Monday, 11, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Mr Bruno D Costa vs Mr Fr James Charlie
2024 Latest Caselaw 9579 Kant

Citation : 2024 Latest Caselaw 9579 Kant
Judgement Date : 2 April, 2024

Karnataka High Court

Mr Bruno D Costa vs Mr Fr James Charlie on 2 April, 2024

                                               -1-
                                                             NC: 2024:KHC:13438
                                                            MFA No. 802 of 2024




                        IN THE HIGH COURT OF KARNATAKA AT BENGALURU

                            DATED THIS THE 2ND DAY OF APRIL, 2024

                                             BEFORE
                              THE HON'BLE MR JUSTICE R. NATARAJ
                    MISCELLANEOUS FIRST APPEAL NO. 802 OF 2024 (AA)
                   BETWEEN:
                   MR. BRUNO D'COSTA
                   S/O JOSEPH D'COSTA
                   AGED ABOUT 38 YEARS
                   R/AT VARTHEGUNDI
                   TARIKERE TALUK
                   CHIKMAGALURU DISTRICT
                   PIN 577 134
                                                                    ...APPELLANT
                   (BY SRI. BALAGANGADHAR G.S., ADVOCATE)

                   AND:
                   MR. FR. JAMES CHARLIE
                   SR. JOSEPH'S CHURCH
                   AGED ABOUT 38 YEARS
                   BASKAL VILLAGE
                   CHIKKAMAGALURU DISTRICT
                   PIN 577 134
Digitally signed                                                  ...RESPONDENT
by
MARKONAHALLI       (BY SRI. H.N.MANJUNATH PRASAD, ADVOCATE FOR CAVEATOR
RAMU PRIYA
Location: HIGH     RESPONDENT)
COURT OF
KARNATAKA

                          THIS MFA IS FILED UNDER SECTION 37(1)(b) OF THE
                   ARBITRATION AND CONCILIATION ACT, 1996, AGAINST THE ORDER
                   DATED 04.01.2024 PASSED IN A.A.NO.05/2023 ON THE FILE OF THE
                   II     ADDITIONAL    DISTRICT     AND    SESSIONS     JUDGE,
                   CHIKKAMAGALURU, REJECTING THE APPLICATION FILED UNDER
                   SECTION 9 OF THE ARBITRATION AND CONCILIATION ACT, 1996.

                          THIS APPEAL, COMING ON FOR ADMISSION, THIS DAY, THE
                   COURT DELIVERED THE FOLLOWING:
                               -2-
                                            NC: 2024:KHC:13438
                                           MFA No. 802 of 2024




                        JUDGMENT

The applicant in Arbitration Application No.5/2023 on

the file of the II Additional District and Sessions Judge,

Chikkamagaluru, (henceforth referred to as 'the Trial

Court') has filed this appeal challenging the correctness of

an order dated 04.01.2024 by which an application filed by

him under Section 9 of the Arbitration and Conciliation Act,

1996 (for short, 'the Act') was rejected.

2. The parties shall henceforth be referred to as

they were arrayed before the Trial Court.

3. The applicant and the respondent had entered

into an agreement dated 10.02.2021 for demolition and

renovation of a Church building at Sy. No.96, Baskal

village, Vasthare Hobli, Chikkamagaluru Taluk, Mangalore

District. The estimated value of the contract was

Rs.1,34,18,917/-. The agreement contemplated duties and

responsibilities of both the parties and also provided for a

dispute resolution mechanism, initially through mutual and

amicable consultation and if consensus was not reached,

NC: 2024:KHC:13438

to be referred to arbitration by a sole Arbitrator. The

applicant claimed that after completing the 7th stage of the

work, the Engineer appointed by the Church Mr. John P.

Marties and the Church committee measured the work and

the bill was paid. After completing 8th and 9th stage work,

the applicant had submitted a bill to the Priest on

09.08.2023. The priest called him on 12.08.2023 at about

9.30 a.m. and at such meeting, he informed the applicant

that action would be initiated to make the payment. He

claimed that the priest of the Church informed him that

they had already paid excess amount to him and they

would not pay any amount and that the construction would

be completed by the Church itself. The applicant

addressed a letter dated 09.08.2023 through email to the

respondent informing them to permit the completion of the

work as per the agreement and not to give any room for

violation. He also had made a claim for Rs.19,79,031/-.

The applicant apprehending that the respondent may

undertake the remaining construction, filed an application

under Section 9 of the Act of 1996 for an order of

NC: 2024:KHC:13438

temporary injunction restraining the respondent from

continuing the remaining construction work in the

application schedule property till the disposal of the case.

The Trial Court after hearing the applicant, had granted an

ex parte order of injunction.

4. This application was opposed by the respondent

who claimed that a sum of Rs.1,22,08,796/- was already

paid to the applicant and he had only achieved 40% of the

work. He claimed that a message was sent through

whatsapp on 30.08.2023 and the applicant was called for a

meeting on 05.09.2023. However, on 01.09.2023, the

applicant sent a message that he would not be available

for the next 15 days as he had to go to Bengaluru for

some other work. Thereafter, on 11.09.2023 a letter was

addressed to the applicant to attend for a meeting on

21.09.2023 to discuss regarding the work turned out by

the applicant and the payment he received. However, the

applicant replied through his Advocate on 18.09.2023

demanding a further sum of Rs.19,00,000/-. The

NC: 2024:KHC:13438

respondent contended that again on 20.09.2023, a

message was sent by whatsapp and email calling upon the

applicant to attend a meeting on 21.09.2023. He

contended that even before the meeting dated 21.09.2023

was arranged, the applicant had filed the present

application seeking for interim reliefs. He further

contended that he never denied to make any payment, if

the same was payable to the applicant after getting

measurement of the work done by the applicant in his

presence and the presence of the Building Committee and

the Engineer. He, therefore, contended that it was the

applicant who was irresponsible and did not take any steps

for an amicable settlement. On the contrary, he

abandoned the work and since the balance work had to be

completed, the respondent had undertaken the

construction. After the respondent entered appearance

and filed his objection, the Trial Court in terms of the

impugned order, rejected the application filed by the

applicant on the ground that the applicant had not made

any effort to get the dispute resolved amicably though

NC: 2024:KHC:13438

several attempts were made by the respondent and that

the applicant had failed to establish his bona fides in

seeking the discretionary relief of interim injunction.

5. Being aggrieved by the said order, the applicant

has filed this appeal.

6. Learned counsel for the applicant submitted

that as per the agreement, if there is any dispute between

the applicant and the respondent, it was incumbent upon

them to appoint a conciliator and if the conciliation failed,

the parties were at liberty to undertake the process of

arbitration. He submits that there was no attempt on the

part of the respondent to conciliate differences between

the applicant and the respondent and the respondent

unilaterally without even terminating the agreement, had

refused to make any payment and had proposed to

complete the balance work. He submits that so long as

the agreement is in force, the applicant is entitled to

restrain the respondent from completing the balance

construction.

NC: 2024:KHC:13438

7. In reply, the learned counsel for the respondent

submitted that the applicant has already initiated

proceedings for resolution of the dispute through

arbitration by issuing a notice dated 18.09.2023 and

therefore, it is deemed that the parties have terminated

the contract. He submits that the attempts made by the

respondent to consider the dispute was turned down by

the applicant and hence, the respondent had no other

option than to undertake the completion of the balance

work. He submitted that the Trial Court in the

circumstances felt that the grant of an order of injunction

would affect the interest of the respondent and therefore,

refused to grant interim relief sought for by the applicant.

He further submits that though the applicant has caused a

notice invoking arbitration clause, he has not taken any

steps under Section 11 of the Act of 1996. He submits that

it was always open for the applicant to invoke the

provisions of Section 17 of the Act of 1996 before the

Arbitrator.

NC: 2024:KHC:13438

8. I have considered the submissions made by the

learned counsel for the applicant and the learned counsel

for the respondent.

9. It is now well settled that while considering an

application under Section 9 of the Act of 1996, the

principles for grant of interim injunction adumbrated under

Order XXXIX Rules 1 and 2 of CPC have to be applied,

namely, whether the plaintiff has a prima facie case for

grant of injunction and whether any hardship would be

caused to the parties, if injunction is refused and in whose

favour the balance of convenience lies in granting the

order of injunction. The Court is also bound to consider

whether the applicant can be compensated in terms of

money instead of granting an order of injunction. In the

case on hand, the applicant claims that he had constructed

a substantial portion of the construction that was

entrusted to him. He does not dispute the fact that the

total estimated value of the contract was

Rs.1,34,18,917/-. He also does not dispute the fact that

NC: 2024:KHC:13438

he had received a sum of Rs.1,22,08,796/- from the

respondent. The respondent claimed that he had paid a

sum of Rs.1,22,08,796/- to the applicant. The documents

placed on record indicate that apart from the amount

allegedly paid by the respondent, the applicant had laid a

claim for a sum of Rs.19,00,000/- in respect of 8th stage of

construction. This only meant that the applicant was

claiming more than the agreement value entered into

between him and the respondent. The applicant claims

that certain works which were not initially agreed upon

between the parties were incorporated in the contract and

therefore, the value of the contract exceeded the initial

contract value. However, no document in this regard is

placed by the applicant either before the Trial Court or this

Court. Nonetheless, these are questions which have to be

considered before the Arbitrator. Having regard to the fact

that the building that is sought to be constructed was a

Church, if the applicant abandoned the work, the

respondent cannot be tied down to the contract and

cannot be restrained from completing the construction.

- 10 -

NC: 2024:KHC:13438

Moreover, the applicant has already commenced the

arbitration proceedings by issuing a notice dated

18.09.2023 and hence, it can safely be held for the

present that the agreement between the parties stood

terminated. The grant of any order of injunction

restraining the respondent from putting up the

construction would unduly cause more hardship to the

respondent than to the applicant. After all, the applicant

is only concerned with the value of the work already

executed and nothing more, which could be worked out in

the arbitration proceedings. Since the applicant has not

taken any steps for appointment of an arbitrator to

adjudicate a dispute and has also not taken any steps for

drawing up of an inventory of the work already done,

granting an order of injunction to restrain the respondent

from putting up any construction or complete the balance

construction in the application schedule property would be

more injurious to the respondent and hence, the Trial

Court was justified in not granting an order of injunction.

There is no error committed by the Trial Court warranting

- 11 -

NC: 2024:KHC:13438

interference by this Court. Any observation made in this

order will not come in the way of the Arbitrator to decide

the dispute on merits.

10. Hence, the appeal is dismissed.

11. I.A No.1/2024 for temporary injunction and I.A.

No.2/2024 for production of documents do not survive for

consideration and the same stand disposed off.

Sd/-

JUDGE

SMA

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter