Citation : 2021 Latest Caselaw 2349 Ker
Judgement Date : 21 January, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE SMT. JUSTICE P.V.ASHA
THURSDAY, THE 21ST DAY OF JANUARY 2021 / 1ST MAGHA, 1942
WP(C).No.27862 OF 2020(G)
PETITIONER:
P.THYAGARAJAN, AGED 60 YEARS, S/O.S.PANKAJAKSHAN,
VRINDAVAN, PERINGAMALA, KALLIYOOR P.O.,
THIRUVANANTHAPURAM-695 742.
BY ADV. SRI.S.SACHITHANANDA PAI
RESPONDENT:
THE EXECUTIVE ENGINEER,
CENTRAL PUBLIC WORKS DEPARTMENT,
OFFICE OF THE EXECUTIVE ENGINEER, C WING,
1ST FLOOR, CGO COMPLEX, POONKULAM, VELLAYANI P.O.,
THIRUVANANTHAPURAM-695 522.
BY ADVS.SRI.P.VIJAYAKUMAR, ASG OF INDIA
SRI.GIRISHKUMAR.V., CGC
SRI.CGC.SMT.KRISHNA,
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
21.01.2021, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
WP(C).No.27862 OF 2020(G)
-2-
JUDGMENT
Dated this the 21st day of January 2021
The petitioner, who is an A class civil
works contractor, has filed this writ
petition aggrieved by Ext.P6 order dated
8.12.2020 of termination of the contract. He
seeks a direction to the respondent to permit
him to complete the construction within a
reasonable time.
2. As per Ext.P1 letter dated 16.7.2018
the respondent accepted the e-tender
submitted by petitioner for the work of
"construction of 0.75 unit dormitory (G+1)
for girls at Navodaya Vidyalaya, Vithura,
District Thiruvananthapuram, Kerala including
water supply, sanitary installations,
drainage and internal electrical
installations, fans and fittings." It is WP(C).No.27862 OF 2020(G)
stated that after furnishing performance
guarantee on 25.7.2018, he started the work
in August 2018; but he was unable to complete
the work within the stipulated time because
of the outbreak of Covid-19 pandemic. He has
further stated that, in answer to a show
cause notice from the respondent, he had
submitted Ext P2 explanation on 4.6.2020,
undertaking to complete the work by
30.9.2020. It is his further case that the
Principal of the School, where the
construction was going on, had requested him
as per Ext.P3 letter, dated 29.07.2020, to
stop the work due to the fear of spread of
Covid-19, pointing out that the teachers were
residing there with family. It is also
submitted that he was constrained to stop the
work on the basis of the said letter as well WP(C).No.27862 OF 2020(G)
as the oral direction of the respondent.
While so, the petitioner was issued with
Ext.P4 show cause notice on 30.10.2020
proposing termination of the contract
invoking Clause 3(a)(b) of General Conditions
of Contract for Central PWD works 2014. It is
stated that though petitioner submitted
Ext.P5 explanation on 10.11.2020 explaining
the entire circumstances, the respondent
issued Ext.P8 order on 8.12.2020, terminating
the contract and forfeiting the performance
guarantee as well as the earnest money
deposit. Petitioner was directed to report
before the respondent for joint measurement.
It is stated that contract is terminated
without appreciating the fact that the work
had to be stopped at the request of the
Principal; without taking note of the WP(C).No.27862 OF 2020(G)
scarcity of labourers after the Covid-19
outbreak and without considering any of the
factual circumstances pointed out in his
explanation. It is stated that he had
already requested for extension of time up to
30.01.2021 and not to take any penal action
against him.
3. According to the petitioner, he
would be able to complete the work, in case
he is given three months' time as he has made
all arrangements for the same. The learned
counsel for the petitioner submitted that a
re-tender at this stage would only be
contrary to public interest as it would
involve more expenditure to the Government as
the rate of work would be different.
