Citation : 2025 Latest Caselaw 209 Kant
Judgement Date : 14 May, 2025
IN THE HIGH COURT OF KARNATAKA AT DHARWAD
BENCH
DATED THIS THE 14TH DAY OF MAY 2025
PRESENT
THE HON'BLE MR. JUSTICE B. M. SHYAM PRASAD
AND
THE HON'BLE MR. JUSTICE C.M. JOSHI
REGULAR FIRST APPEAL NO. 100189 OF 2018
BETWEEN
1. THE CHIEF ENGINEER
KNNL, IRRIGATION (NORTH)
CLUB ROAD, BELAGAVI-590001.
2. THE EXECUTIVE ENGINEER
OFFICE OF THE EXECUTIVE ENGINEER
KNNL IRRIGATION DEPARTMENT
GLBC DIV NO.3, BILGI
DIST. BAGALKOT
3. THE MANANGING DIRECTOR
KNNL, 4TH FLOOR, COFFEE BOARD
BUIDLING, DR. AMBEDKAR VEEDHI
BENGALURU-560001.
ALL APPELLANTS ARE REP BY
APPELLANT NO.2 WHO IS AUTHRORISED
TO REPRESENT
...APPELLANTS
(BY SRI. M.B.NARAGUND, SENIOR COUNSEL FOR
SRI. A.S.PATIL, ADVOCATE)
2
AND
M/S. RATHOD AND NAIK CO.,
REGD. PARTNERSHIP FIRM
CIVIL CONTRACTORS
VEERABHADRA NAGAR,
PLOT NO.62, 1ST CROSS,
BELGAVI-590016,
REP. BY ITS PARTNER
SRI. KESU POMU RATHOD
AGE 56 YEARS
OCC: CONTRACTOR
R/O BELAGAVI.
...RESPONDENT
(BY SRI. M.S.BAGALI, ADVOCATE FOR
SRI. MRUTYUNJAY TATA BANGI, ADVOCATE)
THIS REGULAR FIRST APPEAL IS FILED UNDER
SECTION 96 OF CPC AGAINST THE JUDGMENT AND
DECREE DATED 12.12.2017 PASSED IN O.S.No.49/2012
ON THE FILE OF THE I ADDITIONAL SENIOR CIVIL
JUDGE AND CHIEF JUDICIAL MAGISTRATE, BELAGAVI,
PARTLY DECREEING THE SUIT FILED FOR RECOVERY
OF MONEY.
THIS APPEAL HAVING BEEN HEARD AND
RESERVED ON 10.01.2025 AND COMING ON FOR
PRONOUNCEMENT OF JUDGMENT THIS DAY, B.M.
SHYAM PRASAD.,J DELIVERED THE FOLLOWING:
CORAM: THE HON'BLE MR. JUSTICE B.M.SHYAM PRASAD
AND
THE HON'BLE MR. JUSTICE C.M. JOSHI
3
CAV JUDGMENT
(PER: THE HON'BLE MR. JUSTICE B.M.SHYAM PRASAD)
This appeal is by M/s Karnataka Neeravari
Nigam Limited and its officers [the defendants and
are referred to as 'M/s KNNL'] in OS No.49 of 2012 on
the file of the I Additional Senior Civil Judge, Belagavi
[for short, 'the civil Court'], and M/s KNNL is
aggrieved by the civil Court's judgment and decree
dated 12.12.2017. The civil Court has decreed the
respondent's suit in OS No.49 of 2012 for recovery of
money holding M/s KNNL and its officers are jointly
and severally liable to pay to the respondent [a
partnership firm] Rs.6,05,02,830/- along with interest
at 6% per annum from date of the suit till the date of
realization. The civil Court has directed M/s KNNL to
pay this amount of Rs.6,05,02,830/- under the
following heads:
Sl. No. Amount awarded Amount
under
1 Excavation of all kinds Rs.5,64,516.75
of soil
2 Excavation of soft rock
(SR] and some rock Rs.18,09,296.18
blasting [SRB]
3 Towards un-coursed Rs.1,52,918.29
rubble masonry.
4 Towards fabrication of
steel enforcement and
for work of CCM-15, Rs.9,49,735.00
40mm D/S with 15%
plum.
5 Removal and hauling of
debris and de-silting/ Rs.4,12,445.25
dewatering
6 Towards storage of Rs.2,41,50,000.00
materials
7 Towards forfeiture of Rs.1,09,248.00
EMD
8 Removal of hard rock Rs.2,82,02,850.00
9 IV R A Bill Rs.9,55,480.47
2. This Court, on 15.11.2018, has
considered M/s KNNL's request for stay of the
operation of the civil court's impugned judgment and
decree with the respondent beginning execution
proceedings in EP No.97/of 2018. This Court has
stayed further execution proceedings subject to M/s
KNNL paying the respondent a sum of
Rs.75,00,000/-. In this appeal, M/s KNNL has
admitted the liability to this extent. It is brought on
record that M/s KNNL, in compliance with this
condition, has indeed paid the respondents
Rs.75,00,000/-.
The undisputed facts and circumstances:
3. M/s KNNL, under a time bound
Central Government Program called the Central
Assistance of Accelerating Irrigation Benefit Program
[CAAIBP], has envisaged project for modernizing
Ghataprabha Left Bank [GLB] Main Canal over a
stretch of 30 Km between the 71st and 105th Kms of
this Main Canal dividing this into six packages of 5
Kms each. M/s KNNL has issued separate tenders
for these six packages, and the respondent has
successfully participated in the tender issued for the
fifth package [V Package] comprising 5 Kms stretch
between the 93rd and 98th Kms of this Main Canal. A
set of certain other contractors are successful in
offering their respective bids for the other five
packages.
