Citation : 2021 Latest Caselaw 2421 Ker
Judgement Date : 21 January, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE SMT. JUSTICE P.V.ASHA
THURSDAY, THE 21ST DAY OF JANUARY 2021 / 1ST MAGHA, 1942
WP(C).No.23599 OF 2020(Y)
PETITIONER:
PAILY ABRAHAM, AGED 70 YEARS, S/O.PAILY,
ERUMBAIL HOUSE, KUNNACKAL P.O., VALAKOM,
MUVATTUPUZHA, ERNAKULAM - 682 316.
BY ADVS.
SRI.ANIL GEORGE
SRI.JOBY JACOB PULICKEKUDY
SHRI.DAJISH JOHN
SHRI.HARIKRISHNAN P.
RESPONDENTS:
1 KERALA WATER AUTHORITY,
REPRESENTED BY THE MANAGING DIRECTOR, JALABHAVAN,
THIRUVANANTHAPURAM - 695 033.
2 THE SUPERINTENDING ENGINEER,
PH CIRCLE, KERALA WATER AUTHORITY,
MUVATTUPUZHA - 686 673.
3 THE EXECUTIVE ENGINEER,
OFFICE OF THE EXECUTIVE ENGINEER, PROJECT DIVISION,
KERALA WATER AUTHORITY, KATTAPPANA - 685 508.
4 THE FINANCE MANAGER AND CHIEF ACCOUNTS OFFICER,
KERALA WATER AUTHORITY, JALABHAVAN,
THIRUVANANTHAPURAM - 695 033.
R1-4 BY ADV. SRI.P.BENJAMIN PAUL, SC
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
21.01.2021, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
WP(C).No.23599 OF 2020(Y)
-2-
JUDGMENT
Dated this the 21st day of January 2021
The petitioner has completed the works
awarded to him by the Kerala Water Authority
after executing Ext.P1 agreement on 22.02.2018.
2. After completion of the work, the second
respondent issued a Work Completion/
Commissioning Certificate. It is stated that
the work has completed on 12.04.2019. It is
also stated that even after the guarantee period
expired on 12.11.2020 on completion of 18 months
the respondents are holding security deposit,
retention amount, maintenance guarantee amount
and trial run expenses.
3. The learned Standing Counsel for the
Water Authority submits that even though the
work has been completed, the project has not
been commissioned. According to the petitioner,
the delay in commissioning is not on account of
any fault on the part of him. The learned WP(C).No.23599 OF 2020(Y)
standing counsel further points out that the
amount retained towards the trial run
expenses/maintenance guarantee can be refunded
only after the commissioning as well as after
the expiry of maintenance period in tune with
the provisions contained in the agreement and
that cannot be disbursed to the petitioner at
this stage.
4. The learned counsel for the petitioner
points out that, this Court has in various
judgments directed release of the amount when
commissioning was delayed, pointing out that the
delay in commissioning was never on account of
the default on the part of the contractors.
Relying on judgment, dated 9.10.2015, in W.P.(C)
No.30040 of 2015, produced as Ext.P3, the
learned counsel for the petitioner seeks
direction to the respondents to disburse the
amounts due to petitioner on execution of a
simple bond. The judgment dated 27.06.2019 in
W.P.(C) No.11327 of 2019 is also relied on. WP(C).No.23599 OF 2020(Y)
In these circumstances, there shall be a
direction to the 1st respondent - the Managing
Director to consider the claim of the petitioner
for release of the amount due to him, and to
pass orders on the same taking note of the
judgments of this Court directing payment in
such circumstances on execution of a simple
bond. Orders shall be passed within a period of
three weeks from the date of receipt of a
certified copy of this judgment.
The writ petition is disposed of as above.
Sd/-
P.V.ASHA JUDGE akv WP(C).No.23599 OF 2020(Y)
APPENDIX PETITIONER'S/S EXHIBITS:
EXHIBIT P1 THE PHOTOCOPY OF THE AGREEMENT DATED 22/02/2018 BETWEEN THE PETITIONER AND THE 2ND RESPONDENT.
EXHIBIT P2 TRUE PHOTOCOPY OF WORK COMPLETION/COMMISSIONING CERTIFICATE ISSUED BY THE 3RD RESPONDENT.
EXHIBIT P3 THE TRUE PHOTOCOPY OF JUDGMENT DATED 9.10.2015 IN WP(C)NO.30040/15.
EXHIBIT P4 THE TRUE PHOTOCOPY OF JUDGMENT DATED 27.06.2019 IN WP(C)NO.11327/2019.
RESPONDENT'S/S EXHIBITS : NIL.
//TRUE COPY// P.A. TO JUDGE
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!