Citation : 2024 Latest Caselaw 28022 Kant
Judgement Date : 23 November, 2024
1
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 23RD DAY OF NOVEMBER, 2024 R
BEFORE
THE HON'BLE MR. JUSTICE H.P. SANDESH
M.F.A. NO.2859/2024 (AA)
BETWEEN:
NATIONAL HIGHWAYS AUTHORITY OF INDIA
PROJECT IMPLEMENTATION UNIT-MANGALORE
DOOR NO.3-29, "BETHEL", THARETHOTA,
NEAR PUMPWELL (NH-66),
MANGALORE - 575 002
REP. BY ITS THE PROJECT DIRECTOR.
... APPELLANT
(BY SRI PRAKASHA V. ANGADI, ADVOCATE)
AND:
1. SRI. ABDUL GAFOOR KOTEKAR
S/O HAJI SHEIK HUSSAIN SAHEB
R/AT FLAT NO.703, ORCHARD APARTMENTS
ARYA SAMAJ ROAD, BALMATTA,
MANGALURU.
2. THE ARBITRATOR AND DEPUTY COMMISSIONER
D.K. DISTRICT, MANGALORE-575 001.
3. THE SPECIAL LAND ACQUISITION OFFICER
AND COMPETENT AUTHORITY,
NHAI, N.G.O.S BUILDING
MINI VIDHANA SOUDHA COMPOUND
MANGALURU-575 001. ... RESPONDENTS
(BY SRI VISHWAJITH RAI M., ADVOCATE FOR R1;
SRI GOPAL KRISHNA SOODI, AGA FOR R2 AND R3)
2
THIS M.F.A. IS FILED UNDER SECTION 37(1)(c) OF THE
ARBITRATION AND CONCILIATION ACT, 1996, AGAINST THE
JUDGMENT DATED 06.01.2024 PASSED IN A.P.NO.89/2022 ON
THE FILE OF THE I ADDITIONAL DISTRICT AND SESSIONS
JUDGE, MANGALURU, DISMISSING THE PETITION FILED U/S.34
OF ARBITRATION AND CONCILIATION ACT R/W ORDER 7 RULE 1
OF CPC AND ETC.
THIS APPEAL HAVING BEEN HEARD AND RESERVED FOR
JUDGMENT ON 08.11.2024 THIS DAY, THE COURT
PRONOUNCED THE FOLLOWING:
CORAM: HON'BLE MR JUSTICE H.P.SANDESH
CAV JUDGMENT
This miscellaneous first appeal is filed challenging the
order dated 06.01.2024 passed in A.P.No.89/2022 by the I
Additional District and Sessions Judge, Mangaluru and
consequently set aside the arbitral award passed in
No.C.DIS.ARB(2). NH.LAQ.CR - 127/2017-18 DATED 19.04.2022
passed by respondent No.2 for enhancing the compensation at
the rate of Rs.1,28,800/- per cent.
2. Heard the learned counsel appearing for
therespective parties.
3. The factual matrix of the case is that a notification
came to be issued for acquiring the land for the purpose of
widening of National Highway No.66 at Kotekar village under
Section 3A(1) of the National Highways Act (for short 'NH Act')
on 08.02.2010 and the Special Land Acquisition Officer passed
the award determining the compensation in respect of the land
bearing Sy.No.24/5B measuring 546.34 square meters
residential converted land situated in Kotekar village, Mangaluru
taluk for which compensation was determined at Rs.1,00,000/-
per cent considering the same as dry land. The respondent
herein filed a petition under Section 3G(5) of the NH Act to the
Deputy Commissioner, D.K., Mangaluru being aggrieved by the
determination of compensation of Rs.1,00,000/- per cent.
Respondent No.2 i.e., the Arbitrator-cum-Deputy Commissioner
of D.K., Mangaluru, vide order dated 19.04.2022, determined
the compensation as Rs.1,28,800/- per cent considering the land
as residential in nature with 9% interest as applicable under
Section 3H(5) of the NH Act and with all benefits admissible
under the provisions of RFCTLARR Act, 2013. The appellant
herein has filed the Arbitration Petition before the I Additional
District and Sessions Judge, Mangaluru challenging the arbitral
award passed by respondent No.3 and the District and Sessions
Judge, dismissed the said petition vide order dated 06.01.2024.