3.1 M/s KNNL and the respondent have
signed the contract dated 17.11.2006 [referred to as,
'the Agreement'] with the respondent entrusting the
work of Concrete Lining for the stretch of 5 Kms
between 93rd and 98th Kms and issued Work Orders
dated 28.11.2006. M/s KNNL has handover the site
to the respondent on 01.03.2007. The respondent, in
performance of the terms of the Agreement, had to
complete the Concrete Lining work after the requisite
extraction, and removal of debris within four [4]
months between 01.03.2007 and 30.06.2007 as the
work could only be executed during this period before
the commencement of rains1.
3.2 The respondent, when he could not
complete the Contracted Work before 30.06.2007,
1 This stipulation admittedly is part of Clause 38 of the Agreement.
has requested for extension of time, and M/s KNNL
has granted such extension of time during the years
2008 and 2009 requiring the respondent to complete
the Contracted Work by 30.06.2009. However, with
the Contracted Work not being completed even
during the extended period, M/s KNNL has cancelled
the Agreement and entrusted the balance work to
third-party contractors after issuing fresh tender.
The other five packages are completed without
dispute.
3.3 The Contracted Work requires the
respondent to cut earth on either side of the existing
canal excavating all kinds of soil [AKS], Soft Rock
[SR] and Soft Rock Blasting [SRB] to provide for the
requisite Full Supply level [FSL] with Free Board [FB]
and Berm2 maintaining the requisite Canal Bed
Level/ Width and Slope. The extent of cutting
[excavation] varies along the stretch because of the
terrain, and therefore, the measurements will also
2 BERM means a flat strip of land [a raised bank] bordering a canal [or even a River].
vary. The nature of work with the Full Supply Level
with Free Board and specifications [subject to
variation as aforesaid] are explained by this
schematic representation [diagram].
The respondent - plaintiff's case:
4. M/s KNNL estimated the cost of the
Contracted Work at Rs.4,98,69,860/-, and the
respondent offered 33% more than the aforesaid
amount [in a sum of Rs.6,63,26,914/-]. This amount
was revised to Rs.6,08,24,847/- based on the
Technical Standing Committee's recommendation,
and the respondent accepted to execute the work for
this amount. M/s KNNL estimated the cost of work
in the year 2006 when the canal was in use, and as
such, the work entrusted under the Agreement did
not correspond with the site condition. M/s KNNL, to
prepare the estimates had to inspect the Canal when
it was not in use, and M/s KNNL, in notifying the
work based on improper estimation contrary to the
site condition, has committed a fundamental breach.
The respondent therefore had to mobilize men and
machinery beyond the estimated work to handle the
site's condition.
4.1 The respondent, describing the
aforesaid as the fundamental breach, has alleged that
M/s KNNL has committed breach such as [a]
preparation of the estimate based on cross sections of
the Canal at the interval of 50 meters instead of
interval of 20 meters resulting in the difference in
measurements and increase in excavation, [b] the
existing Ground Level, Canal Bed Level, Side Slope
and such others mentioned in the agreement did not
tally with the site's condition [c] the insistence on the
execution of the Canal Lining Work [Concrete Lining]
despite these errors would result in mismatch of
Canal Bed Levels at the Distribution Outlets, and
therefore improvisations had to be done [d] the
stretch at the 94th KM required Deep Cut but the
estimate did not correspond with the site conditions
like Slope, Top and bottom Widths, [e] the Concrete
Lining using Mechanical Paver Machine required a
minimum of 1.5 meter wide Berm but this was not
shown, [f] executing the excavation work to achieve
the required Full Supply Board and Free Board
required extensive removal of earth contrary to the
estimate, [g] the estimate only provided for excavation
of Soft Rock/Soft Rock Blasting but the site's
condition required extraction of Hard Rock.
4.2 The respondent brought these
defects to the notice of the concerned from M/s KNNL
seeking Technical Clearance for Additional Work as
contemplated under Clause 12 of the Agreement, but
M/s KNNL remained silent to gloss over the defect
and directed the respondent [orally] to execute the
work with no decision on the increase in the
excavation work and the cost. The Engineers with
M/s KNNL coerced the respondent to execute the
work without the technical approval for the increased
quantities.
4.3 The respondent has executed the
work during the years 2007, 2008 and 2009 despite
all the difficulties and in anticipation of the requisite
technical approval for the additional work. The
engineers with M/s KNNL have prevailed with the
Technical Sub-committee to decide on cancelling the
Agreement despite the Sub-committee's observations
about payments, which are detailed in para 13 of the
plaint.
4.4 The respondent also asserts that
because of the above, M/s KNNL is liable to pay
different amounts under the following heads along
interest at 24% p.a.
[i] The delayed interim payments for the work done and delay in release of amounts according to the Running Account submitted with effect from 01.07.2007,
[ii] For excavation of Soft Rock/ Soft Rock Blasting in a sum of Rs.28,26,546/- [at the rate of Rs.125.26 for the quantity measuring 22,565.43 m³],
[iii] For excavation of All Kinds of Soil [AKS] in a sum of Rs.10,05,479/- [at the rate of Rs.62.34 for the quantity of 16,128.95 m³ ],
[iv] For Uncoursed Rubble Masonry in a sum of Rs.2,88,581/- [at the rate of Rs.2279.29 for a quantity of 126.61 m³],
[v] For fabrication of steel reinforcement a sum of Rs.9,49,735/- [at the rate of Rs. 61.34 for a quantity of 15,483.12 KG of Steel],
[vi] For Cement Concrete with M-15 grade, 40mm d/s 15% plum at Rs.1,00,58,718/- [at the rate of Rs.4,382.96 for a quantity of 2,294.96],
[vii] For removing and hauling debris in a sum of Rs. 7,36,968/- [at the rate of Rs.112.57 for the quantity of 6546.75 m³],
[viii] For excavation of Hard Rock in a sum of Rs. 3,13,22,578/- [at the rate of Rs.364.80 for the quantity of 85,862.33 m³],
[ix] For Storing Materials [such as sand] in a sum of Rs.76,50,000/- [at the rate of Rs.1700/- for a quantity of 4500 m³],
[x] For storing jelly at site in a sum of Rs.1,65,00,000/- [at the rate of Rs.2200/- for the quantity of 7500 metric tons],
[xi] For the charges incurred in procuring rubble [at the rate of Rs.200 per cubic metre], and
[xii] For the cost of two Concrete Transit Mixers in a sum of Rs.75,94,627/-.
