Citation : 2021 Latest Caselaw 2544 Ker
Judgement Date : 22 January, 2021
W.P(C).No.17633/2020-D 1
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE SMT. JUSTICE P.V.ASHA
FRIDAY, THE 22ND DAY OF JANUARY 2021 / 2ND MAGHA, 1942
WP(C).No.17633 OF 2020(D)
PETITIONER:
N.D. JOSEPH,
AGED 59 YEARS
PROPRIETOR, TRAVANCORE EARTH MOVING COMPANY,
NELLIMATTATHIL HOUSE, THIRUVAMKULAM P.O.,
PIN-682305, ERNAKULAM.
BY ADVS.
SRI.M.K.DILEEPAN
SRI.DEEPAK T.NEDUNGADAN
SMT.P.SUMITHRA
RESPONDENTS:
1 THE STATE OF KERALA
REPRESENTED BY THE SECRETARY, PUBLIC WORKS
DEPARTMENT, GOVERNMENT OF KERALA, GOVERNMENT
SECRETARIAT, THIRUVANANTHAPURAM, PIN-695033.
2 THE CHIEF ENGINEER,
PUBLIC WORKS DEPARTMENT (ROADS AND BRIDGES),
THIRUVANANTHAPURAM, PIN-695033.
3 THE SUPERINTENDING ENGINEER,
PUBLIC WORKS DEPARTMENT (ROADS AND BRIDGES),
CENTRAL CIRCLE, ALUVA, PIN-683101,
ERNAKULAM DISTRICT.
4 THE EXECUTIVE ENGINEER,
PUBLIC WORKS DEPARTMENT (ROADS DIVISION), PAINAVU,
PIN-685603, IDUKKI DISTRICT.
R4 BY GOVERNMENT PLEADER SMT.VINITHA B.
THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON
12.01.2021, THE COURT ON 22.01.2021 DELIVERED THE FOLLOWING:
W.P(C).No.17633/2020-D 2
P.V.ASHA, J.
-----------------------------------------------------
W.P(c) No.17633 of 2020-D
----------------------------------------------------
Dated this the 22nd day of January, 2021
JUDGMENT
The Writ Petition is filed seeking the following
reliefs:
"a) Issue a writ of mandamus or other appropriate
writ, direction or Order directing the respondents to
raise final bill for the work mentioned in Exhibit-P7
supplementary agreement and to effect payment of amount
due to petitioner for the executed work immediately.
b) Issue a writ of mandamus or other writ
direction or order directing the 2nd respondent to take
immediate steps to settle the bills and to pay amounts
due to petitioner as per Exhibit-P14 letter.
and
c) Grant such other reliefs and orders that this
Hon'ble Court may be deem fit and proper in the facts
and circumstances of the case.
2. The petitioner was awarded the work of NABARD-
RIDF-XV- improvements to Kanjar-Koovappilly-Chakkikavu
- Elaveezhapoonchira - Melukavu-Kanjiramkavala Road in
Idukki district on 21.3.2010. It is stated that on
account of the orders issued in Writ Petitions filed by
other contractors, the petitioner was not able to
commence the work except after the Honourable Supreme
Court passed order dated 26.02.2013 in the Civil
Appeal. The Government thereafter issued Ext.P1 order
dated 03.02.2014 revising the rates from 2009 schedule
of rates to 2012 schedule of rates. The administrative
sanction for the same was issued as per Ext.P2 order on
05.12.2016, for a sum of Rs.16,49,73,183/-. It is
stated that there were other obstacles for continuing
the work as widening of the road and shifting of
electric post etc. could not be done. It is stated that
as per Ext.P3 order dated 15.09.2018 time for
completion of the work was extended upto 31.08.2019
without imposing fine, pointing out that the time had
expired on 31.08.2018. In the meanwhile petitioner had
executed Ext.P4 supplementary agreement on 27.2.2018.
It is stated that the work was originally funded by
NABARD. As the funding RIDF -XV by NABARD expired on
31.03.2017 and the work was not completed within the
period of the said scheme, it became necessary for the
Government to allocate the funds for the work. It is
stated that only 3 part bills were paid to the
petitioner as on 31.10.2016 and thereafter no payment
was made even against part bills though the petitioner
had executed substantial portion of the work. It is
stated that the 4th running account bill was raised by
the Assistant Engineer and it was approved on 28.3.2018
for a sum of Rs.7,64,95,439/-. But the payment was not
made in the absence of fund allocation by the
Government. Therefore, the petitioner approached this
Court filing W.P(C).No.20182 of 2018. As per Ext.P6
judgment, this Court directed the respondents to take
appropriate steps to release the payment within a
period of three months. It is stated that thereafter
the Government passed Ext.P9 order on 22.01.2019
allotting a sum of Rs.5,97,34,634/-. The petitioner
was thereafter paid a sum of Rs.2,96,92,831/- on
21.03.2019. It is pointed out that even that payment
was made only after the petitioner filed a contempt
case. The contempt case was closed as per Ext.P10
judgment allowing the petitioner to raise disputes if
any, regarding the amounts due to the petitioner.
3. It is further stated that the petitioner had
executed Ext.P7 supplementary agreement on 15.09.2018
after extension of time was granted upto 31.08.2019.
It is also stated that the 2nd respondent had requested
for administrative sanction for the work as per Ext.P8
letter on 17.10.2018 based on 2012 SoR. In that letter
request was made for a sum of Rs.14,25,88,281/- for
completion of the work against which the Government had
allotted only Rs.5,97,34,634/-. It is stated that the
fourth part bill which was a subject matter of the Writ
Petition covered by Ext.P6 judgment was in respect of
the work carried out before 28.03.2018. After the
fourth part bill, the respondents did not raise any
part bill though the petitioner continued the work till
31.08.2019. The petitioner submitted that payment was
made against Ext.P4 bill only for the quantity as per
tender schedule and the respondent did not obtain
approval of revised estimate on the basis of the actual
quantity. However, it is stated that by 01.08.2019
approval was obtained for the revised estimate before
the expiry of the extended period of contract. It is
stated that the petitioner had requested for payment of
a sum of Rs.1,78,45,727/- towards the work executed
over and above the scheduled quantity which was part of
the fourth part bill in addition to a sum of
Rs.56,24,097/- towards the work done thereafter. The
respondents did not make any payment thereafter though
the petitioner made several requests. It is stated
that as per Ext.P11 representation the petitioner had
requested the 2nd respondent to relieve him from the
work. The 4th respondent issued Ext.P12 letter
directing the petitioner to complete the work
immediately, alleging inaction on his part to complete
the work as per the revised estimate. As per Ext.P13
letter dated 04.02.2020, the petitioner informed that
he would not be able to complete the balance work under
2012 schedule of rates in view of the adverse site
conditions and in view of his bank loan account being
turned as NPA due to non payment of bills. It is
stated that thereafter he submitted Ext.P14
representation on 17.06.2020 demanding payment of
Rs.1,78,45,727/- for the work done over and above the
original schedule quantity of the work till the fourth
part bill dated 28.3.2018 for Rs.56,24,097/- towards
the work done till 31.08.2018 and for another Rs.30
lakhs for the work executed upto 31.8.2019 along with
interest @ 12.45% per annum. The Writ Petition was
filed thereafter alleging that the respondents are not
taking any action. According to the petitioner, he is
not responsible for the delay caused in carrying out
the work. It is stated that the very fact that the
extension was granted without any penalty would show
that the delay was not attributable to him. It is
stated that the petitioner had to carry out the work by
mobilising funds from banks since the respondents did
not make any payment on the ground that the funds from
NABARD had lapsed. The petitioner states that when the
respondents have not even raised bills for the works
executed upto 31.8.2019 and also for the extra work
done, he is not bound to execute the balance work.
4. The 4th respondent filed a statement. It is
stated that the work awarded to the petitioner was
under the NABARD RIDF-XV scheme which was originally
tendered for administrative sanction amount of Rs.10
crores on 03.02.2010. But on account of a stay order
in W.P(C).No.9016/2010 filed by another contractor, the
agreement could be executed only on 10.3.2011.
Subsequent to the judgment in that Writ Petition on
24.02.2011, the site was handed over to the contractor
on 19.03.2011 and the department took necessary steps
to start the work by taking initial levels. The work
was stayed by the Supreme Court on 04.04.2011 in SLP
No.8169/2009. The contract was renewed after the said
stay order was vacated in February, 2013, extending the
validity period upto 21.01.2014. It is stated that the
total length of the road for the work was 13.46
kilometres (main road 10.92 km and bi-roads of 0.800 km
and 1.74 km). The petitioner requested to refix the
rate in the year 2013 in view of the lapse of time. The
Government thereupon issued G.O.Ms.10/2014/PWD
dt.03.02.2014 for revising the estimate under SOR 2012.
Revised estimate was prepared and forwarded for
sanction on 14.08.2014 and it was sanctioned on
30.08.2017. In the meanwhile, extension was granted
for completion of work upto 19.02.2015, 19.02.2016,
19.02.2017 and 31.08.2018. It is stated that as
against 13.46 km which was to be improved the work
executed by the petitioner is only 4 km; the works like
culvert, drainage and retaining wall were not completed
even in the said 4 km, apart from the fact that tarring
work was not satisfactory. It is stated that the road
is even now not traffic worthy and the petitioner did
not rectify the defect. It is stated that the
petitioner was directed to complete the work at the
earliest issuing a letter dated 01.01.2020 which was
followed by another notice on 22.01.2020 and thereafter
as per Ext.P12 notice in which the petitioner was
informed that on failure to complete the work, it could
be terminated at his risk and cost. It is stated that
despite all these, the petitioner did not resume or
complete the work though Ext.R4(b) notice was issued on
17.06.2020. It is also stated that recommendation is
already made for terminating the contract at the risk
and cost of the petitioner.
5. The petitioner has filed a reply to the
statement pointing out that the work could be commenced
only after 26.2.02013 at a time when 2012 PWD schedule
of rates was in force. Even though the respondent had
issued Ext.P1 order on 03.02.2014 granting
administrative sanction for the work under 2012 SOR,
the said order was issued under the impression that a
portion of the work was completed before implementation
of 2012 SOR. Thereafter, revised orders were issued
only on 5.12.2016, after the delay of more than 3 years
and 10 months. It is stated that eventhough Ext.P2
order was issued on 5.12.2016, there were some more
anomalies to be clarified and the final order was
issued only on 30.08.2017 by the 2nd respondent. It is
stated that despite this the petitioner continued to
work and the first RA bills were prepared under 2009
SOR.
6. According to the petitioner, he has completed
the formation of entire 13.5 km and also 2 layer of
metallic work by 27.9.2016. The respondents made
payment only for the work till 09.1.2017 towards 3 RA
bills. It is also stated that the funds from NABARD
got lapsed only because of the laches on the part of
the respondents in getting administrative sanction in
the revised rate. It is stated that the petitioner
lost the opportunity to compound the sale tax also on
account of the delay. Pointing out the injustice in
denying the payment of Rs.1,83,12,993.84 despite the
fact that the fourth RA bill was for Rs.7,80,47,628/-,
the petitioner submitted that the denial of payment is
unjust as the petitioner has been continuing the work.
It is stated that the respondents had approached the
Government for fund allocation only after the
petitioner filed a contempt case and despite the
administrative sanction granted in Ext.P9 order the
amount paid to the petitioner on 21.3.2019 was not in
accordance with the bills raised and the respondents
did not pay the amount due to the petitioner towards
the work covered by the first 3 bills under the
schedule of revised rates. It is also alleged that
Ext.P8 would show the amount already paid to the
petitioner as well as amount to be paid to the
petitioner till the fourth part bill and to be paid to
the petitioner thereafter which could not be paid due
to the lapse of the NABARD fund. It is also pointed
out that the amount required for compliance of the
judgment was also stated in Ext.P8, but payment was not
made based on the said statement.
7. The petitioner also pointed out that Ext.P15
bill was raised by the Assistant Engineer towards the
work done by the petitioner till 2019, which would
show that the petitioner had completed the work for
Rs.8,57,92,413.66 out of which the amount paid was only
4,80,05,825/-. It is also his case that except
Ext.P16 notice dated 09.10.2020, that too, after filing
of the Writ Petition, asking him to fill the pot holes
and to rectify the defect, no other notice was issued
pointing out any defects and the petitioner had already
informed the respondents that defect would be rectified
on settlement of the payment.
8. According to the learned Government Pleader,
steps are afoot for termination of the work at the risk
and cost of the petitioner for which recommendation is
already made. It is stated that when termination is
ordered, 30% of the amount for the work is to be
realised/withheld by the Department. The amount due to
the petitioner would not be sufficient to meet the said
30%. Therefore, no payment can be made.
9. Having heard the contentions on both sides it
is clear that the petitioner was able to commence the
work only after 26.02.2013, on account of interdiction
by the orders from this Court/the Apex Court. It is
also clear that the administrative sanction for the
work, granted on the basis of 2009 schedule of rates
was revised to 2012 rates and after two rectifications
the revised administrative sanction was issued only on
30.08.2017. The contention of the petitioner is that
payment towards 3 part bills were made as on
31.10.2016. It cannot be disputed that the said
payment was made at 2009 rates, as sanction for the
revised estimate under the 2012 rate was accorded only
on 30.08.2017. Therefore, there is no justification in
denying payment of the balance amount due towards the
three part bills, to the petitioner reckoning the
revised rates of 2012.
