Citation : 2021 Latest Caselaw 5718 Ker
Judgement Date : 17 February, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE SMT. JUSTICE P.V.ASHA
WEDNESDAY, THE 17TH DAY OF FEBRUARY 2021 / 28TH MAGHA,1942
WP(C).No.17468 OF 2020(G)
PETITIONER:
K.KANNAN
AGED 58 YEARS
S/O.KARUNAN, AMRUTHAM, CHIRAKKAL,
CHIRAKKAL P.O., KANNUR-670011.
BY ADVS.
SRI.P.C.SASIDHARAN
SHRI.GOPIDAS E.N.
RESPONDENTS:
1 THE KERALA WATER AUTHORITY
REPRESENTED BY ITS MANAGING DIRECTOR,
JALABHAVAN, VELLAYAMBALAM,
THIRUVANANTHAPURAM-695033.
2 THE SUPERINTENDING ENGINEER,
PH CIRCLE, KERALA WATER AUTHORITY,
KANNUR-670012.
3 THE EXECUTIVE ENGINEER,
PROJECT DIVISION, KERALA WATER AUTHORITY,
KANNUR-670012.
4 THE MANAGER, KERALA GRAMIN BANK,
THANA, KANNUR-670012.
BY SRI.P.BENJAMIN PAUL, SC, KERALA WATER AUTHORITY
BY ADV. SRI.M.GOPIKRISHNAN NAMBIAR
BY ADV. SRI.K.JOHN MATHAI
BY ADV. SRI.JOSON MANAVALAN
BY ADV. SRI.KURYAN THOMAS
BY ADV. SRI.PAULOSE C. ABRAHAM
BY ADV. SRI.RAJA KANNAN
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
17.02.2021, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
WP(C).No.17468 OF 2020(G)
2
J U D G M E N T
Petitioner, who is an A class Contractor, was
awarded the work of construction of 14 MLD Output
Capacity of Water Treatment Plant (Rapid and Filter)
and Allied Structures at Madamthattu (Part-I) and
construction of 45 lakhs litre capacity GL tank at
Nelliyattupara (Part-II)-Package II. It is stated that
after executing Ext.P2 agreement on 03.06.2013, the
work was completed on 08.05.2014 and the final bill
was paid on 31.12.2015. The defect liability period as
per the agreement is 18 months from the date of
commissioning. It is stated that petitioner was asked
to furnish bank guarantee and accordingly Ext.P4 bank
guarantee was furnished on 13.07.2018 and it was
extended as can be seen from Ext.P5 and after
31.01.2020 the bank guarantee is not extended. It is
stated that since the water authority is not issuing
their consent letter the bank is not releasing the WP(C).No.17468 OF 2020(G)
bank guarantee.
2. Respondents 1 to 3 have filed a counter
affidavit stating that the defect liability period
would be over only on completion of 18 months from the
date of commissioning and that the work is not
commissioned. It is stated that the construction
carried out by the petitioner is of 45 MLD Capacity GL
Tank and the Bank guarantee can be released only after
the defect liability period is over as trial run can
be done only after the commissioning. According to
respondents though the work was completed in 2014,
trial run could not be done so far since water
treatment plant could not be commissioned. It is
stated that the contractor has to run the plant with
his operators and to take care of all chemicals, parts
specially required during the maintenance period and
the said maintenance period would start only from the
date of commissioning. It is also stated that the only
security with the respondents to cover liability from WP(C).No.17468 OF 2020(G)
the petitioner for defects if any, is the bank
guarantee and therefore consent cannot be granted for
releasing the same.
3. According to the learned counsel for the
petitioner, the delay in commissioning is not on
account of any default on the part of petitioner and
when the normal period of defect liability is only 18
months, the delay in commissioning even after more
than 6 years of the completion of the construction and
keeping the bank guarantee furnished by the petitioner
indefinitely with the respondent is arbitrary.
4. Though the learned Standing Counsel for the
water authority argued that the trial run has to be
conducted by the contractor as per the provisions in
the agreement and the bank guarantee has to be
retained till then, the learned counsel for the
petitioner points out that this Court has in a batch
of writ petitions, by Ext.P6 common judgment dated
11.04.2019 in W.P.(C).No.747/2019 & connected cases, WP(C).No.17468 OF 2020(G)
directed the respondents to release the retention
amount in such cases on securing a simple bond from
the contractors for a period of one year. Though the
learned Standing Counsel for the water authority
submitted that in the said cases bank guarantee was
not furnished, it also relates to the cases where
trial run was not conducted.
In the circumstances there shall be a direction
to the 3rd respondent to take appropriate action for
releasing the bank guarantee to petitioner after
securing sufficient assurance from the petitioner
getting a bond executed by him. This shall be done
within a period of 'six weeks' from the date of
receipt of a copy of the judgment.
The writ petition is disposed of accordingly.
Sd/-
P.V.ASHA, JUDGE AS WP(C).No.17468 OF 2020(G)
APPENDIX PETITIONER'S EXHIBITS:
EXHIBIT P1 TRUE COPY OF THE WORK ORDER DATED 27.5.2013 ISSUED BY THE 2ND RESPONDENT.
EXHIBIT P2 TRUE COPY OF THE AGREEMENT DATED 3.6.2013 EXECUTED BETWEEN THE PETITIONER AND THE 2ND RESPONDENT.
EXHIBIT P3 THE TRUE COPY OF THE VOUCHER DATED 31.12.2015 EVIDENCING THE FINAL PAYMENT.
EXHIBIT P4 TRUE COPY OF BANK GUARANTEE DATED 13.7.2018 ISSUED BY THE 4TH RESPONDENT.
EXHIBIT P5 TRUE COPY OF THE LETTER DATED 12.12.2018 ISSUED BY THE 3RD RESPONDENT TO THE 4TH RESPONDENT.
EXHIBIT P6 TRUE COPY OF THE JUDGMENT IN W.P.C.NO.7487 OF 2019 AND CONNECTED CASES DATED 11/4/2019
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!