Citation : 2021 Latest Caselaw 3032 Ker
Judgement Date : 28 January, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MRS. JUSTICE ANU SIVARAMAN
THURSDAY, THE 28TH DAY OF JANUARY 2021 / 8TH MAGHA, 1942
WP(C).No.25762 OF 2020(U)
PETITIONER:
BIJU G
AGED 42 YEARS
BIJU MANDIRAM,
MELEPANDALAM MUKKU,
PULIPPARA P.O,
KADAKKAL-691536
BY ADV. SMT.NISHA JOHN
RESPONDENTS:
1 REGISTRAR , STUDENT REGISTRATION DIVSION
IGNOU, MAIDAN GARHI, NEW DELHI-110 068
2 DIRECTOR,
INDIRA GANDHI NATIONAL OPEN UNIVERSITY, REGIONAL
CENTRE, THIRUVANANTHAPURAM, KARAMANA P.O,
THIRUVANANTHAPURAM.
R1-2 BY ADV. SRI.K.MOHANAKANNAN
THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON 19-
01-2021, THE COURT ON 28-01-2021 DELIVERED THE FOLLOWING:
W.P.(C).No.25762/2020
2
ANU SIVARAMAN, J.
= = = = = = = = = = = = = = =
W.P.(C).No.25762 of 2020
= = = = = = = = = = = = = = = =
Dated this the 28th day of January, 2021
JUDGMENT
This writ petition is filed seeking the following prayers:-
"i) To issue a Writ of Mandamus or other appropriate writ or order, directing the Respondents to accept the project proposal of the petitioner and to evaluate the same;
(ii) To issue a Writ of Mandamus or other appropriate writ or order directing the Respondents to permit petitioner to appear for the coming Term End Examination after accepting fees;
(iii) To issue a Writ of Mandamus or other appropriate writ or order directing the Respondents to permit petitioner to complete the course without insisting for sitting through the entire course duration;"
2. Heard the learned counsel for the petitioner and the
learned counsel for the University.
3. It is submitted that the petitioner had joined the BCA
program in the respondent University in the year 2008. The
program had 6 semesters and the petitioner completed 5 of the
semesters successfully. For the final 6 th semester, a project W.P.(C).No.25762/2020
proposal had to be submitted which was to be approved by the
University and the course would be complete only on such
project being approved. It is submitted that the petitioner had
submitted the project proposal in time as per Ext.P3 calendar,
but the outcome of the same was not communicated in time.
After 7 months, it was informed that the project was not
satisfactory and the petitioner resubmitted the proposal. It was
not even evaluated on the ground that the program had to be
completed within 4 years of joining.
4. The learned counsel for the petitioner submits that the
delay in re-submission of the project was only on account of the
delay in valuing the project. It is submitted that since the
evaluation was delayed, the petitioner was unable to resubmit
the project in time. Though Ext.P5 request was made for a
readmission with carry over of the credits earned by him, the
same has also been rejected by the respondents. It is stated that
if the rejection of the project was intimated within the 30 days as
mandated by Ext.P3 calendar, the petitioner could have
resubmitted the same after curing defects within the time
provided.
W.P.(C).No.25762/2020
5. A statement has been placed on record by the
respondents. It is submitted that the duration of the BCA
program was 3 years and the maximum validity was 6 years. It
is stated that the petitioner was aware when he joined the
course in 2008 itself that the validity of this program will be
over in December 2013 and that if he did not complete the
course in all aspects within the time, his admission would
lapse. It is submitted that the petitioner had submitted the
project proposals in the first instance on 30.12.2013 and the
project was returned after evaluation without approval in
February 2014. It is stated that it was resubmitted on
25.06.2014 and returned unapproved in July 2014. Thereafter,
the project was submitted only on 05.07.2016, by which time
the validity of the program had ended in December 2015 and
the project was not liable to be evaluated. It is submitted that
since the validity of the program had ended in December 2015,
the petitioner's third submission of project proposal could not
be considered.
W.P.(C).No.25762/2020
6. The petitioner has filed a reply affidavit. It is stated that
with the submission of the project proposal on 30.12.2013, the
petitioner had completed the program. He had taken
readmission to complete the process and since the dates of
rejection of the project proposal without approval is not
specified in the counter affidavit, it is clear that there was no
such rejection and that the petitioner's course is to be declared
as completed.
7. I have considered the contentions advanced. It is the
specific case of the respondents that the validity of the course
was only till December 2015 and that no project could have
been validly submitted thereafter. The petitioner in the instant
writ petition also does not have a case that there was approval
for the project submitted by the petitioner on any date before
December 2015. On the contrary, the petitioner specifically
contends that the project was resubmitted on 05.07.2016.
Therefore, it is evident from the pleadings placed on record by
the petitioner himself that there was no approved project
during the currency of the validity of the course, which ended
in December 2015.
W.P.(C).No.25762/2020
In the above factual situation, I am of the opinion that the
prayers as sought for by the petitioner cannot be granted. The
writ petition thus fails and the same is, accordingly, dismissed.
Sd/-
Anu Sivaraman, Judge sj W.P.(C).No.25762/2020
APPENDIX PETITIONER'S EXHIBITS:
EXHIBIT P1 TRUE COPY OF THE ENROLMENT CERTIFICATE.
EXHIBIT P2 TRUE COPY OF GRADE CARD STATUS ISSUED BY IGNOU
EXHIBIT P3 TRUE COPY OF THE CALENDER FOR THE PROJECT .
EXHIBIT P4 TRUE COPY OF THE COMMUNICATION DATED 23.07.2016.
EXHIBIT P5 TRUE COPY OF THE LETTER ISSUED TO 3RD RESPONDENT.
EXHIBIT P6 TRUE COPY OF LETTER ISSUED BY 2ND RESPONDENT TO 1ST RESPONDENT.
EXHIBIT P7 TRUE COPY OF THE COMMUNICATION RECEIVED FROM 2ND RESPONDENT.
True copy
PS to Judge
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!