Citation : 2025 Latest Caselaw 11463 Kant
Judgement Date : 16 December, 2025
-1-
NC: 2025:KHC:53608
CMP No. 250 of 2023
HC-KAR
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 16TH DAY OF DECEMBER, 2025
BEFORE
THE HON'BLE MR. JUSTICE SURAJ GOVINDARAJ
CIVIL MISC. PETITION NO. 250 OF 2023
BETWEEN
SIEMENS FACTORING PRIVATE LIMITED
PLOT NO 02, SECTOR NO 2
KHARGHAR NODE, NAVI MUMBAI
RAIGARH - 410210
REP BY ITS AUTHORISED SIGNATORY
.... PETITIONER
(BY SRI PRAMOD NAIR, LEARNED SENIOR COUNSEL FOR
SRI. HANSI ZULFIQUAR AHMED NISAR AHMED., ADVOCATE)
AND
ABB INDIA LIMITED
HAVING ITS OFFICE AT DISHA,
Digitally signed 3RD FLOOR, PLOT NO 5 AND 6,
by SHWETHA
RAGHAVENDRA 2ND STAGE,
Location: HIGH PEENYA INDUSTRIAL AREA IV, PEENYA,
COURT OF BENGALURU - 560058
KARNATAKA
REP BY ITS MANAGING DIRECTOR
.... RESPONDENT
(BY SRI ARUN KUMAR, LEARNED SENIOR COUNSEL FOR SRI. KEERTI KUMAR D. NAIK., ADVOCATE)
THIS CMP IS FILED UNDER SECTION 11(5) OF THE ARBITRATION AND CONCILIATION ACT, 1996 PRAYING TO APPOINT MR. TUSHAR SHAH, ADVOCATE OR ANY OTHER JUDICIAL PERSON TO
NC: 2025:KHC:53608
HC-KAR
ACT AS AN ARBITRATOR FOR THE EFFICACIOUS AND SPEEDY RESOLUTION OF THE DISPUTES BETWEEN THE PARTIES AS PROVIDED UNDER CLAUSE 16 OF THE SAID AGREEMENT DATED 28TH JUNE 2021, VIDE ANNEXURE-A AND ETC.
THIS CMP COMING ON FOR ORDERS AND HAVING BEEN RESERVED FOR ORDERS ON 21.11.2025, THIS DAY, THE COURT PRONOUNCED THE FOLLOWING:
CORAM: HON'BLE MR. JUSTICE SURAJ GOVINDARAJ
CAV ORDER
1. The Petitioner is before this Court seeking for the
following reliefs:
"1. This Hon'ble Court be pleased to appoint Mr. Tushar Shah, Advocate or any other judicial person to act as an Arbitrator for the efficacious and speedy resolution of the disputes between the parties as provided under Clause 16 of the Said Agreement dated 28th June 2021, vide Annexure-A.
2. Pass any other order that this Hon'ble Court may deem fit in the interest of justice."
2. The Respondent, being in the business of automation
technology that manufactures market transformers,
had entered into a master rental agreement dated
28.06.2021 with Translab Equipment Solution Private
Limited ('Translab' for short) for providing parking
NC: 2025:KHC:53608
HC-KAR
services/deliverables and equipment at the
Respondent's location on a rental basis as per the
terms and conditions contained in the said
Agreement, which inter alia detailed the services to
be provided by Translab. There being various
services to be provided by Translab, the Respondent
was required to make payment of the amounts as
indicated in the rental schedule to the Agreement.
3. An amended agreement came to be executed on
09.07.2021, deleting Clause 12(ii) of the original
Agreement, which provided an option to the
Respondent to terminate the Agreement at any time,
either partially or only providing 90 days' notice to
Translab. Subsequent thereto, Clause 14 of the
Agreement providing for assignment, a term sheet
came to be issued by the Petitioner to Translab,
agreeing to take over the receivables of Translab,
with the obligations of delivering service continuing
to be with Translab.
NC: 2025:KHC:53608
HC-KAR
4. The said term sheet was forwarded to the
Respondent and the Respondent had accepted the
same wherein it is categorically stated that the
Petitioner as the assignee assumes none of the
obligations of Translab and/or the supplier of the
equipment, and the Respondent would continue to
retain all its rights and remedies under the master
rental Agreement against Translab and/or the
supplier of the equipment. It is only the amounts
receivable under the master rental Agreement which
are assigned to the Petitioner.