4.5 The respondent apart from these
amounts has also sought for special damages under
different heads such as reimbursement of the extra
expenditure incurred in employing men and
machinery for commencing the work after the delay
with an appropriate escalation in price of Rs.
2,00,000/- per month for the extended period
starting from 01.07.2007 towards overhead charges,
and other special damages under different heads.
M/s KNNL's defense:
5. M/s KNNL, without denying that the
estimate is prepared based on the cross-sections of
the Canal at intervals of 50 meters and not 20
meters3, has contended that the respondent, which
had to begin work simultaneously on all the
3 According to M/s KNNL, the Estimation is prepared based on the cross sections at 50 meter intervals for existing canals and for construction of new canals the Estimation is prepared based on the cross sections at 20 meter intervals.
stretches, commenced work only on the 94th KM
stretch employing just an excavator. Therefore, the
Assistant Executive Engineer wrote to the respondent
on 27.02.2007 to expedite commencement of work on
all the stretches to ensure that the Contracted Work
is completed by 30.06.2007. M/s KNNL has
specifically denied the allegation that the preliminary
estimation was prepared when the Canal was in use
stating that this exercise was undertaken during the
canal closure period.
5.1 M/s KNNL has averred that the
site's conditions for assessment of the Deep Cuts,
Partial Cutting, Bank-work reaches and Cross-section
at 50 meter intervals were collected during the canal
closure period and submitted to the Chief Engineer
[Irrigation] Belagavi, and that this Chief Engineer has
approved the Estimate [and other details of the
Contracted Work] after a detailed scrutiny. M/s KNNL
also contends that, as typically there will be variation
between the estimation and the site's condition,
Clause 20 is incorporated in the Agreement providing
for adjustments in terms of Clause 13 of the General
Conditions of Contract.
5.2 M/s KNNL asserts that the
respondent during the contract period could only
achieve financial closure of Rs.35,14,000/- as against
Rs. 6,08,24,000/- and that too only along the 94th
KM stretch denying the respondent's case that during
this period its representative had filed details of the
defects in Estimation. However, M/s KNNL accepts
that the Chief Engineer, in August 2007 [after
completion of the contractual period], suggested
modifications4 as the Deep Cut Reaches had to be
altered because the Canal width had to be increased
from 4.11 meters to 8.01 meters, but contending that
this did not render the tender defective as the tender
provided for additional work.
4 The details in these regards are stated in paragraph 16.3 of the Written Statement.
5.3 M/s KNNL, while detailing the work
executed by the respondent along the 94th KM stretch
to justify its case that the respondent had achieved a
financial closure of Rs.35,14,000/-as against the
tender work of Rs.6,08,24,000/-, has contended that
on 09.01.2008 the respondent submitted Schedule
of Program undertaking to complete the work by
30.06.2008, but did not even turn up at the site to
begin the work during the canal closure period in the
year 2008. M/s KNNL asserts that the respondent
had abandoned the work in the year 2008 and
therefore the concerned mooted proposal to begin
criminal proceedings, but no action was taken as the
respondent pleaded bona fides and undertook to
execute the work during the canal closure period in
2009.
5.4 M/s KNNL further contends that the
respondent had not submitted any bill as was
required under the Agreement and therefore its
officers arranged for measurement and prepared the
Bill taking the respondent's counter signature for
payment, and that subsequently in the year 2009,
the respondent showed progress of Rs.69,77,000/-
and submitted Second Running Account and Third
Running Account Bills for a sum of Rs.16,05,000/-.
Thereafter, a decision was taken to cancel the
Agreement without penalty and risk. M/s KNNL
contests the respondent's reliance upon the Sub-
committee's observations asserting that such
observations are internal, and the respondent cannot
draw any support from the same.
5.5 M/s KNNL has denied the liability to
pay the different amounts claimed by the respondent
under the specific heads on different grounds while
also denying the claim for special damages such as
the alleged improper forfeiture of EMD. M/s KNNL
has further denied the liability essentially contending
that the respondent will not be entitled to the
different amounts claimed because it has not
completed the work within the contractual period or
the extended period, and because the quantity of
work is part of the tender either as estimated or as an
additional work.
Issues framed by the civil Court
6. The civil Court has at the first
instance framed Issues such as whether the
respondent proves that it could not execute the
Contracted Work within the stipulated period
because M/s KNNL was in breach and whether M/s
KNNL proves that the suit is not maintainable and
that it had no jurisdiction to entertain the suit5.
However, the civil Court has framed Additional
Issues6 such as whether the respondent proves [i]
that there was defective estimation, [ii] that the
5 The civil Court at the first instance had framed Issue No.1 requiring the respondent to prove that he has executed the tender work for M/s KNNL as per the terms of the agreement, but on 28.06.2017 has reframed this Issue to be whether the respondent proves that he could not carry out the tender work within the stipulated period because of latches by M/s KNNL.
6 These Issues are framed on 02.06.2017, when the suit was listed for judgement, but the civil Court has heard the learned counsels for the parties after framing these additional Issues.
actual site condition differed from the details based
on which M/s KNNL has prepared the estimates, [iii]
that it had to excavate hard rock which is not part of
the quantities identified in the Estimate, [iv] it has
[a] excavated 85,862.33 Cubic Meter of hard rock,
[b] excavated Soil of All Kinds [SAK] in 16,128.95 Cubic Meter,
[c] excavated Soft Rock/Soft Rock Blast in 22,565.43 Cubic Meter,
[d] used rubble masonry in 126.61 Cubic Meter in the ratio of 1:5,
[e] used additional steel reinforcement of 15,483.12 KG,
[f] executed CCM-15, 40 MM d/s with 15% plum for 2294.96 Cubic Meter, and
[g] removed and hauled debris in 6546.75 Cubic Meter.