10. In the judgment Ext.P6 in W.P.(C)
No.20182/2018, this Court directed payment towards the
part bill dated 28.03.3018. Thereafter, the Chief
Engineer had, in the letter Ext.P8 addressed to the
Principal Secretary, explained the amount due towards
the first 3 bills, from which it is seen that a sum of
Rs.1,83,12,994 is due. Ext.P8 would also show that the
respondents could not make payment to the contractor
due to the termination of the NABARD RIDF-XV which was
closed on 31.3.2017. The respondents do not deny the
contents of Ext.P8 letter. If at all the petitioner
has not completed the work, in Ext.P8 it is stated as
follows:
"Administrative Sanction for the subject work was
accorded vide GO (Rt) 34/2010/PWD dated 07.01.2010 for
Rs.10 Crores. Technical Sanction was issued vide TS
No.896/CE/2009-10 dated 15.01.2010 and awarded to
Travancore Earth moving company to complete the work
within 24 months Due to legal proceedings such as WP(C)
No.9016/2010 and wit appeal 198/2011 before the Hon'ble
High Court of Kerala and the proceedings before the
Hon'ble Supreme Court in Special leave to appeal (Civil)
No.S/8169/2011 at the instance of Contractors whose
tenders were not accepted, the execution of the work was
delayed. Finally the Hon'ble Supreme Court by order in
special leave to appeal dated 26.02.2013, allowed the
Travancore Earth moving company to commence the work.
Since the PAC for the work was originally fixed
based on 2009 PWD schedule of Rates the contractor could
not even commence the work even after 2012 schedule of
rates was implemented. The contractor requested for
revision of rates and it took time to get Revised
Administrative Sanction from the Government for the work
with rate enhancement. As per order GO (MS)
No.10/2014/PWD Dated 3.2.2014 issued by the Secretary to
Government Administrative Sanction with enhancement of
rates at 18.1% below 2012 schedule of rates for the
balance portion of the work was allowed. Thereafter by
GO (Rt) No.1664/2016/PWD dated 5.12.2016 the Deputy
Secretary to Government accorded revised Administrative
Sanction for the work for an amount of Rs.16,49,73,183/-
against Rs.10 crores originally sanctioned. The
contractor has completed a total amount of work of
Rs.7,80,47,628/- of which Rs.1,83,12,994/- only was paid
to the contractor till date. A balance amount of
Rs.5,97,34,634/- to be paid to the contractor for items
of the work which he has already completed till date.
The Contractor had filed a case before the Hon'ble
High Court of Kerala case No.WP(C) 20182 of 2018 where
in the Hon'ble High Court passed the judgment (Ref:2)
directing the Government to take appropriate steps to
release the payment within a period of three months at
the earliest and it was also directed that any request
made from the contractor for an early release of the
bill also be considered sympathetically by the
Government in its finance department.
A total amount of Rs.14,25,88,281/- is needed for
the payment of the work already completed and for the
balance work is to be completed.
The bill already paid and to be paid to the
contractor and the amount further needed for the
satisfactory completion of the work are as below.
Details of bill paid to the contractor.
Sl. Description Bill No. & Date C.V.B No. Bill amount in No. Rs.
1 CC Ist and Part bill 3/N/2014-15 CBV 14/Dn. Of 08/14 67,02,375/-
dtd.25.7.2014 dtd 5.8.2014
2 CC IInd and Part bill 2/N/2015-16 dtd CBV 10/Dn. Of 08/14 28,02,431/-
25.5.2015 dtd 15.09.2015
3 CC IIIrd and part bill 6/N/2016-17 dted CBV 14/Dn.of 08/14 88,08,188/-
9.1.17 dtd 30.3.2017.
Total 1,83,12,994/-
Details of the bill amount to be paid to the contractor
Sl.No. Description Bill amount in Re Rs.
marks
1 Part bill IV 3,62,89,525/-
2 Part Bill V 56,24,097/-
3 The bill amount to be 1,78,21,012/- The amount was not paid to the
paid for the work already contractor due to the termination
completed of the NABARD RIDF XV
Total 5,97,34,634
Since the NABARD-RIDF XV tranche was already closed
on 31.03.2017, there is no scope of any fund for payment
from NABARD for this work. A total amount of
Rs.14,25,88,281/- is to be sanctioned from the State fund.
To comply the judgement as per reference (2) cited an
amount of Rs.5,97,34,634/- is to be paid to the contractor
before 31.10.2018. So I kindly request your goodself to
take necessary action for sanctioning the required amount
at the earliest."
