Monday, 04, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M.A.Ameer vs The State Of Kerala
2021 Latest Caselaw 4296 Ker

Citation : 2021 Latest Caselaw 4296 Ker
Judgement Date : 5 February, 2021

Kerala High Court
M.A.Ameer vs The State Of Kerala on 5 February, 2021
         IN THE HIGH COURT OF KERALA AT ERNAKULAM

                         PRESENT

           THE HONOURABLE MR.JUSTICE N.NAGARESH

 FRIDAY, THE 05TH DAY OF FEBRUARY 2021/16TH MAGHA,1942

                WP(C).No.14889 OF 2020(I)


PETITIONERS:

            M.A.AMEER,
            AGED 50 YEARS,
            PWD CONTRACTOR,
            MUNAMBA HOUSE,
            P.O.CHENGALA, KASARAGOD-671541.

            BY ADVS.
            SRI.K.L.VARGHESE (SR.)
            SMT.SANTHA VARGHESE
            SRI.RAHUL VARGHESE
            SRI.RANJITH VARGHESE

RESPONDENTS:

     1      THE STATE OF KERALA,
            REPRESENTED BY THE SECRETARY TO GOVERNMENT,
            PLANNING AND ECONOMIC AFFAIRS (A) DEPARTMENT,
            GOVERNMENT SECRETARIAT,
            THIRUVANANTHAPURAM-695001.

     2      THE EXECUTIVE ENGINEER,
            PWD ROADS DIVISION,
            PWD COMPLEX,
            PULIKUNNU, KASARAGOD-671 121.

     3      THE SPECIAL OFFICER AND GOVERNMENT JOINT
            SECRETARY,
            KASARAGOD DEVELOPMENT PACKAGE,
            CIVIL STATION,
            KASARAGOD-671123.
 W.P.(C) No.14889/2020
                             :2:


      4      THE DISTRICT COLLECTOR,
             KASARAGOD, KASARAGOD DEVELOPMENT PACKAGE,
             CIVIL STATION,
             KASARAGOD-671123.

             SR. GOVERNMENT PLEADER SRI K.V.MANOJ KUMAR

     THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY
HEARD ON 05-02-2021, THE COURT ON THE SAME DAY DELIVERED
THE FOLLOWING:
 W.P.(C) No.14889/2020
                                       :3:




                           N. NAGARESH, J.

          `````````````````````````````````````````````````````````````
                      W.P.(C) No.14889 of 2020

          `````````````````````````````````````````````````````````````
              Dated this the 5th day of February, 2021

                            JUDGMENT

~~~~~~~~~

Petitioner, who is an A-Class Contractor of the

Kerala Public Works Department, has filed this writ petition

seeking to quash Ext.P8 and to direct the 4 th respondent-

District Collector to take immediate steps for rectification of

mistake in declining the amount and to release ₹23,38,367/-

to the petitioner, as recommended by the Executive Engineer

in Exts.P6 and P7 within a time to be stipulated by this Court.

The petitioner has also sought interest at 15% per annum on

the said amount.

2. The petitioner undertook the work of "Improvement

of Adoor Mandakol Road" for the PWD. The original scope

of the work provided "construction of carriage way with

20 mm. thick premixed open grade chipping carpet". W.P.(C) No.14889/2020

Subsequently, the scope of work was modified from

"premixed open grade chipping carpet" to "Bituminous

Macadam and Bituminous Concrete". The Government

sanctioned the change as per Ext.P2 and the work was

accordingly completed by the petitioner. The final bill was

settled on 27.09.2017.

3. The petitioner states that ₹5,00,00,000/- was

deposited for the project work. However, the final bill was

only for ₹4,80,86,314/-. The balance amount of ₹19,13,686/-

was returned to the accounts of the 4 th respondent-District

Collector. When the petitioner's auditor scrutinised his

accounts, the auditor noted that there was a deficit in the

amount due to the petitioner on account of an oversight and

more amount was due to the petitioner from the respondents.

Therefore, on 01.10.2019, the petitioner submitted Ext.P3

request to the Executive Engineer to re-examine the bills.

4. The petitioner had procured all the materials

required for the work from his own sources. The

respondents did not supply any material at all. However, an W.P.(C) No.14889/2020

amount of ₹22,35,692/- was seen recovered from the amount

due to the petitioner towards differential cost of materials, by

mistake. In fact, the Agreement provided that no

departmental materials shall be supplied to the petitioner by

the Department. Though the petitioner had himself procured

Bitumen and emulsion with his own funds, the said amount

was seen erroneously deducted from the total amounts due

to the petitioner.

5. The Executive Engineer noticed this defect and

issued Ext.P5 letter dated 27.01.20020 to the District

Collector. The Executive Engineer stated that an amount of

₹19,16,997/- was deducted from the 2 nd part bill of the

petitioner and another amount of ₹3,18,695/- from the 3 rd

part bill, totalling to ₹22,35,692/-. The Executive Engineer

recommended that the said amount may be re-credited to the

account of the project work for onward payment to the

petitioner.

6. As per Ext.P6 dated 27.02.2020, the Special

Officer & Government Joint Secretary of Kasaragod W.P.(C) No.14889/2020

Development Package issued letter to the Executive

Engineer seeking details of agreed PAC, part bills and final

bill for further scrutiny on account of the discrepancies. By

Ext.P7 letter dated 29.02.2020, the Executive Engineer

informed the Special Officer & Government Joint Secretary

that the amount recovered from the 2 nd and 3rd part bills was

₹21,54,869/- and another amount of ₹1,77,548/- was also

erroneously deducted towards cost of empty drums of

Bitumen and yet another amount of ₹5,950/- from the 3 rd and

final bill of the petitioner and the total deduction wrongly

made was ₹23,38,367/- which is to be reimbursed to the

petitioner.

7. Though there was no dispute as regards the

unauthorised deduction from the bills of the petitioner, the

District Collector issued Ext.P8 letter to the Executive

Engineer stating that the project was of the year 2014-'15

and proceedings thereon were completed and therefore the

new proposal for reimbursement need not be considered. A

copy of Ext.P8 was forwarded to the petitioner also. The W.P.(C) No.14889/2020

petitioner is aggrieved by the decision of the District Collector

communicated through Ext.P8.

8. The learned counsel for the petitioner argued that

the denial of payment of ₹23,38,367/- by the District Collector

is unlawful and unjustifiable. Being a mutual mistake, the

non-return of the said amount tantamount to deprivation of

legitimate dues to the petitioner. The petitioner has

completed the work making considerable savings to the

respondents. The petitioner quoted a very competitive rate

of 23.78% below the estimate rate. The work was done to the

satisfaction of the respondents. When the audit of accounts

disclosed the mistake and the Executive Engineer certified

the same, it would be highly arbitrary and unjust on the part

of the 4th respondent to decline the amount to the petitioner

for the sole reason that the project was of the year 2014-'15.

9. Learned counsel for the petitioner pointed out that

an executive authority must be rigorously held to the

standards by which it professes its actions to be judged and

it must scrupulously observe those standards on pain of W.P.(C) No.14889/2020

invalidation of the act in case of violation. Relying on the

judgment of the Hon'ble Apex Court in Vestindia

Pharmaceuticals Limited v. State of Uttar Pradesh and

another [2020 SCC Online SC 912], the learned counsel for

the petitioner argued that the question of Limitation Act does

not apply to the writ jurisdiction and the discretion vested in

the Court under Article 226 of the Constitution has to be

judiciously exercised after considering all pros and cons of

the matter, including the nature of the dispute, the

explanation for the delay, whether any third party rights have

intervened etc. Learned counsel pointed out that the

jurisdiction under Article 226 being equitable in nature,

questions of proportionality in considering whether the

impugned order merits interference or not in exercise of the

discretionary jurisdiction will also arise.

10. The learned counsel for the petitioner also relied

on the judgment of the Apex Court in Madras Port Trust v.

Hymanshu International by its Proprietor V. Venkatadri

(Dead) by LRs [(1979) 4 SCC 176] and urged that the W.P.(C) No.14889/2020