The details of the Witnesses examined and the Documents marked:
7. The respondent has examined Sri.
Ravi S/o Kashinath Chavan, a Power of Attorney, as
PW.1 and marked Exhibits P1 to P93, and M/s KNNL
has examined Sri Ulhas S/o Vasanth Kulkarni, a
retired Executive Engineer, who was in service at the
relevant time, as DW.1. M/s KNNL has marked
Exhibits D1 to D90. The respondent and M/s KNNL
have marked some documents twice, and these
documents include certain correspondences inter se
the officers of M/s KNNL and between the respondent
and M/s KNNL apart from the Tender Documents,
Work Order and proceedings of the Technical
Subcommittee Meeting.
The essentials of the civil Court's Reasoning:
8. The civil Court has taken Issue -1
and Additional Issues -1 and 5 together for
consideration, and these Issues require the
respondent to establish latches by M/s KNNL in
preparation of estimate as alleged and M/s KNNL to
show that unless the respondent constructed the
Template Wall, the estimation of Extra Financial
Implication [EFI] was not possible. The civil Court,
while opining that the evidence on record clearly
shows that the tender was faulty in technical
specifications and the officers of M/s KNNL have
made false allegations against the respondent of
executing the work whimsically, has concluded that
the strata classification at the time of estimation for
tender was not proper. The civil Court, in arriving at
this conclusion, has relied upon these following
conclusions.
8.1 The clause 1.5[a] of the tender
stipulates that M/s KNNL shall prepare L Sections
and drawings at intervals of 5 meter along the stretch
with the participation of the respondent's
representative and obtain his counter signature, and
though this clause is admitted, KNNL's witness
[DW.1] has stated that these details are part of the
Measurement Books. The Assistant Executive
Engineer with M/s KNNL [as per Exhibit P.36 dated
28.04.2009] has alleged that the respondent is
executing the work according to his whims and fancy,
but when the requisite sections and drawings are not
furnished, this allegation could not have been made.
8.2 The Chief Engineer along with the
Superintending Engineer, Executive Engineer and
Assistant Executive Engineer [DW.1] have inspected
the site [as per Exhibit P.20 dated 07.08.2007] and
prepared notes of Inspection which show that [a] the
respondent has tackled work in the 93rd, 94th, 95th,
and 96th KMs, [b] the excavation has to be carried out
after constructing Template Wall, [c] there must be
Paver Lining for Berm of 1.5 meter at Free Board with
balance cutting with side Slope at 1:1, and [d] that
Bank Work reaches for the Berm will have to be
provided.
8.3 The civil Court has opined that this
Inspection Note shows that there were instructions to
execute additional work observed at the time of
inspection with extra financial implication to the
respondent, but there is nothing on record to show
that any action was taken in furtherance thereof
before the cancellation of the Agreement except that
the proposal for approval of the financial implication
for the additional work is sent on 04.12.2009 as per
Exhibit P.44.
8.4 The civil Court has next considered
the Issues No. 4, 6 and 7, and these Issues relate to
the maintainability of the suit, the sufficiency of the
court fee paid and the respondent's right to relief. The
civil Court, on verification of the documents such as
correspondences and the minutes of the Technical
Sub-committee Meetings, has opined that the
respondent has established that M/s KNNL is
responsible for the delay. The civil Court has
concluded that M/s KNNL has acknowledged that
executing the Contracted Work will require extra
excavation/extraction and approval of Extra
Financial Implication [EFI] but has not granted such
approval and the respondent has proved that M/s
KNNL did not even release payment for the financial
closure achieved.
8.5 The civil Court has found in favour
of the respondent on these counts holding that in the
year 2007, the respondent is called upon [as per
Exhibit P.21/D.42] to complete the Contracted Work
by 14.07.2008 without approval of EFI, that in the
year 2008, the respondent is also called upon [as per
Ex. D.45-D.51] to complete the work by 14.07.2008
and it is informed that the contract will be closed at
its risk and cost without approval of EFI or payment,
that in the year 2009-2010, the respondent is
informed that:
[a] the contract will be extended on a
penalty of 7.5% but only to be later
informed that the penalty will be at the
rate of Rs.100/- per day for the period
between 30.06.2007 to 30.04.2010,
[b] the Technical Sub-committee is not
given all the information,
[c] the legal opinion [Exhibit P.59]
rendered to the Technical Sub-
committee is that the closure of
contract would not be appropriate
because no clear breach by the
respondent is established and there is
nothing to show that the respondent
has been assigned the additional work,
and
[d] in a hurriedly convened manner the
Technical Sub-committee thereafter
has decided to close the Agreement and
forfeit the EMD.
8.6 The civil Court referring to a series
of decisions on the tendency amongst the
Government officials to encourage litigation to protect
themselves without taking decisions and the
requirement in the Government Officials to act fairly,
has opined that M/s KNNL is unfair in its conduct
and the respondent has established its entitlement to
receive compensation holding that the suit is
maintainable.
M/s KNNL's case in brief as urged in this appeal
9. Sri Nargund, the learned Senior
Counsel for M/s KNNL, in his endeavour to persuade
this Court to interfere with the Civil Court's
impugned judgment and decree canvasses the
following.
9.1 The Civil Court has awarded a total
sum of Rs.6,05,02,830/- under different heads but
without even considering M/s KNNL's specific case
and the evidence that is placed on record to vindicate
the same. This can be seen, amongst others, in the
Civil Court awarding a sum of Rs.2,82,02,850/-
towards Removal of Hard Rock and a sum of
Rs.2,41,50,000/-towards Storage of Materials.