11. In the said circumstances, the denial of
payment for the said work, which is covered by the
judgment Ext.P6 and admitted in Ext.P8 letter is
illegal. If at all the respondents propose to issue
orders of termination of work at risk and cost, they
can take appropriate steps which are legally available
to them to realise the loss if any caused. The
respondents are not justified in denying payment based
on grounds which they did not raise or even mention in
Ext P8 letter. The amount found due to the petitioner
in Ext.P8 letter was a sum of Rs.5,97,34,634/-, out of
which the respondents paid only a sum of
Rs.2,96,92,831/-. The petitioner would therefore be
entitled to the balance amount in tune with Ext.P8
letter. Regarding the work carried out thereafter the
respondents have raised a dispute.
12. Therefore, the Writ Petition is disposed of
with a direction to the respondents to effect the
payment of the balance amount due to the petitioner in
accordance with the calculation made in Ext.P8 letter,
ie - balance towards the total amount of
Rs.5,97,34,634/-, within a period of two months from
the date of receipt of a copy of the judgment.
13. The claim of the petitioner for the subsequent
period is left open.
Sd/- (P.V.ASHA, JUDGE)
rtr/
APPENDIX PETITIONER'S EXHIBITS:
EXHIBIT P1 TRUE COPY OF THE ORDER ISSUED BY 1ST RESPONDENT DATED 03.02.2014.
EXHIBIT P2 TRUE COPY OF THE ORDER ISSUED BY 1ST RESPONDENT DATED 05.12.2016.
EXHIBIT P3 TRUE COPY OF THE ORDER ISSUED BY 3RD RESPONDENT DATED 15.09.2018.
EXHIBIT P4 TRUE COPY OF SUPPLEMENTAL AGREEMENT DATED 27.02.2018.
EXHIBIT P5 TRUE COPY OF THE REPRESENTATION GIVEN BY PETITIONER DATED 20.03.2018.
EXHIBIT P6 TRUE COPY OF THE JUDGMENT IN W.P.
(C)NO.20182/2018 DATED 30.07.2018.
EXHIBIT P7 TRUE COPY OF SUPPLEMENTAL AGREEMENT DATED 15.09.2018.
EXHIBIT P8 TRUE COPY OF LETTER ISSUED BY 2ND RESPONDENT TO THE PRINCIPAL SECRETARY DATED 17.10.2018.
EXHIBIT P9 TRUE COPY OF THE FUND ALLOCATION ORDER ISSUED BY GOVERNMENT DATED 22.01.2019.
EXHIBIT P10 TRUE COPY JUDGMENT IN CONTEMPT CASE(C)NO.229/2019 DATED 01.08.2019.
EXHIBIT P11 TRUE COPY OF THE LETTER ISSUED BY PETITIONER TO 3RD RESPONDENT DATED 01.11.2019.
EXHIBIT P12 TRUE COPY OF THE LETTER ISSUED BY 4TH RESPONDENT TO PETITIONER DATED 22.01.2020.
EXHIBIT P13 TRUE COPY OF THE REPLY LETTER ISSUED BY PETITIONER TO 4TH RESPONDENT DATED 04.02.2020.
EXHIBIT P14 TRUE COPY OF THE LETTER ISSUED BY PETITIONER TO 3RD RESPONDENT DATED 17.06.2020.
EXHIBIT P15 TRUE COPY OF THE 5TH R.A BILL PREPARED BY ASST.EXECUTIVE ENGINEER TO 4TH RESPONDENT DATED 26/8/2020.
EXHIBIT P16 TRUE COPY OF THE NOTICE ISSUED BY ASST.EXECUTIVE ENGINEER, THODUPUZHA DATED 9/10/2020.
EXHIBIT P17 TRUE COPY OF THE REPLY GIVEN BY PETITIONER TO EXHIBIT-P16 NOTICE DATED 22/10/2020.
EXHIBIT P18 TRUE EXTRACT OF THE RELEVANT PAGE OF PWD MANUAL REGARDING RETENTION OF AMOUNT FROM BILL.
RESPONDENTS' EXHIBITS
ANNEXURE R4(a) TRUE COPY OF THE NOTICE DATED 1.1.2020 ISSUED BY THE ASSISTANT ENGINEER, ROADS SECTION, MUTTAM, IDUKKI.
ANNEXURE R4(b) TRUE COPY OF THE NOTICE DATED 17.06.2020 ISSUED BY THE ASSISTANT ENGINEER, ROADS SECTION, MUTTAM, IDUKKI.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!