Citation : 2021 Latest Caselaw 19 Ker
Judgement Date : 4 January, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE N.NAGARESH
MONDAY,THE 4TH DAY OF JANUARY 2021/14TH POUSHA, 1942
WP(C).No.16547 OF 2020(P)
PETITIONERS:
1 K.M.SHAJU, AGED 52 YEARS,
S/O. K.P. MOHAMMED SALI,
PROPRIETOR, M/S. VOLTAMP,
NEAR GOVERNMENT HIGH SCHOOL,
KARUNAGAPPALLY, KOLLAM DISTRICT-690 518.
2 MOHAMMED ILLYAS, AGED 48 YEARS,
S/O. LATE K. MOHAMMED SAHIB,
M/S. HAJEE, K. MOHAMMED SAHIB,
KMS COMMUNICATIONS, KMS BUILDING,
NEAR SBI, PUNALUR, KOLLAM DISTRICT-691 305.
3 RAJESH BABU, AGED 44 YEARS,
S/O. M.V. BABU, PROPRIETOR,
UNIVERSAL TELESERVICES,
ST. GEORGE BUILDING, PULAMON P.O.,
KOTTARAKKARA, KOLLAM DISTRICT-691 531.
BY ADVS.
SRI.M.V.THAMBAN
SRI.R.REJI
SMT.THARA THAMBAN
SRI.B.BIPIN
RESPONDENTS:
1 THE CHIEF GENERAL MANAGER TELECOM,
BHARAT SANCHAR NIGAL LIMITED,
KERALA CIRCLE, DOORSANCHAR BHAVAN,
PMG JUNCTION, THIRUVANANTHAPURAM-695 033.
2 THE PRINCIPAL GENERAL MANAGER TELECOM,
BHARAT SANCHAR NIGAL LIMITED, KOLLAM,
BSNL SANCHAR BHAVAN, KOLLAM-691 001.
WPC No.16547/2020
:2:
3 THE ASSISTANT GENERAL MANAGER (MARKETING),
OFFICE OF THE GENERAL MANAGER TELECOM
BHARAT SANCHAR NIGAM LIMITED, KOLLAM,
BSNL SANCHAR BHAVAN, KOLLAM-691 001.
4 ZAREENA SHAMSUDEEN,
PROPRIETOR IMPERIAL SYSTEMS,
EMBRAYIL, PAZHAKULAM P.O., ADOOR,
PATHANAMTHITTA DISTRICT-691 523.
5 SHAMSUDEEN, EMPRAYIL, PAZHAKULAM P.O.,
ADOOR, APTHANAMTHITTA DISTRICT, PIN-691 523.
R1-R3 BY SRI.MATHEWS K.PHILIP, SC, BSNL
THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY
HEARD ON 04-01-2021, THE COURT ON THE SAME DAY DELIVERED
THE FOLLOWING:
WPC No.16547/2020
:3:
N. NAGARESH, J.
`````````````````````````````````````````````````````````````
W.P.(C) No.16547 of 2020
`````````````````````````````````````````````````````````````
Dated this the 4th day of January, 2021
JUDGMENT
~~~~~~~~~
The petitioners are aggrieved by the action of the
3rd respondent in granting time for participation in tender and
for furnishing mutual non-disclosure agreement on stamp
paper, after opening the bid. The petitioners therefore pray
that Ext.P1 tender notice and all further proceedings
pursuant thereto, be quashed.
2. The petitioners state that the 3 rd respondent-
Assistant General Manager (Marketing), BSNL invited sealed
Expression of Interest for the operation and maintenance of
BSNL CSCs in Kollam. The bids were to be submitted before
1.30 pm, 23.07.2020 and opening of bids was scheduled at
14.00 Hrs, 23.07.2020.
WPC No.16547/2020
3. The petitioners submitted their bids and the 3 rd
respondent opened the bids on 23.07.2020. According to the
petitioners, none of the participants had submitted mutual
non-disclosure agreements on stamp paper. As bids were
opened, in the absence of non-disclosure agreements of the
participants, the 3rd respondent ought to have re-tendered
the work. However, the 3rd respondent issued letters to all the
participants granting time to produce non-disclosure
agreements on stamp papers and certain other documents,
as per Ext.P2.
4. Learned counsel for the petitioner would submit
that in Ext.P1, the participants were directed to produce
certain documents along with the Expression of Interest.
After opening the sealed tenders and after the secrecy of the
tender has become public, the 3 rd respondent ought not have
provided opportunity to the participants to produce the
documents insisted in the tender notice. The action was a
calculated attempt to support the 4th respondent.
5. Learned counsel for the petitioner argued that WPC No.16547/2020
once sealed tenders are opened, the secrecy of the tenders
is lost and hence there is no question of providing
opportunity to participants to produce documents which
ought to have been produced along with Expression of
Interest. Opportunity to produce the documents was given at
the instance of the 5th respondent. The said action of the 3 rd
respondent is to help respondents 4 and 5 out of the way and
hence cannot be sustained.
6. Respondents 1 to 3 filed a statement and
contested the writ petition. Respondents 1 to 3 pointed out
that participants or their authorised representatives were free
to attend the tender opening session. None of the petitioners
attended the bid opening session. Such opportunity was
given to raise objections, if any. The Tender Opening
Committee opened the tender through e-tender portal and
the report of the Tender Opening Committee was submitted
to the Tender Evaluation Committee.
7. The Tender Evaluation Committee, while
evaluating the technical bids, observed that some documents WPC No.16547/2020
including the mutual non-disclosure agreement were not
submitted by all the bidders. In fact, none of the bidders had
submitted all documents. Since it is for the Evaluation
Committee to decide on the documents, a decision was
taken to permit all participants to submit requisite documents
within seven days.
8. The learned Standing Counsel for respondents 1
to 3 pointed out that the mutual non-disclosure agreement
has nothing to do with the competitiveness of bids. All the
participants were given opportunity to produce documents
including non-disclosure agreement. In all tenders,
evaluation is concluded primarily on the basis of most
advantageous "by price". The Evaluation Committee is at
liberty to call for documents if the Committee considers it
necessary.
9. The petitioners are already franchisees of BSNL
and their offers need to be evaluated further, before a
decision is taken on awarding the tender. It is not correct to
say that the decision of respondents 1 to 3 is intended to WPC No.16547/2020
help the 4th respondent alone. In the absence of submission
of requisite documents, even the bids made by the
petitioners were defective. None including the petitioners
objected to grant of opportunity to the participants to produce
relevant documents, when the bid was opened on
23.07.2020. Delay in finalising the Expression of Interest will
adversely affect the services of the BSNL, contended the
learned Standing Counsel.
10. I have heard the learned counsel for the
petitioners and the learned Standing Counsel appearing for
respondents 1 to 3.
11. The learned counsel for the petitioners relied on
the judgment of this Court in Thomas P.C. and Co. v.
Executive Engineer, Central Public Works Department
[2013 KHC 47] to contend that in the absence of provision in
the tender notification, a disqualified tenderer cannot rectify
the mistake at a later stage after opening the tender. A
reading of the said judgment shows that the disqualified
tenderer in that case, failed to remit requisite tender WPC No.16547/2020
processing fee, along with the tender. The said deficiency
was sought to be regularised by paying the requisite amount
subsequently. Under the circumstances this court held that
such a mistake cannot be permitted to be rectified at a later
stage. The facts involved in the said decision and the facts
of this case are entirely different. The judgment in Thomas
P.C. and Co. (supra) therefore cannot be of any help to the
petitioners.