9.2 The respondent has admittedly not
completed the work, and M/s KNNL is compelled to
publish fresh tenders and award fresh Work Orders
for completion of the modernization of the canal
between 93 and 98 KMs. M/s KNNL has this time
issued Work Orders to 5 [five] different agencies for
this stretch of 5 [five] KMs. These agencies have
completed the work and none of these 5 [five]
agencies have submitted a bill for payment for the
extraction of Hard Rock. M/s KNNL, to establish this
facet of their defense, has produced Balance Work
Sheet and Completion Report Balance Sheet [Exhibit
D.88 and D.89] and M/s KNNL's witness [DW.1] has
also spoken about this in his evidence, but he has
not been cross-examined.
9.3 The civil Court has not considered
these circumstances, and crucially, the civil Court
has failed to consider that the respondent has placed
no detail on [i] the stretch where the Hard Rock is
extracted, [ii] the men and machinery employed to
remove Hard Rock and [iii] the disposal thereof to
establish its case that it has extracted Hard Rock or
to refute the evidence as per Exhibits D.88 and D.89
to controvert M/s KNNLs' case.
9.4 The civil Court has accepted the
cross sections furnished by the respondent
overlooking the fact that the respondent has prepared
these cross sections unilaterally just before the
commencement of the suit and although the
respondent has signed Measurement Books. These
Books not only show the respondent has not
completed the Contracted Work despite repeated
extensions but also that the respondent is paid
according to the work executed in terms of the
Agreement. This would also be with the Running
Bills/Final Bills which are signed on behalf of the
respondent accepting that the measurements as
mentioned therein are true and correct.
9.5 The respondent's witness [PW.1] has
also admitted to signing the Measurements Book and
the Running/Final Bills in stating that "it is shown
that whatever the work the plaintiff has executed
during the tender period is recorded by the defendant
in the Measurement Book at points of time". The civil
Court, despite this overwhelming evidence, has
drawn conclusions against M/s KNNL.
9.6 The respondent's witness [PW.1] was
cross-examined on commission, and the civil Court,
because the Commissioner's Report containing the
cross examination was kept separately, has not
considered the cross-examination. The civil Court has
thus excluded vital material. The civil Court should
have examined the entire evidence in determining the
liability to pay compensation under the specific heads
upon consideration of the specifics of the respective
cases.
9.7 Sri Nargund, relying upon the
synopsis of the submissions on behalf of M/s KNNL,
proposes to take this Court through the details of the
findings by the Technical Sub-committee to justify
that the civil Court could not have accepted the
respondent's case on the extent of the work executed
or the expenses incurred in the execution, including
the cost of material such as jelly and sand in
computing the amount payable. The learned Senior
counsel emphasizes that M/s KNNL has shown the
liability to pay only a sum of Rs.75,00,000/- to the
respondent, which is in fact paid in compliance with
the interim orders of this Court in the present
proceedings.
A brief statement on the response on behalf of the respondent
10. Sri. M S Bagali, the learned counsel
for the respondent, stoutly refutes the canvass on
behalf of M/s KNNL, but he is not convincing in his
efforts to persuade this Court to accept that the civil
Court has actually considered the cross-examination
of the respondent's witness. The learned counsel
argues that this Court must not interfere with the
impugned judgement and decree, notwithstanding
certain circumstances in favour of M/s KNNL,
because the essentials of the respondent's case are
established.
10.1 Sri. M S Bagali argues that the
evidence on record establishes that [a] M/s KNNL
prepared the Estimate when the Canal was in use, [b]
the respondent has constructed the Template Walls
as directed by the Assistant Executive Engineer, [c]
the respondent objected to increase the canal width
in the Deep Cut Portions along the entire stretch
between the 93rd and 98th KMs, [d] the respondent
was restricted in commencing the work because it's
representatives were asked to await prior approval
from the competent authority for the additional
work/construction of Template Walls [e] the Chief
Engineer's Inspection Report, which refers to certain
additional works and deficiencies, bears testimony to
the Estimate being faulty.
10.2 Sri M.S. Bagali, relying upon the
details as underscored in the List of Dates and
Events filed on 22.11.2024, proposes to rely upon
correspondences [such as Exhibit P. 21, Exhibits P. 23
- P.30, Exhibits P.35 - P.41] to contend that these
Exhibits must be construed in a particular manner
that vindicates the respondent's case. However, the
learned counsel, with Sri Nargund seriously
contesting such reading of these exhibits, does not
dispute that this particular reading of these Exhibits
have not been put to M/s KNNL's witness.
The point/s for consideration:
11. This Court has called for a glossary
of the technical terms used and a PPT on the details
of the Contracted Work to understand the nuances.
With both Sri Nargund and Sri M.S. Bagali accepting
that M/s KNNL and the respondent must have
another opportunity to bolster their evidence to
substantiate their respective cases, this Court has
heard them on deciding the appeal on merits calling
for a report from the civil Court as contemplated
under Order XLI Rule 27 of the Code of Civil
Procedure [for short, 'the CPC'].
11.1 Further, as part of consideration of
the afore question, this Court has also heard Sri M.B.
Nargund and Sri M.S. Bagali on the question of
remanding the suit for reconsideration setting aside
the impugned judgement and decree with liberty to
file Interrogatories as contemplated under Order XI of
CPC and to lead further evidence.
This Court's reasoning on remand as against calling for a report
12. This Court must refer to one of the
recent decisions of the Apex Court on remand as
against the appellate Court itself deciding on the
merits. The Apex Court in Shivakumar v.
Sharanabasappa7 has held that a remand routinely
will not be justified when available evidence suffices
to dispose of the appeal on merits, but a remand may
be necessary in certain eventualities depending on
the facts and circumstances of each case. The Apex
Court has thus declared rejecting a canvass for
remand for reconsideration of the due execution and
authentication of a purported last Will and
Testament. The Apex Court has held thus:
A conjoint reading of Rules 23, 23-A and 24 of Order 41 brings forth the scope as also contours of the powers of remand that when the available evidence is sufficient to dispose of the matter, the proper course for an appellate court is to follow the mandate of Rule 24 of Order 41 CPC and to determine the suit finally. It is only in such cases where the decree in challenge is reversed in appeal and a retrial is considered necessary that the appellate court shall adopt the course of remanding the case. It remains trite that order of remand is not to be passed in a routine manner because an unwarranted order of remand merely elongates the life of the
7 (2021) 11 SCC 277
litigation without serving the cause of justice.
An order of remand only on the ground that the points touching the appreciation of evidence were not dealt with by the trial court may not be considered proper in a given case because the first appellate court itself is possessed of jurisdiction to enter into facts and appreciate the evidence. There could, of course, be several eventualities which may justify an order of remand or where remand would be rather necessary depending on the facts and the given set of circumstances of a case.
12.1 The essential controversy for the
decision in the suit is whether the respondent has
established that M/s KNNL is liable to pay the
different amounts claimed with the onus being on
M/s KNNL to show that the respondent has not
completed the Contracted Work despite the extension
of time. This controversy is presented for decision
with the rival pleadings leading to multifarious Issues
that have been framed and re-framed by the civil
Court with these Issues being reframed even after the
hearing of arguments. It cannot be gainsaid that the
Issues are presented in the backdrop of a technical
matter i.e., an assessment of the structure of the
canal as it existed, the details of the work to be
executed to change the structure to provide
additional features [modernizing the canal], and the
details of the work executed by the respondent.
12.2 These technical aspects will have to
be examined based only on the circumstances as
could be gathered today because M/s KNNL,
admittedly, has completed the modernization of the
subject stretch of the canal engaging the services of
other contractors after issuing fresh tender cancelling
the Agreement with the respondent. This Court
opines that, in these circumstances, the saying in law
that it is not the bulk of [the quantity of] the evidence
but the effectiveness of the evidence that will be
material is emphasized.
12.3 The respondent has examined a
Power of Attorney, whose competence to give evidence
is under serious dispute with M/s KNNL asserting
that this person was not supervising the work and
that he is not acquainted with all the technical
details. The respondent has marked 93 Exhibits, and
these include [apart from the correspondences]
technical documents showing the different quantities.
M/s KNNL through its witness [Sri Ulhas S/o Vasant
Kulkarni - DW1 - a retired Executive Engineer who
was in service at the relevant time] has marked 90
documents, and most of these exhibits are internal
communications or communications with the
respondent and technical documents such as
Estimates and Estimate Face Sheet with certain
abstracts, measurements and such other technical
details.
12.4 Undeniably, the evidence that M/s
KNNL and the respondent have let in is mostly
documentary evidence. The ocular evidence on the
relevance and probative value of the documentary
evidence is rendered tenuous with neither M/s
KNNL's witness nor the respondent's witness
speaking about them in the context of the specific
Issues that are considered. If the witnesses have not
explained the relevance of the correspondences or the
technical details in the documents in their chief
examination, they have also not been cross-examined
in this regard.
12.5 Perhaps it could be argued that the
onus cannot be on the other side to cross-examine on
the relevance of the documents if the witness has not
spoken about the documents marked through him,
but indubitably in the present case the assessment of
both the probative and relevance of the documentary
evidence is vastly undermined by the lack of
exhaustive examination of the witnesses on the
documents marked in evidence. This Court must
refer to certain specific aspects, which are as follows.
12.5.1 Measurement Book/s Running
Bills. M/s KNNL relies upon the Measurement
Books, which are marked as Exhibits P.84 and P.85.
As canvassed by Sri Nargund, these Exhibits [as
also the Running /Final Bills - Exhibit D.10] show
that the joint measurement was taken along each
stretch of the canal as per the Contracted Work at
intervals of 20 meters. It is emphasized that the
details in these Measurement Books and
Running/Final Bills do not reflect the quantities, or
the measurements, for which the respondent has
filed a claim in the suit.
12.5.2 The respondent has marked
the Measurement Books and M/s KNNL has marked
the Running/Final Bills. On behalf of M/s KNNL,
the respondent's witness is cross-examined on the
relevance of the entries in these Books/ Bills, but
M/s KNNL's witness has not explained the same in
his evidence and as such there is cross-
examination. These documents have multiple data,
and unless the witnesses concerned speak about the
relevance with appropriate cross-examination, these
documents serve no purpose, and this can only
mean that the trial is not effectively concluded.
Further, the civil Court has not considered these
documents.
12.5.3 Temporary and Permanent
Benchmarks: The civil Court, referring to clause 1.3
of the agreement, has opined that M/s KNNL has
failed to provide Temporary Benchmarks and this
was necessary for effective measurement of the work
executed by the respondent because the respondent,
based on such Temporary Benchmarks, was required
to erect the Permanent Benchmarks to facilitate final
measurements. The respondent's witness, while
admitting that the respondent has not written to
appellants asking for Temporary Benchmark, has
denied the suggestion that the Temporary
Benchmark would not be relevant but without
furnishing details.
12.5.4 Sri M.B. Nargund and Sri. M S
Bagali propose to take this Court elaborately
through the documents on the significance of the
Temporary/Permanent Benchmark. However, this
Court must observe that neither M/s KNNL's nor the
respondent's evidence is conclusive in this regard,
and if either M/s KNNL or the respondent can take
advantage of any failure in establishing/ erecting
the Temporary and Permanent Benchmarks, they
should have placed on record cogent evidence. As
such, this Court cannot arrive at a particular
conclusion without evidence.
