clearance would be processed. It is also stated

by the petitioner that in the light of the affidavit filed by the

petitioner, the SEAC has decided to conduct a site visit and to W.P.(C) No.3870 of 2020 ..7..

verify the authenticity of the various statutory approvals

obtained by the petitioner for the project in the meanwhile.

After the site inspection and verification of the authenticity of

the statutory approvals obtained by the petitioner, the SEAC

took the view that since the petitioner commenced the

construction of the project without obtaining prior

environmental clearance, they are to be proceeded against for

having committed violation of the EIA Notification and made a

recommendation to that effect to the SEIAA. Pursuant to the

said recommendation, the SEIAA has decided to proceed

against the petitioner for having violated the EIA Notification

and to suspend the construction activities undertaken by the

petitioner till environmental clearance is issued for the project.

In addition, the SEIAA has directed the District Collector to

initiate steps for prosecution of the petitioner under Sections

15 and 19 of the Environment (Protection) Act, 1986. Ext.P17

is the order issued by the Member Secretary of the SEIAA in

this regard on 7.9.2015. In terms of Ext.P17, the District

Collector, Ernakulam was directed to enforce the said order. It

is seen that no action was taken by the District Collector

pursuant to the directions issued by the SEIAA, as the District W.P.(C) No.3870 of 2020 ..8..

Collector entertained a doubt as to his authority to do so

under the Environment (Protection) Act, 1986.

            5.        In     the    meanwhile,             with    effect        from

06.11.2006,      the        State   Government            has     extended        the

provisions of the Kerala Municipality Building Rules, 1999 to

Thrikkakkara Grama Panchayat by notification issued under

Section 274(1) of the Kerala Panchayat Raj Act, 1994. Later,

with effect from 30.11.2010, the Thrikkakkara Grama

Panchayat was upgraded as a Municipality. When the

Panchayat was upgraded as Municipality, the petitioner

applied to the Municipality for regularization of the

construction. On the said application, on 23.12.2014, the

Municipality regularized the construction of the petitioner by

issuing Ext.P16 building permit. Despite Ext.P17 order, the

petitioner continued the construction of the project on the

strength of Ext.P16 building permit and obtained even

occupancy certificates in respect of the first three blocks from

the Municipality. The occupancy certificate in respect of the

first block was obtained by the petitioner on 23.12.2014 and

the occupancy certificate in respect of the second block was

obtained by the petitioner on 17.02.2017. Similarly, the W.P.(C) No.3870 of 2020 ..9..

occupancy certificate in respect of the third block was

obtained by the petitioner on 25.09.2018.

6. While so, the Central Government issued a

notification under the Environment (Protection) Act, 1986 on

14.03.2017, providing that where projects or activities

requiring prior environmental clearance in terms of the EIA

Notification are brought for environmental clearance after

commencement of the construction work, appraisal of the

same for grant of environmental clearance shall be considered

only by the Expert Appraisal Committee at the central level.

Ext.P23 is the notification issued by the Central Government

in this regard. It is stated that though the petitioner was not

obliged to obtain environmental clearance for the project in

terms of the EIA Notification, with a view to resolve the issues

relating to the project, they preferred a fresh application for

environmental clearance before the Expert Appraisal

Committee at the Central level in terms of Ext.P23

notification. On the said application, the Expert Appraisal

Committee confirmed the case of the petitioner to be one of

violation of the EIA Notification and ordered that action shall

be taken against the petitioner by the State Pollution Control W.P.(C) No.3870 of 2020 ..10..

Board and that occupancy certificate shall not be issued for

the project until the project is granted environmental

clearance. Ext.P24 is the decision taken by the Expert

Appraisal Committee at the Central level in this regard in their

meetings held from 19.02.2018 to 21.02.2018. In Ext.P24, it

was also ordered that there shall be a Terms of Reference for

undertaking the environment impact assessment and for

preparation of environment management plan concerning the

project of the petitioner; that the petitioner shall be required

to submit bank guarantee to the State Pollution Control Board

for the amount required for remediation plan and natural and

community resource augmentation plan prior to the grant of

environment clearance, the quantum of which shall be

recommended by the SEAC and finalized by the SEIAA and

that the bank guarantee shall be released only after

successful implementation of the environment management

plan, followed by recommendations by SEAC and approval by

SEIAA. Ext.P23 notification, in terms of which Ext.P24 order

was passed, was subsequently amended on 08.03.2018 by

Ext.P25 notification issued by the Central Government, as per

which the SEAC was authorised to deal with the application W.P.(C) No.3870 of 2020 ..11..

submitted by the petitioner for environmental clearance.

7. Pursuant to Ext.P25 notification, though SEAC

considered the application of the petitioner for environmental

clearance again on 04.12.2018, the decision thereon was

deferred as it found that some more information was required

from the petitioner for consideration of the application.

Ext.P26 communication was consequently issued to the

petitioner by the Administrator of the SEIAA and the

petitioner has furnished the information called for. The

application was considered again by the SEAC in their meeting

held during the third week of September, 2019. In the said

meeting, the petitioner submitted the environment impact

assessment report based on the Terms of Reference approved

by the SEAC. In the said meeting, the SEAC constituted a sub

committee for appraisal of the report for environmental

clearance and adjourned the matter for the report of the sub

committee. The application was taken up later by the SEAC in

its meeting held during the last week of November, 2019. The

representatives of the petitioner did not appear in the said

meeting for hearing. The application of the petitioner was

consequently adjourned and taken up by the SEAC again in W.P.(C) No.3870 of 2020 ..12..

their meeting held on 24.12.2019. In the meanwhile, the sub

committee constituted by the SEAC reported that the

petitioner continued the construction while the application for

environmental clearance was pending and completed almost

even the fourth block and started the land development for

the fifth block. In the light of the said report, the SEAC

decided to recommend the SEIAA to issue stop memo to the

petitioner and also to initiate proceedings for violation of EIA

Notification, after affording the petitioner an opportunity of

hearing. Later, in the meeting of the SEAC held on

14.01.2020, the SEAC confirmed the said decision after

affording the petitioner an opportunity of hearing.

8. The writ petition was filed immediately

thereupon on 10.02.2020, seeking the following reliefs:

i) Issue a writ in the nature of declaration declaring that in view of the fact that the petitioner commenced construction activities based on Ext.P1 NOC, the petitioner is not required to take Environmental Clearance under the provisions of the EIA Notification, 2006 which was issued on 14th September, 2006,

ii) Issue a writ in the nature of declaration declaring that since the petitioner commenced construction activities based on Ext.P1 No Objection Certificate, W.P.(C) No.3870 of 2020 ..13..

the petitioner cannot be treated as a violator under the provisions of sections 15 and 19 of the EIA Act, 2006 which was notified on 14 th September 2006;

iii) Issue a writ in the nature of declaration declaring that since the petitioner submitted Ext.P6 application on 31.7.2012 and no decision was communicated to the petitioner, within 105 days, as prescribed by clause 8 of the EIA Notification, 2006, the petitioner is deemed to have been granted Environmental Clearance;


                      iv)    pass such other orders as this Hon'ble Court
                             deem      fit      and    proper     in    the   facts     and
                             circumstances of the case and


                      v)     award costs.



The case set out by the petitioner in the writ petition is that

insofar as they have commenced construction of the project

based on Ext.P1 certificate issued before the EIA notification,

they are not required to obtain environmental clearance. The

petitioner has also set out a case that since they were not

communicated the decision on Ext.P6 application preferred by

them for environmental clearance on 31.07.2012 within 105

days as provided for in clause 8 of the EIA Notification, they

are deemed to have been granted the environmental W.P.(C) No.3870 of 2020 ..14..

clearance sought for.

9. During the pendency of the writ petition, the

SEIAA has accepted the recommendation made by the SEAC

on 14.01.2020 and issued stop memo to the petitioner and

also directed the State Pollution Control Board to initiate

action against the petitioner under Section 19 of the

Environment (Protection) Act, 1986. Ext.P30 is the

communication issued in this regard by the Administrator of

the SEIAA to the petitioner. Pursuant to Ext.P30, the District

Collector addressed to the District Superintendent of Police to

enforce the stop memo issued to the petitioner by SEIAA. In

the light of Ext.P30, the petitioner has stopped the

construction activities.

10. A statement has been filed in the matter on

behalf of the SEIAA and the SEAC by their Standing Counsel.

11. A counter affidavit has been filed by the

Secretary of the sixth respondent Municipality in the matter

stating, among others, that the petitioner has commenced the

construction after obtaining Ext.P1 certificate; that the

requirement for construction of a building in the erstwhile

Thrikkakkara Grama Panchayat prior to the introduction of the W.P.(C) No.3870 of 2020 ..15..

Kerala Municipality Building Rules, 1999 was only to obtain a

certificate in the nature of Ext.P1 from the Panchayat and that

the petitioner had completed the piling works and started the

works of the super structure in respect of two blocks in terms

of the entries in the register maintained by the Municipality as

on 22.05.2007. It is also stated in the counter affidavit that in

terms of the circular issued by the Government, building

permit is required to be obtained for all buildings, the

construction of which was though commenced based on the

No-objection Certificate issued by the erstwhile Panchayat,

but not completed before the enforcement of the Kerala

Municipality Building Rules, 1999 in the Panchayat and it is in

the light of the said circular, Ext.P16 building permit was

issued to the petitioner after collecting the permit fee.

12. In the reply affidavit filed by the petitioner to

the statement filed on behalf of the SEIAA and the SEAC, it is

stated that the petitioner has sent a reply to Ext.P17 order

issued by the Member Secretary of SEIAA suspending the

construction activities undertaken by the petitioner. Likewise,

it is stated in the said reply affidavit that similarly situated

builders have been permitted to continue construction without W.P.(C) No.3870 of 2020 ..16..

environmental clearance by SEIAA and it is in such

circumstances that they continued the construction despite

Ext.P17 order.

13. On 01.10.2020, this court passed following

interim order:

This writ petition is pending before this court for the last more than six months. The matter is related to environmental clearance required to be obtained by the petitioner for the construction undertaken by them.

2. The learned Standing Counsel for the State Environmental Impact Assessment Authority submits that the petitioner had submitted two applications. The learned Senior counsel appearing for the petitioner submits that there are no two applicants; both are in relation to the same project. Any how, it is desirable that the applications are taken into its logical conclusion within a period of six weeks after notice to the petitioner. The petitioner shall be given an opportunity of hearing either in person or through electronic medium. The learned senior counsel for the petitioner would point out that the 3rd respondent has given environmental clearance to many similarly situated projects.

3. The petitioner is at liberty to move the 3rd respondent for any permission to complete the existing work. If such a request is made, the same shall be considered without any delay.

Post on 17.11.2020.

W.P.(C) No.3870 of 2020 ..17..

Pursuant to the said interim order, the SEIAA considered the

matter and ordered to inform the petitioner that

environmental clearance cannot be issued before completing

the action for violation of the EIA Notification. The decision

taken by the SEIAA in this regard during its meeting held

during the 3rd week of October, 2020 is part of the

proceedings as Ext.P39. In Ext.P39, the SEIAA has also

requested the SEAC and the State Pollution Control Board to

expedite proceedings initiated against the petitioner for

violation of the EIA Notification.

14. Heard the learned counsel for the petitioner,

the learned Government Pleader, the learned Standing

Counsel for the sixth respondent as also the learned Standing

Counsel for respondents 3 and 4.

15. The learned counsel for the petitioner

vehemently argued, placing reliance on Ext.P1 certificate, that

they have started the construction of the project long before

the EIA Notification and the requirement to obtain prior

environmental clearance does not therefore apply to their

project. It was pointed out by the learned counsel that this

aspect has been clarified subsequently by the Central W.P.(C) No.3870 of 2020 ..18..

Government in terms of Circular F.No.J-11013/41/2006-1A-II(I)

dated 21.11.2006. It was also pointed out by the learned

counsel that the issue is covered in favour of the petitioner by

the decision of the Division Bench of this Court in All Kerala

River Protection Council v. State of Kerala, 2015 (2) KLT

78. It was submitted by the learned counsel that the

consistent case of the petitioner all throughout was that the

petitioner has applied for environmental clearance only for the

comfort of the investors and buyers of residential apartments

in the project. It was argued by the learned counsel that the

proceedings initiated against the petitioner for the alleged

violation of EIA Notification is therefore, per se illegal and

arbitrary. It was also pointed out by the learned counsel that

none of the constructions of similar nature carried out within

the limits of the sixth respondent Municipality based on similar

No-objection Certificates issued by the erstwhile Grama

Panchayat have obtained environmental clearance in terms of

EIA Notification and no action whatsoever has been initiated in

respect of the said constructions. It was also argued by the

learned counsel that even assuming that the EIA Notification

applies to the project of the petitioner, they are denied W.P.(C) No.3870 of 2020 ..19..

environmental clearance on the incorrect assumption that the

constructions are unauthorised insofar as they have been

made without obtaining building permit. It was pointed out

that building permit was not insisted at the relevant time in

Thrikkakkara Grama Panchayat as the Kerala Municipality

Building Rules, 1999 were not implemented, and the only

requirement for construction then was to obtain a No-

objection Certificate from the Panchayat. It was pointed out

that the petitioner has not only obtained the No-objection

Certificate before the construction, but also obtained building

permit for the project later when the Building Rules were

implemented in the Panchayat. It was argued that in the light

of Ext.P16 building permit, the constructions carried out by

the petitioner cannot be said to be unauthorised in any

manner and there is therefore absolutely no reason to deny

environmental clearance for the project, especially when

similar and identical structures were granted environmental

clearance. It was also argued by the learned counsel that at

any rate, insofar as the decision on Ext.P6 application

preferred by the petitioner for environmental clearance has

not been communicated to the petitioner within 105 days, the W.P.(C) No.3870 of 2020 ..20..

petitioner is deemed to have been issued environmental

clearance in terms of clause 8 of the EIA Notification. It was

pointed out that in the said circumstances, even if it is found

that the petitioner is not entitled to environmental clearance

for the project, proceedings can be initiated only for

cancellation of the environmental clearance and no

proceedings whatsoever could be initiated against the

petitioner for violation of the EIA Notification.

16. Per contra, the learned Standing Counsel for

respondents 3 and 4 submitted that insofar as the petitioner

has not completed the construction of their massive

residential project before introduction of EIA Notification, they

are bound to comply with the same. It was also pointed out by

the learned Standing Counsel counsel that the requirement in

the EIA Notification is to obtain prior environmental clearance

and insofar as the petitioner has commenced the construction

of the project without obtaining environmental clearance and

continued the construction when the application for

environmental clearance was pending consideration, the

statutory authorities cannot be found fault with for having

initiated proceedings against the petitioner for violation of the W.P.(C) No.3870 of 2020 ..21..

EIA Notification. It was also pointed out by the learned

Standing Counsel that the competent authorities would be

considering the application of the petitioner for environmental

clearance after completion of the proceedings initiated against

the petitioner for violation of the EIA Notification.

17. Having bestowed my attention to the

contentions advanced by the learned counsel for the parties

and having perused the materials on record, it is seen that the

following questions arise for consideration in the matter:

(i) Whether the petitioner was required to obtain

environmental clearance for their project in terms of the

EIA Notification?

(ii) Whether the petitioner is deemed to have been

issued environmental clearance in terms of clause 8 of

the EIA Notification? and

(iii) Whether respondents 3 and 4 are justified in

initiating proceedings against the petitioner for violation

of the EIA Notification?

18. Question (i): As noted, the Kerala Municipality

Building Rules, 1999 was implemented in the erstwhile

Thrikkakkara Grama Panchayat only with effect from

06.11.2006. It is admitted by the Secretary of the sixth W.P.(C) No.3870 of 2020 ..22..

respondent Municipality in the counter affidavit that the

practice prevailing prior to the implementation of the Kerala

Municipality Building Rules, 1999 in the Panchayat was to

obtain a certificate in the nature of Ext.P1 from the Panchayat

for construction of buildings. In other words, the

commencement of the construction of the project by the

petitioner on the strength of Ext.P1 certificate cannot be said

to be illegal. As noted, EIA Notification was issued by the

Central Government on 14.09.2006, after about seven months

from the date of issuance of Ext.P1 certificate. There is

nothing on record to indicate as to whether the petitioner has

in fact commenced the construction before 14.09.2006. Later,

after about a month, the Municipality Building Rules, 1999 was

also introduced in the Panchayat, with effect from 06.11.2006.

There is nothing on record also to indicate as to whether the

petitioner has commenced construction of the project prior to

06.11.2006. Even assuming that the petitioner has

commenced construction prior to 14.9.2006, there is nothing

on record to indicate as to the stage at which the construction

had reached at the time when the Kerala Municipality Building

Rules, 1999 was implemented in the Panchayat. The only W.P.(C) No.3870 of 2020 ..23..

material available on record in this regard is Ext.R6(1)

produced by the Municipality. As indicated, after

implementation of the Kerala Municipality Building Rules,

1999, the erstwhile Panchayat has recorded in a register the

stage of the various constructions commenced prior to the

implementation of the Building Rules in the Panchayat.

Ext.R6(1) is the relevant page in the said register pertaining to

the construction of the petitioner. It is seen from the counter

affidavit filed by the Municipality that the stage of the

construction of the petitioner recorded in Ext.R6(1) is the

stage of construction as on 22.5.2007. Ext.R6(1) indicates that

as on 22.5.2007, the petitioner has completed only the piling

works of the first two blocks. The question whether the

petitioner was required to obtain environmental clearance for

their project in terms of the EIA Notification is to be

considered in the aforesaid background.

19. Clause 2 of the EIA Notification reads thus:

Requirements of prior Environmental Clearance (EC):- The following projects or activities shall require prior environmental clearance from the concerned regulatory authority, which shall hereinafter referred to be as the Central Government in the Ministry of Environment and Forests for matters falling under W.P.(C) No.3870 of 2020 ..24..

Category 'A' in the Schedule and at State level the State Environment Impact Assessment Authority (SEIAA) for matters falling under Category 'B' in the said Schedule, before any construction work, or preparation of land by the project management except for securing the land, is started on the project or activity:

(i) All new projects or activities listed in the Schedule to this notification;

(ii) Expansion and modernization of existing projects or activities listed in the Schedule to this notification with addition of capacity beyond the limits specified for the concerned sector, that is, projects or activities which cross the threshold limits given in the Schedule, after expansion or modernization;

(iii) Any change in product - mix in an existing manufacturing unit included in Schedule beyond the specified range.

It is clear from the extracted clause of the EIA Notification that

the environmental clearance provided for in terms of the said

notification for a project is one to be obtained before

commencement of the construction work of the project. It is

also clear from the extracted clause that environmental

clearance in terms of the notification is required to be

obtained for all new projects listed in the schedule to the

notification and also for expansion of the existing projects,

which cross the threshold limits given in the schedule, after W.P.(C) No.3870 of 2020 ..25..

the expansion. Therefore, there cannot be any doubt that the

question as to whether environmental clearance is required

for a particular project is to be determined, having regard to

the fact as to whether the project is one existing as on the

date of the notification. A building project can be said to be

existing only if its construction has already been commenced,

for otherwise, the same would be a project in the

contemplation of the project proponent, and such a project

cannot be said to be existing. In other words, even in a case

where a building permit in terms of the applicable rules has

been obtained by the project proponent, environmental

clearance is required for the same if, the construction work of

the project has not commenced as on the date of the EIA

Notification. The said view has been taken by this court in

Kent Constructions Private Ltd. v. Corporation of Kochi,

2013 SCC Online Ker 21912.

20. Reverting to the facts, as noted, the materials

on record are not sufficient to render a finding as to whether

the petitioner has commenced the construction of the project

before 14.09.2006, the date on which the EIA Notification was

issued. Ext.R6(1) would indicate only the stage of construction W.P.(C) No.3870 of 2020 ..26..