Being aggrieved by the said order, the present appeal is filed
before this Court.
4. The learned counsel for the appellant would
vehemently contend that inspite of the award has been passed
considering the material available on record, Arbitrator has
committed an error in enhancing the compensation from
Rs.1,00,000/- per cent to Rs.1,28,800/- per cent holding that
the land acquired has good potential for future development and
the said approach is erroneous. It is also contend that the
Arbitrator under the provisions of Arbitration and Conciliation Act
is required to exercise the powers as conferred under Section
3G(7) of the NH Act, 1956 and extracted the said provisions. It
is also contend that the competent authority by considering the
relevant material passed the well reasoned award on 17.08.2011
which does not call for interference. The District Judge has erred
in not taking note of the said provision. The Arbitrator has also
misinterpreting the judgment passed by the Apex Court and the
ordinance/notification issued by the Government of India
No.S.O.2368(E) dated 28.08.2015 by which the provisions of
RFCTLARR Act, 2013 are made applicable with effect from
01.01.2015 as such the Arbitrator has passed the impugned
award enhancing the compensation by making the provisions of
said Act retrospectively to the land acquired without jurisdiction
and authority of law.
5. The counsel also would vehemently contend that the
land was acquired by the SLAO and CA as per notification dated
08.02.2010 which was published under Section 3A of the NH Act
and award was passed on 17.08.2011 by following the provisions
of the NH Act. However, the Arbitrator passed an impugned
award enhancing compensation by directing the respondent to
recalculate the compensation under the provisions of RFCTLARR
Act, 2013 which came into force with effect from 01.01.2015 and
the Government of India issued notification that the provisions of
Schedule - I, II and III of RFCTLARR Act are made applicable
with effect from 01.01.2015 and passed the impugned order
directing to recalculate the compensation and pay all the
admissible benefits under the said Act and hence, Arbitrator
committed an error in passing such an order and ought not to
have invoke the provisions of RFCTLARR Act. The counsel for the
appellant also would vehemently contend that the Arbitrator has
failed to give reasons as held by the Apex Court that a quasi-
judicial authority is required to assign reasons for passing the
order and the very approach of the Arbitrator is erroneous and
no reasons are assigned and Arbitrator has lost sight of the fact
that compensation amount already paid and determined under
Section 3H(5) of the National Highways Act, 1956.
6. The District Judge also when the said grounds has
been raised, also failed to consider the material available on
record and committed an error in accepting the reasons of the
Arbitrator and also the scope of Section 34(2) of the Act and the
power exercised by the Arbitrator is against the provisions of the
Arbitration and Conciliation Act. The counsel also would
vehemently contend that Section 3(J) is clear that the new
enactment is not applicable for National Highways Act and
Section 3(J) excluding applicability of Land Acquisition Act, 1894
resulting in non-grant of solatium and interest in respect of lands
acquired under the NH Act. Inspite of it, the District Judge
committed an error and misunderstood the judgment of the
Apex Court. Hence, it requires interference of this Court.
7. The learned counsel for the respondent in his
arguments would vehemently contend that, the Trial Court has
not committed an error in dismissing the application filed under
Section 34 of the Arbitration and Conciliation Act and explanation
to Section 34 is very clear that for the avoidance of doubt, the
test as to whether there is a contravention with the fundamental
policy of Indian law shall not entail a review on the merits of the
dispute. The counsel would vehemently contend that though
properties were acquire in the year 2010, award was passed in
the year 2011 and it is a continuous proceedings and arbitration
petition was disposed of in the year 2022. The District Judge
also taken note of the judgment of the Apex Court and also
taken note of the notification of the Union of India and opined
that only compensation was paid in part, not entire
compensation and hence, rightly comes to the conclusion that
new enactment of 2013 is applicable to the case on hand. The
counsel in support of his arguments relied upon the judgment of
the Apex Court reported in (2019) 9 SCC 304 in the case of
UNION OF INDIA AND ANOTHER vs TARSEM SINGH AND
OTHERS. The counsel referring this judgment would contend
that Apex Court, in this judgment held that Section 3-J excluding
applicability of LA Act, 1894 resulting in non-grant of solatium
and interest in respect of lands acquired under National
Highways Act, which were available if lands were acquired under
Land Acquisition Act, held, violative of Article 14 of the
Constitution of India and the impugned judgment of the High
Court affirmed.