12.5.5 Construction of Template Walls:
The civil Court has referred to M/s KNNL's witness
admitting to certain blanks in the Tender
Documents to opine that there are some latches in
M/s KNNL on giving instructions to the respondent
to execute the Contracted Work. M/s KNNL, to
assert that the blanks in the Tender Document will
not be significant given the other terms of the
Tender Documents/ Agreement, contends that the
respondent was required to construct Template
Walls at regular intervals and if the respondent had
constructed such Template Walls, the difference, if
any, in the quantity could have been assessed.
12.5.6 The respondent's witness is
elaborately cross-examined with reference to M/s
KNNL's correspondence calling upon the respondent
to construct Template Walls. The respondent's
witness has disputed the correspondences asserting
that these have been written although the
respondent had constructed Template Walls. If the
respondent's version is to be believed and held
against M/s KNNL, this Court must opine that it
was imperative for the respondent to place on record
the details of the construction of the Template Walls.
12.5.7 The civil court overlooking this
material aspect has opined that the question of
construction of the Template Walls will not be
relevant because neither the Executive Engineer nor
the Superintending Engineer have examined the
financial repercussions to the respondent. This
conclusion is a consequence of the party's failure to
place on record cogent and relevant evidence to
justify conclusions on technical aspects.
12.5.8 The reliance on
Correspondences: M/s KNNL and respondents have
relied upon, as aforesaid, on a series of
correspondences. The evidentiary value of these
correspondences must be firstly explained in the
chronology that they are written and secondly based
on the specific areas that those correspondences
relate to. These details will provide the context in
which the probative value of these correspondences
must be assessed. If these details are not furnished
with the opportunity to the other to admit the
consequence or the inference that could be from
these correspondences, neither M/s KNNL nor the
respondent can implore this Court/s to draw
inferences on a technical subject that could cause
jumbled conclusions.
12.5.9 The civil Court, in the absence
of these details, has opined that some
correspondences [Exhibits P.18, 19 and 20] are self-
explanatory and that these correspondences
indicate that the respondent required Additional
Funding as it had to execute additional work. In this
appeal, M/s KNNL and the respondent want this
Court to test the merits of the civil Court's
conclusions, but if this Court undertakes this
exercise in the absence of the details, it tantamount
to substituting its own reading on technical matters
without clear and cogent evidence.
12.5.10 The Respondent's claim of
removal of Hard Rock and Storage of Materials: Sri
M.B. Nargund has taken this Court through the civil
Court's reasoning to allow the respondent's claim for
removal of Hard Rock in a sum of Rs.2,82,02,850/-
and towards Storage of Materials in a sum of
Rs.2,41,50,000/- to demonstrate the deficiencies in
the civil Court's consideration of the respective
cases. The learned Senior Counsel emphasizes,
amongst others, that if the respondent had
extracted Hard Rock it should have been reflected
either in the Measurement Books or the Running
Bills but they are not mentioned in these documents
and that the Contracted Work, which is abandoned
by the respondent, is completed by five different
agencies after a fresh tender and none of these
agencies have made any claim for extracting Hard
Rock.
12.5.11 These would indeed be
substantial circumstances, and these must be
considered for a complete evaluation in the
backdrop of any other material that the respondent
has produced. The civil Court's conclusion in these
regards is found in paragraph-188 and onwards of
the impugned judgment, and this Court must opine
that the civil Court's conclusions are essentially
inferential or presumptive.
12.5.12 The civil Court, based on its
own reading of certain Exhibits, such as Exhibit
P.20, which refers to an increase in the slope for the
canal, has inferred that the respondent has
extracted Hard Rock. The civil Court is also
presumptive in its conclusion that the respondent
should succeed in its claim for reimbursement of the
costs incurred in removal of hard rock in opining
that the Chief Engineer or the other concerned from
M/s KNNL should have visited the site to verify.
12.5.13 This Court must opine that the
decision on the respondent's claim for
reimbursement at the cost of removal of hard rock/
Storage of Materials must be assessed based on
whether there is material to show that the
respondent has indeed removed hard rock/ stored
material and the actual quantity of hard rock
removed and the material stored as also the price
that is payable. The Tender Document/Agreement
provide for rates at which M/s KNNL must pay the
respondent for additional work; if the additional
work is within 125% of the volume, at a particular
rate and if the additional work is more than that, at
a rate determined in a particular manner.
12.5.14 This Court must observe that
the evidence is inconclusive, and that both M/s
KNNL and the respondent, who rely upon certain
circumstances must first call upon the other to
admit the foundational facts from which it could be
held either that the respondent has removed a
certain quantity of hard rock and stored the
material and the price that is payable. The civil
Court overlooking these decisive factors has
accepted the respondent's claims on these.
13. This Court must also observe that
the respondent's witness strangely asserts that M/s
KNNL did not handover the site to the respondent
and Contracted Work is also executed. This Court,
upon going through this witness's testimony in its
entirety, must opine that there is a definite
irreconcilability in his evidence lending credence to
M/s KNNL's case that this witness is only examined
as a Power of Attorney and he does not personally
know all the material facts, and the respondent must
have another opportunity. In the light of the afore,
this Court concludes that the appeal must be allowed
in part restoring the suit for reconsideration with
liberty to lead evidence instead of deciding the appeal
on the merits calling for a report from the civil Court.
14. This Court must observe that
neither M/s KNNL nor the respondent has availed the
recourse available to them under Order XI of CPC,
and if indeed they had availed this recourse, given
the technical nature of the dispute and the nature of
evidence relied upon by them, the civil Court could
have separated the admitted facts from the disputed
facts with respect to the specific areas of dispute and
answered the Issues based on the sufficiency of the
evidence. M/s KNNL's/respondent's failure has
contributed to an undeniable impression that the
impugned judgment and decree is despite an
incomplete trial. In this context, this Court must also
observe that it cannot be conclusively opined that the
civil Court has had the advantage of the cross-
examination of the respondent's witness.
