Citation : 2021 Latest Caselaw 5675 Ker
Judgement Date : 17 February, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE N.NAGARESH
WEDNESDAY, THE 17TH DAY OF FEBRUARY 2021 / 28TH MAGHA,1942
WP(C).No.24907 OF 2020(K)
PETITIONER:
M/s ALECTRONA ENERGY PVT. LTD.,
REP. BY ITS MANAGING DIRECTOR,
MR.ROHIT RABINDERNATH,
S/O.LATE MR.RABINDERNATH,
AGED 42 YEARS,
HAVING ITS REGISTERED OFFICE AT 3RD FLOOR,
BLOCK A, BANNARI AMMAN TOWERS, NO.29,
DR.RADHAKRISHNAN ROAD,
MYLAPORE, CHENNAI-600 004
BY ADVS.
SRI.M.R.HARIRAJ
SRI.THANUJA ROSHAN GEORGE
SHRI.VISHWAJITH C.K
SMT.GANGA A.SANKAR
SHRI.CHACKOCHEN VITHAYATHIL
SMT.GISHA G. RAJ
SHRI.REJIVUE
RESPONDENTS:
1 KERALA STATE ELECTRICITY BOARD LTD.,
A GOVT OF KERALA UNDERTAKING,
REP. BY ITS CHIEF ENGINEER 9TH FLOOR,
VYDYUTHI BHAVANAM, PATTOM,
THIRUVANANTHAPURAM-695 001
2 STATE OF KERALA,
REP. BY THE SECRETARY TO GOVERNMENT OF KERALA,
DEPARTMENT OF ELECTRICITY,
THIRUVANANTHAPURAM-695 001
WP(C) No.24907/2020
:2 :
3 DCB BANK LTD.,
HAVING ITS CENTRAL OFFICE AT 601 AND 602,
PENINSULA BUSINESS PARK, 6TH FLOOR, TOWER A,
SENAPATHI BAPAT MARG, LOWER PAREL,
MUMBAI 400013,
REP. BY ITS MANAGER NUNGAMBAKKAM BRANCH
R1 BY ADV. SRI.SUDHEER GANESH KUMAR.R.,SC
R2 BY GOVERNMENT PLEADER SMT. RASHMI K.M.
THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD
ON 17.02.2021, THE COURT ON THE SAME DAY DELIVERED THE
FOLLOWING:
WP(C) No.24907/2020
:3 :
JUDGMENT
~~~~~~~~~
Dated this the 17th day of February, 2021
The petitioner, a Company in the business of
manufacture and installation of Solar Photovoltaic Modules,
Electronic Controls, Solar Inverters and Solar Water pumps, is
before this Court seeking to quash Ext.P19 and to direct the
respondents to allow the petitioner to complete the execution
of agreement.
2. The 1st respondent-KSEB invited tenders for
erection of 1.0 MW solar power plant at Mylatty as per Ext.P1.
The petitioner participated in the tender successfully and was
given Ext.P2 work order on 07.12.2017. The petitioner would
contend that there were certain issues relating to tax structure
which would have affected the price quoted. The said issue
delayed execution of the agreement. Finally, the agreement
was executed in the month of March, 2018 as per Ext.P3. WP(C) No.24907/2020
3. The petitioner submits that the 1st respondent called
a meeting relating to execution of the contract on 21.02.2019.
The petitioner submitted Ext.P5 revised schedule of project
implementation. The petitioner also sent Ext.P6 e-mail with an
update on the AC and DC works. In the said e-mail, the
petitioner informed the respondents of engaging of local
labour as local contractor. The respondents took the
engagement of local labours as sub contract and on that
ground and without issuing any show-cause notice, issued
Ext.P7 terminating the project agreement.
4. By Ext.P8 dated 10.07.2019, the petitioner clarified
to the respondents that what was meant by the petitioner was
only engagement of local labour for the work and it was not a
question of sub contracting.