8. The counsel also brought to notice of this Court
paragraph 13 of the said judgment wherein a discussion was
made with regard to Fourth Schedule of the New Act to be read
along with Section 105 expressly includes under item 7, the
National Highways Act, 1956. In item 9, this schedule also
includes the Requisitioning and Acquisition of Immovable
Property Act, 1952. By a Notification dated 28.08.2015 issued
under Section 105 read with Section 113 of the 2013 Act, it is
provided that the 2013 Act compensation provisions will apply to
acquisitions that take place under the National Highways Act.
The result is that both before the 1997 Amendment Act and after
the coming into force of the 2013 Act, soltium and interest is
payable to landowners whose property is compulsorily acquired
for the purposes of National Highways. The counsel also brought
to notice of this Court a details discussion made by the Apex
Court in the aforesaid judgment particularly brought to notice of
this Court paragraph 48 of the judgment wherein also discussion
was made with regard to ordinance as well as the notification
have applied the principle contained in Nagpur Improvement
Trust'scase reported in (1973) 1 SCC 500 and as the Central
Government has considered it necessary to extend the benefits
available to landowners generally under the 2013 Act to similarly
placed landowners whose lands are acquired under the 13
enactments specified in the Fourth Schedule, the National
Highways Act being one of the aforesaid enactments. The
counsel also brought to notice of this Court paragraph 52 of the
said judgment wherein it is held that Section 3-J is, to this
extent, violative of Article 14 of the Constitution of India and,
therefore, declared to be unconstitutional. The counsel referring
this judgment would vehemently contend that contention of the
appellant counsel that Section 3-J is clear that same is not
applicable cannot be accepted.
9. Having heard the learned counsel appearing for the
respective parties and also the grounds which have been urged
in this appeal and the principles laid down in the judgment
referred supra, the point that would arise for the consideration of
this Court are:
1. Whether the I Additional District and Sessions Judge committed an error in confirming the order passed by the Arbitrator in applying the provisions of RFCTLARR Act, 2013 in awarding the compensation?
2. What order?
Point No.1:
10. Having heard the learned counsel appearing for the
respective parties and also on perusal of the material available
on record, it is not in dispute that National Highways has issued
notification on 08.02.2010 for acquiring the property of the
respondent. It is also not in dispute that the Land Acquisition
Officer has passed the award determining the compensation in
respect of the subject matter of the acquired land determining
the compensation as Rs.1,00,000/- per cent. The Arbitrator
revised the same enhancing to Rs.1,28,800/- per cent. The
contention of the appellant that the Arbitrator committed an
error in enhancing the compensation and fails to take note of
Section 3G(7) of the NH Act that the Arbitrator while
determining the amount under sub-section (1) or sub-section
(5), shall take into consideration the market value of the land on
the date of publication of the notification under Section 3A and
also the damage, if any, sustained by the person interested at
the time of taking possession of the land, by reason of the
acquisition injuriously affecting his other immovable property in
any manner and the competent authority considered the above
relevant material while passing the award on 17.08.2011. It has
to be noted that the District Judge, while considering the
material available on record taken note of the fact held that the
land acquired was converted land and the same was converted
for non-agricultural purpose that is for residential purpose and
while determining the compensation by Special Land Acquisition
Officer taken note of the fact that it is a dry agricultural land and
the same is erroneous. The District Judge also while considering
the material available on record taken note of Section 3G(7) of
the NH Act in paragraph 24 and also taken note of various
factors and law and calculation for compensation made by the
authority has been rectified by the Arbitrator and the same is
observed in paragraph 25. In paragraph 26 also discussed in
detail regarding passing of an order by the Arbitrator that is in
respect of awarding of compensation.
11. The other contention of the appellant's counsel is
that the provisions of RFCTLARR Act, 2013 would not apply to
the acquisition in question and Arbitrator ought not to have
invoked the same and District Judge also taken note of the fact
that Land Acquisition Act, 1894 was repealed and new
enactment brought in the year 2013 and came into force on
01.01.2014 and the object for bringing new enactment was also
discussed in paragraph 28 and also discussed Section 26 of the
2013 Act criteria to be adopted for assessing the market value
which has been dealt in paragraph 29. In paragraph 31 also
taken note of Section 105(1) of the 2013 Act wherein a provision
is made that provisions of 2013 Act shall not apply to the
enactment specified in Fourth Schedule subject to the provisions
of sub-section (3) of Section 105. The District Judge also taken
note that the National Highways Act, 1956 finds mention in
Fourth Schedule and also observation is made that under sub-
section (3) of Section 105 within one year from the date of
commencement of the 2013 Act, the Central Government by a
notification could make applicable the beneficial provisions of the
2013 Act with regard to determination of compensation in
accordance with First, Second and Third Schedule to the
enactment specified in Fourth Schedule and comes to the
conclusion that the application of new Act shall be made with
exceptions or modification that it may not result in reduction of
compensation or dilution of the provisions of the 2013 Act. The
District Judge also in detail discussed Ordinance No.9 of 2013
Act was promulgated on 31.12.2014 extending the provisions of
the 2013 Act to the cases of land acquisition under the
enactments specific in Fourth Schedule to the 2013 Act. To give
continuity, Ordinance No.4 of 2015 dated 03.04.2015 and
Ordinance No.5 of 2015 dated 30.05.2015 were promulgated.
Ordinance No.5 of 2015 lapsed on 31.08.2015. The order dated
28.08.2015 was issued by the Central Government exercising
power under Section 113 of 2013 Act. The order came into
effect from 01.09.2015. The Central Government extended the
benefit of 2013 Act with regard to determination of
compensation, rehabilitation and settlement to the land acquired
under enactment mentioned in Fourth Schedule to 2013 Act.
The object of this was to extent the benefit of the 2013 Act
uniformly to the land acquired under the enactments in Fourth
Schedule of 2013 Act. It is also very clear that ordinances are
issued only with an intention to clarify the confusion created by
the circulars. It was clarified by the comprehensive guidelines
that Section 24 of the 2013 Act is not applicable to the
acquisition under the National Highways Act. Clause 4.6 (i) and
(ii) elucidated that the relevant date for determination of the
market value is the date on which notification under Section 3A
of 1956 Act was published. Sub-clause (iii) of clause 4.6 deals
with applicability of First, Second and Third Schedule appended
to the 2013 Act. Sub-clause 4.6(iii) has three clauses. Clause
(a) provides two instances in which compensation is to be paid in
accordance with First Schedule to the 2013 Act. In all cases
where award was not announced under Section 3G of 1956 Act
till 31.12.2014 or where the award is announced but
compensation not paid as on 31.12.2014 in respect of majority
of land holding under acquisition. Sub-clause (b) deals with
cases where the award under Section 3G of 1956 Act was
announced before 01.01.2015 but the full amount of award was
not deposited by the acquisition agency with CALA. In such
cases also, the compensation is to be determined in accordance
with First Schedule with effect from 01.01.2015. As per sub-
clause (c) where the process of land acquisition is deemed to be
complete and settled, such cases are not to be reopened. The
pre-requisites under sub-clause (c) are that on or before
31.12.2014 the award under Section 3G of 1956 Act was
announced by CALA, the amount deposited by the acquiring
agency CALA and compensation paid to the land owners in
respect of majority of land holdings under acquisition. The
District Judge also while considering the applicability of new
enactment also discussed in detail and in view of clause-
4.6(iii)(a) of the guidelines issued by the Ministry of Road
Transport and Highways dated 28.12.2017, if award had been
announced but compensation had not been paid in respect of
majority of the land holdings under acquisition as on
31.12.2014, the compensation would be payable in accordance
with First Schedule of the RFCTLARR Act 2013.
12. The District Judge having taken note of these
aspects and also taken note of the case on hand held that land
was acquired in the year 2010 but award was passed in the year
2011 and also not stated by the appellant that on what date,
they made the compensation and the National Highway Authority
is in possession of all documents pertaining to acquisition. When
they have not produced the documents for having paid the
compensation in entirety and also they did not take up the
specific contention that the amount has been paid, the authority
was directed to furnish the date of payment, but they did not
provide the same. Hence, invoked Section 114(g) of the Indian
Evidence Act and is not produced, would, if produced, be
unfavourable to the person who withholds it. Having taken note
of the said fact in consideration comes to the conclusion that
RFCTLARR Act are applicable to the case on hand. In the case
on hand also appellant has not placed any documents before this
Court, even for having paid the entire compensation.
13. It is also important to note that the District Judge
also while passing an order taken note of the decision reported
in (2019) 9 SCC 304 in the case of UNION OF INDIA vs
TARSEM SINGH AND OTEHRS and particularly taken note of
paragraphs 40 and 41 regarding invoking of new enactment.
14. The counsel for the respondent also brought to
notice of this Court paragraph 13 of the judgment which reads
as follows:
"13. The First Schedule to the said Act provides that solatium equivalent to 100% of the market value multiplied by various factors, depending on whether the land is situated in a rural or urban area, constitutes minimum compensation package to be
given to those whose land is acquired. The Fourth Schedule to this Act, to be read along with Section 105, expressly includes under Item 7, the National Highways Act, 1956. In Item 9, this Schedule also includes the Requisitioning and Acquisition of Immovable Property Act, 1952. By a Notification dated 28-8-2015 issued under Section 105 read with Section 113 of the 2013 Act, it is provided that the 2013 Act compensation provisions will apply to acquisitions that take place under the National Highways Act. The result is that both before the 1997 Amendment Act and after the coming into force of the 2013 Act, solatium and interest is payable to landowners whose property is compulsorily acquired for purposes of National Highways. This is one other very important circumstance to be borne in mind when judging the constitutional validity of the 1997 Amendment Act for the interregnum period from 1997 to 2015."
(emphasis supplied)
15. Having read this paragraph 13, it is very clear that
the Apex Court discussed the provision of Section 105 as well as
taken note of Fourth Schedule to the Act and item 9 of the
Schedule also includes the Requisitioning and Acquisition of
Immovable Property Act, 1952 so also inclusion of National
Highways Act. Hence, it is clear that the National Highways
Authority also included if any acquisition is made.
16. The Apex Court also in detail discussed with regard
to Article 14 of the Constitution of India that there cannot be any
discrimination and discussed in paragraph 25 and 26 and also
even discussed the judgment of Nagpur Improvement Trust's
case referred supra regarding discrimination is concerned and
comes to the conclusion that if any acquisition, there cannot be
any discrimination. The counsel for the respondent also brought
to notice of this Court paragraph 48 of the said judgment
wherein once again the judgment of Nagpur Improvement
Trust's case was discussed in detail and held that new
enactment as well as the Central Government also issued the
notification to extend the benefits available to the landowners
generally under 2013 Act similarly, whose lands are acquired
under 2013 enactment specified in the Fourth Schedule and also
an observation is made that NH Act being one of aforesaid
enactments and also observation is made that this being the
case it is clear that the Government has itself accepted that the
principle of Nagpur Improvement Trust's case would apply to
acquisitions which take place under the National Highways Act
and that solatium and interest would be payable under the 2013
Act to persons whose lands are acquired for the purpose of
National Highways as they are similarly placed to those
landowners whose lands have been acquired for other public
purposes under the 2013 Act.
17. This Court would like to extract the very paragraph
48 of the said judgment which reads as follows:
"48. It is thus clear that the Ordinance as well as the notification have applied the principle contained in Nagpur Improvement Trust v. Vithal Rao, (1973) 1 SCC 500, as the Central Government has considered it necessary to extend the benefits available to landowners generally under the 2013 Act to similarly placed landowners whose lands are acquired under the 13 enactments specified in the Fourth Schedule, the National Highways Act being one of the aforesaid enactments. This being the case, it is clear that the Government has itself accepted that the principle of Nagpur Improvement Trust would apply to
acquisitions which take place under the National Highways Act, and that solatium and interest would be payable under the 2013 Act to persons whose lands are acquired for the purpose of National Highways as they are similarly placed to those landowners whose lands have been acquired for other public purposes under the 2013 Act. This being the case, it is clear that even the Government is of the view that it is not possible to discriminate between landowners covered by the 2013 Act and landowners covered by the National Highways Act, when it comes to compensation to be paid for lands acquired under either of the enactments. The judgments delivered under the 1952 Act as well as the Defence of India Act, 1971, may, therefore, require a re-look in the light of this development. [The Defence of India Act, 1971, was a temporary statute which remained in force only during the period of operation of a proclamation of emergency and for a period of six months thereafter -- vide Section 1(3) of the Act. As this Act has since expired, it is not included in the Fourth Schedule of the 2013 Act.] In any case, as has been pointed out hereinabove, Union of India v. Chajju Ram, (2003) 5 SCC 568, has been referred to a larger Bench. In this view of the matter, we are of the view that the view
of the Punjab and Haryana High Court in Union of India v. Tarsem Singh, 2018 SCC OnLine P&H 6036, in Jang Bahadur v. Union of India, 2018 SCC OnLine P&H 6034, in Union of India v. Abhinav Cotspin Ltd., 2016 SCC OnLine P&H 19319 is correct, whereas the view of the Rajasthan High Court in Banshilal Samariya v. Union of India, 2005 SCC OnLine Raj 572 : 2005-06 Supp RLW 559 is not correct."
(emphasis supplied)
18. Having considered the discussions made in
paragraph 48, an observation is made that this being the case, it
is clear that even the Government is of the view that it is not
possible to discriminate between landowners covered by the
2013 Act and landowners covered by the National Highways Act,
when it comes to compensation to be paid for lands acquired
under either of the enactments.
19. It is also brought to notice of this Court that the
Apex Court held that provisions of Section 3J is violative of
Article 14 of the Constitution of India and therefore, declared to
be unconstitutional. Having considered the principles laid down
in the judgment referred supra and also discussions made in the
judgment and also the contentions, the very contention of the
counsel for the appellant that the Arbitrator committed an error
in invoking new enactment of 2013 Act AND same is not
applicable cannot be accepted and in detail District Judge while
considering the application filed under Section 34 of the
Arbitration and Conciliation Act discussed the same elaborately
and rightly comes to the conclusion that the same is applicable.
The very contention that discussion made in paragraph 36 of the
judgment is not correct cannot be accepted and rightly comes to
the conclusion that the same is also applicable.
20. The other contention of the counsel for the appellant
that Section 3J is clear not applicable also cannot be accepted
and the very contention that even District Judge also
misunderstood the judgment is also cannot be accepted and
even the Apex Court in the said judgment categorically held that
excluding applicability of LA Act, 1894 resulting in non-grant of
solatium and interest in respect of lands acquired under National
Highways Act, which were available if lands were acquired under
Land Acquisition Act, held, violative of Article 14 of the
Constitution of India. When clear discussion was made with
regard to Fourth Schedule and each Schedule of the new
enactment and also a clear discussion was made with regard to
the guidelines as well as notifications and also the Union of India
issued the notification and even discussion was made that
Government also did not oppose the same in the judgment
referred supra and the District Judge also in paragraph 34 in
keeping the ordinance as well as Section 105(1) of the 2013 Act
held that in the absence of any material for having paid the
entire compensation and also it is a continuous process of
determination of the compensation and the matter was also
referred to the Arbitrator-cum-Deputy Commissioner who has
been arrayed as respondentNo.2 in the A.P.No.81/2022 and
award was also passed on 19.04.2022 subsequently to the new
enactment and new enactment is applicable and the very
contention of the appellant's counsel that award passed in the
year 2011 itself and cannot invoke new enactment cannot be
accepted. Hence, I do not find any merit in the appeal.
Accordingly, the point No.1 is answered as negative.
Point No.2:
21. In view of the discussions made above, I pass the
following:
ORDER
The miscellaneous first appeal is dismissed.
Sd/-
(H.P. SANDESH) JUDGE
SN
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!