Citation : 2021 Latest Caselaw 12260 Ker
Judgement Date : 26 April, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE N.NAGARESH
MONDAY, THE 26TH DAY OF APRIL 2021 / 6TH VAISAKHA, 1943
WP(C).No.2200 OF 2021(Y)
PETITIONER:
M/S.P AND C PROJECTS PVT. LTD.,
P AND C TOWERS, 2ND FLOOR 140,
PERUNDURAI ROAD, ERODE-638011,
REPRESENTED BY ITS GENERAL MANAGER AND
AUTHORIZED SIGNATORY
T.VISWANATHAN.
BY ADVS.
SRI.K.P.DANDAPANI (SR.)
SRI.MILLU DANDAPANI
SRI.RAMEEZ NOOYH
SMT.MEERA RAMESH
SMT.BHAIRAVI S.N
SMT.FATHIMA K.
RESPONDENTS:
1 STATE OF KERALA,
REPRESENTED BY THE PRINCIPAL SECRETARY,
DEPARTMENT OF HEALTH AND FAMILY WELFARE,
216, 3RD FLOOR, NORTH SANDWICH BLOCK,
GOVERNMENT SECRETARIAT,
THIRUVANANTHAPURAM-695001.
2 KERALA STATE INFRASTRUCTURE INVESTMENT FUND
BOARD(KIIFB),
2ND FLOOR, FELICITY SQUARE, MG ROAD,
STATUE, THIRUVANANTHAPURAM-695001,
REPRESENTED BY ITS CHIEF EXECUTIVE OFFICER,
SHRI.K.M.ABRAHAM.
3 M/S.INKEL LIMITED,
DOOR NO.7/473 ZA-5 AND 6, AJIYAL COMPLEX,
POST OFFICE ROAD,
KAKKANAD, COCHIN-682030.
REPRESENTED BY ITS MANAGING DIRECTOR,
SHRI.A.MOHAN LAL.
WP(C) No.2200/2021
:2 :
R1 BY SRI.P.NARAYANAN, SR. GOVERNMENT PLEADER
R2 BY ADV. SRI.V.G.ARUN (K/795/2004)
R3 BY ADV. SRI.P.U.SHAILAJAN
THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD
ON 26-04-2021, THE COURT ON THE SAME DAY DELIVERED THE
FOLLOWING:
WP(C) No.2200/2021
:3 :
JUDGMENT
~~~~~~~~~
Dated this the 26th day of April, 2021
The petitioner, a registered Private Limited Company
which has entered into Ext.P3 Bilateral Agreement and Ext.P6
Supplemental Agreement with the 3 rd respondent, is aggrieved
by the termination of those agreements by the 3 rd respondent.
2. The petitioner states that the petitioner-Company
entered into Ext.P3 agreement with the 3 rd respondent for
construction of the flagship project of "Cochin Cancer
Research Centre, Ernakulam". The project is funded by the
2nd respondent-Kerala State Infrastructural Investment Fund
Board (KIIFB). The 3rd respondent is a Special Purpose
Vehicle (SPV) for the Cochin Cancer Center Project, acting on
behalf of the 1st respondent-State of Kerala.
3. The petitioner was the successful bidder. The work
was awarded for ₹87,14,32,492/- on 13.06.2018. Ext.P3
agreement with the SPV was signed on 06.08.2018. The WP(C) No.2200/2021
work was to be completed within 730 days. The petitioner
started the work on 25.07.2018 and had to complete the work
by 23.07.2020. The unprecedented floods in the years 2018
and 2019 and the Covid-19 pandemic of 2020 caused
hindrance. These coupled with non-payment of pending bills,
labour problems and delay in approval of drawings, made it
impossible to complete the work in time.
4. The petitioner has been communicating to the
respondents regarding delays occurring at various stages of
the work due to unforeseen events as well as for reasons
attributable to the 3rd respondent. The petitioner requested for
extension of time to complete the work. Thereupon, Ext.P6
Supplemental Agreement was executed on 24.09.2020
extending the completion date upto 28.02.2021, though the
petitioner had opposed the time frame.
5. In spite of extension of time, the 3rd respondent did
not release pending bills and showed lethargy in approval of
designs and drawings. The continuing threat of Covid-19
pandemic added to the hardships. In spite of all these, the WP(C) No.2200/2021
petitioner proceeded with the work. However, on 26.12.2020,
the 3rd respondent issued Ext.P8 show-cause notice alleging
that the progress of work is slow. The petitioner submitted
Ext.P9 reply. The petitioner also issued Ext.P10 letter dated
06.01.2021 to the 3rd respondent raising a dispute and
requesting to constitute a Dispute Redressal Committee
invoking Clause No.25 of Ext.P4 General Conditions of
Contract. Without considering the representation of the
petitioner, the 3rd respondent issued Ext.P13 on 18.01.2021
terminating Exts.P3 and P6 Agreements. The petitioner
challenges Ext.P13 order of termination.
6. The 3rd respondent contested the writ petition. The
3rd respondent stated that the delay caused is not due to
non-payment of part bills, labour disputes or delay in providing
drawings, etc. The petitioner has been delaying the work from
the very beginning. The agreement provided 10 milestones of
work. It was a condition that if any milestone is not achieved
on the stipulated day, bill amounts will be withheld and paid
only after reaching and completing the subsequent milestone WP(C) No.2200/2021
within the respective time limit.
7. As the petitioner failed to complete the work as
agreed in Ext.P3, Ext.P6 Supplemental Agreement was
signed extending the period up to 28.02.2021, taking into
account Covid-19 pandemic. The petitioner cannot rely on
floods for failure to complete work, after signing Ext.P6
Supplemental Agreement. The petitioner was paid ₹4.36
Crores as mobilisation advance. The petitioner did not renew
bank guarantees executed to secure the mobilisation
advance, after 30.11.2020. The petitioner was given secured
advance of ₹2,09,42,271/-. The delay or withholding of
payments is due to non-completion of milestones. An amount
of ₹6,47,049/- was paid to the petitioner towards RAB 06 after
adjusting the amount to be recovered from the petitioner.
RAB 07 is under process.
8. Due to poor progress of work, Ext.P8 show-cause
notice was issued to the petitioner. As per Clause III of the
General Conditions of Contract, the contract can be
terminated if the contractor fails to complete the work or a part WP(C) No.2200/2021
of the work within the respective dates of completion or before
the stipulated or extended dates. The petitioner completed
only 35% of their work. The progress of work was poor. The
quality of the work was also found wanting. Therefore, after
considering the explanation given by the petitioner, the
contract was terminated as per Ext.P13. Ext.P13 cannot be
set aside on all or any of the grounds urged by the petitioner,
contended the 3rd respondent.
9. The 2nd respondent-KIIFB also contested the writ
petition. The 2nd respondent pointed out that the Technical
Inspection Wing of the 2nd respondent conducted a site
inspection and found serious lapses on the part of the
petitioner in the progress of the work as well as in the design
adopted by the petitioner. A project oriented meeting was
convened and in the meeting, the progress of construction
work was reviewed. Specific instructions were given to
explore the possibility of termination of contract due to
continuous non-performance and lethargic attitude of the
petitioner in executing the work.
WP(C) No.2200/2021
10. On 25.11.2019, Porsche slab of the construction
collapsed during concreting. The collapse caused major
structural damage to the existing structure. Workmen were
injured and had to be hospitalised. Preliminary investigation
conducted by the Chief Executive Officer of the 2 nd
respondent noticed that there were serious lapses on the part
of the 3rd respondent and the petitioner. The quality of the
work of the petitioner was found very low. The site was
maintained by the petitioner in a careless manner.
11. The 2nd respondent stated that the project is an
important one for the State of Kerala and if commissioned in
time, it will be a solace to large number of cancer patients in
the State. The respondents are in the process of entrusting
the work to another contractor. If the termination order is
cancelled permitting the petitioner to carry out further work,
the project will not be completed in the near future, contended
the 2nd respondent.