15. The importance of interrogatories
and discoveries in technical and complex matters
have been underscored even by attorneys in other
jurisdictions, and an immediate reference could be
made to the Article called "The Effective Use of Written
Interrogatories" published way back in the year
19768. The importance is underscored thus:
"In complex litigation interrogatories are often the only practical and efficient means of obtaining certain information. For example,
8 THE EFFECTIVE USE OF WRITTEN INTERROGATORIES" - Adrian P. Schoone and Edward L. Miner, Marquette Law Review, Vol. 60:29, 1976
although depositions are relatively effective for obtaining spontaneous answers, the information is restricted to the knowledge of the deposed individual. Answers to interrogatories, on the other hand, represent the collective knowledge of the opponent and his attorneys and agents. Moreover, the answering party is required to conduct a reasonable investigation if this is necessary in order to formulate an adequate response to the questions.
............................
Written interrogatories are also the ideal discovery device where the information sought can be obtained only by reference to several documents or where the information is of such a complex and technical nature that it cannot be communicated verbally in an organized and comprehensible manner."
16. This Court must now refer to the
Apex Court's decision in T A. Shanmugam v. Ariya
Kshatriya Rajakula Vamsathu Madalaya
Nandhavana Paripalanai Sangam9. The Apex
Court, while emphasizing that the parties must set
forth sufficient factual details to reduce the ability to
9 [2012] 6 SCC 430
put forward a false or exaggerated claim or defense
and that the Courts must carefully look into the
pleadings, has declared that it is imperative that the
Judges must have a complete grip of the facts before
they deal with the case and that a proper admission
and denial are imperative in disposal of the cases.
The relevant extract reads:
"29. Ensuring discovery and production of documents and a proper admission/denial is imperative for deciding civil cases in a proper perspective. In relevant cases, the courts should encourage interrogatories to be administered."
17. The other important facet of the
present dispute is its nature, which is technical and
complex. This suit, with the promulgation of the
Commercial Courts Act, 2015, should have been
transferred to be decided as a commercial dispute but
for the proviso to Section 15 of the Act. In fact, this
Court, by the order dated 04.09.2024, has examined
whether the appeal should have been entertained by
this Court's Commercial Division to opine that the
civil Court has justifiably decided the suit without
transferring the suit to the Commercial Court
because it had reserved the suit for judgement prior
to the constitution of the Commercial Court in
Belagavi, and therefore, the appeal, is rightly before
this Court.
18. This Court has opined that the civil
Court's impugned judgement and decree is without
an effective and complete trial and that it will be just
and reasonable to set aside this judgement and
decree remanding the suit for fresh consideration.
Further, this Court is also of the opinion that M/s
KNNL and the respondent must file for
Interrogatories before the relative merits of their
respective cases are assessed for a decision on
merits. The next question for consideration, therefore,
is whether this suit must be restored to the
Commercial Court at Belagavi or be restored to the
civil Court, and if the suit is to be tried by the
Commercial Court, Order XI of CPC as applicable to
the Commercial Courts will apply and filing for
interrogatories will be in order.
19. As observed by this Court in the
aforesaid order dated 04.09.2024, the present
dispute between M/s KNNL and the respondent
emanate from a tender issued by M/s KNNL for civil
construction [modernization of a stretch of a canal],
and Section 2[1][c][vi] of the Commercial Courts Act10,
a dispute arising out of a tender would be a
commercial dispute by definition. The respondent's
suit, if it was pending as of today, should have been
decided as such by the Commercial Court at
Belagavi, and with this Court interfering with the
judgement restoring the same suit for
reconsideration, it must necessarily be considered by
the Commercial Court and not by the civil Court.
20. As such, the suit must be restored
to the Commercial Court at Belagavi with the
10 Section 2[1] [c]: "Commercial Dispute" means a dispute arising out of-
[vi] Construction and Infrastructure Contracts, including tender;
respondent and M/s KNNL filing for Interrogatories
as contemplated under Order XI of CPC applicable to
the Commercial Courts. The respondent and
appellants must file for Interrogatories based on the
exhibits that are already marked with liberty to lead
fresh evidence. This Court must observe that the
ocular evidence on record must be part of the record
and considered in the light of the response to the
Disclosure/Discovery and Interrogatories and further
evidence that the parties may lead consequent to the
remand.
ORDER
The appeal is allowed in part, and the
impugned judgement and decree dated 12.12.2017
in OS No. 49/2012 on the file of the First
Additional Senior Civil Judge and CJM, Belagavi,
is set aside restoring the suit for reconsideration
by the Commercial Court at Belagavi with the
following directions:
[a] The suit as OS No. 49/2012 shall be
listed before the First Additional Senior Civil
Judge and CJM, Belagavi, at Belagavi on
16.06.2025 and the appellants [M/s KNNL
and its Officers] and the respondent shall
appear without further notice on 16.06.2025.
[b] The First Additional Senior Civil Judge
and CJM, Belagavi, at Belagavi shall transfer
the suit to the Commercial Court, at Belagavi
under Section 15 of the Commercial Courts
Act, 2015 fixing the date of first appearance
before such Court.
[c] The Commercial Court at Belagavi shall
permit the appellants [M/s KNNL and its
Officers] and the respondent to file
Interrogatories as contemplated under Order
XI Rule 2 of CPC as applicable to the
Commercial Courts and lead further evidence
based on the response to the respective
Interrogatories. The Commercial Court shall
expedite a decision on merits as required
under Section 15 of the Commercial Courts
Act, 2015.
[d] The Office is directed to refund the
Court Fee paid as permissible under the
provisions of the Karnataka Court Fees and
Suits Valuation Act, 1958.
[e] The Office is also directed to transmit
TCR forthwith.
[f] No costs.
Sd/-
(B.M. SHYAM PRASAD) JUDGE
Sd/-
(C.M. JOSHI) JUDGE
NV*
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!