5. Alleging that the Respondent did not make payment
of the due amount, the Petitioner invoked the
Arbitration Clause under the master rental
Agreement, in terms of Clause 16 thereof, which is
reproduced hereunder for easy reference:
"16. Governing Law & Dispute Resolution: This Agreement shall be subject to the exclusive jurisdiction of the courts at Bengaluru and is governed by the laws of India. Any dispute or difference arising out of or in connection with this
NC: 2025:KHC:53608
HC-KAR
Agreement, which cannot be settled amicably within thirty (30) calendar days from the notification of such dispute by one Party to the other Party, shall be finally settled under the Indian Arbitration and Conciliation Act, 1996 and its amendments in effect by sole arbitrator appointed mutually by parties. The place of arbitration shall be Bengaluru, India. The language of the arbitration shall be English. The final award shall be binding Parties. Parties shall fully comply and adhere with the applicable anti- corruption laws and under this Agreement."
6. A notice came to be issued on 21.02.2023, invoking
the Arbitration Clause and nominating an Arbitrator.
The said notice was replied to by the Respondent,
stating that since there are only the receivables
which were assigned, the entire Agreement not
having been assigned, the arbitration agreement
cannot be said to have been assigned, and there is
no Arbitration agreement.
7. A detailed reply was also issued on 15.03.2023
stating that Translab had not commissioned and
handed over the project; without such a handover,
bills had been raised by Translab. There is complete
non-performance on the part of Translab.
Deficiencies having been pointed out in the work of
NC: 2025:KHC:53608
HC-KAR
Translab, Translab had not rectified them. Finally,
Translab has not complied with the obligation, the
Respondent claimed that the Agreement between the
Respondent and Translab had been terminated and
as such, there was no requirement to appoint an
Arbitrator. It is in that background that the Petitioner
had approached this Court seeking the aforesaid
reliefs.
8. Notice having been issued, the Respondent has
entered appearance and filed his statement of
objections.
9. Sri Pramod Nair, learned Senior Counsel appearing
for the Petitioner, would submit that;
9.1. There being an assignment of receivables under
the Agreement and the term sheet having been
endorsed by the Respondent, the arbitration
agreement would also be binding on the parties
NC: 2025:KHC:53608
HC-KAR
and as such, the Petitioner would be entitled to
invoke the Arbitration Clause.
9.2. His submission is that the receivables being
under the master rental Agreement, the
Arbitration Clause under the master rental
Agreement would enure to the benefit of the
Petitioner even though the Respondent claims
that the Agreement with the Translab has been
terminated. In view of the amended Agreement
deleting Clause 12 (ii), there is no right vested
with the Respondent to terminate the
Agreement; that issue is a matter of fact which
should be decided by an Arbitrator.
9.3. Respondent having availed of service from
Translab, emails had been issued by the
Petitioner to the Respondent, calling upon the
Respondent to make payment of the due
amounts, the amounts not having been paid,
NC: 2025:KHC:53608
HC-KAR
there is an arbitrable dispute between the
parties, which was not amicably settled within
30 days, and as such, the Petitioner has
invoked the Arbitration Clause.
9.4. He has referred to various decisions, namely
the decision in Lifeforce Cryobank Sciences
V. Cryoviva Biotech (P) Ltd.,1 the decision in
DLF Power Ltd., V. Mangalore Refinery &
Petrochemicals Ltd.,2 the decision in
Siemens Factoring Pvt. Ltd., V. Future
Enterprises Pvt. Ltd.,3 the decision in
Bestech India (P) Ltd., V. MGF
Developments Ltd.,4 and the decision in Cox
& Kings Ltd., V. SAP India (P) Ltd.5
9.5. The sum and substance of all those decisions
which have been relied upon by Sri Pramod
2024 SCC Online SC 3215
2016 SCC Online Bom 5069
Commercial Arbitration Application.No.174/2022
2009 SCC Online Delhi 698
(2024) 4 SCC 1
NC: 2025:KHC:53608
HC-KAR
Nair, learned Senior Counsel for the Petitioner
is to urge that there being an assignment of the
Agreement, the Arbitration Clause would also
stand assigned, and therefore, the Petitioner
would be entitled to invoke the Arbitration
Clause. I am not extracting the relevant
paragraphs of judgments due to the orders that
I propose to pass, so as not to bulk the record.
10. Sri Arun Kumar, learned Senior Counsel for the
Respondent, would submit that;
10.1. The Agreement between the Respondent and
Translab has been terminated on account of
Translab not having rendered any services.
Hence, the question of making payment of any
monies would not arise.
10.2. His submission is also that, only receivables
which had been assigned, the entire Agreement
has not been assigned, and therefore, the
- 10 -
NC: 2025:KHC:53608
HC-KAR
Petitioner cannot claim assignment of the
Arbitration Clause to invoke it.