12. The learned counsel for the petitioners also relied
on the judgment of the Apex Court in Mr. B.S.N. Joshi and
Sons Ltd. v. Nair Coal Services Ltd. and Others [(2006)
11 SCC 548] to contend that if there are essential conditions,
the same must be adhered to and if there is no power of
general relaxation, ordinarily the same shall not be exercised
by the tendering authority. A reading of the said judgment of
the Apex Court would reveal that it was a case where one of
the bidders did not satisfy the essential qualifications laid
down for technical bid and was hence ineligible for award of
the contract. The Hon'ble Apex Court, in such circumstances, WPC No.16547/2020
held that such essential conditions cannot be made good at
a later date. The said judgment therefore is also
distinguishable on facts.
13. The prime grievance of the petitioners is as
regards Ext.P2 letter issued to the participants in the bid,
requiring them to make available mutual nondisclosure
agreement and audited results of financial year 2016-'17.
The argument of the petitioner is that such opportunity was
given after opening of the bids. Once the bids are opened
and the secrecy of the bids are lost, the 3 rd respondent
cannot permit the participants to make good the defect. The
3rd respondent under such circumstances had no option than
to re-tender the work.
14. It has to be noted that none of the participants
submitted mutual non-disclosure agreement on stamp
papers along with their Expression of Interest. Some of the
participants did not attach audited results of the financial
year 2016-'17. When these shortcomings were noted at the
time of opening of the bids, the Tender Evaluation WPC No.16547/2020
Committee decided to give opportunity to all the participants
to provide necessary documents. The petitioners did not
object to the decision at that point of time. In fact, neither the
petitioners nor their representatives were present at the time
of opening of the bids, though they could have themselves or
through their representatives raised objections.
15. This Court is of the definite opinion that the action
of respondents 1 to 3 in giving opportunity to the participants
in the bid to produce necessary documents, has not vitiated
the tender process. Opportunity was given to produce non-
disclosure agreement on stamp papers and financial
statements. When an essential condition of tender is not
complied with, it is open to the Tender Inviting Authority to
reject the same. Whether a condition is essential or
collateral, it could be ascertained by reference to the
consequence of non-compliance thereto. The documents
sought for by the respondents in this case, though are
important for deciding eligibility for final award of tender, they
have no direct impact over the competitiveness of the bids. WPC No.16547/2020
16. The Hon'ble Apex Court has held in the judgment
in Air India Ltd. v. Cochin International Airport Ltd. and
others [(2000) 2 SCC 617] that even when some defect is
found in the decision making process, the Court must
exercise its discretionary power under Article 226 with great
caution and should exercise it only in furtherance of public
interest and not merely on the making of a legal point. The
Court should always keep the larger public interest in mind in
order to decide whether its intervention is called for or not.
Only when it comes to a conclusion that overwhelming public
interest requires interference, the Court should intervene.
17. Opportunities to produce documents were given to
all the participants. The petitioners could have also submitted
documents. The petitioners, instead of doing so, have
approached this Court seeking re-tender. Since this Court is
of the definite opinion that the action of respondents 1 to 3 in
giving opportunity to all the participants in the tender to
produce requisite documents, is neither illegal or arbitrary,
respondents 1 to 3 cannot be forced to re-tender the work WPC No.16547/2020
again.
In the circumstances, this Court finds that the writ
petition filed by the petitioners is without any merit and is
liable to be dismissed. It is ordered accordingly.
Sd/-
N. NAGARESH, JUDGE aks/28.12.2020 WPC No.16547/2020
APPENDIX PETITIONERS' EXHIBITS:
EXHIBIT P1 TRUE COPY OF THE EXTRACT OF TENDER NOTIFICATION EOI NO.KLM/AGM MKTG/ EOI/CSC OUTSOURCING/ 2020-21/3 DATED 18/06/2020.
EXHIBIT P2 TRUE COPY OF THE LETTER SIGNED BY THE THIRD RESPONDENT ON 06/08/2020.
EXHIBIT P3 TRUE COPY OF THE LETTER SENT TO THE 3RD RESPONDENT DATED 01/08/2020.
EXHIBIT P4 TRUE COPY OF THE LETTER ISSUED BY THE 3RD RESPONDENT DATED 06/08/2020.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!