Citation : 2024 Latest Caselaw 4956 Kant
Judgement Date : 19 February, 2024
-1-
NC: 2024:KHC-D:3891
RP No. 100049 of 2022
IN THE HIGH COURT OF KARNATAKA, DHARWAD BENCH
DATED THIS THE 19TH DAY OF FEBRUARY, 2024
BEFORE
THE HON'BLE MR JUSTICE HEMANT CHANDANGOUDAR
REVIEW PETITION NO. 100049 OF 2022 (-)
BETWEEN:
1. THE CHIEF ENGINEER IRRIGATION CENTRAL ZONE
KARNATAKA NIRAVARI NIGAMA LIMITED KNNL,
MUNIRABAD KOPPAL,
TQ: AND DIST: KOPPAL.
2. THE EXECUTIVE ENGINEER
KARNATAKA NIRAVARI NIGAM LIMITED KNNL,
NO.II, CANAK DIVISION,
ODDARAHATTI,
TQ: GANGAVATHI,
TQ. AND DIST: KOPPAL.
...PETITIONERS
(BY SRI. UMESH C AINAPUR, ADVOCATE)
AND:
1. SRI. M D GHOUSE KHAN
AGE: 76 YEARS,
KM
SOMASHEKAR OCC: CONTRACTOR,
R/O. H.NO. 1 MAZAHAR MANZIL,
Digitally signed by MUNIRABAD 580323,
K M SOMASHEKAR
TQ: GANGAVATHI,
Date: 2024.02.21
05:50:08 +0530 DIST: KOPPAL.
2. THE ASSISTANT DIRECTOR
OFFICE OF CERTIFIED SUB TREASURER
GANGAVATHI, DIST: KOPPAL.
...RESPONDENTS
(BY SRI.V.S.KALASURMATH, HCGP FOR R2)
REVIEW PETITION FILED UNDER ORDER 47 RULE 1 READ
WITH SECTION 114 OF CPC, PRAYING TO ALLOW THIS REVIEW
-2-
NC: 2024:KHC-D:3891
RP No. 100049 of 2022
PETITION AND BE PLEASED TO REVIEW THE JUDGMENT DATED
15.04.2021PASSED BY THIS HON'BLE COURT IN WP
NO.14073/2020 AS AT ANNEXURE-A AND CONSEQUENTLY BE
PLEASED TO ALLOW THE RESPONDENTS/PETITIONERS NOT TO
IMPOSE THE INTEREST FROM THE DATE OF COMPLETED
CONTRACT WORK FOR FSD AMOUNT IN THE INTEREST OF
JUSTICE AND EQUITY.
THIS PETITION, COMING ON FOR ORDERS, THIS DAY,
THE COURT MADE THE FOLLOWING:
ORDER
The learned High Court Government Pleader accepts notice for the respondent No.2.
2. This petition is filed to review the order dated 15.4.2021 passed this Court in WP No.147073/2020 insofar as it relates to directing the petitioners/respondents No.1 and 2 to pay the interest at 8% p.a. from the date of completed contract work till the date of actual payment.
3. The learned counsel for the petitioners contended that, in the agreement between the petitioners and the respondent No.1 herein, there is no clause providing for interest on the belated payment of final security deposit. Therefore, the order insofar as it relates to granting interest at the rate of 8% p.a. on the final security deposit is not sustainable.
4. The respondent No.1 herein was the successful bidder in pursuance of tender notification invited by the petitioners, and the work order was issued to complete the
NC: 2024:KHC-D:3891
project, and thereafter, the respondent No.1 completed the project, and the completion certificate was issued, and final bill was submitted with the petitioners. However, the petitioners paid the amount under the contract, but however, did not refund the final security deposit.
5. The petitioners were under an obligation to release the final security deposit after the certificate of completion of the work was issued in favour of the petitioners. The petitioners having not released the same, are liable to pay the interest on the belated payment on the final security deposit. Therefore, I do not find any illegality or error apparent on the face of the record to review the order. Accordingly, I pass the following:
ORDER The petition stands dismissed.
Sd/-
JUDGE
BKM CT:ANB
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!