Citation : 2025 Latest Caselaw 3904 Kant
Judgement Date : 13 February, 2025
-1-
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 13TH DAY OF FEBRUARY, 2025
PRESENT
THE HON'BLE MR. N.V. ANJARIA, CHIEF JUSTICE
AND
THE HON'BLE MR. JUSTICE K.V. ARAVIND
COMMERICAL APPEAL NO. 51 OF 2024
BETWEEN:
1 . SRI B. PRASHANTH
AGED ABOUT 44 YEARS
S/O LATE BASAVARAJ M
RESIDING AT 2902,
KANTHARAJ URS ROAD
SARASWTHIPURAM
MYSURU - 570 009.
... APPELLANT
(BY SRI DHANANJAY V. JOSHI, SENIOR ADVOCATE FOR
SRI GIRISH KUMAR B.M., ADVOCATE)
AND:
1 . SRI GANESH S POOJARI
AGED ABOUT 29 YEARS
S/O LATE SANJEEV S. POOJARI
No.57/1, 'SAHANA NILAYA'
5TH CROSS ROAD, GAYATHRINAGARA
BENGALURU - 560 021
... RESPONDENT
(BY SRI Y.K. NARAYANA SHARMA, ADVOCATE)
---
THIS COMMERCIAL APPEAL IS FILED UNDER SECTION 13(1A) OF THE COMMERCIAL COURT ACT, 2015 R/W SECTION 37(1)(A) OF THE ARBITRATION AND CONCILIATION ACT, 1996, PRAYING TO CALL FOR RECORDS IN COM.O.S.NO.237/2023 ON THE FILE OF THE PRINCIPAL DISTRICT AND SESSIONS JUDGE AT MYSURU; AND SET ASIDE THE ORDER DATED 20/01/2024 PASSED ON I.A.NO.4 IN COM.O.S.NO.237/2023 BY THE PRINCIPAL DISTRICT AND SESSIONS JUDGE AT MYSURU AND CONSEQUENTLY ALLOW THE APPLICATION (I.A.NO.4) DATED 05/09/2023 FILED UNDER SECTION 8 OF THE ARBITRATION AND CONCILIATION ACT, 1996 R/W SECTION 151 OF CPC & ETC.
THIS APPEAL HAVING BEEN HEARD AND RESERVED FOR JUDGMENT, COMING ON FOR PRONOUNCEMENT THIS DAY, JUDGMENT WAS PRONOUNCED AS UNDER:
CORAM: HON'BLE THE CHIEF JUSTICE MR. JUSTICE N.V. ANJARIA and HON'BLE MR JUSTICE K.V. ARAVIND
C.A.V. JUDGMENT
(PER: HON'BLE THE CHIEF JUSTICE MR. JUSTICE N. V. ANJARIA)
The challenge in this Commercial Appeal is directed against
judgment and order dated 20th January 2024 passed by learned
Principal District and Sessions Judge, Mysuru in Commercial
Original Suit No.237 of 2023, whereby the application of the
appellant-original defendant under Section 8 of the Arbitration and
Conciliation Act, 1996 for referring the subject matter to the
arbitration came to be rejected.
2. It was a suit instituted by the plaintiff-respondent herein for
recovery of Rs.4,09,06,283/- with interest. The plaintiff and
defendant had previously entered into a Partnership Deed on 24th
June 2020 and were engaged in partnership business of sale of
motor spirit, motor oils, greases, LPG, CNG and other motor
accessories manufactured by the Bharat Petroleum Corporation
Ltd., in the name and style of 'Shree Service Station'.
3. In the plaint it was the case of the plaintiff inter alia that the
said service station which was situated at Kantharaja Urs Road,
Saraswathipuram, Mysuru was under the ownership of the
defendant, his sisters and his mother and originally belonged to the
father. It was stated that the plaintiff had initially invested the
amount towards working capital and it was agreed that for a period
of five years the plaintiff would be entitled to 99% profit and the rest
1% profit will go to the defendant. While the investment of the
plaintiff was Rs.30,00,000/- as working capital, the defendant had
collected in addition Rs.2,49,50,000/-
3.1 It was averred by the plaintiff that defendant started to insist
that the plaintiff should receive back investment made in the
partnership firm by him, and exit the partnership. For this, the
defendant agreed to pay Rs.3,75,00,000/- within stipulated time
and upon such payment, the plaintiff was to leave from the
partnership. The terms and conditions relating to above agreement
came to be reduced into writing in agreement dated 10th August
2022 between the parties. It is the say of the plaintiff that even
after execution of this agreement, defendant failed to pay the sum
agreed to be paid, and requested the plaintiff to give further time.
Despite notices, the amount was not paid, the suit was therefore,
required to be instituted, stated the plaintiff.
3.2 In the aforementioned suit, the defendant filed application
under Section 8 of the Arbitration and Conciliation Act, 1996 on the
ground that the Partnership Deed dated 24th June 2020, there
existed an Arbitration Clause No.21 and in view of that the suit
dispute was required to be referred to the Arbitrator and that the
suit was not maintainable.
3.3 Clause No.21 relied on by the defendant from the
Partnership Agreement dated 24th June 2020 was as under,
"21. Arbitration: That if any dispute would arise in interpretation of any of the clause of this deed the same shall be referred to the arbitrator/arbitrators, in accordance with the Arbitration Act and the award of the arbitrator/arbitrators shall be final and binding upon the partners. The place and jurisdiction of arbitration is Facilitation council, Bangalore, Karnataka."
3.4 The application for reference to the arbitration was contested
contending that the suit was based on agreement dated 10th
August 2022 under which the defendant agreed to pay a definite
sum, in view of his not fulfilling the terms and conditions of the
Partnership Deed, it was contended that the subsequent
agreement clearly showed that the partnership constituted on 24th
June 2020 was not taken up and that the plaintiff and the
defendant had agreed to exit from the partnership.
3.5 In the above light, it was contended that eventhough the
original Partnership Deed contained the arbitration clause relating
to business of partnership, in view of settlement of the dispute
between the parties and in light of fresh agreement having been
entered into the suit for implementation of the commitment given by
the defendant in the said subsequent agreement was maintainable
and that the arbitration clause would not apply in as much as no
dispute regarding partnership business could be said to have
subsisted.
3.6 The court below framed two issues. Firstly, whether it was
necessary to direct the parties to invoke arbitration clause in the
Deed of Partnership between them. Secondly, whether in view of
the arbitration clause in the Partnership Deed, the Court had
jurisdiction to try the suit, answering both the issues in the
negative.
4. Learned Senior Advocate for the appellant assailed the
judgment and order of the Commercial Court below to submit that
the commercial suit was filed for a dispute which originated from
partnership agreement and that the partnership agreement
contained arbitration clause. According to learned Senior Counsel,
for the suit dispute, the arbitration clause was referable and
invokable. It was further contended that dispute between the
partners to a partnership agreement is a commercial dispute within
the meaning of Section 2(1)(c)(xv) of the Commercial Courts Act,
2015. The submission was furthered by canvassing that had the
dispute not been one arising from the partnership deed, the
commercial suit would not have been competent and a simplicitor
suit for recovery of money would have been instituted.
4.1 Learned Senior Advocate for the appellant, after
emphasizing that in the plaint if was not stated that the partnership
deed dated 24th June 2020 was terminated, submitted that
assuming without admitting that the agreement of partnership
brought about a cessation of the partnership, the arbitration clause
in the deed dated 24th June 2020 would still be subsisting and that
the parties would be bound by it. It was submitted that because of
the subsequent agreement regarding payment of dues by the
defendant, the arbitration clause in the partnership agreement did
not survive.
4.2 Learned Senior Advocate thereafter proceeded to highlight
the scope and ambit of Section 8 of the Arbitration Act, 1996. In
this regard, the decision of the Supreme Court in Praveen
Electricals Pvt. Ltd. vs. Galaxy Infra and Engineering Pvt. Ltd.
[(2021) 5 SCC 671], was relied on. For the proposition that merely
because that the contract has come to an end by its termination
due to breach, the arbitration clause does not get perished nor it is
rendered inoperative. But would survive for the resolution of
disputes arising 'in respect of' or 'with regard to' or 'under the
contract', pressed into service was the decision in Branch
Manager, Magma Leasing and Finance Ltd. vs. Potluri
Madhavilata [(2009) 10 SCC 103].
4.3 On the other hand, learned Senior Advocate for the
respondent-originally plaintiff supported the impugned judgment
and order of the court below. He took the court through the
contents of the partnership agreement and then highlighted the
nature of and conditions in agreement entered into afresh by
pinpointing terms and conditions incorporated in the new
agreement, to emphasise that the subsequent was entirely an
agreement which created obligations between the parties anew, in
which, the arbitration clause found in the partnership was not
extended either expressly or impliedly. It was his submission that
the arbitration agreement ceased to exist post-entering into the
new agreement and the arbitration clause also did not survive to
operate.
4.4 Learned Senior Counsel lastly submitted on the conduct of
the appellant-defendant that the defendant has not paid the
amount agreed upon in the subsequent agreement. On one hand
he has resiled from his obligation under the fresh agreement
forcing the respondent herein to institute the recovery suit, on the
other hand, now he has been trying to protract by filing such
applications as a delaying tactics.
5. The core question that arises in the backdrop of above
controversy is whether after the parties entering into agreement
dated 10th August 2022, the arbitration clause found in the
partnership agreement dated 24th June 2020 survives and whether
the Arbitration clause was operative to refer the suit dispute to the
arbitration; whether the partnership agreement stood rescinded or
the new agreement was an extension, to be read into it the
arbitration clause; whether the partnership agreement and the
subsequent continued to bear nexus to each other.
5.1 Although the clause in a contract for arbitration is perceived
in law to be independent in itself, the arbitration clause is always
referable to the contract or the agreement in which it is
incorporated. The arbitrable dispute arise when the disputes are of
the kind to be 'based on', or 'in relation to' or 'in connection with'
the contract. It could be said that the existence of contract in which
the arbitration clause is inserted, becomes a prerequisite for
applying the arbitration clause.
5.1.1 In certain circumstances, for certain purposes, in given case,
it could be viewed however that arbitration clause may survive for
its applicability for resolution of disputes even after the contract as
such, has worked out for itself. One of such instances is that the
contract has come to an end by virtue of doctrine of frustration, in
which case the contract would be cease for all purposes, but only
for future performance. In other words, where contracts are
consensual, the question whether the arbitration clause survives or
perishes, would depend upon the nature of the disputes and their
effect on the contractual terms.
5.2 The discussion on position of law on this score is found in the
decision of the Hon'ble Supreme Court in Damodar Valley
Corporation vs. K.K. Kar [(1974) 1 SCC 141]. The issue is
- 10 -
addressed by the Hon'ble Supreme Court in that decision in the
context of Sections 62 and 39 of the Contract Act, 1872, was
whether the arbitration clause incorporated in a contract perishes
along with unilateral repudiation of the contract. The question for
determination was: "where one of the parties refers a dispute or
disputes to arbitration and the other party takes a plea that there
was a final settlement of claims, is the court, on an application
under Sections 9(b) and 33 of the Arbitration Act, 1940, entitled to
enquire into the truth and validity of the averment as to whether
there was or was not a final settlement on the ground that if that
was proved, it would bar a reference to the arbitration inasmuch as
the arbitration clause itself would perish."
5.2.1 As explained by the Hon'ble Supreme Court in Damodar
Valley Corporation (supra), the questions of unilateral repudiation
of the rights and obligations under the contract or of a full and final
settlement of the contract are relatable to the performance or
discharge of the contract, in which eventuality, much less the
arbitration clause is put an end to, such questions fall within the
purview of the arbitration clause.
5.2.2 It was observed, however, that the case was not one where
the plea is raised that the contract is void, illegal or fraudulent. It is
- 11 -
to be added here by this Court that even in respect of a new
contract entered into in substitution of or rearranging the
contractual obligations into new contract in place of the existing
one, the complexion would arise differently, stated the Supreme
Court,
"This is not a case where the plea is that the contract is void, illegal or fraudulent, etc., in which case, the entire contract along with the arbitration clause is non est, or voidable. As the contract is an outcome of the agreement between the parties it is equally open to the parties thereto to agree to bring it to an end or to treat it as if it never existed. It may also be open to the parties to terminate the previous contract and substitute in its place a new contract or alter the original contract in such a way that it cannot subsist. In all these cases, since the entire contract is put an end to, the arbitration clause, which is a part of it, also perishes along with it."
(Para 7)
5.2.3 Referring to Section 62 of the Contract Act, it was stated
that it incorporates the very principle when it provides that when the
parties to a contract agreed to substitute any contract or to rescind
or alter it, the original contract need not be performed,
"Where therefore, the dispute between the parties is that the contract itself does not subsist either as a result of its being substituted by a new contract or by rescission or alteration, that dispute cannot be referred to the arbitration as the arbitration clause itself would perish if the
- 12 -
averment is found to be valid. As the very jurisdiction of the arbitrator is dependent upon the existence of the arbitration clause under which he is appointed, the parties have no right to invoke a clause which perishes with the contract."
(Para 7)
5.3 In State of Maharashtra vs. Navbharat Builders [1994
Supp (3) SCC 83], as well as in M/s. P.K. Ramaiah and
Company vs. Chairman & Managing Director, National Thermal
Power Corporation [1994 Supp (3) SCC 126], wherein a
construction work contract, the contractor had accepted either by
mutual agreement or voluntarily an unconditionally the payment in
settlement of the contract claim, it was held that no arbitrable
dispute survived and the contractor was not entitled to put forward
the labour escalation or any subsequent claim was not an
arbitrable dispute.
5.3.1 The question was whether the arbitration clause in the
original contracts could claim any effect for it. The view of the
Calcutta High Court that the third original contract and the
arbitration clause contained therein has ceased to exist as a result
of last settlement, was confirmed by the Apex Court by observing
that the third settlement contract was in substitution of the three
contracts, and after its execution the earlier contracts stood
extinguished and the arbitration clause also stood extinguished.
- 13 -
5.3.2 The judgment of the Hon'ble Supreme Court per majority
culled out the following principles, (i) An arbitration clause is a
collateral term of a contract as distinguished from its substantive
terms; but none the less it is an integral part of it; (ii) However
comprehensive the terms of an arbitration clause may be, the
existence of the contract is a necessary condition for its operation;
it perishes with the contract; (iii) The contract may be non est in
the sense that it never came legally into existence or it was void ab
initio; (iv) Though the contract was validly executed, the parties
may put an end to it as if it had never existed and substitute a new
contract for it solely governing their rights and liabilities thereunder;
(v) In the former case, if the original contract has no legal
existence, the arbitration clause also cannot operate, for along with
the original contract, it is also void; in the latter case, as the original
contract is extinguished by the substituted one, the arbitration
clause of the original contract perishes with it; (vi) Between the two
falls many categories "of disputes in connection with a contract,
such as the question of repudiation, frustration, breach etc. In those
cases it is the performance of the contract that has come to an end,
but the contract is still in existence for certain purposes in respect
of disputes arising under it or in connection with it. (vii) As the
contract subsists for certain purposes, the arbitration clause
- 14 -
operates in respect of these purposes. It is to be observed that
such is not the case in the present set of facts.
5.4 In the Union of India vs. Kishorilal Gupta [AIR 1959 SC
1362], respondents had entered into three contracts with the
appellant, each of which had the arbitration clause. Before the
contracts could be fully executed, disputes arose between the
parties and allegations of breach was leveled. The parties
thereafter entered into three fresh contracts on different successive
dates settling the disputes on the terms contained in the new
contract, wherein the respondents agreed to pay to the appellants
certain monies in settlement of the dispute related to first two
original contracts, and by last of the new agreement, the
respondents agreed to pay to the appellant the specified amount
preferable to third original contract.
5.5 The law in this regard came to be discussed by the Supreme
Court also in Nathani Steels Ltd. vs. Associated Constructions
[1995 Supp (3) SCC 324], wherein it was held that once there is a
full and final settlement in respect of a particular dispute or
difference in relation to a matter covered under arbitration clause
and if such dispute is finally settled, it does not remain arbitrable
dispute and that the arbitration clause cannot be invoked. It was
- 15 -
stated that unless the settlement is set aside in an appropriate
proceedings, a party to the settlement is not permissible to spurn it
and to seek to invoke the arbitration clause.
5.5.1 The Supreme Court further observed,
"If this is permitted the sanctity of contract, the settlement also being a contract, would be wholly lost and it would be open to one party to take the benefit under the settlement and then to question the same on the ground of mistake without having the settlement set aside. In the circumstances, in the instant case since the dispute or difference was finally settled and payments were made as per the settlement, it was not open to the respondent unilaterally to treat the settlement as non est and proceed to invoke the Arbitration clause." (Para
3)
5.6 The principles came to be highlighted and summarized by
the Supreme Court also in Gujarat Composite Ltd. vs. A.
Infrastructure Ltd. [AIR 2023 SC (Civil) 1654]. The discussion is
found in paragraphs 17, 18, 19 and 20 of the judgment which
confirmed the view taken by the Gujarat High Court [AIR 2018
Gujarat 142]. The Delhi High Court in Larsen and Toubro Ltd. vs.
IREO Victory Valley Pvt. Ltd. which was C.S (Comm)
No.534/2023 decided on 24th April 2024, had an occasion to
address the issue which considered the aforementioned decisions
of the Apex Court to conclude that it is a settled legal position that if
- 16 -
a mutual settlement supercedes the original contract, the original
arbitration clause would not survive. It was stated that if there is
unilateral repudiation, in such eventuality, the arbitration clause
may survive depending upon the facts.
5.7 Whether the arbitration clause in earlier contract which may
have been substituted with another contract by the parties would
survive to operate for the purpose of obligation and disputes arising
out of the subsequent contract, is a question to be considered in
light of set of facts, having regard to the nature of the subsequent
agreement juxtaposed with the previous one, the intention of the
parties and whether the new contract introduced fresh rights and
obligations between the parties. It is always a question of
interpretation of contracts.
5.8 Reverting to the facts of the present case, as noted above,
between the parties there existed a Deed of Partnership dated 24th
June 2020 which was registered on 2nd July 2020. The said Deed
of Partnership contained provision for arbitration, which was clause
21 in the contract. In view of the disputes arising, navigating
through negotiation, the parties decided to enter into new
agreement dated 10th August 2022 wherein the defendant agreed
to pay sum of Rs.3,75,00,000/- in view of having failed to fulfill the
- 17 -
terms and conditions in the Partnership Deed. Both the partners-
the plaintiff and the defendant had agreed to put an end to the
partnership. The suit was filed on the basis of the said agreement
dated 10th August 2022.
5.9 The parties thus had earlier between them a partnership
contract subsisting. Both the plaintiff and defendant bear their
relationship as partners. The partnership business was set up with
terms and conditions arrived at attending to the partnership. The
defendant was unhappy and wanted to exist from partnership. He
offered payment of definite amount in lieu of doing away with the
partnership relationship. It was a dispute which was resolved by
entering into new agreement dated 10th August 2022. This
agreement was in place of the partnership agreement dated 22nd
June 2020.
6. The new subsequent agreement is reproduced in its relevant
portions,
"WHEREAS the First Party and Second Party herein had entered into a Deed or Partnership on 24.06.2020 at Mysuru City in the name and style 'M/s. Shree Service Station' having Firm Number: MYS-F43-2020-21 dated 02/07/2020 by the Office of the Registrar of Firms, Mysore.
- 18 -
WHEREAS, meanwhile the first party and Second party entered in to Memorandum of Understanding dated 10/01/2020, the First party has not fulfill his words/Conditions as per Partnership deed and Memorandum of understanding between first and second party. Now the both the parties have decided that they will exit from the Partnership upon the First Party fulfilling the terms and conditions as mutually agreed amongst themselves and deduced herein below;
01. The First Party has agreed to pay a sum of Rs.3,75,00,000/- (Rupees Three Crore Seventy Five Lakh only) to the Second Party before the end of 31st December, 2022 in following manner:-
(a) Rs.1,31,81,019/- (Rupees One Crore Thirty one Lakh Eighty one Thousand and Nineteen only) by 3 No's Cheques respectively each of Rs.43,93,673/- to the Account No. 002210100023140 of Shobha S Poojari, in Bharath Co Operative Bank, Malleshwaram branch, Bangalore.
(b) Rs. 2,37,65,373/- (Rupees Two Crore Thirty Seven Lakh Sixty five Thousand and Three Hundred seventy Three only) by 3 No's Cheques respectively each of Rs.79,21,791/- to the Account No. 002212100009243 of Shri Sagar, in Bharath Co Operative Bank, Malleshwaram branch, Bangalore.
(c) Rs.5,53,608/- (Rupees Five Lakh Fifty Three Thousand and Six Hundred Eight only) to the Account No. 002210100034678 of Ganesh S Poojari, in Bharath Co Operative Bank, Malleshwaram branch, Bangalore.
- 19 -
02. The Second Party upon receiving the sum of Rs.3,75,00,000/- (Rupees Three Crore Seventy Five Lakh only) from the First Party towards full and final settlement shall retire/exit from 'M/s. Shree Service Station', partnership and shall execute such documents as required to give effect to the same.
03. The parties herein have agreed that the sum agreed to be paid by the First Party to the Second Party includes the Capital brought in by the Second Party. It is mutually agreed that the sum of Rs.3,75,00,000/- (Rupees Three Crore Seventy Rive Lakh only) is a consolidated final settlement amount.
04. It is further agreed that irrespective of profit of loss of the Partnership, the First Party shall pay the Second Party the amount as agreed herein in full and final settlement.
05. It is further agreed by the parties that each partner shall mean and include all their heir/s, successor, representatives, executors and assignees.
06. If the first party is failed to fulfill the conditions of this agreement that the Second Party is entitled to specifically enforce this agreement under the provisions of Specific Relief Act 1963 before the competent Authority/Court.
In witness whereof both the parties have affixed their signatures to this Agreement on the day & place as mentioned herein above."
6.1 It would be noticed from the aforesaid agreement and terms
entered into between the parties that it was a memorandum of
understanding which was reached at in view that the first party that
- 20 -
is defendant was unable to fulfill the conditions of the partnership
deed. It was recited and agreed, as reflected in the said
agreement, that the parties would exit from the partnership. It is in
this light that the first party agreed to pay a definite sum to the
second party. This agreement marked termination of partnership
and obliteration of the terms and conditions which operated
amongst the partners in the partnership agreement.
6.1.1 It was agreed that irrespective of profit or loss of the
partnership, the second party shall pay the amount as above in full
and final settlement. It was a condition that second party upon
receiving the amount paid towards full and final settlement shall
retire and exit from the partnership which was in the name of 'M/s.
Shree Service Station' and that necessary documents shall be
executed to give effect to such arrangement of exit.
6.2 The conditions read as they stood in the fresh agreement,
evidently evinced the intention of the parties to put an end to the
partnership agreement. It had the effect of dissolution of
partnership, one of the two partners exiting from the partnership.
The partnership was broken by mutual agreement and fresh
obligations and an entirely new obligation of payment of money by
one party to another was settled.
- 21 -
6.3 The jural relationship which existed previously between the
parties as the partners, came to an end with execution of a fresh
contract. With the jural relationship having been put to an end by
new contract, the partnership agreement perished. All the terms
and conditions of the partnership deed stood rescinded. The said
contract of partnership dated 22nd June 2020, having been
replaced by new agreement dated 10th August 2022, did not
survive on facts and in law.
6.4 Consequentially, the arbitration clause which was contained
in the partnership agreement lost its existence. It perished with
discontinuance of the partnership agreement. It was not carried in
the new contract, nor there was an intention of the parties to carry
forward the same. The agreement dated 10th August 2022 was in
the nature of novation whereby the parties rescinded mutual rights
and obligations as partners of the partnership firm, to be governed
by fresh counts of rights and obligations. The exit of partnership
was indeed coupled with exit of arbitration clause which stood in
the forsaken partnership deed only. Invocation of Section 8 of the
Arbitration and Conciliation Act, 1996 and prayer on that basis to
refer the suit dispute to arbitration was misconceived. There
existed no arbitration clause to be taken recourse to.
- 22 -
6.5 For all the aforesaid reason, the judgment and order of
commercial court below refusing the prayer of the defendant to
refer the suit dispute for arbitration was eminently proper and legal.
7. The present appeal fails and stands dismissed.
Sd/-
(N.V. ANJARIA) CHIEF JUSTICE
Sd/-
(K.V. ARAVIND) JUDGE
KPS
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!