Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

T.K.Kesavan vs Kerala Police Housing ...
2021 Latest Caselaw 4286 Ker

Citation : 2021 Latest Caselaw 4286 Ker
Judgement Date : 5 February, 2021

Kerala High Court
T.K.Kesavan vs Kerala Police Housing ... on 5 February, 2021
         IN THE HIGH COURT OF KERALA AT ERNAKULAM

                            PRESENT

              THE HONOURABLE MR.JUSTICE N.NAGARESH

  FRIDAY, THE 05TH DAY OF FEBRUARY 2021/16TH MAGHA,1942

                   WP(C).No.21595 OF 2013(Y)


PETITIONER:

              T.K.KESAVAN,
              THALIYARA HOUSE, P.O.NIRAMARUDUR,
              TIRUR, MALAPPURAM DISTRICT-676 109.

              BY ADV. SRI.O.D.SIVADAS

RESPONDENTS:

     1        KERALA POLICE HOUSING CONSTRUCTION
              CORPORATION LIMITED,
              CHANDRASEKHARAN NAIR STADIUM,
              VIKAS BHAVAN.P.O.,
              THIRUVANANTHAPURAM-695 033,
              REPRESENTED BY ITS MANAGING DIRECTOR.

     2        THE MANAGING DIRECTOR,
              KERALA POLICE HOUSING CONSTRUCTION
              CORPORATION LIMITED,
              CHANDRASEKHARAN NAIR STADIUM,
              VIKAS BHAVAN.P.O.,
              THIRUVANANTHAPURAM-695 033.

     3        THE SENIOR PROJECT ENGINEER,
              KERALA POLICE HOUSING AND CONSTRUCTION
              CORPORATION LIMITED,
              CHANDRASEKHARAN NAIR STADIUM,
              VIKAS BHAVAN.P.O.,
              THIRUVANANTHAPURAM-695 033.

              R1-3 BY SRI.GOVINDAN.C.K., SC, KPHCC
              BY ADV. SMT.M.V.LIGI

     THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD
ON 05.02.2021, THE COURT ON THE SAME DAY DELIVERED THE
FOLLOWING:
 WP(C) No.21595/2013
                                    :2 :




                           JUDGMENT

~~~~~~~~~

Dated this the 5th day of February, 2021

The petitioner, who is a Building Contractor, has

filed this writ petition seeking the following reliefs:-

"i) call for the records leading tot he proceeding and quash Ext.P9 and P12 by issuing a writ of certiorari.

ii) issue a writ of mandamus or any other appropriate writ, order or direction tot he respondents to sanction and disburse balance amount of ₹3,06,920/- with interest at 18% per annum for the delay in payment without effecting any recovery."

2. The petitioner states that as per Ext.P1 letter, he

was awarded the work of construction of Truss Roofing for the

Administrative Block of KAP-I Battalion, Ramavarmapuram,

Thrissur. Work order was received on 28.02.2011 and

Agreement was executed on 06.04.2011. The stipulated date

of completion of work was 24.04.2011. The 3 rd respondent WP(C) No.21595/2013

orally informed the petitioner that instead of the proposed

ordinary G.I. roofing sheets, Lloyd sheets should be used for

the truss. By Exts.P2 to P4 letters, the petitioner requested to

confirm the roofing material. The decision on change of

roofing material was approved by the 2 nd respondent only on

12.04.2012.

3. By the time, the stipulated date for completion of

work had expired. However, the petitioner completed the

work by 25.08.2012. To the surprise of the petitioner, the

respondents issued Ext.P7 show-cause notice dated

25.01.2013 on the petitioner, proposing to impose penalty for

53 days delay in completion of work. The petitioner submitted

Ext.P8 reply on 30.01.2013. The respondents, without

considering the explanation given, imposed a fine of

₹25,903/- as per Ext.P9 order dated 19.03.2013. In appeal,

the 2nd respondent reduced the fine as ₹15,000/-.

4. The petitioner would submit that after the

completion of work, the petitioner submitted a final bill for

₹5,39,284/-, but only an amount of ₹2,32,364/- has been paid WP(C) No.21595/2013

to the petitioner. An amount of ₹3,06,920/- was withheld due

to insufficiency of funds. The petitioner would submit that the

non-payment of the full amount under final bill is grossly

arbitrary. The imposing of ₹15,000/- as fine for the delay in

completion of work is also illegal, since the delay was not

caused due to any fault of the petitioner.

5. On 30.08.2013, when this writ petition was

admitted, this Court passed an interim order directing that the

admitted amount shall be released to the petitioner forthwith.

The petitioner states that pursuant to the interim order,

₹3,06,920/- has been paid to the petitioner. Therefore, the

remaining question to be decided in this writ petition is as

regards the sustainability of imposition of fine.

6. The learned counsel for the petitioner would submit

that the delay in completion of work is substantially due to the

fact that the respondents proposed to change the material of

roofing. Though the petitioner submitted Exts.P2 to P4 letters

to the respondents, the final approval for change of material

was granted only on 12.04.2012. Due to this delay, there was WP(C) No.21595/2013

an escalation in the cost of work, labour charges and

materials. There was delay in issuing sanction to substitute

the electrical work items also.

7. I have heard the learned counsel for the petitioner

and the learned Standing Counsel appearing for the

respondents.

8. As regards the competency of the respondents to

impose fine, the learned Standing Counsel would submit that

there is provision in the Agreement enabling the respondents

to impose fine by way of compensation for the delay in

completion of work resulting in breach of contract. A perusal

of the pleadings in the writ petition would show that though

the approval for change of materials was given on

12.04.2012, the petitioner did not complete the work within a

reasonable time thereafter. The respondents have condoned

substantial part of the delay, which can be attributable to the

change of materials and time taken to get approval for it.

9. Even excluding the period of getting approval for

change of materials, still there was substantial delay. The WP(C) No.21595/2013

respondents have computed fine limiting the delay to a period

of 53 days only. The initial imposition of ₹25,903/- as fine was

reduced to ₹15,000/-. The fine has been calculated as per

the terms of the tender documents of the Kerala Police

Housing and Construction Corporation Limited.

In the circumstances, this Court does not find any

reason to interfere with the order of fine or quantum thereof.

No further relief can be granted in the writ petition. The writ

petition is therefore dismissed.

Sd/-

N. NAGARESH, JUDGE

aks/05.02.2021 WP(C) No.21595/2013

APPENDIX PETITIONER'S EXHIBITS:

EXHIBIT P1 TRUE COPY OF THE LETTER DATED 30.12.2010 OF THE RESPONDENTS.

EXHIBIT P2 TRUE COPY OF THE LETTER DATED 9.5.2011.

EXHIBIT P3 TRUE COPY OF THE LETTER DATED 4.8.2011 ADDRESSED TO THE 2ND RESPONDENT.

EXHIBIT P4 TRUE COPY OF THE LETTER DATED 18.10.2011 ADDRESSED TO THE CHAIRMAN- CUM-MANAGING DIRECTOR.

EXHIBIT P5 TRUE COPY OF THE APPROVAL DATED 12.4.2012.

EXHIBIT P6 TRUE COPY OF THE LETTER DATED 18.6.2012.

EXHIBIT P7 TRUE COPY OF THE SHOW CAUSE NOTICE ISSUED BY THE RESPONDENTS.

EXHIBIT P8 TRUE COPY OF THE REPLY DATED 30.1.2013 SUBMITTED BY THE PETITIONER.

EXHIBIT P9 TRUE COPY OF THE PROCEEDING DATED 19.03.2013 ISSUED TO THE PETITIONER.

EXHIBIT P10           TRUE   COPY    OF   THE  PETITION   DATED
                      29.03.2013     SUBMITTED   TO   THE   2ND
                      RESPONDENT.

EXHIBIT P11           TRUE   COPY    OF    THE    LETTER    DATED
                      04.04.2013.

EXHIBIT P12           TRUE COPY OF THE          PROCEEDING DATED
                      15.05.2013  ISSUED          BY   THE   2ND
                      RESPONDENT.
 WP(C) No.21595/2013





RESPONDENTS EXHIBITS:

EXHIBIT R1(A)         TRUE COPY OF AGREEMENT NO.08/2011-2012
                      DATED 16.04.2011
EXHIBIT R1(B)         TRUE        COPY        OF        LETTER
                      NO.TPS/3410/KPHCC/2010             DATED
                      17.04.2012     RESPONDENTS     TO    THE
                      PETITIONER
EXHIBIT R1(C)         TRUE     COPY      OF     WORK     ORDER
                      NO.TPS/3410/KPHCC/2010             DATED

30.12.2010 ISSUED BY RESPONDENT TO THE PETITIONER EXHIBIT R1(D) TRUE COPY OF SHOW CAUSE NOTICE FOR REMITTING THE PENALITY DATED 25.01.2013 ISSUED TO THE PETITIONER EXHIBIT R1(E) TRUE COPY OF ORDER NO.TPS/3410/KPHCC/2010 DATED 15.05.2013 ISSUED BY 3RD RESPONDENT TO THE PETITIONER

SR

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter