Citation : 2021 Latest Caselaw 1925 Ker
Judgement Date : 19 January, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE N.NAGARESH
TUESDAY, THE 19TH DAY OF JANUARY 2021/29TH POUSHA, 1942
WP(C).No.35294 OF 2019(J)
PETITIONER:
C.K.K.CATERING SERVICES,
PB NO.1776, SOUTH RAILWAY STATION ROAD,
ERNAKULAM-682016,
REPRESENTED BY ITS MANAGING PARTNER,
C.K.K.MOIDOO.
BY ADVS.
SRI.HARIS BEERAN
SMT.O.A.NURIYA
RESPONDENTS:
1 INDIAN RAILWAY CATERING AND TOURISM
CORPORATION LIMITED,
HAVING ITS REGIONAL OFFICE AT 40/8194,
SALIH ARCADE, 1ST FLOOR, CONVENT RD,
ERNAKULAM-682035
REPRESENTED BY ITS REGIONAL MANAGER.
ADDL. 2 DIVISIONAL RAILWAY MANAGER,
SOUTHERN RAILWAY, DIVISIONAL OFFICE,
COMMERCIAL BRANCH, THIRUVANANTHAPURAM-14.
ADDL. 3 MANAGER, CATHOLIC SYRIAN BANK LTD.,
CHITTOOR ROAD, VALANJAMBALAM BRANCH,
KOCHI-682016.
(ADDL.R2 AND ADDL.R3 ARE IMPLEADED AS PER ORDER
DATED 16-09-2020 IN IA 3/2020 IN WPC
35294/2019)
R1 BY SMT.ASHA CHERIAN, SC, IRCTC
R2 BY ADV. SRI.A.DINESH RAO
R3 BY ADV. SRI.K.ANAND, SC
THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD
ON 19-01-2021, THE COURT ON THE SAME DAY DELIVERED THE
FOLLOWING:
WP(C) No.35294/2019
:2 :
JUDGMENT
~~~~~~~~~
Dated this the 19th day of January, 2021
The petitioner, a registered partnership firm engaged in
the business of catering services, is before this Court seeking
to call for the records leading to the invocation of the bank
guarantee of the petitioner and to quash the same and
command the respondents to return the amount provided as
bank guarantee to the petitioner forthwith.
2. The Southern Railway floated a tender in the year
2014 for provision of Vegetarian Refreshment Room (VRR) at
Ernakulam Junction Railway Station. The petitioner was the
successful bidder. A Master Agreement was entered into
between the Southern Railway and the petitioner on
15.06.2016. The petitioner was to conduct the VRR from
05.05.2016 to 04.05.2021. An extent of 2250 sq. ft. area was WP(C) No.35294/2019
provided to the petitioner, for a licence fee of ₹1,31,40,000/-
per annum. The licence fee was payable in advance for each
year.
3. By way of a Tripartite Agreement, the Southern
Railway assigned all its rights and liabilities as Licensor under
the Master Agreement to the 1 st respondent-Indian Railway
Catering and Tourism Corporation Limited, on 14.08.2017.
On 10.08.2017, the 1st respondent issued Ext.P1 letter
alleging that the petitioner is occupying an additional area of
58.30 m² for running the VRR. The petitioner was directed to
remit a sum of ₹4,29,371/- as proportionate licence fee for the
additional area. The demand was disputed by the petitioner.
However, the 1st respondent reiterated the demand on
11.10.2017. In this letter, the demand was enhanced to
₹48,57,874/-. The petitioner would contend that the petitioner
paid the licence fee in full and was entitled to run the VRR till
04.05.2019. On 06.12.2018, the petitioner informed the
Southern Railway that after the expiry of the present licence
year, the petitioner would like to stop services at the VRR. WP(C) No.35294/2019
The Southern Railway did not give any reply to the petitioner.
On the other hand, the 1 st respondent as per Ext.P2 letter
dated 15.12.2018 informed the petitioner that the licence fee
payable has been increased by 3.26% with effect from
26.09.2018 and hence the petitioner is liable to pay
₹3,16,052/- as additional licence fee for the period up to
04.05.2019.