10.3. He relies upon the decision of the Hon'ble Apex
Court in Hindustan Petroleum Corporation
Ltd., Vs. BCL Secure PRmises Pvt. Ltd.6,
more particularly, para Nos.35 and 38 thereof,
which are reproduced hereunder for easy
reference:
"35. This does not mean that where the Referral Court finds prima facie a party is not a veritable party still the matter is left to the Arbitral Tribunal. To hold so, would relegate the Referral Court to the status of a monotonous automation. Further, to countenance such an extreme proposition would lead to disastrous consequences, where absolute strangers could walk into the Referral Court and contend that the matter has to perforce go to the Arbitral Tribunal for a decision on the veritable nature of the party. We are not prepared to accept such an extreme proposition.
38. Apart from the above, not only has the respondent not shown any consent for assignment as required under clause 3.17 of the tender document, nothing even prima facie has been shown to establish that there was any semblance of an intent to effect legal relationship between the respondent and the party originally granting the contract
- 11 -
NC: 2025:KHC:53608
HC-KAR
and/or to indicate that the respondent was a veritable party."
10.4. By relying on BCL Secure Premises case, his
submission is that Section 11 Court would have
to decide on whether a person is a party to an
arbitration or not, and the same cannot be left
to be decided by the Arbitral Tribunal in all the
cases. Unless there is a legal relationship which
is established, a party cannot be referred to an
arbitration.
11. Heard Sri Pramod Nair, learned Senior Counsel for
the Petitioner, Sri Arun Kumar, learned Senior
Counsel for the Respondent and perused papers.
12. This is a peculiar case and would have to be decided
on the facts of the matter. There can be no dispute
about the principles laid down in the decisions relied
upon by Sri Pramod Nair, learned Senior Counsel for
the Petitioner. Admittedly, a master rental
- 12 -
NC: 2025:KHC:53608
HC-KAR
agreement was entered into between Translab and
Respondent. It is only the receivables under said
Agreement which are assigned by Translab in favour
of the Petitioner. The obligations under the
Agreement for which the amounts were to be paid by
the Respondent continue to be with that of Translab
and/or the suppliers that is to say that without
performance of the obligations by Translab, there will
be no receivables required to be collected by the
Petitioner.
13. The contention of the Respondent is that the
Agreement has been terminated. The contention of
the Petitioner is that the Agreement cannot be
terminated. Be that as it may, the aspect of
continuance of the services and/or whether the
Agreement is terminable or not, cannot be for the
Petitioner to contend inasmuch as what has been
assigned is only the receivables and the service
contract continued bwtween Translab and the
- 13 -
NC: 2025:KHC:53608
HC-KAR
Respondent. Admittedly, Translab is not a party to
these proceedings. No notice has been issued by
Translab, nor has any action been taken by the
Petitioner along with Translab. The said conduct,
apart from being suspicious, only reinforces the
situation that the Petitioner intends to claim
payments for the works allegedly done by Translab,
when the Respondent contends that Translab has not
done those works, suffice it to say that without the
Petitioner establishing that Translab has done the
work, the question of the Petitioner claiming any
amount should not arise.
14. Translab not being a party to these proceedings, I
am of the considered opinion that in the absence of
Translab, the Petitioner cannot claim any amounts or
initiate any proceedings. More so, when the
Agreement is alleged to have been terminated by the
Respondent and Translab has not taken any action in
relation thereto.
- 14 -
NC: 2025:KHC:53608
HC-KAR
15. The question of the Petitioner claiming that the
Agreement cannot be terminated and continues to be
enforced is not sustainable without Trabslab
asserting that by challenging the termination, what is
to be taken into consideration is that it is only the
receivables which have been assigned to the
Petitioner, the other parts of the Agreement have not
been assigned. Without those parts of the Agreement
being performed, there would be nothing for the
Petitioner to receive by way of assignment.
16. These factors going to the root of the matter. Hence,
I am of the considered opinion that these peculiar
facts would require this Court to consider these
aspects before appointment of an Arbitrator and if
these aspects are considered, it would only result in
an irresistible conclusion that without Translab, no
arbitral proceedings can be maintained and no claim
can be made by the Petitioner. For that reason, no
arbitration notice having been issued to Translab,
- 15 -
NC: 2025:KHC:53608
HC-KAR
requirement of Section 21 not having been complied
with, Translab cannot be subsequently made a party
to the arbitral proceedings. As such, the invocation of
the arbitral clause only against the Respondent
without Translab being a party cannot be sustained.
In that background, I am of the opinion that no
Arbitrator can be appointed, as such, the petition
stands dismissed.
SD/-
(SURAJ GOVINDARAJ) JUDGE
KTY List No.: 2 Sl No.: 1
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!