Citation : 2021 Latest Caselaw 5518 Ker
Judgement Date : 16 February, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE SHAJI P.CHALY
TUESDAY, THE 16TH DAY OF FEBRUARY 2021 / 27TH MAGHA,1942
Con.Case(C).No.2134 OF 2020 IN WP(C). 40269/2016
AGAINST THE JUDGMENT IN WP(C) 40269/2016(G) OF HIGH COURT OF
KERALA
PETITIONER/PETITIONER IN WPC NO.40269/2016
K.K.LAKSHMI
AGED 63 YEARS
CHANTHIRUTHY HOUSE,KADAMBAZHIPURAM.P.O,
PALAKKAD.
BY ADV. SRI.ANIL KUMAR M.SIVARAMAN
RESPONDENT/1ST RESPONDENT IN WPC 40269/2016
DR.P.SURESH BABU IAS
AGE AND FATHER'S NAME NOT KNOWN TO THE
PETITIONER,DISTRICT COLLECTOR,
COLLECTORATE,PALAKKAD-678001.
SRI.SURIN GEORGE IPE,SR.GP
THIS CONTEMPT OF COURT CASE (CIVIL) HAVING COME UP FOR
ADMISSION ON 16.02.2021, THE COURT ON THE SAME DAY DELIVERED THE
FOLLOWING:
2
Con.Case(C).No.2134 OF 2020 IN WP(C). 40269/2016
JUDGMENT
Dated this the 16th day of February 2021
This contempt petition is filed complaining
that the directives contained in the judgment in
W.P.(C)No.40269/2016 dated 05.04.2019 are not
complied with.
2. The direction issued by this Court in the
judgment is as follows:-
"5. Therefore, the writ petition is disposed of, directing the 1st respondent to convene a meeting of the aforesaid bodies within three months from the date of receipt of a copy of this judgment, and identify whether Ext.P6 order can be implemented in its letter and spirit. If the District Collector finds that the order cannot be implemented the Collector will, be at liberty to refer the matter to the State Government and the State Government is directed if any reference is made, to attain finality to the same at the earliest possible, and at any rate, within three months from the date of receipt of any reference from the District Collector."
3. Today when the matter was taken up, learned
Government Pleader has produced a communication
addressed by the District Collector Palakkad to the
Advocate General, Ernakulam, from where I could
Con.Case(C).No.2134 OF 2020 IN WP(C). 40269/2016
gather that, as per the direction issued by this
Court to solve the problem of water logging in the
paddy field as complained by the petitioner two
culverts were constructed instead of two pipes, but
due to Covid -19 pandemic the work could not be
completed before 31st March, 2020. However, the work
was completed and there was no flooding in the area
in question during the last monsoon and also the
water was flowing properly. It is also stated that
the block in the pipes and the culverts were also
cleaned.
4. Therefore according to the learned Senior
Government Pleader, the directions issued by this
Court in the judgment was complied with, however,
learned counsel for the petitioner submitted that,
the directions issued by this Court in the judgment
was not carried out by the District Collector or
other authorities in the letter and spirit of the
direction contained in the judgment. It is also
pointed out that, as per the order passed in order
Con.Case(C).No.2134 OF 2020 IN WP(C). 40269/2016
to rectify the issue of flooding in the area three
culverts were in contemplation, however, even going
by the instructions given by the District Collector
only two culverts were constructed.
5. I have considered the rival submissions
made across the Bar. In my considered opinion, when
the District Collector has forwarded a
communication to the Advocate General stating that,
the flooding that was occurring in the area in
question could be rectified by constructing two
culverts, the insistence for construction of three
culverts is not a viable proposition and it was
never directed by this Court also. It was
specifically made clear in the judgment that, if
the District Collector finds that Ext.P6 order,
which was the foundation of the writ petition, if
can be implemented it is to be implemented in its
letter and spirit. Therefore, when now the District
Collector has addressed the office of the Advocate
General that, the flooding of water could be
Con.Case(C).No.2134 OF 2020 IN WP(C). 40269/2016
rectified by construction of two culverts, this
Court is not expected to sit over such a factual
circumstance in order to identify whether the
respondents have committed contempt of the judgment
of this Court. If the petitioner is still
aggrieved, petitioner is to take up the matter
before the appropriate forum in order to ventilate
the grievances, that have occurred consequent to
the construction carried out by the respondents in
accordance with the directions contained in the
judgment.
Since the petitioner has submitted that, still
the flooding of water is not rectified, I think it
is only appropriate that the contempt case can be
closed, observing appropriately. Therefore, the
contempt petition is closed, recording the above
aspects and also observing that,the District
Collector shall oversee as to whether any flooding
occurs in the area due to non-construction of the
3rd culvert in Ext.P6 order referred to in the
Con.Case(C).No.2134 OF 2020 IN WP(C). 40269/2016
judgment in question and if still the flooding is
occurring in that area, it is for the District
Collector to take appropriate action to rectify the
same.
Sd/-
SHAJI P.CHALY JUDGE hmh
Con.Case(C).No.2134 OF 2020 IN WP(C). 40269/2016
APPENDIX PETITIONER'S/S EXHIBITS:
ANNEXURE A1 CERTIFIED COPY OF THE JUDGMENT DATED 5/4/2019 IN W.P(C)NO.40269/2016 OF THIS HON'BLE COURT.
ANNEXURE A2 TRUE COPY OF THE JUDGMENT DATED 21-
11-2019 IN CONT.CASE NO.1764/2019 IN W.P.(C)NO.40269/2016 ON THE FILE OF THIS HON'BLE COURT.
RESPONDENT'S/S EXHIBITS: NIL
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!