4. To the predicament of the petitioner, the 1 st
respondent issued Ext.P3 letter dated 04.02.2019 stating that
the competent authority has decided to close the VRR by
05.02.2019 and directing the petitioner to handover vacant
possession of the site to the 1st respondent. The officials of
the 1st respondent illegally and forcibly sealed and took over
the VRR on 05.02.2019. By Ext.P4 letter, the 1 st respondent
required the petitioner to clear the dues.
5. The petitioner challenged the action in forcibly
closing the VRR, filing W.P.(C) No.3769/2019. On 07.02.2019,
this Court passed an interim order directing the 1 st respondent
to permit the petitioner to operate the VRR. On 28.03.2019, WP(C) No.35294/2019
this Court disposed of the writ petition holding that the dispute
is arbitrable and relegating the parties to the appropriate
Forum. This Court, as per Ext.P5 judgment, directed that
coercive action against the petitioner should stand suspended
for a period of 10 days.
6. The petitioner thereupon filed a petition under
Section 9 of the Arbitration and Conciliation Act, 1996, before
the District Court, Thiruvananthapuram. As per Ext.P6 order,
the District Court, Thiruvananthapuram restrained the 1 st
respondent from obstructing the consumers from entering and
using the VRR till 04.05.2019. In spite of the order of the
District Court pending invocation of Arbitration Clause, the 1 st
respondent invoked the bank guarantee of around ₹65 lakhs
for recovery of disputed amounts. It is aggrieved by the said
illegal invocation of the bank guarantee that the petitioner is
before this Court.
7. The learned counsel for the petitioner contended
that pending arbitration proceedings, the 2 nd respondent
cannot unilaterally invoke bank guarantee. The dispute WP(C) No.35294/2019
should be first adjudicated in arbitral proceedings. A bank
guarantee is a separate contract. The additional 3 rd
respondent-bank is not a party to the original contract.
Similarly, the petitioner is not a party to the bank guarantee.
Therefore, bank guarantee cannot be invoked pending arbitral
proceedings.
8. The learned counsel for the petitioner would further
submit that the bank guarantee can be invoked if the petitioner
fails to perform the agreement. However, in Ext.P8 invocation
letter, the Southern Railway has stated that since the
petitioner has exited the contract on 05.02.2019, the entire
security amount is to be forfeited and transferred to Railways
and therefore the bank guarantee is invoked. The learned
counsel for the petitioner urged that bank guarantee cannot be
invoked claiming disputed amounts. The 1 st respondent
acknowledges that the petitioner has disputed the amount. In
the circumstances, invocation of bank guarantee is illegal and
unsustainable.
WP(C) No.35294/2019
9. The learned counsel for the petitioner relied on the
judgment of the Hon'ble High Court of Patna in Hindustan
Steel Works Construction v. State of Bihar [2008 SCC
OnLine Pat 1291] to contend that a writ petition against
invoking bank guarantee is maintainable against an
instrumentality of State, in appropriate case. In the said
judgment, the Hon'ble High Court of Patna held that the bank
guarantee is conditional and contingent upon stated terms and
then becomes unconditional. It only means that if stated
terms/conditions are satisfied and disclosed so to bank, then
the bank will be bound to unconditionally honour its promise to
pay but not otherwise.
10. Relying on the judgment of Union of India and
others v. Tantia Construction Private Limited [(2011) 5
SCC 697], the learned counsel for the petitioner argued that
the pendency of the arbitration proceedings does not act as a
bar against this Court examining the issue of revocation of
guarantee in proceedings on its merits. Placing reliance on
the judgment of the Apex Court in Gangotri Enterprises WP(C) No.35294/2019
Limited v. Union of India and others [(2016) 11 SCC 720],
the learned counsel for the petitioner argued that when the 1 st
respondent itself stated that the amount is disputed by the
petitioner, then the 1st respondent should have invoked bank
guarantee only after a proper adjudication by a judicial
authority.
11. The learned counsel for the petitioner pointed out
that in the judgment in Oswal Agro Mills Ltd. and another v.
Assistant Collector of Central Excise, Division Ludhiana
and others [(1995) Supp (3) SCC 65], the Hon'ble Apex Court
has held that when revenue had no powers to use their
executive powers to get such a bank guarantee encashed, the
court can direct refund of money. In the judgment in
Hindustan Steel Works Construction v. State of Bihar
(supra), the Hon'ble High Court of Patna has directed bank to
refund the bank guarantee to the petitioner therein, finding
that the invocation of bank guarantee was illegal. The learned
counsel for the petitioner strenuously contended that in the
petitioner's case also, this Court has to give appropriate WP(C) No.35294/2019
directions.
12. The 1st respondent resisted the prayers of the
petitioner, filing counter affidavit. The 1 st respondent stated
that under the Master Licence Agreement executed on
15.06.2016, the petitioner was allotted 2250 sq. ft. area.
Soon, the petitioner encroached upon nearby area. The
petitioner was orally required to vacate the encroached area.
The petitioner took a stand that the petitioner require
additional area for the conduct of their business. The
petitioner was required to pay additional licence fee for the
encroached area. As the petitioner did not pay fee on
request, the 2nd respondent issued Ext.R2(a) written demand
on 20.06.2016. Ext.R2(a) was also not responded to by the
petitioner. Using additional area without remitting requisite
licence fee, is a material breach of contract, as per Clause
No.15.1(e) of the Agreement. In such a case, Railway acted
in accordance with Clause No.16.1(a).
13. In the Tripartite Agreement, it was made clear that
the 1st respondent will have the right over the payments WP(C) No.35294/2019
pertaining to the petitioner's unit, which become due
thereafter. The Tripartite Agreement also required in Clause
No.8.8 that petitioner should produce a 'No Dues Certificate'
from the Railways to run the unit under IRCTC after
14.08.2017. The petitioner did not produce 'No Dues
Certificate'. By letters dated 31.08.2017 and 30.09.2017, the
petitioner required IRCTC for additional space. Even in these
letters, the petitioner did not raise any dispute with regard to
the demand for additional licence fee.
14. The petitioner was given the option either to vacate
the extra space or to pay proportionate additional fee. The
additional area encroached by the petitioner was 627.30 sq. ft.
and the proportionate additional licence fee would be
`3,63,479/-. In WP(C) No.3769/2019, as per Ext.P5 judgment
dated 28.03.2019, this Court directed the petitioner to move
under Arbitration and Conciliation Act, 1996. To enable the
petitioner to do so, coercive action by the 1 st respondent was
suspended for a period of 10 days. In OP(Arb) No.129/2019
filed by the petitioner, the Additional District Court only WP(C) No.35294/2019
permitted the petitioner to continue to operate the unit till
04.05.2019. Left with no other remedy, the security deposit
was encashed by Railways on 03.09.2019 in exercise of
Clause No.16 of the Master Agreement. In view of the above,
the grounds urged by the petitioner are unsustainable.
15. The learned Standing Counsel for the 2 nd
respondent contended that since the petitioner has invoked
the alternate remedy of arbitration pending adjudication by the
Arbitrator, a writ petition is not maintainable. The judgment in
Hindustan Paper Corporation v. Keneilhouse Angami
[(1990) 1 Cal LT 20] relied on by the petitioner will not apply
since in the said case there was no arbitration proceedings
pending. In the judgment of the Apex Court in Tantia
Construction Private Limited (supra) also, there was no
arbitration proceedings pending. Therefore, the petitioner
cannot seek relief based on those judgments.
16. The 2nd respondent has invoked bank guarantee
due to violation of Articles 15.1 and 16.1 of Ext.R2(b)
agreement. Non-payment of licence fee for occupation of WP(C) No.35294/2019
additional space contrary to the terms of the Agreement, is a
material breach of agreement and the Railway is entitled to
invoke bank guarantee for additional licence fee for the area
occupied by the petitioner additionally. The bank guarantee
unequivocally states that the amount would be paid without
demur or objection, irrespective of any dispute that might crop
up or might have been pending.
17. The learned Standing Counsel for the 2 nd
respondent relied on the judgment of the Hon'ble Apex Court
in U.P. State Sugar Corporation v. M/s. Sumac
International Ltd. [AIR 1997 SC 1644], Himadri Chemicals
Industries Ltd. v. Coal Tar Refining Company [(2007) 8
SCC 110] and BSES Ltd. v. Fenner India Ltd. [AIR 2006 SC
1148] to content that if the bank were to go into the questions
relating to dispute between the parties, the very purpose of
giving the bank guarantee would be defeated. The only two
exceptions carved out to the well-known principles of non-
intervention are: (a) fraud and (b) irretrievable injury. As long
as there is no allegation of fraud or irretrievable injury, this WP(C) No.35294/2019
Court would not be justified in interfering with the matter,
contended the learned Standing Counsel.
18. The learned Standing Counsel further argued that
the petitioner as well as the 2 nd respondent are bound by
Ext.P5 judgment. The petitioner has invoked arbitration
proceedings in compliance of Ext.P5 judgment. When the
question as to occupation of additional space and liability for
payment of additional licence fee is pending consideration
before the Arbitrator, the Award of Arbitrator will bind the
parties. The petitioner is not entitled to get refund of the bank
guarantee at this stage.
19. I have heard the learned counsel for the petitioner,
the learned Standing Counsel appearing for the 1 st respondent
and the learned Standing Counsel appearing for additional
respondents 2 and 3.
20. The 2nd respondent has invoked bank guarantee on
the allegation of violation of Articles 15.1 and 16.1 of Ext.R2(b)
agreement between the Railway and the petitioner. As per
Clause 15.1.(e), failure of the licensee to pay licence fee along WP(C) No.35294/2019
with interest to the Railway on or before due dates, would be
deemed to be material breach on the part of the licensee. In
such event, as per Clause 16.1, the Railway have the right of
forfeiture of the security deposit furnished by the licensee.
21. The contention of the petitioner is that since the
amount allegedly payable by the petitioner is disputed, the 2 nd
respondent cannot invoke bank guarantee without
adjudication of dispute. This Court finds that there is no
documentary material to show that when the respondents
issued notices to the petitioner demanding additional licence
fee for the extra space occupied by the petitioner, the
petitioner did dispute the fact of occupation of additional
space. Since the dispute is pending in arbitral proceedings, it
would be for the Arbitrator to finally decide whether there was
unauthorised occupation of additional space by the petitioner
and whether there was breach of agreement by the petitioner.
The question to be decided in this writ petition is whether the
respondents can invoke bank guarantee pending arbitral
proceedings.
WP(C) No.35294/2019
22. In the judgment in Hindustan Steel Works
Construction (supra) of the Hon'ble High Court of Patna
relied on by the petitioner, the Hon'ble High Court held that in
an appropriate case, a writ petition against State or
instrumentality of the State arising out of a contractual
obligation is maintainable. The said case was also relating to
invocation of bank guarantee. The Hon'ble Patna High Court
held that a bank guarantee is conditioned and contingent upon
stated terms and then becomes unconditional. The Hon'ble
Patna High Court interfered with the matter on a finding that
the conditions for invocation of the bank guarantee therein
was confined to contingencies occurring during the period
prior to agreement. Invocation of bank guarantee after the
execution of agreement was found to be vitiated by the court.
The facts of the said case are distinguishable.
23. In Tantia Constructions Private Limited (supra),
the issue was of termination of contract. The Hon'ble High
Court of Patna found that the termination was illegal and
unwarranted and consequently directed the Railways to WP(C) No.35294/2019
expeditiously clear the payments of the respondent-Company.
The Hon'ble Apex Court in its judgment held that
notwithstanding the provisions relating to the arbitration clause
contained in the agreement, the High Court was fully within its
competence to entertain and dispose of the writ petition. But,
it may be noted that in the said case, no arbitration
proceedings were initiated or pending when the case was
decided.
24. In the judgment in Gangotri Enterprises Limited
(supra), the Hon'ble Apex Court found that invocation of bank
guarantee was not proper and granted injunction to the
appellant under Section 9 of the Arbitration and Conciliation
Act. That was a case where the appellant entered into two
distinct agreements with the respondent and had executed a
bank guarantee in respect of the second work. The
respondents invoked the bank guarantee for violation of
conditions in respect of the first work. The appellant sought
injunction. The Hon'ble Apex Court found that since the
agreement in respect of which the bank guarantee was WP(C) No.35294/2019
furnished was satisfactorily completed, the respondents
should not have invoked the bank guarantee for violation of
agreement conditions in respect of the first agreement while
arbitration proceedings were pending. The judgment of the
Hon'ble Apex Court is distinguishable on facts and would not
be of any help to the petitioner herein.
25. In the judgment in Hindustan Paper Corporation
Limited (supra), the Hon'ble Calcutta High Court held that the
rights and liabilities in respect of bank guarantee has to be
decided not by the terms of the original contract. The bank
guarantee is a contract separate from original contract
pursuant to which the bank guarantee is furnished. The
learned counsel for the petitioner argued that the illegal
invocation of bank guarantee by the 2nd respondent cannot be
adjudicated in an arbitral proceedings which is undertaken
under the Master License Agreement. Therefore, this Court
can entertain the writ petition and grant relief to the petitioner.
26. The 2nd respondent has invoked the bank guarantee
on the ground that terms of the Master Agreement have been WP(C) No.35294/2019
violated by the petitioner. The said issue is pending
consideration before the Arbitrator. The bank guarantee in
unequivocal terms provides that the amount under the bank
guarantee would be paid without demur or objection and
irrespective of any dispute that might crop up or might have
been pending. In view of the said specific recital in the bank
guarantee, this Court do not find any illegality or irregularity in
invoking the bank guarantee by the 1st respondent.
27. The Hon'ble Apex Court has held in U.P. State
Sugar Corporation (supra) that if the bank were to go into the
questions relating to dispute between the parties, the very
purpose of giving the bank guarantee would be defeated. The
exceptions carved out to the well-known principles of
non-intervention are fraud and irretrievable injury. The
petitioner has no case that the 1 st respondent or Railway has
played fraud in obtaining the bank guarantee. For intervention
under the head irretrievable injury, the injury or injustice
contemplated must be of such an exceptional and irretrievable
nature which will override the terms of the guarantee. The WP(C) No.35294/2019
Hon'ble Apex Court held that for availing injunction on the
ground of irretrievable injury, the party seeking injunction
would have to show that exceptional circumstances exist
which make it impossible for the guarantor to reimburse
himself if he ultimately succeeds. The Hon'ble Apex Court
specifically held that existence of any dispute between the
parties to the contract, is not a ground for issuing an injunction
against invocation of bank guarantee.
Considering the facts and circumstances of the
case and the law laid down by the Apex Court, this Court is of
the view that the contentions urged in this writ petition are not
sufficient to interfere with the action of the 2 nd respondent in
invoking the bank guarantee. The writ petition therefore fails
and it is consequently dismissed.
Sd/-
N. NAGARESH, JUDGE
aks/13.01.2021 WP(C) No.35294/2019
APPENDIX PETITIONER'S EXHIBITS:
EXHIBIT P1 A TRUE COPY OF THE LETTER DATED
10.08.2017 ISSUED BY THE RESPONDENT
EXHIBIT P2 A TRUE COPY OF THE LETTER DATED
15.12.2018 ISSUED BY THE RESPONDENT
EXHIBIT P3 A TRUE COPY OF THE ORDER DATED
04.02.2019 ISSUED BY THE RESPONDENT
EXHIBIT P4 A TRUE COPY OF THE LETTER DATED
06.02.2019 ISSUED BY THE RESPONDENT
(WITH TYPED COPY)
EXHIBIT P5 A TRUE COPY OF THE JUDGMENT DATED
28.03.2019 PASSED IN WRIT PETITION
(CIVIL) NO.3769/2019
EXHIBIT P6 A TRUE COPY OF THE ORDER DATED
12.04.2019 IN IA NO.1040/2019 IN
OP(ARB)NO.129/2019 OF THE HON'BEL
ADDITIONAL DISTRICT JUDGE,
THIRUVANANTHAPURAM
EXHIBIT P7 TRUE COPY OF THE AGREEMENT DATED
26/05/2015.
EXHIBIT P8 TRUE COPY OF LETTER OF 2ND RESPONDENT
RAILWAY DATED 19/08/2019.
EXHIBIT P9 TRUE COPY OF LETTER OF PETITIONER TO
3RD RESPONDENT BANK DATED 06/08/2020.
EXHIBIT P10 TRUE COPY OF ARGUMENT NOTE FILED BY
PETITIONER.
EXHIBIT P11 TRUE COPY OF JUDGMENT IN HINDUSTAN
STEEL WORKS CONSTRUCTION V. STATE OF
BIHAR 2008 SCC ONLINE PAT 1291.
EXHIBIT P12 TRUE COPY OF JUDGMENT IN UNION OF
INDIA AND ORS V. TANTIA CONSTRUCTIONS
PVT LIMITED 2011 5 (SCC) 697.
WP(C) No.35294/2019
EXHIBIT P13 TRUE COPY OF JUDGMENT IN DR.GANGOTRI
ENTERPRISES LIMITED V. UNION OF INDIA
AND ORS (2016) 11 SCC 720.
EXHIBIT P14 TRUE COPY OF JUDGMENT IN HINDUSTAN
PAPER CORPORATION LIMITED V.
KENEILHOUSE ANGAMI 1989 SCC ONLINE CAL
EXHIBIT P15 TRUE COPY OF JUDGMENT IN OSWAL AGRO
MILS LIMITED AND ANR V. ASSISTANT
COLLECTOR OF CENTRAL EXCISE, LUDHIANA
AND ORS.1995 SUPP (3) SCC 65.
RESPONDENTS' EXHIBITS:
EXHIBIT R1(A) TRUE COPY OF RELEVANT PORTION OF THE
MASTER LICENSE AGREEMENT DATED
15/6/2016 BETWEEN PETITION AND
RAILWAY.
EXHIBIT R1(B) TRUE COPY OF TRIPARTITE AGREEMENT
DATED 14/8/2017 BETWEEN PETITIONER,
RAILWAY AND IRCTC
EXHIBIT R1(C) TRUE COPY OF CHECK LIST PREPARED AT
THE TIME OF HANDING OVER OF
VRR/ERNAKULAM BETWEEN RAILWAY AND
IRCTC
EXHIBIT R1(D) TRUE COPY OF LETTER DATED 31/8/2017 OF
THE PETITIONER TO THE RESPONDENT
RM/IRCTC/ERS
EXHIBIT R1(E) TRUE COPY OF LETTER DATED 11/10/2017
OF SR.DIVISIONAL COMMERCIAL MANAGER,
SOUTHERN RAILWAY, ERNAKULAM TO THE
PETITIONER
EXHIBIT R1(F) TRUE COPY OF LETTER DATED 4/4/2018 OF
THE RESPONDENT TO THE PETITIONER
EXHIBIT R1(G) TRUE COPY OF LETTER DATED 17/11/2018
OF THE RESPONDENT TO THE PETITIONER
WP(C) No.35294/2019
EXHIBIT R1(H) TRUE COPY OF LETTER DATED 6/12/2018 OF
THE PETITIONER TO THE RESPONDENT
EXHIBIT R2(A) TRUE COPY THE WRITTEN DEMAND DATED
20.6.2016 ISSUED BY THE 2ND RESPONDENT
EXHIBIT R2(B) TRUE COPY OF THE RELEVANT PORTITION OF
THE AGREEMENT DATED 15.6.2016
EXHIBIT R2(C) TRUE COPY OF THE TRIPARTITE AGREEMENT
DATED 14.08.2017 BETWEEN THE
PETITIONER RAILWAY AND IRCTC
EXHIBIT R2(D) TRUE COPY OF THE EXTRACT OF THE
RELEVANT PORTION OF THE MASTER
AGREEMENT DATED 15.06.2016
EXHIBIT R2(E) TRUE COPY OF THE EXTRACT OF THE
RELEVANT PORTION OF THE MASTER
AGREEMENT DATED 15.06.2016
EXHIBIT R2(F) TRUE COPY OF THE NOTICE DATED
29/10/2019 ISSUED BY THE PETITIONER
SR
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!