4. The learned central Government
Counsel has filed a statement on behalf of WP(C).No.27862 OF 2020(G)
the respondent refuting the contentions
raised by the petitioner. It is stated that
pursuant to Ext.P1 letter of acceptance, an
agreement was entered into between the
petitioner and the Executive Engineer,
wherein it was stipulated that the period of
completion of the work would be 210 days,
specifying the date of commencement of the
work as 31.07.2018 and due date of completion
as 25.2.2019. It is therefore stated that
the outbreak of Covid-19 pandemic which
occurred after an year could not have been
the reason for delay in completion of work.
It is stated that the respondent had been
asking the petitioner to accelerate the
progress of work with due diligence issuing
Annexure R1(b) to R1(p) letters issued
between 25.01.2019 and 27.11.2019 and WP(C).No.27862 OF 2020(G)
thereafter, informing him the violation of
contractual conditions and obligations from
his part with warning that the department
would be forced to take action under Clause 3
of the contract on failure to maintain
desired progress of the work. It is stated
that during inspections several defects in
the work and lapses in safety were found. He
was given several chances to improve the
quality of work, speed etc. to abide by the
programme of work, in each of the notices
issued to him, where the lapses were
explained. On expiry of the time schedule on
25.02.2019, extension was granted upto
31.08.2019 without prejudice to the right of
Government to recover liquidated damages; the
Chief Engineer had also examined the case and
it was found that petitioner was responsible WP(C).No.27862 OF 2020(G)
for the delay. It is stated that despite the
direction of the Chief Engineer in Annexure
R1(e) letter dated 08.08.2019, while giving
another opportunity to petitioner, even after
finding the petitioner solely responsible for
the delay, petitioner did not submit the
application for rescheduling of milestone for
completion of work on war footing, in a
proper format, even after reminding him the
same in Annexure R1(i) letter of the
respondent or in Annexure R1(j) letter of the
Superintending Engineer. In the absence of
any proper application for ROM or for
extension of time and taking note of the slow
pace in the work the Chief Engineer issued
Annexure R1(k) show cause notice on
27.11.2019 under Clause 2 of the agreement
proposing action against the petitioner for WP(C).No.27862 OF 2020(G)
imposing compensation for the prolonged delay
and the casual approach of the petitioner,
stating that there was no likelihood of
completion of work within 07.02.2020, as per
the work schedule submitted by petitioner. It
is stated that the respondent had issued
another show cause notice Annexure R1(l)
dated 03.05.2020 to petitioner for action
under Clause 3 and after considering the
explanation of the petitioner and taking note
of the outbreak of Covid-19 and the lockdown
measures the respondent had, in Ext.R1(m)
letter dated 04.06.2020, recommended
extension of time till 30.09.2020. But even
thereafter petitioner did not take any pro-
active steps. Therefore Ext.P4 show cause
notice was issued for proceeding under clause
3. It is stated that Annexure R1(n)and R1(o) WP(C).No.27862 OF 2020(G)
letters would show that the explanation of
petitioner was considered. While terminating
the contract the reasons for the same are
also stated in Ext.P6, which are sufficient
for termination. It is stated that the
Principal as well as the Chairman of the
managing Committee had expressed serious
concern over the delay in completion of the
work in their letters Annexure R1(p) dated
27.11.2019, Annexure R1(r)letter dated
25.02.2020. It is stated that the Principal
had as per Annexure R1(s) letter dated
06.10.2020 requested to hand over the
building immediately, pointing out the
inconvenience caused to them. It is stated
that petitioner himself assumed that
extension was given till 31.01.2021, even in
the absence of any such orders. He used to WP(C).No.27862 OF 2020(G)
raise false allegations against the
department. It is also pointed out the
petitioner has already been found responsible
for the delay in completion of construction
of other two hostels also in
Thiruvananthapuram.
5. The petitioner filed a reply affidavit stating that though the respondent never extended the period of
contract fixed as on 25.02.2019, the request
of petitioner for extension till 30.01.2021
was never objected. It is stated that he has
satisfactorily completed several works like
those covered by Exts.P6 and P7 produced
along with the reply affidavit, under the
respondent and that he had been carrying out
the present work also with due diligence.