as on 22.05.2007. As noted, Ext.R6(1) indicates that the

petitioner has only completed the piling work of the first two

blocks and started the superstructure work of the said two

blocks as on the said date. The pointed question is as to

whether the petitioner could be relieved of the obligation to

obtain environmental clearance for the project on account of

the said construction. Though the petitioner recites in the writ

petition that they are not obliged to obtain environmental

clearance for the project as they have commenced the

construction of the project before the EIA Notification and that

they have applied for environmental clearance with a view to

comfort the investors and buyers of the apartments in the

complex, the case put forth by the petitioner in Ext.P8

submission made before the SEIAA was that they have

completed the construction of the first two blocks for which

environmental clearance was not required and that they

propose to construct the remaining three blocks with a built

up area of 33,916 square meters, for which they need

environmental clearance before commencement of the

construction. Paragraphs 6 and 9 of Ext.P8 submission read

thus:

W.P.(C) No.3870 of 2020 ..27..

"6. That, we have started the construction and substantial work was completed on 14/09/2006 for tower 1 & tower 2. There are about 240 apartments in these two towers and are ready for occupancy. Majority of these apartments are sold out and hence a third party is also created. No Environmental Clearance is required for these two towers.

                          xxx
                          9.    That,   currently,   we   propose      to   start

construction of the remaining 3 towers with a built-up area 33,916 sq.m. and for which we need prior environmental clearance before the start of construction.

In terms of the EIA Notification, environmental clearance is

required for construction of projects involving built up area

exceeding 20,000 square meters. In other words, even if it is

found that the petitioner was not required to obtain

environmental clearance for the first two blocks of the project

as claimed by them in Ext.P8 submission, the construction of

which is stated to have begun before the EIA Notification,

environmental clearance was certainly required for the

remaining three towers proposed by the petitioner during the

year 2012 when they made Ext.P8 submission. I take this view

also for the reason that in terms of the EIA Notification,

environmental clearance is required even for expansion of the W.P.(C) No.3870 of 2020 ..28..

existing projects which would cross the threshold limits given

in the schedule after the expansion.

21. The circular of the Central Government

referred to by the learned counsel for the petitioner dated

21.11.2006 provides that EIA Notification does not apply to

projects for which Consent to Establish under the Water

(Prevention and Control of Pollution) Act, 1974 or Air

(Prevention and Control of Pollution) Act, 1981 was obtained

from the State Pollution Control Board. The petitioner has no

case that they have obtained consent to establish the project

from the State Pollution Control Board in terms of the Water

(Prevention and Control of Pollution) Act, 1974 or Air

(Prevention and Control of Pollution Act) 1981. The circular

aforesaid, in the circumstances, has no application. In All

Kerala River Protection Council, this court held that EIA

Notification does not apply to granite quarries covered by

existing quarrying leases in terms of the Kerala Minor Mineral

Concession Rules as on the date of the notification. The said

decision, according to me, cannot have any application to the

case of the petitioner. The case of the petitioner that

environmental clearance is not required for their project, in W.P.(C) No.3870 of 2020 ..29..

the circumstances, is liable to be rejected and I do so.

Question (i) is answered accordingly.

22. Question (ii) : Clause 8 of the EIA Notification

reads thus:

8.Grant or Rejection of Prior Environmental Clearance (EC): (i) The regulatory authority shall consider the recommendations of the EAC or SEAC concerned and convey its decision to the applicant within forty five days of the receipt of the recommendations of the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned or in other words within one hundred and five days of the receipt of the final Environment Impact Assessment Report, and where Environment Impact Assessment is not required, within one hundred and five days of the receipt of the complete application with requisite documents, except as provided below.

(ii) The regulatory authority shall normally accept the recommendations of the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned. In cases where it disagrees with the recommendations of the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned, the regulatory authority shall request reconsideration by the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned within forty five days of the receipt of the recommendations of the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned while stating the reasons for the disagreement. An intimation of this decision shall be simultaneously conveyed to the applicant. The Expert Appraisal Committee or State Level Expert Appraisal Committee concerned, in turn, shall consider the observations of the regulatory authority and furnish its W.P.(C) No.3870 of 2020 ..30..

views on the same within a further period of sixty days. The decision of the regulatory authority after considering the views of the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned shall be final and conveyed to the applicant by the regulatory authority concerned within the next thirty days.

(iii) In the event that the decision of the regulatory authority is not communicated to the applicant within the period specified in sub-paragraphs (i) or (ii) above, as applicable, the applicant may proceed as if the environment clearance sought for has been granted or denied by the regulatory authority in terms of the final recommendations of the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned.

(iv) On expiry of the period specified for decision by the regulatory authority under paragraph (i) and (ii) above, as applicable, the decision of the regulatory authority, and the final recommendations of the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned shall be public documents.

(v) Clearances from other regulatory bodies or authorities shall not be required prior to receipt of applications for prior environmental clearance of projects or activities, or screening, or scoping, or appraisal, or decision by the regulatory authority concerned, unless any of these is sequentially dependent on such clearance either due to a requirement of law, or for necessary technical reasons.