5. The petitioner challenged Ext.P7 filing W.P.(C)
No.20009/2019. This Court found the said writ petition as
premature and dismissed the writ petition. Thereafter, the
petitioner sought constitution of a Dispute Resolution
Committee by Ext.P10 representation dated 03.10.2019. The WP(C) No.24907/2020
Dispute Resolution Committee was constituted and a meeting
was held on 04.02.2020. In the said meeting, the petitioner
pointed out that the original photovoltaic modules offered in
the contract have become obsolete and the petitioner is ready
to provide their own modules of new model, which are more
efficient, without any additional cost.
6. Subsequently, the petitioner was served with
Ext.P11 minutes of the meeting of the Dispute Resolution
Committee. In Ext.P11, it was stated that the Chair agreed to
the request of the petitioner in principle subject to the
condition that the petitioner shall pay the KSEB an amount
equal to the generation loss (deemed) during the period of
such extension. It was stated in Ext.P11 that the amount
equal to generation loss per year comes approximately to
₹50,57,500/-. Ext.P11 further stated that if the project is not
successfully completed and handed over to the Board as
agreed, the said generation loss will be deducted from the
Bank Guarantee executed in favour of the KSEB. WP(C) No.24907/2020
7. The petitioner was not agreeable to the quantum of
generation loss. Therefore, the petitioner sent Ext.P12
representation dated 03.03.2020 to the Chief Engineer (RE &
ES), KSEB. The 1st respondent required that the Bank
Guarantee submitted by the petitioner through the 3rd
respondent may be extended. The 1st respondent extended
the time of contract by four months as per Ext.P14
communication dated 01.04.2020.
8. The petitioner wold submit that Ext.P14 was served
to the petitioner during the lock down period consequent to
Covid-19 pandemic. When the Company office started
functioning, the petitioner requested the respondents to
confirm if the project could be implemented using the new
modules. However, to the surprise and predicament of the
petitioner, the 1st respondent issued Ext.P19 letter to the 3rd
respondent-Bank demanding that the Bank Guarantee
provided by the petitioner be encashed. It is aggrieved by the
arbitrary and illegal action of the respondents to realise the
Bank Guarantee that the petitioner is before this Court. WP(C) No.24907/2020
9. The learned counsel for the petitioner would submit
that the termination of the agreement without hearing the
petitioner is violative of the principles of natural justice. The
termination of the project agreement is devoid of any
justifiable reason. There was no deficiency on the part of the
petitioner in executing the work. The Dispute Resolution
Committee deemed it fit to extent the time of the contract. The
petitioner also offered to complete the contract with new
technology module. When the petitioner was willing to
complete the project using new technology module and since
there was extension of time to complete the agreed work, the
respondents are not justified in invoking the Bank Guarantee.
10. The respondents defended the writ petition filing
counter affidavit. The respondents contended that the
intention of the petitioner in approaching this Court is not to
carry out the petitioner's contractual obligation in accordance
with the agreement but to delay and prolong the project. In
view of the judgment in Hindustan Steel Construction Ltd.
v. Tarapore & Co. and another [(1996) 5 SCC 34], the WP(C) No.24907/2020
respondents are justified in invoking invoking the Bank
Guarantee. A prior notice or determination or quantification of
loss is not required for invoking Bank Guarantee, contended
the Standing Counsel for the respondents.
11. The Standing Counsel for the respondents further
argued that the offer of new technology module made by the
petitioner is not acceptable to the respondents. The
respondents wanted the petitioner to proceed with the project
using the agreed module. The petitioner has failed to execute
the project within the extended time given by the respondents.
Therefore, the present writ petition is only a ruse to hinder
realisation of Bank Guarantee by the respondents.
12. I have heard the learned counsel for the petitioner
and the learned Standing Counsel appearing for the
respondents.
13. It is to be noted that the work was awarded to the
petitioner on 07.12.2017. However, the petitioner came
forward to execute the agreement only on 01.03.2018.
Subsequently, the petitioner took almost five months to take WP(C) No.24907/2020
over the site for implementation of the project. The project
had to be completed by 13.02.2019. The respondents
granted extension of time to the petitioner-Company. It is the
case of the respondents that the petitioner has not even
started the work. The delay in execution of the work is
therefore attributable to the petitioner.
14. From the pleadings, it is evident that there was
unexplained delay in implementation of the project by the
petitioner at various stages. There was delay in executing the
agreement. There was delay in taking over the site. In spite
of the extension of time granted by the respondents, the
petitioner could not execute the work. On the other hand, the
petitioner has been offering implementation of the project
through alternate technology, which is not acceptable to the
respondents.
15. The pleadings would also indicate that there was
some disputes between the shareholders of the Company
which has delayed the starting of the work. Though the
petitioner had assured the completion of work by 15.05.2019, WP(C) No.24907/2020
that is within three months from 12.02.2019, it was not done.
In the circumstances, this Court is of the considered opinion
that the decision of the respondents to invoke and realise the
Bank Guarantee is justifiable.
16. The petitioner would contend that the Bank
Guarantee had to be reduced to 3% by Exts.P22 and P23
orders issued by the Government of India. I have considered
the said arguments. Paragraph 3 of Ext.P22 order would
show that when there is a dispute or litigations are
contemplated, the amounts of Bank Guarantee are not
expected to be reduced by the authorities.
In view of all the above facts, this Court finds no
reason to interfere with the decision of the respondents in
invoking Bank Guarantee. The writ petition fails and it is
accordingly dismissed.
Sd/-
N. NAGARESH, JUDGE
aks/17.02.2021 WP(C) No.24907/2020
APPENDIX PETITIONER'S EXHIBITS:
EXHIBIT P1 TRUE COPY OF TENDER NO.8/KSEBL/CE (RESS)/SPV-MYLT/1.0MW/ 2016-17
EXHIBIT P2 TRUE COPY OF WORK ORDER NO.4/2017-18 DATED 7.12.2017
EXHIBIT P3 TRUE COPY OF AGREEMENT NO.20/2017-18 DATED 1.3.2018
EXHIBIT P4 TRUE COPY OF MINUTES OF MEETING DATED 21.2.2019
EXHIBIT P5 TRUE COPY OF REVISED SCHEDULE OF PROJECT IMPLEMENTATION SUBMITTED BY THE PETITIONER
EXHIBIT P6 TRUE COPY OF EMAIL SENT BY THE PETITIONER DATED 20.6.2019
EXHIBIT P7 TRUE COPY OF ORDER NO.CE(RESS) PROJECTS/AEE1/SPV MYLATTY/2019-20/532 DATED 2.7.2019
EXHIBIT P8 TRUE COPY OF EMAIL SENT BY THE PETITIONER TO THE FIRST RESPONDENT DATED 10.7.2019
EXHIBIT P9 TRUE COPY OF THE JUDGMENT DATED 30.9.2019 IN WP(C) 20009/2019 OF THIS HONOURABLE COURT
EXHIBIT P10 TRUE COPY OF REPRESENTATION DATED 3.10.2019 WP(C) No.24907/2020
EXHIBIT P11 TRUE COPY OF THE MINUTES OF THE MEETING OF DISPUTE RESOLUTION COMMITTEE ON 4.2.2020
EXHIBIT P12 TRUE COPY OF THE REPRESENTATION DATED 3.3.2020
EXHIBIT P13(A) TRUE COPY OF THE LETTER NO.CE(REES)/ SOLAR/MYLATTY/1MW/2019-20/2045 DATED 19.2.2020
EXHIBIT P13(B) TRUE COPY OF THE LETTER NO.CE(REES)/ SOLAR/MYLATTY/1MW/2019-20/2047 DATED 19.2.2020
EXHIBIT P14 TRUE COPY OF THE LETTER NO.CE(REES)/ PROJECTS/AEEZ/SPV/MYLATTY/2019-20/2341 DATED 1.4.2020
EXHIBIT P15 TRUE COPY OF REPRESENTATION DATED 23.6.2020
EXHIBIT P16 TRUE COPY OF REPRESENTATION DATED 27.6.2020
EXHIBIT P17 TRUE COPY OF REPRESENTATION DATED 29.8.2020
EXHIBIT P18 TRUE COPY OF REPRESENTATION DATED 20.10.2020
EXHIBIT P19 TRUE COPY OF LETTER NO.CE(REES)/ PROJECTS/AE-2/SPU MYLATTY/ 2020-21/888 DATED 12.11.2020
EXHIBIT P20 TRUE COPY OF OM.NO.283/18/2020-GRID SOLAR DATED 13.8.2020.
EXHIBIT P21 TRUE COPY OF OM NO.F.9/4/2020-PPD DATED 12.11.2020 FOR BID SECURITY.
EXHIBIT P22 TRUE COPY OF OM NO.F.9/4/2020-PPD
DATED 12.11.2020 FOR PERFORMANCE
SECURITY.
WP(C) No.24907/2020
EXHIBIT P23 OM.F.NO.32/645/2017-SPV DIVISION
(PART-3) DATED 07.12.2020.
EXHIBIT P24 TRUE COPY OF THE CERTIFICATE ISSUED BY
THE TUVRHEINLAND FOR THE PRODUCT OF THE PETITIONER EXHIBIT P25 TRUE COPY OF LETTER NO.1016/SHLS-
CFL/SCHEMES/2013-14 DATED 10/12/2020 ISSUED BY TAMILNADU ENERGY DEVELOPMENT AGENCY.
EXHIBIT P26 TRUE COPY OF THE LETTER REFERENCE NO.NREDCAP/SE/SPVPS/ISSUE OF EXPERIENCE CERTIFICATE/2017-18 DATD 23/4/2018 ISSUED BY NEW AND RENEWABLE ENERGY DEVELOPMENT CORPORATION OF ANDHRA PRADESH LTD.
EXHIBIT P27 TRUE COPY OF CERTIFICATE OF COMPLETION REFERENCE NO.3917/CREDA/SSY/2019-20 DATED 19/6/2019 ISSUED BY CHHATTISGARH STATE RENEWABLE ENERGY DEVELOPMENT AGENCY (CREDA) EXHIBIT P28 TRUE COPY OF CERTIFICATE DATED 28/1/2016 ISSUED BY THE CHENNAI PORT TRUST EXHIBIT P29 TRUE COPY OF PERFORMANCE CERTIFICATE DATED 17/1/2017 ISSUED BY GRASSROOT TRADING NETWORK FOR WOMEN, AHMEDABAD, GUJARAT
RESPONDENTS' EXHIBITS:
EXHIBIT R1 A THE TRUE COPY OF THE BANK GUARANTEES
EXECUTED BY THE PETITIONER DATED
03.02.2018.
EXHIBIT R1 B THE TRUE COPY OF LETTER DATED
19.12.2017, E-MAIL DATED 05.01.2018 AND LETTER DATED 05.02.2018 FROM THE PETITIONER SEEKING TIME EXTENSION FOR EXECUTING THE AGREEMENT.
EXHIBIT R1 C THE TRUE COPY OF B.O (FTD) NO.05/2020(CE(REES)/SPV-MYLTY/2019-20) TVPM DATED 06.01.2020 REGARDING FORMATION OF DISPUTE RESOLUTION COMMITTEE.
EXHIBIT R1 D THE TRUE COPY OF B.O(FTD) NO.244/2020/ CE(REES)/SPV-MYLTY/2019-20 DATED, TVM 30.03.2020 REGARDING TIME EXTENSION. WP(C) No.24907/2020
EXHIBIT R1 E THE TRUE COPY OF LETTER AND E-MAIL DATED 01.04.2020 REGARDING THE TIME EXTENSION.
EXHIBIT R1 F THE TRUE COPY OF LETTER DATED 07.06.2018, 08.10.2018 REGARDING THE MAKE OF PV MODULES.
SR
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!