According to him, the delay occurred because WP(C).No.27862 OF 2020(G)
of the inaction of the respondent in
furnishing the drawings, non-finalisation of
location lay out, etc. It is stated that the
revised structural drawings for foundation
details of the building were made available
only on 08.11.2018; plinth level and
foundation details were finalised only on
12.11.2018; architectural drawings were
issued only on 16.04.2019, that too after a
series of correspondence in Exts.P9 to P12
letters sent to the respondent between
03.09.2018 and 23.02.2019, in which he had
explained the hindrances occurred in the
execution of work. It is stated that the
drawings of the part plan basement level and
ground level of toilet block was issued only
on 17.08.2019, as evident from Ext.P8 letter
of the respondent, whereas the actual WP(C).No.27862 OF 2020(G)
completion of the work stipulated was
25.01.2019. It is also his case that his
application for extension of period of
contract was accepted by the respondent
without any reservation. It is stated that
the work which was stopped at the instance of
the Principal of the School could be
restarted only with the minimized structural
resources in the absence of sufficient number
of labourers. Pointing out Ext.P13 payment
agreement as well as 7th RA bill approved in
Ext.P15 by the respondent on 30.10.2020 and
5.12.2020 respectively and the payment
effected as per Ext.P16 memorandum on
21.12.2020, the petitioner claims that the
respondent had impliedly granted extension
based on his request in Ext P14 letter dated
07.09.2020. According to him payment could WP(C).No.27862 OF 2020(G)
not have been made to him in the absence of
extension of time for completion of work or
after termination of contract. It is stated
that the work, which he had to stop in July
2020 at the instance of Principal, could be
restarted only after permission was granted
on 26.08.2020. The work could be restarted by
15.09.2020, after arranging sufficient
labourers, and materials. According to
petitioner, he had explained the reasons for
the delay, in the explanation he had
submitted and had assured to complete the
work by 30.01.2021. After the respondent
allowed the petitioner to continue with the
work, the termination of contract by Ext.P6
order is mala fide. It is stated that the
work awarded to him at 2016 schedule of rates
would have to be re-arranged only at WP(C).No.27862 OF 2020(G)
escalated rate of 2018 which would incur more
expenditure to Government. It is the case of
the petitioner that he has not violated any
of the conditions of contract and it would be
in furtherance of public interest to permit
him to complete the work.
6. I heard Sri.Sachithanada Pai the
learned Counsel for the petitioner and the
learned CGC appearing for the respondent.
The learned counsel for the petitioner
submits that petitioner requires only three
more months' time to complete work. The
learned Central Government Counsel on
instructions submitted that the respondent as
well as the Department has lost confidence in
the petitioner. The learned Central
Government Counsel also points out that when
the respondents have arrived at the decision WP(C).No.27862 OF 2020(G)
to terminate the contract only after taking
note of all the circumstances, the progress
of work etc. this Court may not interfere
with the same. It is also argued that nothing
prevents the respondent from making payment
for the work that have been already carried
out and such payment cannot imply grant of
extension of time for completion of work.
7. When the petitioner submits that
he has completed major part of the work, it
is disputed by the respondent. Similarly the
reason for the delay caused in completion,
according to petitioner, is on the
respondent; whereas it is solely on
petitioner, according to the respondent.
Petitioner claims that there was implied
extension of time for completion which is
stoutly opposed by respondent.
WP(C).No.27862 OF 2020(G)
8. Admittedly there is no order
granting extension of time to the petitioner
for the period up to 30.01.2021. Petitioner
claims only implied extension.
9. It is seen that the contract is
terminated in accordance with the provisions
contained in the agreement executed between
the parties as well as the provisions
contained in the General Conditions of
Contract. There is serious dispute as to the
reason for the delay apart from the plea of
loss of confidence on the petitioner. In such
circumstances, this Court will not be
justified in interfering with the issue.
