Citation : 2021 Latest Caselaw 16850 Ker
Judgement Date : 12 August, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE MURALI PURUSHOTHAMAN
THURSDAY, THE 12TH DAY OF AUGUST 2021 / 21ST SRAVANA, 1943
WP(C) NO. 3408 OF 2011
PETITIONER:
P.M.ASSAINAR
AGED 51 YEARS, S/O.LATE KUTTY MOHAMMED,PROPRIETOR,
M/S.V-PRO ENGINEERS, XI-446, MANATH COMPLEX, NGO
QUARTERS, THRIKKAKARA P.O., KAKKANAD, KOCHI-682021.
BY ADVS.
SRI.C.A.CHACKO
SRI.N.A.SHAFEEK
SRI.M.S.UNNIKRISHNAN OASIS
RESPONDENTS:
1 STATE OF KERALA
REPRESENTED BY SECRETARY TO GOVERNMENT,
IRRIGATION AND WATER RESOURCES DEPARTMENT, SECRETARIAT,
THIRUVANANTHAPURAM.
2 THE KERALA WATER AUTHORITY
REPRESENTED BY ITS MANAGING DIRECTOR, JALA BHAVAN,
THIRUVANANTHAPURAM-695033.
3 THE MANAGING DIRECTOR, THE KERALA WATER AUTHORITY,
JALA BHAVAN, THIRUVANANTHAPURAM-695033.
4 THE CHIEF ENGINEER,
KERALA WATER AUTHORITY, CENTRAL REGION, HOSPITAL ROAD,
KOCHI-682011.
5 THE SUPERINTENDING ENGINEER
KERALA WATER AUTHORITY, P.H.CIRCLE, MUVATTUPUZHA.
6 THE EXECUTIVE ENGINEER,KERALA WATER AUTHORITY, PROJECT
DIVISION, KATTAPPANA, VELLAYANIKUZHI P.O., IDUKKI.
W.P.(C) 3408/2011 2
7 THE ASSISTANT EXECUTIVE ENGINEER
KERALA WATER AUTHORITY, PROJECT DIVISION, KATTAPPANA,
IDUKKI DISTRICT.
SR.GOVERNMENT PLEADER SRI.JUSTIN
SRI.GEORGE MATHEW, SC, KERALA WATER AUTHORITY
SRI.P.BENJAMIN PAUL, SC, KERALA WATER AUTHORITY
SRI.GEORGE MATHEW, SC, KERALA WATER AUTHORITY
THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON
12.08.2021, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
JUDGMENT
The petitioner, a contractor, was awarded the work
'CARWSS to Elappra and adjoining Villages - Supply, Erection,
Testing and Commissioning of Two Nos.315 KVA, 11
KV/1415/V Transformers and connected works at Raw Water
Pump House, Heliburia' by the Kerala Water Authority (KWA).
The period of completion of work was nine months from
9.3.2010. On being awarded the work, the petitioner was
asked to execute an agreement for the work. Since the
petitioner came to know that no land was acquired by the
respondents for execution of the work, the petitioner vide
Ext.P2 requested the fifth respondent, the Superintending
Engineer, KWA to relieve him from the work and to refund the
earnest money deposit of Rs.50,000/-. Later, at the request of
the fifth respondent, the petitioner remitted Rs.1,00,000/-
towards security deposit and executed agreement on
22.11.2010. According to the petitioner, since the land was
not available at the original site for execution of the work,
and utilities including electric lines were not removed from
the space made available, he could not put the available land
to use for execution of the work. The petitioner again
approached the fifth respondent requesting to relieve him
from the work and to release the security deposit. However,
the fifth respondent directed the petitioner to proceed with
the work. The petitioner was told that if the work is not
started on or before 10.01.2011, the same will be terminated
and the security deposit will be forfeited. Later, by Ext.P16,
the fifth respondent terminated the work and ordered to
forfeit the security deposit and to re-arrange the work at the
risk and cost of the petitioner. It was also ordered to take
action to blacklist the petitioner. Ext.P16 is impugned in the
writ petition. The petitioner has also prayed for refund of
security deposit with interest.
2. The first respondent State and respondents 2 to
7 have filed separate counter affidavits in the writ petition.
They have denied the contention of the petitioner that the
work could not be executed due to non-availability of land.
The respondents have stated that the possession of land was
not required for procuring the materials and even after
obtaining the land, the petitioner did not take any steps to
execute the work. Though sufficient space was available to
the petitioner to construct the 6 pole structure, he did not
take any steps to carry out the work. Allegation of
insufficiency of space is only a ruse to avoid execution of the
work. Since the petitioner did not carry out the work, the
KWA was constrained to issue Ext.P16 order terminating the
work and forfeiting the security deposit.
3. A reply affidavit is filed by the petitioner to the
counter affidavit filed by the first respondent rebutting the
averments therein and stating that he was ready to execute
the work, but it was only due to the lethargic attitude of the
respondents that the work could not be executed.
4. Heard the learned counsel for the petitioner, the
learned standing counsel for the Kerala Water Authority and
the learned Government Pleader.
5. According to the petitioner, the work awarded by the
KWA could not be carried out since there was no sufficient
space to construct a 6 pole structure and its fencing. In the
land available, there were obstructions and the KWA did not
take any steps to remove the utilities. Therefore, due to the
non co-operation on the part of the officials of the KWA, the
petitioner could not carry out the work. The non-availability
of land and the lethargic attitude of the respondents
contributed to the delay in carrying out the work. The
petitioner, therefore, submits that, Ext.P16 order terminating
the contract and forfeiting the security deposit and the steps
to blacklist the firm, is illegal and arbitrary.
6. Per contra, the respondents would submit that
adequate opportunities have been given to the petitioner to
start the work and the allegation of inadequacy of land or the
obstructions at the site stated by the petitioner is baseless
and the petitioner did not take any earnest effort to start the
work and therefore the contract was terminated. The
standing counsel for the KWA submits that the work was re-
arranged and the security deposit as well the EMD was
forfeited towards the risk and cost.
7. The fact remains that the work awarded to the
petitioner was not completed within the stipulated period.
The work was re-arranged on termination. The security
deposit as well the earnest money deposited by the petitioner
was forfeited towards the risk and cost. The petitioner as well
as the respondents accuse each other for the delay in
commencement of the work. When the petitioner contends
that the site was not available for execution of the work, the
respondents would contend that inadequacy of land or
obstructions at the site are only a ruse put by the petitioner
to avoid execution of the work and the petitioner did not even
take steps for procuring materials and therefore, the
respondents cannot be attributed with lethargy and it is the
attitude of the petitioner in not commencing the work and to
avoid execution of work that led to the termination of the
work and the forfeiture of deposit.
Going through the rival contentions, this Court, in
exercise of jurisdiction under Article 226 of the Constitution,
cannot decide on the allegations and counter allegations of
latches and breaches arising from and relating to the
contract. The question as to who has contributed for the
factors leading to the termination of work has to be
adjudicated in a proper forum after taking evidence. Since
disputed questions of facts with regard to the breach arise for
determination, this Court is not inclined to entertain the
challenge against Ext.P16 order. Therefore, without prejudice
to the right of the petitioner to approach civil court, this writ
petition is dismissed. There will be no order as to costs.
Sd/-
MURALI PURUSHOTHAMAN JUDGE
APPENDIX
PETITIONER'S EXHIBITS:
P1:TRUE COPY OF THE LETTER DATED 9.3.2010 ISSUED BY THE 5TH
RESPONDENT.
P2:TRUE COPY OF THE LETTER DATED 7.4.2010 SENT BY THE
PETITIONER TO THE 5TH RESPONDENT.
P3:TRUE COPY OF THE LETTER DATED 14.10.2010 OF THE 5TH
RESPONDENT TO THE PETITIONER.
P4:TRUE COPY OF THE LETTER DATED 23.10.2010 SENT BY THE
PETITIONER TO THE 5TH RESPONDENT.
P5:TRUE COPY OF THE LETTER DATED 4.11.2010 SENT BY THE
PETITIONER TO THE 5TH RESPONDENT.
P6:TRUE COPY OF THE LETTER DATED 11.11.2010 FROM THE 5TH
RESPONDENT TO THE PETITIONER.
P7:TRUE COPY OF THE LETTER DATED 2.12.2010 OF THE 6TH
RESPONDENT TO THE PETITIONER.
P8:TRUE COPY OF THE ACKNOWLEDGMENT FORM SENT BY THE 7TH
RESPONDENT.
P9:TRUE COPY OF THE LETTER DATED 10.12.2010 SENT BY THE
PETITIONER TO THE 5TH RESPONDENT.
P9:TRUE COPY OF THE LETTER DATED 10.12.2010 SENT BY THE
PETITIONER TO THE 5TH RESPONDENT.
P10:TRUE COPY OF THE LETTER DATED 15.12.2010 OF THE 5TH
RESPONDENT TO THE PETITIONER.
P11:TRUE COPY OF THE REPRESENTATION DATED 22.12.2010 SUBMITTED
BY THE PETITIONER BEFORE THE 5TH RESPONDENT.
P12:TRUE COPY OF THE LETTER DATED 31.12.2010 OF THE 5TH
RESPONDENT.
P13:TRUE COPY OF THE LETTER DATED 31.12.2010 OF THE 6TH
RESPONDENT.
P14:TRUE COPY OF THE LETTER DATED 4.1.2011 WITH SKETCH SENT BY
THE PETITIONER TO THE 5TH RESPONDENT.
P15:TRUE COPY OF THE LETTER DATED 5.1.2011 OF THE 5TH
RESPONDENT.
P16:TRUE COPY OF THE ORDER DATED 11.1.2011 OF THE 5TH
RESPONDENT.
P17:TRUE COPY OF THE JUDGMENT DATED 16.7.2008 IN W.P.(C)
NO.17115/2008 OF THIS HON'BLE COURT.
RESPONDENTS' EXHIBITS:
R2(A):TRUE COPY OF LETTER DATED 13.10.2010 ISSUED BY
HAILEYBURIA ESTATE.
spc/
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!