Citation : 2021 Latest Caselaw 4630 Ker
Judgement Date : 9 February, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE SMT. JUSTICE P.V.ASHA
TUESDAY, THE 09TH DAY OF FEBRUARY 2021 / 20TH MAGHA,1942
WP(C).No.19765 OF 2020(U)
PETITIONER:
T.P.ANTONY,
AGED 60 YEARS,
S/O.POULOSE, ALANKAR CONSTRUCTION COMPANY,
THOTTATHIL HOUSE, NADAKKAVU P.O.,
UDAYAMPEROOR,
ERNAKULAM DISTRICT, PIN-682 307.
BY ADVS.
SRI.BABU JOSEPH KURUVATHAZHA
SMT.K.S.ARCHANA
RESPONDENTS:
1 KERALA LAND DEVELOPMENT CORPORATION LIMITED,
T.C.11/570, BAINS COMPOUND, MUSEUM, KOWDIAR P.O.,
THIRUVANANTHAURAM-695 003,
REPRESENTED BY ITS MANAGING DIRECTOR.
2 CONSTRUCTION ENGINEER,
KERALA LAND DEVELOPMENT CORPORATION LIMITED,
28/47, SABARI GARDENS, CHANDANAKKAVU ROAD,
CHUNGAM, ALAPPUZHA-688 011.
3 PROJECT ENGINEER,
KERALA LAND DEVELOPMENT CORPORATION LIMITED,
BUILDING NO.508, SAI DARSHAN, CHIRAKKADAVAM,
KAYAMKULAM P.O.,
ALAPPUZHA DISTRICT, PIN-690 572.
4 ROY ABRAHAM,
CHATHAMTHADATHIL HOUSE,
EDAYAR P.O.,
KOOTHATTUKULAM MUNICIPALITY,
(COUNCILOR, DIVISION NO.XXV AND THE CHAIRMAN,
KOOTHATTUKULAM MUNICIPALITY),
KOOTHATTUKULAM P.O.,
ERNAKULAM DISTRICT, PIN-686 662.
WP(C).No.19765 OF 2020
2
BY ADVS. SRI.G.BAIJURAJ
THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON
09.02.2021, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
WP(C).No.19765 OF 2020
3
JUDGMENT
The termination of contract ordered by
the 2nd respondent in Ext.P13, imposing risk
and cost liability on petitioner is under
challenge in this writ petition.
2. Based on a tender notification issued
by the 2nd respondent for renovation of
Chandathodu and for effecting improvements to
Paddy production in Koothattukulam Grama
Panchayat, petitioner was awarded the work;
agreement was executed on 07.11.2018
stipulating the time for completion as twelve
months. The site was handed over to petitioner
as per Ext.P1 proceedings on 17.11.2018. The
case of the petitioner is that though he went
to the site along with technical/skilled staff
and machinery, for commencing the work on
27.11.2018, on account of obstructions caused
by the 4th respondent, who was the Councilor WP(C).No.19765 OF 2020
of the said ward along with several other
local people, the petitioner was unable to
carry out the work. Petitioner had brought
these incidents to the notice of the
respondents 2 and 3 several times, by way of
representations Exts.P3, P4, P5, etc and had
been requesting them to take appropriate
action to enable him to carry out the work. It
is stated that based on the demands made by
the 4th respondent and his men, Government had
issued Ext.P6 order on 26.02.2020 giving
approval to revised estimate for the work
awarded to the petitioner, including certain
additional works. Petitioner points out that
the work covered by Ext.P6 order was entirely
different from that covered by the agreement
executed by him/the work order given to him.
It is stated that the 3rd respondent thereafter
as per Ext.P7 letter dated 10.03.2020 directed WP(C).No.19765 OF 2020
the petitioner to commence the work. It is
stated that the 4th respondent had approached
this Court in the meanwhile in W.P.(C)
No.30657/2019 seeking for directions in
respect of the work awarded to the petitioner.
According to the petitioner, even though the
contractor was made a party in that writ
petition, no notice was served on him. Ext.P8
letter dated 18.03.2020 was also issued to
petitioner directing him to commence the work
pointing out the judgments in W.P.(C)
Nos.30657 and 30659 of 2019. Thereupon
petitioner submitted Ext.P9 letter dated
18.03.2020 to the 3rd respondent expressing
his unwillingness to commence the work covered
by the agreement and requesting to relieve
him from the contract. It was followed by
Ext.P10 representation and Ext.P11
representation submitted on 18.05.2020 WP(C).No.19765 OF 2020
requesting to relieve him from the agreement
and to allow him to execute the closure
agreement. Thereafter he approached this Court
in W.P.(C) No.11268/2020 and this Court as per
Ext.P12 judgment directed the 2nd respondent
to pass suitable orders. But the 2nd
respondent issued Ext.P13 order, in
consultation with the 1st respondent,
terminating the work awarded to the petitioner
at his risk and cost stating that he failed to
fulfill his obligation of starting the work
and completing the same.
3. Petitioner points out that he was
unable to carry out the work only because of
the inaction of the respondents in making
available a hindrance free work site. The
original period of agreement expired on
06.11.2019. Thereafter there was no effective
action for extension of the agreement. It is WP(C).No.19765 OF 2020
stated that the termination at the risk and
cost of the petitioner, when the respondents
are very well aware of the fact that the work
got delayed only at their instance, is
arbitrary.
4. The 1st respondent has filed a counter
affidavit. It is stated that the Project
Engineer, who was holding supervisory charge
on the project, had reported that there were
disputes at the site from various corners
suggesting additional work in view of the
floods affected in 2018. On the basis of the
demands made by the Councilor and the local
people, KLDC got the administrative sanction
revised from the Government. It is stated that
in view of the disputes at the site, it
became necessary to undertake re-survey. It is
further stated that since initial levels could
not be reported, the respondents were unable WP(C).No.19765 OF 2020
to give directions to commence the work. It is
stated that the respondents did not expect any
obstruction to the work at the time of
execution of agreement and that entire team of
KLDC tried their best to resolve the disputes
by convening several meetings and discussions
with the Municipality and Padasekhara samithy
and in order to settle the disputes, it was
decided to include additional works in the
estimate and revised estimate was prepared and
submitted to Government. It is stated that
petitioner did not participate in any of the
meetings and did not do anything for an
amicable settlement. It is further stated that
as per the provisions contained in clause 2112
of PWD manual, the contractor has to apply for
extension of time through Project Engineer
before the expiry of period of completion. It
is stated that petitioner did not submit any WP(C).No.19765 OF 2020
application for extension even after Ext.R1(b)
letter was sent on 16.11.2019; in Ext.P7
letter issued after receipt of sanction for
additional work, petitioner was asked to take
steps for extension of agreement and to make
arrangements for execution. It is stated that
there was direction from this Court also in
respect of the work and the petitioner, who
was a party to the judgment, is bound by it.
According to the respondents, petitioner is
bound to execute the project as per the
agreement as well as Ext.P8(a) judgment. It is
stated that the site became clear after
17.03.2020 on completion of re-survey and the
initial level survey and on reporting of the
proposed quantities to the Technical Examiner
on 17.03.2020. It is stated that petitioner is
liable to carry out the work as per the
provisions in the agreement and PWD Manual. It WP(C).No.19765 OF 2020
is stated that in reply to petitioner's
request for foreclosure, the respondent had as
per letter dated 13.05.2020 asked him to
commence the work, as the disputes were
settled and revised estimate was sanctioned.
He did not attend the meeting convened with
Municipality for immediate completion of the
work for protecting the area from flood. Since
he did not co-operate, the respondents had to
arrange urgent work in order to protect the
area from the flood. According to the
respondent, the contractors are expected to
anticipate such contingencies when they are
participating in the tender.
5. Petitioner has filed a reply affidavit
stating that even on 06.11.2019, the date on
which the time stipulated in the agreement
expired, the work site was not ready.
According to the petitioner, a contractor need WP(C).No.19765 OF 2020
seek extension of agreement only if the work
had commenced in time and some hindrance
occurred in the midst. According to him, when
admittedly the work could not be commenced on
account of obstruction from outside the
respondents ought not have terminated the
contract at his risk and cost. It is stated
that the relevant provision in the PWD manual
in such circumstances is not Clause 2112 as
alleged by the respondents but on the other
hand, it is 2003.
6. I heard Sri.Babu Joseph Kuruvathazha,
learned counsel appearing for the petitioner
and Sri.Baijuraj G., learned Standing Counsel
appearing for the respondents.
7. Admitted facts in the case are that
agreement was executed on 07.11.2018 and as
per the agreement, the work was to be
completed before 06.11.2019. But it is also an WP(C).No.19765 OF 2020
admitted fact that the petitioner could not
commence work due to obstructions. In
paragraph 6 of the counter affidavit the first
respondent stated as follows: "As initial
levels could not be reported, we were unable
to give directions to start the work". In
paragraph 13 he stated: "The initial level
survey completed after Re-survey and proposed
quantities reported to the Chief Technical
Examiner on 17.03.2020. Then the site is very
clear to carry out the work." The 1st
respondent has also stated that additional
work was included and revised estimate was
sanctioned on 06.02.2020. Therefore from these
admitted facts, it would appear that the
respondent were unable to provide the work
site, free from hindrance either as on
06.11.2019 and till March 2020.
8. As the respondents rely on Clause 2112 WP(C).No.19765 OF 2020
in support of the contention that it is
incumbent on the contractor to apply for
extension, in view of the following provision
in Clause 2112 of PWD Manual, which reads as
follows: "if however the failure of the
contractor to complete the work on the
stipulated date is due to any departmental
delays or due to design and construction
problems faced during execution then he may
apply for extension of time through the
Assistant Engineer before expiry of the
period of completion. As pointed out by the
learned Counsel for the petitioner, in the
present case the work is admittedly not
commenced. Respondents do not rely on any
provision dealing with extension of agreement
in a case, where the work is not commenced.
9. Clause 2003 of PWD Manual relied on by
the petitioner, provides:
WP(C).No.19765 OF 2020
"xxxx if there is a time lag of one year between the date of preparation of the estimate and date of tender of work, it is necessary to verify whether any changes have occurred necessitating modification to the provisions in the estimate. If the modifications required are only minor the officer competent to enter into contract may invite tenders on the basis of the sanctioned estimate. Otherwise the estimate shall be recast and tenders invited on that basis."
10. It would appear that the aforesaid
provision also does not deal with a case,
where the administrative sanction is obtained
for revised estimate after the awarding of
work and after the execution of agreement. At
any rate, there is modification to the
estimate after more than one year of the
tender and after the agreement. It is a case,
where the petitioner had been requesting for
hindrance free site till the expiry of the
agreement. He has been requesting for
foreclosure of the same from 16.11.2019 WP(C).No.19765 OF 2020
onwards. The respondents themselves say that
work could be started from 17.03.2020 that too
after inclusion of additional work and on a
revised estimate, not covered by the agreement
which expired.
In such circumstances, I am of the
view that the respondents cannot on the
strength of clause 2112 of PWD Manual insist
that petitioner should have got the agreement
extended. The only provision relied on by the
respondents for insisting the petitioner to
apply for extension of the agreement for
completing the work is clause 2112. Normally
this Court would have refrained from
interfering with such matters of contract. But
in the light of the admitted factual
circumstances of the case, I am of the view
that imposing of risk and cost while
terminating the contract was unwarranted. WP(C).No.19765 OF 2020
Therefore, Ext.P13 order to the extent it
stipulates the termination of contract at the
risk and cost of petitioner is set aside.
Accordingly the writ petition is
allowed to the extent indicated above.
Sd/-
P.V.ASHA JUDGE
ww WP(C).No.19765 OF 2020
APPENDIX PETITIONER'S EXHIBITS:
EXHIBIT P1 TRUE PHOTOCOPY OF THE PROCEEDING DATED 17.11.2018, HANDING OVER THE SITE TO THE PETITIONER.
EXHIBIT P2 TRUE COPY OF THE LETTER DATED 19.12.2018 WRITTEN BY THE 4TH RESPONDENT TO THE IST RESPONDENT.
EXHIBIT P3 TRUE COPY OF THE REPRESENTATION DATED 31.12.2018 SUBMITTED BY THE PETITIONER BEFORE THE 2ND RESPONDENT.
EXHIBIT P4 TRUE COPY OF THE RERPESENTATION DATED 2.2.2019 SUBMITTED BY THE PETITIONER BEFORE THE 2ND RESPONDENT.
EXHIBIT P5 TRUE COPY OF THE REPRESENTATION DATED 16.11.2019 SUBMITTED BY THE PETITIONER BEFORE THE 2ND RESPONDENT.
EXHIBIT P6 TRUE COPY OF THE G.O.(RT) NO.263/2020/AGRI.
DATED 26.2.2020 ISSUED BY THE GOVERNMENT.
EXHIBIT P7 TRUE COPY OF THE LETTER DATED 10.3.2020 ISSUED BY THE 3RD RESPONDENT.
EXHIBIT P8 TRUE COPY OF THE DIRECTION DATED 18.3.2020 ISSUED BY THE 2ND RESPONDENT.
EXHIBIT P8(A) TRUE COPY OF THE JUDGMENT DATED 16.11.2019 IN WPC NOS.30657 AND 30659 OF 2019 OF THIS HON'BLE COURT.
EXHIBIT P9 TRUE COPY OF THE REPRESENTATION DATED 18.3.2020 SUBMITTED BY THE PETITIONER BEFORE THE 3RD RESPONDENT.
EXHIBIT P10 TRUE COPY OF THE REPRESENTATION DATED 18.5.2020 SUBMITTED BY THE PETITIONER BEFORE THE 2ND RESPONDENT.
EXHIBIT P11 TRUE COPY OF THE REPRESENTATION DATED 18.5.2020 SUBMITTED BY THE PETITIONER BEFORE THE IST RESPONDENT.
WP(C).No.19765 OF 2020
EXHIBIT P12 TRUE COPY OF THE INTERIM ORDER DATED 26.6.2020 IN WPC NO.11268/2020 OF THIS HON'BLE COURT.
EXHIBIT P13 TRUE COPY OF THE ORDER DATED 20.8.2020 ISSUED BY THE 2ND RESPONDENT.
EXHIBIT P14 TRUE PHOTOCOPY OF SECTION 2003 OF THE PWD MANUAL REVISED EDITION 2012.
RESPONDENTS' EXHIBITS:
EXHIBIT R1(A) TRUE COPY OF THE SPECIFIC PORTION OF PWD MANUAL.
EXHIBIT R1(B) TRUE COPY OF THE LETTER DATED 16/11/2019 ISSUED BY THE 1ST RESPONDENT.
EXHIBIT R1(C) TRUE COPY OF THE LETTER DATED 14/05/2020 ISSUED BY THE 1ST RESPONDENT.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!