Though the petitioner pointed out that he
would complete the work within a period of
three months or that there would be
additional expenditure on account of WP(C).No.27862 OF 2020(G)
enhancement of rate in the event of a re-
tender, when the respondents submit that they
have lost confidence in a party, this Court
cannot compel the respondents to permit the
petitioner to work. It is seen that a number
of notices were being issued to petitioner to
accelerate the progress of work, though
petitioner asserts that delay was caused at
the instance of respondent. The termination
is seen effected after a lot of
correspondence between the parties and it is
stated that the said termination is in
accordance with clause 3 of the agreement.
Therefore it is only appropriate for the
petitioner to co-operate with the respondent
to complete the joint measurement.
10. The scope of judicial review in
contractual matters is very limited. In the WP(C).No.27862 OF 2020(G)
judgment in State of Kerala v. M.K. Jose:
(2015) 9 SCC 433 the Apex Court held that
Court should ordinarily not entertain a writ
petition, if there is a breach of contract
when factual disputes are involved. The Apex
Court was considering an appeal against the
judgment of this court which permitted the
contractor to proceed with the work after
setting aside the termination of contract
based on the report filed by the Advocate
Commissioner, regarding the quantum of work
executed. In the judgment in ABL
International Ltd. v. Export Credit Guarantee
Corpn. of India Ltd.: (2004)3SCC 553, the
Apex Court, held that though judicial review
in contractual matters is not totally
excluded, the plenary right of the High
Court to issue a prerogative writ will not WP(C).No.27862 OF 2020(G)
normally be exercised by the Court unless the
action of the State or its instrumentality is
arbitrary and unreasonable so as to violate
the constitutional mandate of Article 14 or
for other valid and legitimate reasons, for
which the Court thinks it necessary to
exercise the said jurisdiction. In Noble
Resources Ltd. v. State of Orissa:
(2006)10SCC 236 it was held that the question
whether power to exercise judicial review
should be exercised, should be decided in the
factual circumstances of each case. While
considering the challenge against award of
contract the Apex Court, in Tata Cellular:
Union of India: (2004)6 SCC 651, held that
the role of the court in matters involving
contracts is only to review the manner in
which the decision is taken and the Court WP(C).No.27862 OF 2020(G)
which does not have expertise in matters
covered by the tender would not venture to
correct the administrative decision and there
should be a fair play in the joints for an
administrative body and that the
administrative decision must not only be
tested by the application of principle of
reasonableness while it should also be free
from arbitrariness not affected by bias or
actuated by mala fides.
Therefore, I am of the view that interference with the Ext.P6 order is not warranted under Article 226 of the constitution of India. The writ petition
accordingly dismissed. In order to enable the
respondents to re-tender the work, the
petitioner shall co-operate with the
respondents for the joint measurement without WP(C).No.27862 OF 2020(G)
any delay. Admitted payment if any due to the
petitioner shall also be made after the same.
It is made clear that the dismissal of
the writ petition will not stand in the way
of the petitioner invoking the remedies
available to him in accordance with law.
Sd/-
P.V.ASHA JUDGE akv WP(C).No.27862 OF 2020(G)
APPENDIX PETITIONER'S/S EXHIBITS:
EXHIBIT P1 COPY OF THE ACCEPTANCE OF TENDER ISSUED BY THE RESPONDENT.
EXHIBIT P2 EXPLANATION DATED 04.06.2020 OF THE PETITIONER.
EXHIBIT P3 LETTER DATED 29.07.2020 OF THE PRINCIPAL, NAVODAYA VIDYALAYA.
EXHIBIT P4 SHOW CAUSE DATED 30.10.2020 OF THE RESPONDENT.
EXHIBIT P5 EXPLANATION DATED 10.11.2020 OF THE PETITIONER.
EXHIBIT P6 LETTER OF TERMINATION OF CONTRACT OF THE RESPONDENT DATED 08.12.2020.
EXHIBITS ALONG WITH REPLY AFFIDAVIT:
EXHIBIT P6 COPY OF THE COMPLETION CERTIFICATE ISSUED BY THE RESPONDENT DATED 02.07.2016.
EXHIBIT P7 COPY OF THE COMPLETION CERTIFICATE ISSUED BY THE RESPONDENT DATED 06/02/2020.
EXHIBIT P8 COPY OF THE LETTER DATED 17/08/2020 OF THE RESPONDENT.
EXHIBIT P9 COPY OF THE LETTER DATED 03/09/2018 OF THE PETITIONER.
EXHIBIT P10 COPY OF THE LETTER DATED 30/10/2018 OF THE PETITIONER.
EXHIBIT P11 COPY OF THE LETTER DATED 09/11/2018 OF THE PETITIONER.
EXHIBIT P12 COPY OF THE LETTER DATED 23/02/2019 OF THE PETITIONER.
EXHIBIT P13 COPY OF MEMORANDUM OF PAYMENT ON AGREEMENT DATED 30/10/2020.
WP(C).No.27862 OF 2020(G)
EXHIBIT P14 COPY OF THE LETTER DATED 07/09/2020 OF THE PETITIONER.
EXHIBIT P15 COPY OF ABSTRACT BOOK OF RUNNING ACCOUNT DATED 05/12/2020.
EXHIBIT P16 COPY OF MEMORANDUM OF PAYMENT ON AGREEMENT DATED 21/12/2020.
RESPONDENT'S/S EXHIBITS:
ANNEXURE R1(A) COPY OF LETTER FROM THE ASSISTANT ENGINEER DATED 26/08/2020.
ANNEXURE R1(B) COPY OF LETTER FROM THE RESPONDENT DATED 25/01/2019.
ANNEXURE R1(C) COPY OF LETTER FROM THE RESPONDENT DATED 18/07/2019.
ANNEXURE R1(D) COPY OF LETTER FROM THE RESPONDENT DATED 03/08/2019.
ANNEXURE R1(E) COPY OF LETTER FROM THE CHIEF ENGINEER DATED 08/08/2019.
ANNEXURE R1(F) COPY OF LETTER FROM THE PETITIONER DATED 19/08/2019.
ANNEXURE R1(G) COPY OF PROGRAM CHART SUBMITTED BY THE PETITIONER DATED 19/08/2019.
ANNEXURE R1(H) COPY OF LETTER FROM THE CHIEF ENGINEER DATED 22/08/2019.
ANNEXURE R1(I) COPY OF LETTER FROM THE RESPONDENT DATED 27/08/2019.
ANNEXURE R1(J) COPY OF THE LETTER FROM THE SUPERINTENDING ENGINEER DATED 27/09/2019.
ANNEXURE R1(K) COPY OF LETTER FROM THE CHIEF ENGINEER DATED 27/11/2019.
WP(C).No.27862 OF 2020(G)
ANNEXURE R1(L) COPY OF LETTER FROM THE RESPONDENT DATED 13/05/2020.
ANNEXURE R1(M) COPY OF LETTER FROM THE RESPONDENT DATED 10/06/2020.
ANNEXURE R1(N) COPY OF LETTER FROM THE RESPONDENT DATED 19/11/2020.
ANNEXURE R1(O) COPY OF LETTER FROM THE CHIEF ENGINEER DATED 01/12/2020.
ANNEXURE R1(P) COPY OF LETTER FROM THE PRINCIPAL, JNV DATED 27/11/2019.
ANNEXURE R1(Q) COPY OF THE LETTER FROM THE RESPONDENT DATED 06/12/2019.
ANNEXURE R1(R) COPY OF LETTER FROM THE ASSISTANT COLLECTOR, THIRUVANANTHAPURAM DATED 25/02/2020.
ANNEXURE R1(S) COPY OF LETTER FROM THE PRINCIPAL, JNV, VITHURA DATED 06/10/2020.
ANNEXURE R1(T) COPY OF LETTER FROM THE RESPONDENT DATED 20/02/2020.
ANNEXURE R1(U) COPY OF LETTER FROM THE ASSISTANT ENGINEER DATED 03/09/2019.
ANNEXURE R1(V) COPY OF LETTER FROM THE RESPONDENT DATED 05/09/2019.
//TRUE COPY// PA TO JUDGE
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!