Thursday, 14, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The Chief Engineer Irrigation Central ... vs Sri. M D Ghouse Khan
2024 Latest Caselaw 4956 Kant

Citation : 2024 Latest Caselaw 4956 Kant
Judgement Date : 19 February, 2024

Karnataka High Court

The Chief Engineer Irrigation Central ... vs Sri. M D Ghouse Khan on 19 February, 2024

Author: Hemant Chandangoudar

Bench: Hemant Chandangoudar

                                                 -1-
                                                       NC: 2024:KHC-D:3891
                                                          RP No. 100049 of 2022




                       IN THE HIGH COURT OF KARNATAKA, DHARWAD BENCH
                           DATED THIS THE 19TH DAY OF FEBRUARY, 2024
                                              BEFORE
                       THE HON'BLE MR JUSTICE HEMANT CHANDANGOUDAR
                             REVIEW PETITION NO. 100049 OF 2022 (-)
                      BETWEEN:

                      1.   THE CHIEF ENGINEER IRRIGATION CENTRAL ZONE
                           KARNATAKA NIRAVARI NIGAMA LIMITED KNNL,
                           MUNIRABAD KOPPAL,
                           TQ: AND DIST: KOPPAL.

                      2.  THE EXECUTIVE ENGINEER
                          KARNATAKA NIRAVARI NIGAM LIMITED KNNL,
                          NO.II, CANAK DIVISION,
                          ODDARAHATTI,
                          TQ: GANGAVATHI,
                          TQ. AND DIST: KOPPAL.
                                                              ...PETITIONERS
                      (BY SRI. UMESH C AINAPUR, ADVOCATE)

                      AND:

                      1.   SRI. M D GHOUSE KHAN
                           AGE: 76 YEARS,
KM
SOMASHEKAR                 OCC: CONTRACTOR,
                           R/O. H.NO. 1 MAZAHAR MANZIL,
Digitally signed by        MUNIRABAD 580323,
K M SOMASHEKAR
                           TQ: GANGAVATHI,
Date: 2024.02.21
05:50:08 +0530             DIST: KOPPAL.

                      2.   THE ASSISTANT DIRECTOR
                           OFFICE OF CERTIFIED SUB TREASURER
                           GANGAVATHI, DIST: KOPPAL.
                                                                ...RESPONDENTS
                      (BY SRI.V.S.KALASURMATH, HCGP FOR R2)

                          REVIEW PETITION FILED UNDER ORDER 47 RULE 1 READ
                      WITH SECTION 114 OF CPC, PRAYING TO ALLOW THIS REVIEW
                                -2-
                                        NC: 2024:KHC-D:3891
                                          RP No. 100049 of 2022




PETITION AND BE PLEASED TO REVIEW THE JUDGMENT DATED
15.04.2021PASSED BY THIS HON'BLE COURT IN WP
NO.14073/2020 AS AT ANNEXURE-A AND CONSEQUENTLY BE
PLEASED TO ALLOW THE RESPONDENTS/PETITIONERS NOT TO
IMPOSE THE INTEREST FROM THE DATE OF COMPLETED
CONTRACT WORK FOR FSD AMOUNT IN THE INTEREST OF
JUSTICE AND EQUITY.

     THIS PETITION, COMING ON FOR ORDERS, THIS DAY,
THE COURT MADE THE FOLLOWING:

                             ORDER

The learned High Court Government Pleader accepts notice for the respondent No.2.

2. This petition is filed to review the order dated 15.4.2021 passed this Court in WP No.147073/2020 insofar as it relates to directing the petitioners/respondents No.1 and 2 to pay the interest at 8% p.a. from the date of completed contract work till the date of actual payment.

3. The learned counsel for the petitioners contended that, in the agreement between the petitioners and the respondent No.1 herein, there is no clause providing for interest on the belated payment of final security deposit. Therefore, the order insofar as it relates to granting interest at the rate of 8% p.a. on the final security deposit is not sustainable.

4. The respondent No.1 herein was the successful bidder in pursuance of tender notification invited by the petitioners, and the work order was issued to complete the

NC: 2024:KHC-D:3891

project, and thereafter, the respondent No.1 completed the project, and the completion certificate was issued, and final bill was submitted with the petitioners. However, the petitioners paid the amount under the contract, but however, did not refund the final security deposit.

5. The petitioners were under an obligation to release the final security deposit after the certificate of completion of the work was issued in favour of the petitioners. The petitioners having not released the same, are liable to pay the interest on the belated payment on the final security deposit. Therefore, I do not find any illegality or error apparent on the face of the record to review the order. Accordingly, I pass the following:

ORDER The petition stands dismissed.

Sd/-

JUDGE

BKM CT:ANB

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter