                 IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                  PRESENT

                 THE HONOURABLE MR. JUSTICE SHAJI P.CHALY

       THURSDAY, THE 08TH DAY OF APRIL 2021 / 18TH CHAITHRA, 1943

                          WP(C).No.6877 OF 2017(H)


PETITIONER/S:

                CHRISTABEL D'CUNHA
                W/O.LATE GERALD D'CHUNHA, AGED 57 YEARS, DOOR NO.1/136,
                FORT VYPIN, COCHIN-682 508.

                BY ADV. SRI.DENIZEN KOMATH

RESPONDENT/S:

       1        CORPORATION OF COCHIN
                P.V.NO.1016, PARK AVENU, KOCHI-680 211, REPRESENTED BY ITS
                SECRETARY.

       2        THE ASSISTANT EXECUTIVE ENGINEER,
                ZONAL OFFICE, CORPORATION OF COCHIN FOR KOCHI-1.

       3        K.J.SIMON
                S/O.K.J.JOHN, DOOR NO.1/43, FORT VYPIN, COCHIN-682 508.

                R1 BY SRI.V.E.ABDUL GAFOOR,SC,COCHIN CORPORATION

                R1-2 BY ADV. SHRI.K.JANARDHANA SHENOY, SC, KOCHI MUNICIPAL
                CORPORATION




           THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON
           08.04.2021, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
 W.P.(C) No. 6877/2017                 :2:



                Dated this the 8th day of April, 2021.

                             JUDGMENT

This writ petition is filed seeking the following reliefs:

1. Call for the entire records pertaining to the facts pleaded in the writ petition (civil)

2. Issue a writ of mandamus, any other order, writ or direction directing the respondents 1 and 2 to issue a completion certificate and door number to the completed construction works based on Ext. P1 regarding the petitioner's residential building immediately.

2. The petitioner seeks a direction to the Corporation and the

Secretary to issue a completion certificate. In my considered opinion,

no such direction can be issued, since a completion certificate after the

construction of the building is to be issued by the Architect to the

petitioner.

3. However, the learned counsel for the petitioner submitted

that the subject matter has become infructuous.

Therefore, after having heard the learned counsel for the

petitioner and the learned Standing Counsel for the Corporation Sri. K.

Janardhana Shenoy, this writ petition is dismissed as infructuous.

SHAJI P. CHALY, JUDGE.

Rv

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter