Sunday, 19, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Raju Varghese vs Thrippunithura Municipality
2021 Latest Caselaw 473 Ker

Citation : 2021 Latest Caselaw 473 Ker
Judgement Date : 7 January, 2021

Kerala High Court
Raju Varghese vs Thrippunithura Municipality on 7 January, 2021
               IN THE HIGH COURT OF KERALA AT ERNAKULAM

                               PRESENT

           THE HONOURABLE MR. JUSTICE P.B.SURESH KUMAR

    THURSDAY, THE 07TH DAY OF JANUARY 2021 / 17TH POUSHA, 1942

                       WP(C).No.9657 OF 2019(F)


PETITIONERS:

      1        RAJU VARGHESE
               AGED 66 YEARS
               S/O LATE M.I.VARKEY,MUKKADACKAL HOUSE,SEAPORT AIRPORT
               ROAD, IRUMPANAM.P.O,THIRUVANKULAM VILLAGE,-682309.

      2        JOBY RAJ,
               AGED 35 YEARS
               S/O RAJU VARGHESE,MUKKADACKAL HOUSE,
               SEAPORT AIRPORT ROAD,IRUMPAANAM.P.O,
               THIRUVANKULAM VILLAGE-682309.

               BY ADVS.
               SRI.JOLLY JOHN
               SMT.LIZA MEGHAN CYRIAC

RESPONDENTS:

      1        THRIPPUNITHURA MUNICIPALITY
               REPRESENTED BY ITS SECRETARY,
               THRIPPUNITHURA.P.O.682301,ERNAKULAM,
               REPRESENTED BY THE SECRETARY.

      2        SECRETARY,
               THRIPPUNITHURA MUNICIPALITY,
               THRIPPUNITHURA.P.O.682031,
               ERNAKULAM DISTRICT.

               R1-2 BY ADV. SRI.C.V.MANUVILSAN

     THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD         ON
07.01.2021, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
 WP(C).No.9657 OF 2019(F)

                                         2




                           W.P.(C) No.9657 of 2019
                   -----------------------------------------------

                                JUDGMENT

The first petitioner is the father of the second petitioner.

The petitioners hold adjoining lands covered by Exts.P1 and P2 sale

deeds. They have obtained a building permit to put up a commercial

building in the said lands from the first respondent Municipality on

27.09.2014. Ext.P3 is the building permit obtained by the petitioners.

Ext.P3 was valid for a period of three years. It is stated that while the

construction of the building was proceeding on the basis of Ext.P3

building permit, a stranger preferred a complaint before the

Municipality alleging that the petitioners have encroached upon the

adjoining PWD Puramboke as also river Puramboke in the matter of

effecting the construction. The second respondent, in the

circumstances, issued Ext.P6 communication to the petitioners calling

upon them to produce the survey sketch and the possession certificate

of their lands and directed the petitioners to stop the construction

carried on by them. In Ext.P6, it was also mentioned by the second

respondent that the petitioners have not made available the No

Objection Certificate of the Fire Services Department in terms of the WP(C).No.9657 OF 2019(F)

building permit. The petitioners could not comply with the directions in

Ext.P6 communication. Consequently, building permit granted to the

petitioners has been suspended by the second respondent. Ext.P7 is

the communication issued by the second respondent to the petitioners

in this regard. It is stated by the petitioners that as required by the

second respondent, the Tahasildar concerned has forwarded Ext.P8

report and sketch of the lands of the petitioners on 16.02.2016.

Subsequently, on 29.09.2016, the petitioners have obtained No

Objection Certificate from the Fire Services Department and the same

also produced by them before the Municipality. It is stated that despite

production of the documents referred to above, the suspension of the

building permit was not revoked by the Municipality. In the meanwhile,

as the validity of the building permit obtained by the petitioners was

due to expire, the petitioners preferred an application for renewal of

the building permit on 29.08.2017. Ext.P11 is the application preferred

by the petitioners in this regard. It is alleged by the petitioners that

Ext.P11 has not been considered. The writ petition is filed in the

circumstances seeking directions to the respondents to renew Ext.P3

building permit so as to enable them to complete the construction

carried on by them.

2. A statement has been filed on behalf of the

respondents. The fact that the petitioners have produced the WP(C).No.9657 OF 2019(F)

documents required in Ext.P6 and complied with the condition in the

building permit concerning production of the No Objection Certificate

from the Fire Services Department is not disputed by the Municipality

in the statement. It is also admitted by the Municipality in paragraph 7

of the statement that the petitioners have not made any

encroachment. As regards the inaction on the part of the Municipality

in not considering the request of the petitioners for vacating the order

suspending the building permit and the inaction on the part of the

Municipality in not considering the application preferred by the

petitioners for renewal of the building permit, it is vaguely stated by

the Municipality in the statement that it is due to the delay on the part

of the petitioners in curing the defects noted by the Municipality.

3. Heard the learned counsel for the petitioners.

4. It is seen that all the documents required by the

Municipality so as to enable the petitioners to continue the

construction covered by Ext.P3 building permit have been made

available by the petitioners by September 2016. The Municipality has

no case in the statement that the petitioners are not entitled to

construct the building covered by Ext.P3 building permit or that they

have not complied with any of the requirements of the Municipality

concerning the same. In the circumstances, according to me, it was

highly inappropriate for the Municipality to refuse to vacate the WP(C).No.9657 OF 2019(F)

suspension of the building permit granted to the petitioners. Similarly,

it was highly inappropriate in the aforesaid circumstances for the

Municipality to delay consideration of the application submitted by the

petitioners for renewal of the building permit applied for by them on

29.08.2017. Having stopped the construction carried on by the

petitioners investing sizable amounts midway, the Municipality was

obliged in law to vacate the suspension of the building permit once it

was found that the complaint against the construction was without any

basis. Similarly, it is seen that it was due to the interdiction of the

Municipality that the petitioners could not have completed the

construction within the time stipulated originally in the building permit.

The Municipality, in the circumstances, is obliged to renew the building

permit so as to enable the petitioners to complete the construction in

terms of the building permit issued to them.

In the circumstances, the writ petition is allowed and the

respondents are directed to renew Ext.P3 building permit for the usual

period of renewal so as to enable the petitioners to complete the

construction proposed by them. This shall be done within one month.

Sd/-

                                            P.B.SURESH KUMAR

Mn                                                JUDGE
 WP(C).No.9657 OF 2019(F)





                               APPENDIX
PETITIONERS' EXHIBITS:

EXHIBIT P1                 TRUE COPY OF THE SALE DEED NO 2848/06 DATED
                           26/06/2006 EXECUTED BY MR.JOHN PAULO IN
                           FAVOR OF THE 1ST PETITIONER.

EXHIBIT P2                 TRUE COPY OF THE SALE DEED NO.2900/06 DATED
                           26/06/2006 EXECUTED BY MR.JOHN PAULO IN
                           FAVOR OF THE 2ND RESPONDENT

EXHIBIT P3                 TRUE COPY OF THE BUILDING PERMIT DATED

27/09/2014 ISSUED BY THE 2ND RESPONDENT TO THE PETITIONERS.

EXHIBIT P4 TRUE COPY OF THE NOTICE DATED 11/06/2015 ISSUED BY THE 2ND RESPONDENT TO THE PETITIONERS.

EXHIBIT P5 TRUE COPY OF THE REPLY SUBMITTED BY THE PETITIONER TO THE 2ND RESPONDENT DATED 12/06/2015.

EXHIBIT P6 TRUE COPY OF THE NOTICE FROM THE 2ND RESPONDENT DATED 18/06/2015 TO THE PETITIONERS.

EXHIBIT P7 TRUE COPY OF THE STOP MEMO DATED 25/09/2015 FROM THE 2ND RESPONDENT.

EXHIBIT P8 TRUE COPY OF THE REPORT OF THE ADDITIONAL TAHSILDAR DATED 16/2/2016 ALONG WITH THE SURVEY SKETCH DATED 3/12/2015

EXHIBIT P9 TRUE COPY OF THE FIRE SAFETY CLEARANCE FOR SITE DATED 29/09/2016.

EXHIBIT P10 TRUE COPY OF THE APPLICATION BY THE PETITIONERS TO THE 2ND RESPONDENT DATED 14/10/2016 FOR CONTINUATION OF CONSTRUCTION EXHIBIT P-2 BUILDIG PERMIT.

EXHIBIT P11 TRUE COPY OF THE APPLICATION BY THE PETITIONERS' TO THE 2ND RESPONDENT DATED 29/08/2017 ALONG WITH THE RESPECT OF ACKNOWLEDGMENT

EXHIBIT P12 TRUE COPY OF THE APPLICATION ALONG WITH THE COVERING LETTER FILED BY THE PETITIONER WP(C).No.9657 OF 2019(F)

BEFORE THE SECOND RESPONDENT DATED 22/01/2019

EXHIBIT P13 TRUE COPY OF THE APPLICATION WITH THE COVERING LETTER FILED BY THE PETITIONER BEFORE THE SECOND RESPONDENT DATED 25/02/2019.

EXHIBIT P14 ORIGINALS OF THE PHOTOGRAPHS OF THE CONSTRUCTION SITE OF THE PETITIONERS' TAKEN IN THE MONTH OF FEBRUARY.

//TRUE COPY// PA TO JUDGE

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter