Citation : 2021 Latest Caselaw 5015 Ker
Judgement Date : 11 February, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE SMT. JUSTICE P.V.ASHA
THURSDAY, THE 11TH DAY OF FEBRUARY 2021 / 22ND MAGHA,1942
WP(C).No.25998 OF 2020(Y)
PETITIONER:
BENNY THOMAS
AGED 55 YEARS
S/O.P.T. THOMAS, PALATHINGAL HOUSE, KONGORPILLY P.O,
ERNAKULAM DISTRICT.
BY ADVS.
SRI.JOMY GEORGE
SRI.R.PADMARAJ
SRI.M.J.BENNY
SRI.DEEPAK MOHAN
SMT. CHITRA N. DAS
SHRI.RISHAB S.
SMT.ASHA V.S.NAIR
SRI.R.AJITH KUMAR [V.K.EDOM]
RESPONDENTS:
1 STATE OF KERALA
REPRESENTED BY CHIEF SECRETARY, GOVERNMENT
SECRETARIAT, THIRUVANANTHAPURAM - 695001.
2 SUPERINTENDING ENGINEER,
PWD ROADS AND BRIDGES CENTRE CIRCLE, ALUVA - 683101,
ERNAKULAM DISTRICT.
3 EXECUTIVE ENGINEER
PWD ROADS AND BRIDGES DIVISION, THRIKKAKARA P.O,
ERNAKULAM - 682021.
R2 BY adv.SMT.VINITHA.B, GOVERNMENT PLEADER
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
11.02.2021, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
WP(C).No.25998 OF 2020(Y)
2
JUDGMENT
Dated this the 11th day of February 2021
The petitioner is a contractor who has
undertaken the work of "one time maintenance
2015-16 of village roads-Elankunnapuzha beach
road Kana Kizhakke Appangad Palampilly link
road connecting Kana Elankunnapuzha Grama
Panchayat Ward No.2 & 5, improvements to
Kappela Kadathukadavu tarring sandal master-
central boat jetty road in Kadamakkudy Grama
Panchayat ward 5, 13, Puthukkad road-Karthedam
Bank junction road in Mulavukad Grama Panchayat
ward No.15, Vallyaparmbu cultural fine arts
road-Kurisingal Sahakarana road Kurisupalli
& 11" based on Ext.P1 selection notice after
executing agreement on 03.03.2016. Petitioner's
case is that though the date of completion of
the work was on 10.07.2016, the work could be
completed only on 27.02.2017 because of the WP(C).No.25998 OF 2020(Y)
monsoon and boundary disputes. Relying on
Ext.P2 letter dated 08.11.2016 petitioner
stated that the Executive Engineer had
addressed the 2nd respondent recommending
extension of time and accordingly the 3rd
respondent had permitted the petitioner to
complete the work without any fine and the work
was completed to the full satisfaction of the
respondents. Petitioner complains that though
the final bill for a sum of Rs.70,47,596/- was
submitted on 27.02.2017 the respondents were
not taking any action to approve the same and
to release the amount.
2. The 2nd respondent has filed a
statement raising allegations against the
petitioner pointing out the date shown in
Ext.P2. It is stated that the date
'08.11.2016' shown in Ext.P2 is not correct and
the actual date of Ext.P2 was '24.07.2017'. It
is also stated that as per Ext.R2(a) letter
dated 24.07.2017, the 3rd respondent had WP(C).No.25998 OF 2020(Y)
recommended extension of time for completion of
the work up to 10.11.2016; even though the said
letter was handed over to the petitioner
himself on 24.07.2017 for submitting the same
to 2nd respondent, he had not submitted the
same to the 2nd respondent. The 2nd respondent
alleged that the petitioner has filed this writ
petition making false statements and
fabricating documents. The further contention
is that, since the petitioner did not submit
any application, there was no extension of the
agreement and in the absence of a supplementary
agreement, it is not possible to make any
payment. At the same time it is also stated
that, in case the petitioner had submitted the
said letter in time, the 3rd respondent could
have submitted a recommendation to the 2nd
respondent (in advance) and could have
sanctioned the extension before expiry of the
original agreement. It is also stated that the
petitioner submitted both the extension WP(C).No.25998 OF 2020(Y)
applications together to the 3rd respondent,
which he had received from the Assistant
Executive Engineer on 07.07.2016 and on
18.11.2016. In Paragraph No.9 of the statement
the respondents stated as follows:-
"More than 4 years has expired since the expiry of the original agreement and till date the petitioner has not submitted any request or representation to the 2nd respondent regarding the non- sanctioning of the extension of completion time."
3. Heard Adv.Sri.R.Padmaraj, the learned
counsel appearing for the petitioner and
Adv.Smt.B.Vinitha, the learned Government
Pleader.
4. On consideration of the contentions,
it is seen that there is no dispute as to the
work carried out by the petitioner. The
dispute raised relates to the date on which
Ext. P2 was issued. It appears that non-
submission of an application for extension of
the agreement at the relevant time is the WP(C).No.25998 OF 2020(Y)
reason for not approving the bill. At any rate
it is seen that the petitioner had approached
the 3rd respondent and the 3rd respondent had
given a letter which the petitioner did not
produce before the 2nd respondent. That would
show that, in case the 3rd respondent had
issued a letter to the 2nd respondent directly,
there would not have been any difficulty as
alleged.
5. When the respondents do not have any
dispute over the work already carried out, it
cannot be said that payment cannot be made
towards the same. In these circumstances it is
only appropriate that the petitioner approaches
the 2nd respondent with a representation for
extension of time and for execution of
supplementary agreement in order to complete
the formalities, if such formalities are
required to be completed for raising the bill.
In case the petitioner submits such a
representation, within a period of two weeks WP(C).No.25998 OF 2020(Y)
from the date of receipt of a copy of the
judgment, the 3rd respondent shall consider the
representation and take appropriate decision on
it for enabling payment due to the petitioner
within a period of one month and for releasing
the payment without any further delay.
The writ petition is accordingly disposed
of.
Sd/-
P.V.ASHA JUDGE DM WP(C).No.25998 OF 2020(Y)
APPENDIX PETITIONER'S EXHIBITS:
EXHIBIT P1 TRUE COPY OF THE LETTER DATED 10.02.2016 ISSUED BY THE 2ND RESPONDENT ACCEPTING THE TENDER SUBMITTED BY THE PETITIONER.
EXHIBIT P2 TRUE COPY OF THE LETTER DATED 08.11.2016 ISSUED BY THE 3RD RESPONDENT TO THE 2ND RESPONDENT.
RESPONDENTS EXHIBITS
ANNEXURE R2(A) TRUE COPY OF THE LETTER DATED 24.07.2017.
ANNEXURE R2(B) THE EXACT COPY OF EXHIBIT P2 DATED 24.07.2017.
//TRUE COPY//
PA TO JUDGE
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!