(vi) Deliberate concealment and/or submission of false or misleading information or data which is material to screening or scoping or appraisal or decision on the application shall make the application liable for rejection, and cancellation of prior W.P.(C) No.3870 of 2020 ..31..

environmental clearance granted on that basis. Rejection of an application or cancellation of a prior environmental clearance already granted, on such ground, shall be decided by the regulatory authority, after giving a personal hearing to the applicant, and following the principles of natural justice.

As noted, sub clause (i) of clause 8 provides that the

regulatory authority for grant of environmental clearance shall

convey its decision on the application for prior environmental

clearance to the applicant within 45 days of the receipt of the

recommendations of the Expert Appraisal Committee

concerned or within 105 days of the receipt of the final

Environment Impact Assessment Report, and where

environment impact assessment is not required, within 105

days of the receipt of the complete application with requisite

documents, except as provided in the succeeding sub clauses

of the said clause. Sub clause (iii) of clause 8 provides that in

the event that the decision of the regulatory authority is not

communicated to the applicant within the period specified in

sub clause (i), the applicant may proceed as if environmental

clearance sought for has been granted or denied by the

regulatory authority in terms of the final recommendations of

the Expert Appraisal Committee concerned. It is placing W.P.(C) No.3870 of 2020 ..32..

reliance on sub clause (iii) of clause 8 that the petitioner

contends that insofar as the application for environmental

clearance preferred by the petitioner has not been disposed of

within 105 days of the receipt of the same, the petitioner is

deemed to have been granted environmental clearance.

23. I am unable to accept the aforesaid

contention of the petitioner. Sub clause (iii) of clause 8 of the

EIA Notification would apply only in a case where the Expert

Appraisal Committee has made its final recommendation

either to grant or to reject the environmental clearance

sought by the petitioner. The fiction created under sub clause

(iii) is not that the application made by the project proponent

is deemed to have been granted, if a decision is not

communicated on the application. On the other hand, the

fiction is that the recommendations of the Expert Appraisal

Committee, after scoping and due appraisal, whether

approving or rejecting the proposal, are to be treated as the

decision of the Regulatory Authority. In the instant case, the

Expert Appraisal Committee has not submitted their final

recommendations to the Regulatory Authority at all. The

petitioner cannot, therefore, be heard to contend that they are W.P.(C) No.3870 of 2020 ..33..

deemed to have been issued environmental clearance for

their project in terms of clause 8 of the EIA Notification.

24. Question (iii):- I have found, while considering

question (I), that the petitioner was obliged to obtain prior

environmental clearance for their project in terms of the EIA

Notification. As noted, the petitioner has applied for

environmental clearance for the project and was pursuing the

same right from the year 2012. The recitals in Ext.P8

submission made by the petitioner before the SEIAA as

extracted in paragraph 20 above would indicate beyond doubt

that the petitioner was aware of the fact that they are bound

to obtain prior environmental clearance for their project. The

petitioner has not disputed the fact that they have completed

construction of the third block of the project and also

completed a substantial portion of the fourth block of the

project, without obtaining prior environmental clearance, that

too, during the pendency of the application for environmental

clearance and ignoring Ext P17 order of the SEIAA. In the

circumstances, SEIAA cannot be blamed for having initiated

steps against the petitioner for violation of the EIA

Notification. Question (iii) is answered accordingly. W.P.(C) No.3870 of 2020 ..34..

25. As noted, though this Court passed an interim

order on 1.10.2020 directing the SEIAA to take up the

application preferred by the petitioner for environmental

clearance to its logical end, the SEIAA has taken the stand

that environmental clearance can be issued after the

conclusion of the proceedings initiated against the petitioner

for violation of the EIA Notification. It is seen that the action

provided for in the Environment (Protection) Act, 1986 for

violation of EIA Notification is prosecution under Section 15 of

the said statute. Though the SEIAA has issued directions to

the State Pollution Control Board to initiate steps for

prosecuting the petitioner, there is nothing on record to

indicate that any action has been taken by the State Pollution

Control Board in this direction. Be that as it may, even if steps

have been taken towards this end, there is no doubt that the

prosecution would be a time-consuming procedure. Should the

partly completed project remain as it is, till the culmination of

the prosecution against the petitioner is the remaining point

to be addressed, though the petitioner has not addressed

any argument on this aspect. According to me, the stand of

the SEIAA that the partly completed project should remain as W.P.(C) No.3870 of 2020 ..35..

it is, till the culmination of the prosecution against the

petitioner is unjustified, for the same would not only adversely

affect the interests of the buyers of the apartments in the

project, but also result in wastage of resources.

In the circumstances, the writ petition is disposed

directing respondents 3 and 4 to dispose of finally the

application of the petitioner for environmental clearance, as

directed in Ext.P24 decision of the Expert Appraisal

Committee at the Central level, in accordance with the law,

having regard to the present stage of construction, as

expeditiously as possible, without waiting for the culmination

of the proceedings contemplated against the petitioner for

violation of the EIA notification. It is made clear that the

petitioner will not be entitled to resume the work of the

project before the direction aforesaid is complied with.

Sd/-

P.B.SURESH KUMAR JUDGE ds 18.05.2021 W.P.(C) No.3870 of 2020 ..36..


                  APPENDIX OF WP(C) 3870/2020

PETITIONER'S EXHIBITS         :
EXHIBIT P1                TRUE COPY OF THE NOC ISSUED BY 6TH
                          RESPONDENT DATED 04/02/2006 BEARING
                          NO.A4-1/2000.
EXHIBIT P2                TRUE COPY OF THE CERTIFICATE ISSUED BY
                          THE COMMANDANT GENERAL OF THE FIRE &

RESCUE DEPARTMENT BEARING NO.G2-69/09 DATED 17/02/2009.

EXHIBIT P3 TRUE COPY OF THE NO OBJECTION CERTIFICATE ISSUED BY THE SOUTHERN NAVAL COMMAND DATED 15/12/2014 ISSUED FOR 5 BLOCKS.

EXHIBIT P4 TRUE COPY OF THE NO OBJECTION CERTIFICATE ISSUED BY THE AIRPORT AUTHORITY OF INDIA TO THE PETITIONER DATED 27/02/2016, WHICH IS VALID TILL 26/02/2021.

EXHIBIT P5 TRUE COPY OF THE ENVIRONMENTAL CLEARANCE BEARING NO.19/SEIAA/KL/717/2012 DATED 10/08/2012 ISSUED TO M/S.PURAVANKARA PROJECTS LIMITED FOR THE PROJECT PURVA GRAND BAY.

EXHIBIT P6 TRUE COPY OF THE APPLICATION SUBMITTED BY THE PETITIONER BEFORE THE 3RD RESPONDENT DTD.31/07/2012.

EXHIBIT P7 TRUE COPY OF THE RELEVANT PORTION OF THE MINUTES OF THE 7TH MEETING OF THE SEAC HELD ON 1/9/2012.

EXHIBIT P8 TRUE COPY OF THE REPLY DATED 10/09/2012 SUBMITTED BY THE PETITIONER BEFORE THE 3RD RESPONDENT.

EXHIBIT P9 TRUE COPY OF THE LETTER BEARING NO.32/SEIAA/KL/3045/2012 DATED 21/11/2012 AND THE ENVELOPE CONTAINING SEAL ISSUED BY THE POSTAL DEPARTMENT.

W.P.(C) No.3870 of 2020 ..37..

EXHIBIT P10 TRUE COPY OF THE REPLY SUBMITTED BY THE PETITIONER TO THE MEMBER SECRETARY OF 3RD RESPONDENT DTD. NIL.

EXHIBIT P11 TRUE COPY OF THE RELEVANT PORTION OF THE MINUTES OF THE MEETING HELD ON 02/03/2013 BY THE SEAC.

EXHIBIT P12 TRUE COPY OF THE AFFIDAVIT FILED BY THE PETITIONER ON 14/08/2013.

EXHIBIT P13 TRUE COPY OF THE RELEVANT PORTION OF THE MINUTES OF THE MEETING HELD ON 09/09/2013 AND 10/09/2013 BY THE SEAC.

EXHIBIT P14 TRUE COPY OF THE RELEVANT PORTION OF THE MINUTES OF THE MEETING HELD ON 14/02/2014 AND 15/02/2014 BY THE 3RD RESPONDENT SEAC.

EXHIBIT P15 TRUE COPY OF THE REPRESENTATION SUBMITTED BY THE PETITIONER BEFORE THE 3RD RESPONDENT ON 23/7/2014.

EXHIBIT P16 TRUE COPY OF THE REVISED BUILDING PERMIT ISSUED BY THE SECRETARY OF THE THRIKKARA MUNICIPALITY ON 23/12/2014 BEARING NO.BA/851/2014.

EXHIBIT P17 TRUE COPY OF THE PROCEEDINGS BEARING NO.32/SEIAA/KL/3045/2012 DATED 07/09/2015 ISSUED BY THE 3RD RESPONDENT.

EXHIBIT P18 TRUE COPY OF THE REPLY SUBMITTED BY THE PETITIONER ON 20/11/2015 TO 3RD RESPONDENT.

EXHIBIT P19 TRUE COPY OF THE REPLY BEARING NO.32/SEIAA/KL/3045/2012 RECEIVED ON 30/01/2016 BY THE PETITIONER FROM THE SEIAA.

EXHIBIT P20 TRUE COPY OF THE REPRESENTATION DATED 23/02/2016 SUBMITTED BEFORE THE 5TH RESPONDENT.

W.P.(C) No.3870 of 2020 ..38..

EXHIBIT P21 TRUE COPY OF THE COMMUNICATION BEARING NO.M2-9293/2016 ISSUED BY THE 5TH RESPONDENT TO 3RD RESPONDENT DTD.

15/03/2016.

EXHIBIT P22 TRUE COPY OF THE OCCUPANCY CERTIFICATE FOR 1ST BLOCK DATED 23/12/2014.

EXHIBIT P22(A) TRUE COPY OF THE OCCUPANCY CERTIFICATE FOR BLOCK NO.2 DATED 17/02/2017.

EXHIBIT P22(B) TRUE COPY OF THE OCCUPANCY CERTIFICATE FOR BLOCK NO.3 DATED 25/09/2018.

EXHIBIT P22(C) PHOTOGRAPH OF THE BLOCK NO.I. EXHIBIT P22(D) PHOTOGRAPH OF THE BLOCK NO.II. EXHIBIT P22 (E) PHOTOGRAPH OF THE BLOCK NO.III.

EXHIBIT P23 TRUE COPY OF THE MINISTRY OF ENVIRONMENT, FOREST AND CLIMATE CHANGE NOTIFICATION DATED 14/03/2017.

EXHIBIT P24 TRUE COPY OF THE RELEVANT PORTION OF THE MINUTES OF THE MEETING HELD ON 19/02/2018 TO 21/02/2018 BY THE EXPERT APPRAISAL COMMITTEE OF THE 1ST RESPONDENT.

EXHIBIT P25 TRUE COPY OF THE MINISTRY OF ENVIRONMENT, FOREST AND CLIMATE CHANGE NOTIFICATION DATED 08/03/2018.

EXHIBIT P26 TRUE COPY OF THE LETTER BEARING FILE NO.1189(A)/EC2/2018/SEIAA DATED 17/12/2018 SENT BY THE 3RD RESPONDENT TO THE PETITIONER.

EXHIBIT P27 TRUE COPY OF THE REPRESENTATION SUBMITTED BY THE PETITIONER TO THE 3RD RESPONDENT DTD. 27/07/2019.

EXHIBIT P28 TRUE COPY OF THE MINUTES OF THE MEETING HELD ON 17/09/2019 AND 18/09/2019 BY THE 3RD RESPONDENT.

W.P.(C) No.3870 of 2020 ..39..

EXHIBIT P29 TRUE COPY OF THE MINUTES OF THE MEETING HELD ON 24/12/2019 BY THE SEAC.

EXHIBIT P30 TRUE COPY OF THE COMMUNICATION BEARING NO.1189(A)/EC2/2018/SEIAA DATED 23/03/2020 WITH MEETING MINUTES OF SEIAA AND SEAC.

EXHIBIT P31 TRUE COPY OF THE COMMUNICATION BEARING NO.1189(A)/EC2/2018/SEIAA DATED 23/03/2020 ISSUED TO THE MEMBER SECRETARY, KERALA STATE POLLUTION CONTORL BOARD BY 3RD RESPONDENT.

EXHIBIT P32 TRUE COPY OF THE ENVELOP RECEIVED FROM THE 3RD RESPONDENT.

EXHIBIT P33 TRUE COPY OF THE SALE DEED NO.4644 OF 2005 DATED 17/11/2005.

EXHIBIT P34               TRUE COPY OF THE SALE DEED
                          NO.4702/2005 DATED 23/11/2005.
EXHIBIT P35               TRUE COPY OF THE STOP MEMO DATED
                          1.8.2020 ISSUED BY THE FIFTH
                          RESPONDENT.
EXHIBIT P36               TRUE COPY OF THE SALE DEED BEARING

NO.4260/2006 DTD.14.12.2006 IN FAVOUR OF SRI.VIJAYAKUMAR SURANA.

EXHIBIT P37 TRUE COPY OF THE LETTER BEARING NO.1189(A)/EC2/18/SEIAA DATED 12.11.2020.

EXHIBIT P38 TRUE COPY OF THE REPRESENTATION/SUBMISSION SUBMITTED BY THE PETITIONER TO THE 3RD RESPONDENT AND ALSO COPY TO THE 4TH RESPONDENT DTD.19.11.2020.

EXHIBIT P39 TRUE COPY OF THE MINUTES OF 105TH MEETING OF SEIAA HELD ON 22ND AND 23RD OCTOBER, 2020 AND THE RELEVANT PAGES PERTAINING TO THE PETITIONERS MATTER DECIDED BY THE 3RD RESPONDENT.

W.P.(C) No.3870 of 2020 ..40..

EXHIBIT P40 TRUE COPY OF THE MINUTES OF 103RD MEETING OF SEIAA HELD ON 24TH AND 25TH FEBRUARY, 2020.

EXHIBIT P41 TRUE COPY OF THE RELEVANT PORTION OF THE MINUTES OF THE 119TH MEETING OF SEAC, KERALA AND PROCEEDINGS DATED 25.2.2021 ON ITEM NO.119.08 OF THE 3RD RESPONDENT.

RESPONDENT'S EXHIBITS         :
EXHIBIT R6(1)             THE EXTRACT OF THE REGISTER OF
                          BUILDINGS UNDER CONSTRUCTION AS ON THE
                          DATE OF IMPLEMENTING BUILDING RULES.
EXHIBIT R6(2)             THE REPORT PREPARED BY THE SECREATARY
                          OF THE 6TH RESPONDENT BASED ON THE
                          INSPECTION DATED 19.8.2020.
ANNEXURE R4(1)            A TRUE COPY OF THE RELEVANT EXTRACT OF
                          THE MINUTES OF THE 105TH MEETING OF
                          THE SEIAA HELD ON 22-23, OCTOBER, 2020
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter