Citation : 2021 Latest Caselaw 750 Ker
Judgement Date : 8 January, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE N.NAGARESH
FRIDAY, THE 08TH DAY OF JANUARY 2021/18TH POUSHA, 1942
WP(C).No.3766 OF 2020(U)
PETITIONER:
CHICAGO CONSTRUCTIONS INTERNATIONAL (P) LTD,
TC 22/2703, CHICAGO LANE,
KOCHAR ROAD, SASTHAMANGALAM,
THIRUVANANTHAPURAM-695010,
REP. BY THE MANAGING DIRECTOR,
MOHANAKUMAR S.
BY ADVS.
SRI.N.KRISHNA PRASAD
SHRI.B.S.SANKAR LAL
SRI.DEEPAK VARUGHUESE MATHEW
SMT.GEETHU SUSAN VARGHESE
RESPONDENTS:
1 KERALA WATER AUTHORITY,
JALABHAVAN, THIRUVANANTHAPURAM-695033,
REPRESENTED BY ITS MANAGING DIRECTOR.
2 THE MANAGING DIRECTOR,
KERALA WATER AUTHORITY,
JALABHAVAN,
THIRUVANANTHAPURAM-695033.
3 THE SUPERINTENDING ENGINEER,
PH CIRCLE, KERALA WATER AUTHORITY,
JALABHAVAN,
THIRUVANANTHAPURAM-695033.
4 THE EXECUTIVE ENGINEER,
PROJECT DIVISION, KERALA WATER AUTHORITY,
JALABHAVAN, THIRUVANANTHAPURAM-695033.
5 THE CHIEF EXECUTIVE OFFICER,
TECHNOPARK, ELECTRONIC TECHNOLOGY PARK KERALA,
TECHNOPARK CAMPUS,
THIRUVANANTHAPURAM-695033.
WP(C) No.3766/2020
:2 :
R1-4 BY ADV. SMT.MARY BENJEMIN, SC
R1-4 BY SRI.P.BENJAMIN PAUL, SC, KERALA WATER
AUTHORITY
THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD
ON 08.01.2021, THE COURT ON THE SAME DAY DELIVERED THE
FOLLOWING:
WP(C) No.3766/2020
:3 :
JUDGMENT
~~~~~~~~~
Dated this the 8th day of January, 2021
The petitioner, a construction Company, seeks to
direct respondents 1 to 5 to release the original of the Bank
Guarantee along with the Security Deposit of ₹3 lakhs
submitted by the petitioner in connection with the work
captioned "Water Supply Scheme to Technocity at Pallipuram-
Design, Construction and commissioning or 9.2 MLD capacity
Water Plant at Avanavanchery".
2. The fact that the petitioner-Company has
completed their work under the agreement with the
respondents, is not in dispute. The Bank Guarantee and
Security Deposit of the petitioner were retained by the
respondents as the project was not commissioned.
Subsequently, pursuant to an interim order of this Court, the
Security Deposit has been released to the petitioner, though WP(C) No.3766/2020
the project is yet to be commissioned.
3. The learned Standing Counsel for the respondents
would submit that Bank Guarantee can be released only after
commissioning of the project. The project in question has not
been commissioned. On a question as to the reason for non-
commissioning of the project, the learned Standing Counsel
for the respondents submitted that other components of the
project work have not been completed by the respective
contractors and that is the reason why the project could not be
commissioned.
4. Heard.
5. The fact that the petitioner has completed their
work is not in dispute. Other contractors who have to do other
component works which are integral to the project, perhaps
have not completed their part of the work. However, that
cannot be a reason for the respondents to indefinitely delay
the release of Bank Guarantee to the petitioner. At the same
time, the interest of the respondents will also have to be
protected.
WP(C) No.3766/2020
In such circumstances, the writ petition is disposed
of directing the respondents that if the petitioner executes an
ordinary bond in place of the Bank Guarantee, the
respondents shall release the Bank Guarantee within a period
of one month, to the petitioner.
Sd/-
N. NAGARESH, JUDGE
aks/08.01.2021 WP(C) No.3766/2020
APPENDIX PETITIONER'S EXHIBITS:
EXHIBIT P1 TRUE COPY OF THE SELECTION NOTICE ISSUED BY THE THIRD RESPONDENT.
EXHIBIT P2 TRUE COPY OF THE COMPLETION CERTIFICATE DATED 11.6.2014.
EXHIBIT P3 TRUE COPY OF THE RELEVANT EXTRACTS OF THE NOTICE INVITING TENDER (VOLUME I).
EXHIBIT P4 TRUE COPY OF THE MINUTES OF THE MEETING DATED 12.4.2019.
EXHIBIT P5 TRUE COPY OF THE COMMUNICATION OF THE
FIFTH RESPONDENT TO THE THIRD
RESPONDENT DATED 31.5.2019.
EXHIBIT P6 TRUE COPY OF THE COMMUNICATION DATED
30.4.2019 ISSUED BY THE THIRD
RESPONDENT TO THE DGM (PROJECTS) OF THE FIFTH RESPONDENT.
EXHIBIT P7 TRUE COPY OF THE REPRESENTATION DATED 13.1.2020.
EXHIBIT P8 TRUE COPY OF THE BANK GUARANTEE DATED 17.3.2018 SUBMITTED BY THE PETITIONER
EXHIBIT P9 TRUE COPY OF THE COMMUNICATION DATED 15.9.2020 ISSUED BY THE FOURTH RESPONDENT EXHIBIT P10 TRUE COPY OF THE COMMUNICATION DATED 03.12.2020 ISSUED TO THE PETITIONER BY THE FOURTH RESPONDENT.
SR
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!