12. The learned counsel for the petitioner argued that
Clause 25 of Ext.P4 Conditions of Contract provides for a WP(C) No.2200/2021
multilevel dispute resolution mechanism. In the event of a
dispute, the same has to be raised by the aggrieved party
along with a list of disputes and claims. Though the petitioner
raised a dispute as per Ext.P10, the respondents did not refer
the same to the Disputes Redressal Committee. Issuance of
Ext.P13 termination order when a dispute is raised, is highly
arbitrary and offends Article 14 of the Constitution of India.
13. The learned counsel for the petitioner further
argued that the petitioner had preferred Exts.P11 and P12
representations before the 1st and 2nd respondents. The 1st
respondent being the owner of the project and the 2 nd
respondent being its funding agency, are duty-bound to
consider the petitioner's representations. However, no action
was taken on the representations. The learned counsel for
the petitioner further argued that the petitioner has taken all
efforts to complete the work within the time frame. Delay was
caused due to floods, Covid-19 pandemic, etc. The
respondents have ignored those facts. Respondents 2 and 3
are acting arbitrarily.
WP(C) No.2200/2021
14. The learned counsel for the petitioner pointed out
that in issuing Ext.P8 show-cause notice under Clause III of
the Agreement, the 3rd respondent had relied on twelve
documents. However, in Ext.P13 termination order, the 3 rd
respondent took into account an inspection report of the 2 nd
respondent which was not mentioned in Ext.P8. A copy of the
said inspection report was not made available to the
petitioner. The learned counsel for the petitioner submitted
that in Sahi Ram v. Avtar Singh and others [(1999) 4 SCC
511], the Ho'ble Apex Court has held that once the documents
relied on by the Government were not put to the party seeking
his explanation, the issue is to be remitted back to the
Government for reconsideration.
15. Relying on the judgment of the Apex Court in
Gorkha Security Services v. Government (NCT of Delhi)
and others [(2014) 9 SCC 105], the Apex Court has held that
the fundamental purpose behind the serving of a show-cause
notice is to make the noticee understand the precise case
against him which he has to meet and a show-cause notice WP(C) No.2200/2021
should contain the material grounds which necessitated an
action. In the case of the petitioner, the show-cause notice is
defective as the inspection report of the 2 nd respondent was
not referred to in the said show-cause notice. Therefore,
termination based on the said show-cause notice is
unsustainable as the notice is defective, contended the
learned counsel for the petitioner.
16. The learned counsel for the petitioner further relied
on the judgments of the Apex Court in Union of India and
others v. Tantia Construction Private Limited [(2011)5
SCC 697], Joshi Technologies International Inc. v. Union
of India and others [(2015) 7 SCC 728] and Unitech Limited
and others v. Telangana State Industrial Infrastructure
Corporation (TSIIC) and others [2021 SCC OnLine SC 99]
to urge that the writ petition is maintainable since
overwhelming materials available on record would warrant
setting aside of Ext.P13 order.
17. The learned counsel for the 2nd respondent, on the
other hand, relied on the judgment of the Apex Court in State WP(C) No.2200/2021
of Kerala and others v. M.K. Jose [2015 (9) SCC 433] to
contend that writ jurisdiction cannot be extended to cause a
roving enquiry in a dispute falling within the realm of contract.
The learned counsel also relied on the judgment of the Apex
Court in State of U.P. v. Sudhir Kumar Singh and others
[AIR 2020 SC 5215] to argue that a breach of procedure
cannot give rise to a remedy in the courts, unless behind it
there is something of substance which has been lost by the
failure. The Court should not act in vain, contended the
learned counsel for the 2nd respondent.
18. Heard learned counsel for the petitioner, learned
Government Pleader for the 1 st respondent, learned Standing
Counsel for the 2nd respondent-KIIFB and learned Standing
Counsel for the 3rd respondent-SPV.
19. The Hon'ble Apex Court has laid down the scope of
interference in contractual matters, under writ jurisdiction. In
Rishi Kiran Logistics Private Limited v. Board of Trustees
of Kandla Port Trust and others [(2015) 13 SCC 233],
distinguishing between a remedy sought under the Contract WP(C) No.2200/2021
Act, by means of damages for specific performance under the
specified Act and invoking writ jurisdiction, the Apex Court
held that ordinarily, the remedy available for a party
complaining of breach of contract lies for seeking damages.
He would be entitled to the relief of specific performance, if
the contract was capable of being specifically enforced in law.
The remedies for a breach of contract being purely in the
realm of contract are dealt with by civil courts. The public law
remedy, by way of a writ petition under Article 226 of the
Constitution, is not available to seek damages for breach of
contract or specific performance of contract. However, where
the contractual dispute has a public law element, the power of
judicial review under Article 226 may be invoked.
20. In Noble Resources Ltd. v. State of Orissa and
another [(2006) 10 SCC 236], while answering whether a writ
petition was maintainable in contractual matters and if so,
what is the scope of jurisdiction of the Court in such matters,
the Apex Court held that "It is trite that if an action on the part
of the State is violative of the equality clause contained in WP(C) No.2200/2021
Article 14 of the Constitution of India, a writ petition would be
maintainable even in the contractual field. A distinction
indisputably must be made between a matter which is at the
threshold of a contract and a breach of contract; whereas in
the former the court's scrutiny would be more intrusive, in the
latter the court may not ordinarily exercise its discretionary
jurisdiction of judicial review, unless it is found to be violative
of Article 14 of the Constitution."
21. In the case on hand, the petitioner entered into
Ext.P3 Agreement with the 3rd respondent and commenced
the work on 25.07.2018. Admittedly, as per the terms of the
contract, the work had to be completed within 730 days from
the date of handing over of the project site. In view of the said
provision, the petitioner had to complete the work by
23.07.2020. True, Kerala State witnessed flood situation in
the years 2018 and 2019. The respondents would contend
that the floods have not affected the project area and the
petitioner cannot take umbrage under the floods for failure to
perform his part of the contract. The learned counsel for the WP(C) No.2200/2021
petitioner, on the other hand, would argue that the
unprecedented floods which inundated most part of the State,
created substantial difficulties in mobilising men and material
for execution of the work.
22. But, it may be noted that the respondents
considered the situation and permitted the petitioner to enter
into Ext.P6 Supplemental Agreement on 24.09.2020. By
Ext.P6, the period of completion of work under the principle
agreement was enhanced from 730 days to 949 days. Under
the Supplemental Agreement, the petitioner was bound to
complete the project work by 28.02.2021. The petitioner
could not complete the work by the said date. Therefore, the
petitioner cannot be heard to contend that it was the floods
occurred in the years 2018 and 2019 that prevented the
petitioner from completing the work as per agreement.
23. The petitioner would contend that part bills raised
by the petitioner in respect of completed works were not
honoured by the 3rd respondent, which caused difficulties to
the petitioner in executing the work with required expediency. WP(C) No.2200/2021
The learned Standing Counsel for the 3 rd respondent would
point out that there were specific conditions in the agreement
which provided that if any of the stipulated milestone was not
achieved by the prescribed date, the amounts due for that
work will be withheld till the petitioner completes the next
milestone within the date prescribed for the same. When the
petitioner has agreed to such a term of contract, the petitioner
will not be justified in blaming the delay in execution of the
work on non-payment of part-bills raised.
24. The further case of the petitioner is that principles
of natural justice are violated in terminating the contract. The
argument is that the Ext.P8 show-cause notice though
referred to as many as 12 documents in support of
termination, the 3rd respondent relied on, in Ext.P13
termination order, an Inspection Report of the 2 nd respondent
about which the petitioner was not put to notice in Ext.P8
show cause notice, nor was the petitioner was provided with a
copy of that report.
WP(C) No.2200/2021
25. The 3rd respondent has terminated the contract on
two counts, namely slow progress of the work and quality of
work. The fact of extension of time limit for completion of
work and failure to complete the work even in the extended
period is admitted by the petitioner, though the petitioner
would contend that the delay is due to reasons attributable to
the respondents.
26. The inferior quality of work executed by the
petitioner is reflected in Ext.R3(d) letter of undertaking signed
by the petitioner. Therefore, the failure of the 3 rd respondent
to note the inspection report of the 2 nd respondent in Ext.P8
show cause notice by itself cannot be said to have caused
substantial prejudice to the petitioner. The degree of
compliance of the principles of natural justice applicable to
administrative actions of State cannot be made applicable
with the same force, to the 3 rd respondent in a contractual
matter.
27. The further argument of the petitioner is that there
were labour disputes and unwarranted delay on the part of the WP(C) No.2200/2021
3rd respondent in providing drawings which also has
contributed to delay in execution of work within the stipulated
time. These are disputed questions of fact which this Court
cannot adjudicate in writ jurisdiction.
In the result, the writ petition is found to be lacking in
merits and is hence dismissed.
Sd/-
N. NAGARESH, JUDGE
aks/16.04.2021 WP(C) No.2200/2021
APPENDIX PETITIONER'S EXHIBITS:
EXHIBIT P1 A TRUE COPY OF THE NOTICE INVITING TENDER DOCUMENT NO.NIT/INKEL/KIIFB/ 2018-19/010 DATED 05/04/2018 FOR CONSTRUCTION OF COCHIN CANCER RESEARCH CENTRE,ERNAKULAM
EXHIBIT P2 A TRUE COPY OF THE LETTER OF ACCEPTANCE NO.INKEL/CE/LOA/HEALTH/ 2018/037 DATED 13/06/2018 ISSUED BY THE 2ND RESPONDENT TO THE PETTITIONER
EXHIBIT P3 A TRUE COPY OF THE AGREEMENT NO.O4/KIIFB/INKEL/2018-19 DATED 06/08/2018 ENTERED INTO BETWEEN THE 3RD RESPONDENT AND THE PETITIONER
EXHIBIT P4 A TRUE COPY OF THE GENERAL CONDITIONS OF CONTRACT BETWEEEN THE PARTIES WITH NIT NO.NIT/INKEL/KIIFB/2018-19/010
EXHIBIT P5 A TRUE COPY OF LETTER NO.P&C/KLR/CRC-
SITE/INKEL/2020-21/197 DATED 15.09.2020 ALONG WITH ANNEXURES,ISSUED BY THE PETITIONER TO THE 3RD RESPONDENT
EXHIBIT P6 A TRUE COPY OF THE SUPPLEMENTARY AGREEMENT NO.SA-35/KIIFB/INKEL/2020-21 DATED 24.09.2020 BETWEEN THE PARTIES
EXHIBIT P7 A TRUE COPY OF THE RELEVANT PAGE OF THE TIMES OF INDIA NEWSPAPER PUBLISHED ON 19.12.2020 REPORTING THE DISSATISFACTION EXPRESSED BY THE OFFICIALS OF THE 1ST AND 2ND RESPONDENTS REGARDING THE CONDUCT AND WORKING OF THE 3RD RESPONDENT WP(C) No.2200/2021
EXHIBIT P8 A TRUE COPY OF THE SHOW CAUSED NOTICE NO.INKEL/MD/CCRC/2020-21/1225 DATED 26/12/2020 ISSUED BY THE 3RD RESPONDENT TO THE PETITIONER
EXHIBIT P9 A TRUE COPY OF THE REPLY NO.P&C/KLR/CCRC-SITE/2020-21/235 DTD.04.01.2021 ISSUED BY THE PETITIONER TO EXT.P8 SHOW CAUSE NOTICE
EXHIBIT P10 A TRUE COPY OF THE NO.P&C/CCRC-
SITE/2020-21/236 DATED 06/01/2021 ISSUED BY PETITIONER SEEKING REFERENCE OF DISPUTE TO DISPUTE REDRESSAL COMMITTEE
EXHIBIT P11 A TRUE COPY OF THE LETTER NO.P&C/KLR/CCRC/CRC/KIIFB/2020-21/239 DATED 08/01/2021 ISSUED BY THE PETITIONER TO THE 1ST RESPONDENT
EXHIBIT P12 A TRUE COPY OF THE LETTER NO.P&C/KLR/CCRC/CRC/KIIFB/2020-21/237 DATED 08/01/2021 ISSUED BY THE PETITIONER TO THE 2ND RESPONDENT
EXHIBIT P13 A TRUE COPY OF THE TERMINATION LETTER NO.INKEL/CCRC/2021/5554 DATED 18/01/2021 ISSUED BY THE 3RD RESPONDENT TO THE PETITIONER
EXHIBIT P14 TRUE PHOTOGRAPHS OF THE CONSTRUCTION SITE AS ON TODAY.
EXHIBIT P15 TRUE COPY OF NOTICE NO
NIT/INKEI/KIIFB/W0W0-21/118 DTD
22.2.2021 ISUEE BY THE 3RD RESPONDENT
EXHIBIT P16 THE TRUE COPY OF THE APPLICATION FOR EXTENSION OF TIME DATED NIL ALONG WITH RELEVANT PAGES OF THE HINDRANCE REGISTER.
WP(C) No.2200/2021
EXHIBIT P17 TRUE COPY OF THE LETTER NO P & C/KLR/CRC-SITE/INKEL/2020-21/230 DATED 18.12.2020 ISSUED BY THE PETITIONER TO TH EMANAGING DIRECTOR OF THE 3RD RESPONDENT.
EXHIBIT P18 THE TRUE COPY OF THE LETTER NO. P& C/KLR/CRC-SITE/INKEL/2020-21/240 DATED 15.01.2021 ISSUED BY THE PETITIONER TO THE 3R DRESPONDENT.
EXHIBIT P19 TRUE COPY OF THE LETTER NO. P & C /KLR/CRC-SITE/INKEL/2020-21/220 DATED 25.11.2020 ISSUED BY THE PETITIONER TO THE 3RD RESPONDENT.
EXHIBIT P20 TRUE COPIES OF OME OF THE REQUEST LETTERS MADE BY THE 3RD RESPONDNET IN DIFFERENT DATED 04.02.2021, 19.01.2021,05.12.2020, 17.10.2020 AND 15.10.2020 TO VARIOUS EXTERNAL LAB AGENCIES FOR CONDUCTING THE REQUIRED TESTS.
EXHIBIT P21 TRUE COPIES OF SOME OF THE LETTERS OF
LETTERS OF ACCEPATANCE DATED
31.01.2019,12.02.2018 AND 27.12.2017 ISSUED IN FAVOUR OF THE PETITIONER AS PART OF UNDERTAKING OF THE CONSTRUCTION WORK IN THE STATE OF KERALA.
EXHIBIT P22 TRUE COPIES OF SOME OF THE CERTIFICATES OF THE PETITIONERS WORK COMPLETED AHEAD OF THE TIMESHCEDULE ISSUED BY THE PWD, TAMIL NADU DATED 04.11.2015, 16.07.2014 AND 04.08.2015
EXHIBIT P23 TRUE COPY OF THE LETTER NO.
INKEL/CCRC/SITE/20/43 DATED 07.11.2020 SNET BY THE 3RD RESPONDENT TO THE PETITIONER ALONG WITH THE FILED RECTIFICATION REPORT.
WP(C) No.2200/2021
RESPONDENTS' EXHIBITS:
EXHIBIT R2(a) A TRUE COPY OF THE ORDER BEARING
NO.G.O.(Rt)No.6/2017/H&FWD DATED
04.01.2017
EXHIBIT R2(b) A TRUE COPY OF THE PROCEEDINGS BEARING
NO.APR-37139/2017/KIIFB DATED
08.03.2018
EXHIBIT R2(c) A TRUE COPY OF TECHNICAL SUPPORT ORDER
BEARING NO.02/INK/CCRC/APRIL/2018
DATED 04.04.2018
EXHIBIT R2(d) A TRUE COPY OF THE GUIDELINES VIDE G.O
(M.S)NO.69/2018/FIN DATED 24.02.2018 EXHIBIT R2(e) A TRUE COPY OF THE LETTER OF ACCEPTANCE ISSUED TO THE PETITIONER BY THE 3RD RESPONDENT BEARING NO.INKEL/CE/LOA/HEALTH/2018/037 DATED 13.06.2018 EXHIBIT R2(f) A TRUE COPY OF THE AGREEMENT FOR WORK DATED 06.08.2018 EXECUTED BY THE 3RD RESPONDENT AS AN SPV IN FAVOUR THE PETITIONER.
EXHIBIT R2(g) A TRUE COPY OF THE OBSERVATIONS A MEMO WAS ISSUED BY THE 2ND RESPONDENT POINTING OUT THE LAPSES IN THE WORK VIDE LETTER NO.HFW00L-03-TIW-INSP-01 DATED 23.02.2019 EXHIBIT R2(h) A TRUE COPY OF THE LETTER BEARING NO.IA2/1696/2018/KIIFB DATED 07/11/2019 ISSUED BY THE 2ND RESPONDENT TO THE 1ST AND 3RD RESPONDENT.
EXHIBIT R2(i) A TRUE COPY OF THE PHOTOGRAPHS OF THE COLLAPSED PORTION.
EXHIBIT R2(j) A TRUE COPY OF THE REPORT SUBMITTED BY
THE TECHNICAL TEAM OF THE 2ND
RESPONDENT DATED 27.11.2019.
EXHIBIT R2(k) A TRUE COPY OF THE SUSPENSION NOTICE
DATED 27.11.2019 ISSUED BY THE 2ND
RESPONDENT.
EXHIBIT R2(l) A TRUE COPY OF THE LETTER BEARING
NO.HFWOOL-03-TIW-INSP-01 DATED
19.12.2019
WP(C) No.2200/2021
EXHIBIT R2(m) A TRUE COPY OF THE REPRESENTATION
DATED 27.07.2020 SEND BY THE DIRECTOR CCRC TO THE 2ND RESPONDENT EXHIBIT R2(n) A TRUE COPY OF THE INSPECTION REPORT SUBMITTED BY THE TECHNICAL TEAM OF THE 2ND RESPONDENT PURUANT TO THE INSPECTION DONE ON 06.11.2020.
EXHIBIT R2(o) A TRUE COPY OF THE SHOW CAUSE NOTICE
DATED 26.12.2020 BEARING
NO.INKEL/MD/CCRC/2020-21/1225
EXHIBIT R3(a): TRUE COPY OF THE 'F' SCHEDULE IN THE
ESTIMATED COST OF WORKS OF THE
CONSTRUCTION OF COCHIN CANCER RESEARCH CENTRE.
EXHIBIT R3(b): TRUE COPY OF THE RA BILL 6 DATED 28/10/2020 AND THE DETAILS REGARDING THE RECOVERY OF MOBILIZATION ADVANCES AND THE RECEIPT FOR MEMORANDUM OF PAYMENT SUBMITTED BY THE PETITIONER DATED 28/10/2020.
EXHIBIT R3(c): TRUE COPY OF THE PAYMENT DETAILS TO THE PETITIONER UPTO DATE FOR THE CONSTRUCTION OF COCHIN CANCER RESEARCH CENTRE.
EXHIBIT R3(d): TRUE COPY OF THE LETTER OF UNDERTAKING
DATED 10/03/2020 GIVEN BY THE
PETITIONER.
EXHIBIT R3(e): TRUE COPY OF THE REPORT DATED
25/11/2019 SUBMITTED BY GREEN LAB
INDUSTRIAL & ENVIRONMENTAL SOLUTIONS (PVT.). LTD., THRIKKAKARA.
EXHIBIT R3(f): TRUE COPY OF THE TEST REPORT OF THE
SEMI DESTRUCTIVE CORE TEST ON RC
COLUMNS CONDUCTED BY BUREAU VERITAS,
AN NABL ACCREDITED LAB.
WP(C) No.2200/2021
EXHIBIT R3(g): TRUE COPY OF THE LETTER DATED
25/06/2020 ISSUED BY THE PETITIONER ALONG WITH THE TEST LISTS.
EXHIBIT R3(h): TRUE COPY OF THE LETTER DATED
29/11/2018 ISSUED BY THE 3RD
RESPONDENT TO THE PETITIONER.
EXHIBIT R3(i): TRUE COPY OF THE LETTER DATED
06/12/2018 ISSUED BY THE 3RD
RESPONDENT TO THE PETITIONER.
EXHIBIT R3(j): TRUE COPY OF THE LETTER DATED
06/03/2019 ISSUED BY THE 3RD
RESPONDENT TO THE PETITIONER.
EXHIBIT R3(k): TRUE COPY OF THE LETTER DATED
08/04/2019 ISSUED BY THE 3RD
RESPONDENT TO THE PETITIONER.
EXHIBIT R3(l): TRUE COPY OF THE LETTER DATED
03/05/2019 ISSUED BY THE 3RD
RESPONDENT TO THE PETITIONER.
EXHIBIT R3(m): TRUE COPY OF THE LETTER DATED
20/06/2019 ISSUED BY THE 3RD
RESPONDENT TO THE PETITIONER.
EXHIBIT R3(n): TRUE COPY OF THE LETTER DATED
02/07/2019 ISSUED BY THE 3RD
RESPONDENT TO THE PETITIONER.
EXHIBIT R3(o): TRUE COPY OF THE LETTER DATED
22/07/2019 ISSUED BY THE 3RD
RESPONDENT TO THE PETITIONER.
EXHIBIT R3(p): TRUE COPY OF THE LETTER DATED
05/08/2019 ISSUED BY THE 3RD
RESPONDENT TO THE PETITIONER.
EXHIBIT R3(q): TRUE COPY OF THE LETTER DATED
22/11/2019 ISSUED BY THE 3RD
RESPONDENT TO THE PETITIONER.
WP(C) No.2200/2021
EXHIBIT R3(r): TRUE COPY OF THE LETTER DATED
23/07/2019 ISSUED BY THE 3RD
RESPONDENT TO THE PETITIONER.
EXHIBIT R3(s): TRUE COPY OF THE HINDRANCE REGISTER
KEPT AT THE SITE BY THE M/S. INKEL
LIMITED
EXHIBIT R3(t): TRUE COPY OF THE LETTER DATED
27.11.2020 ISSUED BY THE 3RD
RESPONDENT TO THE PETITIONER
EXHIBIT R3(u): TRUE COPY OF THE LETTER DATED
10.02.2021 ISSUED BY THE 3RD
RESPONDENT TO THE PETITIONER.
EXHIBIT R3(v): TRUE COPY OF THE LIST OF EQUIPMENTS
FOR TESTING OF MATERIALS AND
CONCRETES AT SITE LABORATORY PREPARED THE 3RD RESPONDENT.
EXHIBIT R3(w): TRUE COPY OF THE MEMORANDUM OF PAYMENT
OF RA BILL 02 ISSUED BY THE 3RD
RESPONDENT TO THE PETITIONER
EXHIBIT R3(x): TRUE COPY OF THE RELEVANT PAGE OF THE
SPECIAL CONDITIONS AND ADDITIONAL
CONDITIONS OF CONTRACT WHICH STATES ABOUT THE ESTABLISHEMENT OF A SITE LABORATORY EXECUTED BETWEEN THE PETITIONER AND THE 3RD RESPONDENT EXHIBIT R3(x)(1): TRUE COPY OF THE RELEVANT PAGE OF THE SPECIAL CONDITIONS AND ADDITIONAL CONDITIONS OF CONTRACT WHICH STATES ABOUT THE TESTING EXECUTED BETWEEN THE PETITIONER AND THE 3RD RESPONDENT EXHIBIT R3(Y): TRUE COPY OF THE MINUTES OF ONE OF THE REVIEW MEETING DATED 1.4.2019 HELD BY THE 3RD RESPONDENT EXHIBIT R3(Z): TRUE COPY OF THE LETTER DATED 11.11.2020 ISSUED TO THE PETITIONER BY THE 3RD RESPONDENT.
SR
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!