respondents cannot resort to the plea of limitation to defeat

just claim of citizen.

11. The learned counsel for the petitioner argued that

the issue involved in the writ petition is not a disputed

question of fact at all. This Court has held in the judgment in

Grace Joseph v. State of Kerala and others [2006 KHC

783] that when on available materials, it may not at all be

necessary to record evidence and there may not be any hotly

disputed facts, which don't require recording of evidence for

determination, the parties cannot be forced to seek the

desired relief from the civil court.

12. The learned Government Pleader representing the

respondents strongly opposed the writ petition. The learned

Government Pleader argued that the work was completed on

29.03.2017. The claim in the writ petition is in respect of the

differential cost allegedly deducted in part bills which were

submitted on 31.05.2016, 07.02.2017 and 30.03.2017. The

project was closed long back in 2017 and there is no fund or

amount available as the project is closed. W.P.(C) No.14889/2020

13. The contention of the petitioner that the deduction

of amount in the midst of differential cost as if Bitumen was

supplied by the Department, is irrelevant. The subject work

is not an item rate contract and therefore the claim made by

the writ petitioner is not maintainable. The claim of the

petitioner is stale and belated. The Government Pleader

submitted that the estimate rate of Bitumen was higher and

the actual rate was lower. It was under that circumstance the

differential amount was deducted.

14. I have heard the learned counsel for the petitioner

and the learned Government Pleader for the respondents.

15. As regards the plea of delay and limitation, it is to

be noted that the 3rd and final bill was submitted by the

petitioner on 27.09.2017. The petitioner pointed out the

mistake and sought for rectification on 01.10.2019. The

impugned Ext.P8 order was passed by the 4 th respondent on

02.07.2020. The writ petition was filed on 22.07.2020, within

three years of the submission of final bill and of noticing the

error and within three weeks of issuing the impugned W.P.(C) No.14889/2020

communication. Therefore, this Court finds that the writ

petition cannot be dismissed on the basis of delay, laches or

limitation.

16. The further contention of the learned Government

Pleader is that the issue involves disputed questions of fact

and hence this Court should not interfere in the matter. It is

not in dispute that the petitioner quoted the work at a

competitive rate of 23.78% below the estimated rate and the

work was satisfactorily completed. Amounts were deducted

from the bills of the petitioner as differential cost on an

erroneous assumption that Bitumen and emulsion were

supplied by the Department. The fact that the Department

has not supplied Bitumen and emulsion to the petitioner, is

not in dispute. In fact, Clause 28 of Ext.P4-NIT specifically

states that no departmental materials shall be supplied to the

Contractor by the Department.

17. The Executive Engineer pointed out this error to

the 4th respondent-District Collector as per Ext.P5. The

Special Officer & Government Joint Secretary, Kasaragod W.P.(C) No.14889/2020

Development Package called for the required documents to

ascertain the fact. The differential cost of Bitumen deducted

from the bills of the petitioner was ₹21,54,869/-. Cost of

empty drums were also mistakenly deducted to the tune of

₹1,83,498/-. Thus, the total erroneous deduction from the

bills of the petitioner was ₹23,38,367/-. However, the District

Collector chose not to correct the mistake for the specious

reason that the project in question was of the year 2014-'15.

The petitioner could not detect the mistake of erroneous

deduction at the time of settlement of the bills. But, as soon

as the mistake was noted, he brought it to the notice of the

respondents. The concerned Executive Engineer, after

perusing the records including the M-Book, came to the

conclusion that erroneous deductions were made from the

bills of the petitioner. When amounts were erroneously

deducted from the payment to the petitioner, it is the duty of

the State to make refund. The deduction of amounts were

without the authority of law. The State has no right to the

money and it is refundable to the Contractor. W.P.(C) No.14889/2020

In the facts of the case, the writ petition is partly

allowed. Ext.P8 is set aside. The respondents are directed

to take immediate steps for rectification of the mistake and to

release the amount of ₹23,38,367/- to the petitioner as

recommended by the Executive Engineer in Exts.P6 and P7,

within a period of two months.

Sd/-

N. NAGARESH, JUDGE aks/03.02.2021 W.P.(C) No.14889/2020

APPENDIX PETITIONER'S EXHIBITS:



EXHIBIT P1              TRUE COPY OF THE GOVERNMENT         ORDER
                        NO.G.O.(RT.)NO.16/2015/PLG          DATED
                        8.1.2015.

EXHIBIT P2              TRUE   COPY   OF    THE    ORDER    DATED
                        22.4.2015    ISSUED     BY    THE     4TH
                        RESPONDENT-DISTRICT COLLECTOR.

EXHIBIT P3              TRUE   COPY  OF   THE  REQUEST  DATED
                        1.10.2019 ISSUED BY THE PETITIONER TO
                        THE 2ND RESPONDENT.

EXHIBIT P4              TRUE COPY OF THE AGREEMENT FORM NO.83
                        PAGE 20 CONTAINING CLAUSE 28.

EXHIBIT P5              TRUE COPY OF LETTER DATED 27.1.2020
                        ISSUED BY THE 2ND RESPONDENT TO THE
                        4TH RESPONDENT.

EXHIBIT P6              TRUE COPY OF LETTER DATED 27.2.2020
                        ISSUED BY THE 3RD RESPONDENT TO THE
                        2ND RESPONDENT.

EXHIBIT P7              TRUE COPY OF LETTER DATED 29.2.2020
                        ISSUED BY THE 2ND RESPONDENT TO THE
                        3RD RESPONDENT.

EXHIBIT P8              TRUE COPY OF LETTER DATED 2.7.2020
                        ISSUED BY THE 4TH RESPONDENT TO THE
                        2ND RESPONDENT.

SR
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter