Monday, 11, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Formac Engineering Ltd vs M/S.Bosch Ltd
2023 Latest Caselaw 10510 Kant

Citation : 2023 Latest Caselaw 10510 Kant
Judgement Date : 14 December, 2023

Karnataka High Court

M/S Formac Engineering Ltd vs M/S.Bosch Ltd on 14 December, 2023

Author: V Srishananda

Bench: V Srishananda

                                             -1-
                                                           NC: 2023:KHC:45596
                                                         RFA No. 2548 of 2007




                IN THE HIGH COURT OF KARNATAKA AT BENGALURU
                      DATED THIS THE 14TH DAY OF DECEMBER, 2023
                                       BEFORE
                       THE HON'BLE MR JUSTICE V SRISHANANDA
                 REGULAR FIRST APPEAL NO.2548 OF 2007 (MON)
              BETWEEN:
                  M/S. FORMAC ENGINEERING LTD.,
                  A COMPANY REGISTERED UNDER THE,
                  COMPANIES ACT, 1956 AND HAVING,
                  ITS REGISTERED OFFICE AT KANJUR(EAST),
                  BOMBAY - 400 076.
                                                                       ...APPELLANT
              (BY SRI. BHAVANA G. K., ADVOCATE)
              AND:

                  M/S. BOSCH LTD.,
                  A COMPANY REGISTERED UNDER THE,
                  COMPANIES ACT, 1956 AND HAVING,
                  ITS REGISTERED OFFICE AT HOSUR ROAD,
                  ADUGODI,
                  BANGALORE - 560 030.

                  REPRESENTED HERE IN BY ITS,
Digitally
                  DIVISIONAL MANAGER (LAW) AND,
signed by R       COMPANY SECRETARY : MR. B. S. IYER.
MANJUNATHA
                                                                  ...RESPONDENT
Location:
HIGH COURT
OF            (BY SRI.NITIN PRASAD ADVOCATE FOR SRI.VINAY GIRI.,
KARNATAKA     ADVOCATE)
                      THIS RFA IS FILED UNDER SECTION 96 AND ORDER 41
              RULE 1 OF THE CODE OF CIVIL PROCEDURE AGAINST THE
              JUDGMENT       AND   DECREE          DT.3.8.2007     PASSED       IN
              O.S.NO.2451/1993 ON THE FILE OF THE XXXI ADDL. CITY
              CIVIL    JUDGE,   BANGALORE,     DECREEING         THE    SUIT   FOR
                              -2-
                                            NC: 2023:KHC:45596
                                       RFA No. 2548 of 2007




RECOVERY    OF   ADVANCE     MONEY   PAID    BASED   ON   THE
CONTENTION OF BREACH OF CONTRACT.


     THIS APPEAL, COMING ON FOR HEARING, THIS DAY, THE
COURT DELIVERED THE FOLLOWING:
                          JUDGMENT

Present appeal is filed challenging the validity of the

judgment and decree passed in O.S.No.2451/1993 dated

03.08.2007 on the file of Additional City Civil Judge

Bengaluru City (CCH - 14).

2. Parties are referred to as plaintiff and defendant

for the sake of convenience as per their original ranking

before the Trial Court.

3. It is here and there alone, necessary that name

of the plaintiff has been changed from M/s. Motor

Industries Company Limited to M/s. Bosch Limited and

necessary amendment has been carried out in the appeal

memorandum.

4. Case of the plaintiff is that plaintiff had placed

orders for special purpose machinery to be supplied to the

NC: 2023:KHC:45596

plaintiff by defendant as per the drawings provided by the

plaintiff. It is a tailor-made equipment and therefore,

defendant had to cater to the needs of the plaintiff as per

the drawings precisely.

5. As per the contract between the plaintiff and

defendant, defendant prepared three special purpose

machinery as per the drawing and supplied to the plaintiff,

which was accepted by the plaintiff. However, in respect of

two machineries, out of the total sum that was payable to

defendant by plaintiff, a sum of Rs.82,805/- and 85,500/-

respectively were retained by the plaintiff as retention

money for the satisfaction of the proper working of the

special purpose machinery supplied by the defendant to

plaintiff.

6. In respect of the third specialized machinery,

there was no retention money. In respect of fourth

specialized machinery, when the defendant was about to

manufacture the same as per the drawings made by the

NC: 2023:KHC:45596

plaintiff, there were some differences between the plaintiff

and defendant.

7. According to the defendant, when the

machinery was being manufactured, the plaintiff changed

the drawing and therefore, defendant was unable to

complete the manufacturing of the special purpose

machinery as required by the plaintiff and plaintiff also

taking note of the delay in getting the special purpose

machinery delivered to the plaintiff, terminated the

contract only in respect of fourth specialized machinery.

The correspondence between the parties has to establish

the same and therefore, plaintiff sought for return of

entire sum of Rs.3,31,800/- which was given to defendant

for the purpose of manufacture of special purpose

machinery in respect of fourth specialized machinery.

8. Defendant refuted the claim and also sought for

set of in the suit claim by filing detailed written statement

by contending that retention money of Rs.82,805/- and

NC: 2023:KHC:45596

Rs.85,500/- needs to be deducted, while adjudicating the

claim of the plaintiff and sought for dismissal of the suit.

Therefore, learned Trial Judge framed following issues:

"1. Does plaintiff proves that defendant failed and neglected to deliver the machine as per plaintiff's order inspite of extension of time as contended in para-3 to 5 of the plaint?

2. Does plaintiff prove that plaintiff cancelled orders demanded refund of advance amount of Rs.3,31,800/- with 20% interest per annum as per para-5 of the plaint?

3. Does defendant prove that the delay is due to plaintiff for not making the funds available as per para-6 of the written statement?

4. Does defendant prove that this court has no jurisdiction to try the suit as per para-11 of the written statement?

5. Whether there is cause of action to this suit?

6. Whether the plaintiff has paid proper court fee?

7. Whether the plaintiff is entitled for the suit reliefs?

8. If so under what order or decree?"

NC: 2023:KHC:45596

9. In order to prove the case of plaintiff,

Sri.S.Nagaraj, one of his officers got examined as P.W.1

and relied on 06 documents which are exhibited and

marked as Ex.P.1 to Ex.P.6 comprising of copy of the order

dated 10.08.1999 at Ex.P.1, minutes of meeting dated

08.05.1990 at Ex.P.2, letter dated 07.11.1991 at Ex.P.3,

postal acknowledgment at Ex.P.4, reply letter dated

20.12.1991 at Ex.P.5 and copy of the rejoinder dated

08.02.1992.

10. As against the evidence placed on record by the

plaintiff, on behalf of defendant Sri.Shahpur Phiropze Rao

is examined as D.W.1 and relied on 25 documents which

are exhibited and marked as Ex.D.1 to Ex.D.25 comprising

of purchase order dated 22.04.1987 at Ex.D.1, purchase

order dated 13.11.1988 at Ex.D.2, invoice dated

22.04.1987 at Ex.D.3, copy of minutes of meeting dated

08.05.1990 at Ex.D.4, balance confirmation dated

21.10.1991 at Ex.D.5, letter dated 27.04.1994 at Ex.D.6,

NC: 2023:KHC:45596

letter dated 13.03.1993 at Ex.D.7, purchase order dated

10.08.1998 at Ex.D.8, standard format of terms and

conditions at Ex.D.9, copies of letters at Exs.D.10 to 15,

copy of deliver note dated 05.03.1999 at Ex.D.16, packing

list dated 02.03.1990 at Ex.D.17, copy of letter dated

27.03.1990 at Ex.D.18, copy of debit note dated 31/-

1.1992 at Ex.D.19, statement of account at Ex.D.20,

status reports at Exs.D.21 to 23, copy of delivery note

dated 22.05.1989 at Ex.D.24 and copy of invoice dated

29.05.1989 at Ex.D.25.

11. On conclusion of recording of the evidence,

learned Trial Judge heard the parties in detail and on

cumulative consideration of oral and documentary

evidence on record, decreed the suit of the plaintiff as

under:

"For foregoing reasons, suit of the plaintiff stands decreed with costs in the following terms:

The plaintiff is held entitled to recover a sum of Rs.4,65,349-50 together with interest over the principal amount of Rs.3,31,800/- from the date of the suit till this day at the rate of 9% per annum and

NC: 2023:KHC:45596

thereafter, at the rate of 6% per annum till realization; from the defendant."

12. Being aggrieved by the same, defendant has

preferred the present appeal on the following grounds:

 The trial court without appreciating the very relevant aspect of the terms and conditions for supply of special purpose machine has decreed the suit. Further the trial court also failed to take into consideration of the following admitted relevant facts that:

(i)There was an enormous delay in making advance payment,

(ii) Finalizing the drawings and adjusting the advance as against the earlier supply,

(iii) Non payment of dues as against other supplies,

(iv) Mischief recruiting and of appointing an expert sent by the defendant to the plaintiff company for commissioning of the machine, before coming to the conclusion that the defendants owe to the plaintiff. Though there was no specific contract for supply and purchase of the machine, the purchase order, terms and conditions furnished by the defendant for supply of special purpose machine and invoice raised by the defendant constitute an agreement between the parties. As per the understanding the plaintiff was required to pay advance intime and furnish drawings. Further the same was required to be approved and thereafter

NC: 2023:KHC:45596

special designing will be implemented by the defendant. In the present case the plaintiff has totally failed in all respects.

Therefore the defendant is entitled to forfeit the belated payment.

 The trial court failed to note that the defendant has commenced the manufacturing of the machine and has spent about Rs.2,25,000/- for design approval prints and for securing raw materials and for manufacturing of components, moulds and for other related works. The plaintiff has not paid for the earlier supplies and for work done between August, 1988 and March, 1990. Therefore the defendant has every right to withhold the amount. Non compliance by the plaintiff resulted in breach and thereby the defendant is not liable to pay any amount. The same has not been appreciated by the trial court.

 The trial court failed to note that PW-1 has no authority to represent the company. Admittedly there is no Board resolution authorizing PW-1 to give evidence. He has been working in the Department since April, 1994 subsequent filing of the suit. He is totally ignorant about the factual aspects. His deposition is based on the records is the statement of the witness. PW-1, on the face of it, has made false statement that they have paid 30% of purchase value of Rs. 16,59,000/- as advance which comes to Rs. 4,97,700/-. Infact, admittedly the amount paid is Rs. 3,31,800/- (i.e. about 20%). The Trial Court has not taken note off the very relevant fact that PW-1 is most unreliable witness. Hence the trial court ought to have discarded the evidence of PW-1.

 The DW-1 is the person who has dealt with the plaintiff company from the inception. He has

- 10 -

NC: 2023:KHC:45596

categorically stated about all the three transactions. He has also made clear that there was no delay on their part in supplying the first machine. The plaintiff illegally appropriated the advance payment made as against the second machine towards discharge of the dues of the first machine and thereby violated the terms and caused delay in manufacturing of second machine. The reduced advance was paid for the second machine after the joint meeting. But there was enormous delay in sending the plans and designs and also for approval. It is on record and also admitted by PW-1. It is not in dispute that the machine to be manufactured is a special purpose machine for which separate terms and conditions were given to the plaintiff. One of the terms of Ex.D- 9 reads thus:

"CANCELLATION: In the event that an order with advance payment for machinery or equipment is cancelled by a customer, we reserve the right to forfeit the advance, as well as to recover from the customer the Value of all the work completed and in process."

 The defendant has exercised the right under Ex.D-9 and forfeited the advance. The Plaintiff has not denied the terms of Ex.D-9 and there is no Cross-Examination in respect of the said document. Therefore the trial court ought to have relied upon the terms of Ex.D9 and dismissed the suit.

 The learned trial judge while answering Issue no.4 has opined that though the defendants are at Mumbai and all the transactions are concluded at Mumbai, the payment has to be made from Bangalore and goods has to be supplied at Bangalore and therefore the court at Bangalore has jurisdiction and answered

- 11 -

NC: 2023:KHC:45596

issue No.4 in the affirmative. The said view is incorrect. It is an admitted fact that the Defendant Company is situated at Mumbai and orders were placed at Mumbai, payment received at Mumbai and machinery was manufactured at Mumbai. The inspection of machinery has to be at Mumbai as per Clause 3.3 of Purchaser Order Ex. P-1. Therefore contract concluded at Mumbai. The supply of machine to Bangalore is only a consequence pursuant to the concluded contract. The learned Judge is of the view that ultimately machine has to be commissioned at Bangalore and therefore the Court at Bangalore has jurisdiction. Even if such view is accepted, it is clear that the cause of action has arisen both at Bangalore as well as at Mumbai. Exhibit D-9 is clear that in an eventuality the Court at Mumbai is having jurisdiction. Therefore the court at Bangalore has no jurisdiction. The said aspect has not been considered by the trial court.

 The plaintiff has prayed for return of the advance amount of Rs.3,31,800/- with interest on the plea that the defendant has not honoured the commitment of supply of machinery worth Rs. 16,59,000/-. Unless the declaration is given to the effect that the Defendant has not honoured the commitment the refund cannot be ordered. In the present case the trial court has framed Issue No.1 and answered in the affirmative declaring that the defendant has honoured the commitment. Therefore court fee has to be paid on the value of the purchase order under Section 24 (d) of the Karnataka Court Fee and Suits Valuation Act. Hence the reasoning on Issue No.6 is incorrect.

 The trial court declined to take note of the pleading and the evidence of the defendant

- 12 -

NC: 2023:KHC:45596

regarding the extra amount spent for importing rotary table to the extent of Rs.2,00,000/- and the balance amount payable in respect of supply made to their Nasik branch amount to Rs.82,805.54 on the ground that the defendant has not made any counter claim. The said view is contrary to law. The trial court ought to have taken note of the justification for withholding the advance amount by the defendant and dismissed the suit holding that the plaintiff is not entitled to claim the refund. The counter claim is not required when the amount demanded is in respect of related transaction. Hence the view is bad.

 The trial court failed to take note of the liability of the plaintiff in respect of the 3rd purchase order of their Nasik branch on the ground that it is a concluded contract. The said view is contrary to the entire transaction. It is an admitted fact that the plaintiff used to purchase special purpose machineries from the defendant since 1980. It is also on record that advance paid for the 2nd purchase order is adjusted against the payment of 1 machine. Therefore the transactions are interlinked and defendants are entitled to adjust the amount as and when they receive on account of the plaintiff. The same is also evidenced by Ex. D-

20. Hence the approach of the trial court is bad.

 The approach of the trial court that the adjustment of advance paid for manufacturing of 2hd purchase order as against supply of machine under 1st purchase order is inconsequential since the entire amount for the 1st purchase order is discharged, is contrary to terms of the contract and business principle. The advance paid for the manufacturing of machinery under 2nd purchase order cannot be adjusted against the supply of the machinery

- 13 -

NC: 2023:KHC:45596

under 1st purchase order since it violates the supply conditions and the said violation is very much relevant to answer Issue No.1 regarding justification of not refunding the amount.

 The trial court wrongly understood the sequence of events while answering Issue No.3 along with other issues. It is an admitted fact that the PW-1 had no personal knowledge regarding the entire transaction. It is also an admitted fact that the 2nd purchase order Ex.P.2 (Ex.D-4) is dated 10/8/1988. As per the terms advance was supposed to be paid and the advance paid has been adjusted towards supply.

and answered in favour of the Plaintiff. The learned judge ought not to have clubbed Issue No.3 along with Issue No.1, 2, 5 & 7. The appreciation of evidence while answering issues was not properly considered, which resulted in non- consideration of facts in issue. Hence the approach for the learned judge is bad.

 The trial court has not properly appreciated Issue No.3 with reference to documents and pleadings of the parties. It is an admitted fact that the machinery is a special purpose machine, which require distinctive skill in designing and preparing the drawings. The special purpose type of machineries will be manufactured only against the purchase order, provided designs and drawings are furnished and finalised with reference the acceptable technical specifications. In the present case it is very much on record that the purchase order in dispute (Purchase Order No.86715) was placed on 10/8/1988. As per the terms 10% was supposed to be paid along with purchase order. The advance paid was illegally adjusted

- 14 -

NC: 2023:KHC:45596

as against the payment for supply of first purchase order vide No.86624 dated 22/4/1987. An advance of Rs.3,31,800/- was paid on 7/5/1990 after about 1 year 9 months. It is also an admitted fact that there was an enormous delay in sending approved drawings. Without any justification order was cancelled on 7/11/1991 within 1 year 6 months of payment of advance. The DW-1 has categorically stated that they have purchased raw materials and also designed the machineries investing about Rs.2,25,000/-. The same cannot be used for any other purpose. It is also on record that they could not manufacture due to non-availability of funds and finalization of drawings. There is no acceptable explanation by the plaintiff justifying their action of not paying the amount in time. Therefore the trial court ought to have answered Issue No.3 in the affirmative. Therefore the defendant, the Appellant herein has every right to forfeit the advance as per Ex.D-9. The said aspect has not been referred and considered by the trial court.

 The trial court clubbed the pleadings and evidence of the parties out of context and answered Issue No.1 and 2 in favour of the plaintiff. The extension of time is not in conformity with the delay caused by them. The trial court has lost sight of the fact that the plaintiffs have unilaterally adjusted the amount paid as advance towards the payment as against the supply made by the defendant in respect of the first purchase order without reference to the defendant. The advance was paid much after the commitment dated. Under the circumstances the delay is solely due to non payment of advance in time and not furnishing the approved drawings. Therefore the trial court wrongly answered Issue No.1.

- 15 -

NC: 2023:KHC:45596

 The trial court failed to note that the plaintiff has not right to cancel the order since the purchase order placed is in respect of special purpose machine which will be manufactured only on the basis of the purchase order and with reference to the specifications. The only consequences follows if the purchased order is cancelled is to forfeit the advance in accordance with the terms and condition stipulated for specials purpose machine. The said aspect has been totally overlooked by the trial court.

 The trial court failed to note that the plaintiff has sought the relief for refund of the advance amount on the ground that they have cancelled the purchase order for non performance of the contract by the defendant. Unless there is a relief sought for declaration that the purchase order placed by them is not acted upon they are not entitled for the relief of refund of advance. Hence there was no cause of action for the plaintiff to seek the prayer which is consequential in nature. Hence trial court ought to have dismissed the suit.

 The trial court has not take note of the contents of the Ex.P2 wherein the plaintiff has specifically admitted that they will retain 5% of the cost of the machine supplied under first purchase order that works out to Rs.82,805/- till the second machine is commissioned. The said term in Ex.P.2 clearly indicates that all the purchase orders are interlinked. Ex.P.20 - Statement of Accounts which is not in dispute indicate the same. Therefore view of the trial court that the first purchase order is nothing to do with the second purchase order is contrary to the pleadings, evidence and to the records. The trial court ought to have taken note of all the purchase orders, account statement with reference to supply and payment before

- 16 -

NC: 2023:KHC:45596

coming to the conclusion whether the defendant was justified in forfeiting the amount. Hence the judgement is bad in law.

 The learned judge has wrongly understood the statement made by DW-1 in para 7 which he has quoted in the judgement. The answer given was with reference to the question -

"whether the defendant can produce the document to substantiate his statement?" The witness meant that he was not knowing such a question will be asked to bring the documents and to produce then and there. The statement was read out of context. If the deposition is read in toto it will not give the meaning which the learned judge has understood.

 The trial court has not appreciated the nature of work undertaken by the defendant in response to the purchase order placed by the plaintiff. The very nature of the machine is special purpose machine which require the service of technical experts. Admittedly Mr. Shamsundar is a trained Engineer of the defendant. The plaintiff encouraged the said person to leave the job of the defendant and recruited him when the second machine was to be manufactured. At the crucial point of time the services of an expert was deprived. The said aspect is very much on record.

 The trial court failed to note that the design and drawings were finalised in consultation with the experts of the defendant and the work about to be implemented, the cancellation order was sent. The approved design is in the custody of the plaintiff they made use of the said design to complete the process and got the machinery through some other agency and made unreasonable claim against the defendant. The Ex.P.20 is very clear that the Advance for second machine was paid in 2

- 17 -

NC: 2023:KHC:45596

parts. They have not paid for the first machine in time. Instead they have adjusted the said advance against the supply of first machine. Only thereafter they paid advance of about 20% i.e. 5% less than the amount payable as per the terms. Further they have also not paid 5% fallen due on the first machine. They have also not paid the dues towards the supply made to Nasik branch. These aspects though noticed by the trial court has not been appreciated in the proper perspective. Hence the judgement is bad.

 The trial court totally misconstrued Ex.D-9. Ex.D9 is a general terms and conditions for all special purpose machine. The terms and conditions has not been denied by the Plaintiff. Therefore there was no reason for the trial court to decline to appreciate the terms and apply the same to the case. Instead the trial court refused to take note of a specific clause only on the ground that the plaintiff is not a party for the said terms. The said view is incorrect, because once purchased order is issued the acceptance is always subject to the said general terms and conditions. Therefore it is a clear case of non application of mind.

 The Trial Court is of the view that the Defendant has not taken any action against Mr. Sham Sunder when he has left the service presupposes that the same has no effect on implementation of the work. The said view has no basis. Infact, it is the case of the Defendant that the Plaintiff has induced the said person to leave the employment of the Defendant and they recruited in their roll and even now he is working with Plaintiff. The Defendant could do nothing against an employee who has left the service since they are protected under law. The said person has not been examined by the

- 18 -

NC: 2023:KHC:45596

Plaintiff. These facts have not been taken note off by the Trial Court.

 The Ex. P-2 is the minutes of the Meeting dated 8.5.1980 in which they reduced the payment of advance much after the approval of the drawings and made the Defendant to invest their skill and money on the drawings. There is no clause reserving their right to seek refund of amount in case of non-supply of machines within time. The reason for non- inclusion is that the machine is a special purpose machine and it is controlled by a specific terms and conditions which was understood by the parties. The said minute is in continuation of Ex. D-9. The same has not been taken note of.

 The judgement and decree is also bad on various other grounds which will be pointed out at the time of hearing.

13. Smt.Bhavana G.K., learned counsel for the

appellant, reiterating the grounds urged in the appeal

memorandum vehemently contended that the trial Court

has grossly erred in decreeing the suit of the plaintiff,

inasmuch as, the special purpose machinery was made to

order by the defendant was commenced by the defendant

and because of the modification in the drawing, in the

interregnum, the defendant has put to loss and the raw

materials that has been procured for the manufacture of

- 19 -

NC: 2023:KHC:45596

special purpose machinery in pursuance of the purchase

order issued by the plaintiff, the defendant is not obliged

to make any payment.

14. He also contended that in the event of Court

coming to the conclusion that defendant has to make a

payment of sum of Rs.3,31,800/-, a sum of Rs.1,68,305/-

retained by the plaintiff in respect of two specialized

machinery, which has been supplied by defendant to

plaintiff and satisfaction has been recorded by the plaintiff

needs to be set off and for the remaining amount, suit is

to be decreed without any interest. In the absence of any

contract to the contrary, sought for allowing the appeal to

that extent.

15. Per contra, Sri.Nithin Prasad, learned counsel

for Sri.Vinay Giri representing the respondent contended

that there cannot be any set off with regard to sum of

Rs.1,68,305/-, inasmuch as, there was no claim made by

the defendant for return of the retention money and the

amount was retained by plaintiff for the satisfactory

- 20 -

NC: 2023:KHC:45596

working of the specialized machinery that was supplied by

the defendant to plaintiff as per the contract. Therefore,

such a plea cannot be entertained by this Court that too in

the appeal stage.

16. Further, he contended that sum of

Rs.3,31,800/- was paid for the fourth specialized

machinery and if defendant failed to supply the said

machinery in time, the same would result in terminating

the contract only with regard to supply of fourth

specialized machinery. Therefore, the said aspect of the

matter has been rightly appreciated by learned Trial judge

in the impugned judgment while decreeing the suit of the

plaintiff in toto and sought for dismissal of the appeal.

17. In view of the rival contentions of the parties,

this Court perused the material on record meticulously, on

such perusal of material on record, following points would

arise for consideration:

- 21 -

NC: 2023:KHC:45596

1) Whether the appellant has made out a case that it is not liable to pay a sum of Rs.3,31,800/- with interest as claimed in the suit?

2) If not, whether the appellant is entitled for seeking set off in a sum of Rs.1,68,305/- from the suit claim?

3) Whether the interest as ordered by the trial Court is justified?

4) Whether the impugned judgment is suffering from legal infirmity or perversity and thus calls for interference of this Court?

5) What order?

Reg. Point Nos.1 to 4:

18. In the case on hand, there is no dispute that

there was a contract between the plaintiff and defendant

with regard to supply of fourth specialized machinery. In

respect of the said contract, amounts were also paid by

the plaintiff to defendant.

- 22 -

NC: 2023:KHC:45596

19. The defendant manufactured three specialized

machinery and delivered it to the plaintiff and same is

accepted by the plaintiff and there is a satisfaction as to

the working of the special purpose machinery as per the

designs provided by the plaintiff. However, the plaintiff

retained a sum of Rs.82,805/- in respect of one special

purpose machinery and a sum of Rs.85,500/- in respect of

another special purpose machinery as retention money for

satisfactory working of those special purpose machinery.

Further, with regard to last special purpose machinery, the

parties were on logger heads, inasmuch as, according to

defendant, they have commenced the manufacture of the

special purpose machine as per the original drawing and in

the interregnum, plaintiff unilaterally changed the drawing

resulting in loss of defendant and they could not supply

the machinery in time, ultimately, resulting in termination

of the contract in part only with regard to fourth

specialized machinery. All these aspects of the matter are

borne out on record by both oral and documentary

evidence on record. Therefore, the task of the Court is to

- 23 -

NC: 2023:KHC:45596

find out whether the termination of the fourth contract was

justified. Learned Trial Judge has bestowed its attention

and taking note of the notice, reply and rejoinder, has

come to the conclusion that plaintiff was entitled to

terminate the contract in respect of fourth specialized

machinery as the same was not delivered in time.

20. The oral testimony in this regard is to be

considered as only oath against oath and without there

being any documentary proof thereon, the plaintiff has

exercised its right of termination as per the original

contract.

21. Defendant has also admitted that the fourth

specialized machinery could not be delivered in time.

However, according to defendant the explanation for the

delay is the modification in the original drawing.

22. In this regard, there is no specific material

available on record to show that delay is attributable only

to conduct of the plaintiff. Therefore, the finding recorded

- 24 -

NC: 2023:KHC:45596

by learned Trial Judge that plaintiff was entitled to

terminate the contract in part in respect of supply of the

fourth specialized machinery, is just and proper. Having

said so, the plaintiff having paid a sum of Rs.3,31,800/- to

the defendant in respect of fourth specialized machinery is

entitled for the refund of the same with interest.

23. The defendant cannot retain a sum of

Rs.3,31,800/- inasmuch as, it has failed to prove that

termination is on account of the modification in the

drawing by the plaintiff whereby, plaintiff could not have

terminated the contract unilaterally. Under such

circumstances, the amount of Rs.3,31,800/- retained by

the defendant in respect of fourth specialized machinery

would be treated as unjust enrichment as per Section 72

of the Indian Contract Act, 1872.

24. Therefore, defendant is bound to repay sum of

Rs.3,31,800/-. Accordingly point No.1 is to be answered

in negative.

- 25 -

NC: 2023:KHC:45596

REG.POINT NOS.2 TO 4:

25. Having said so, the material evidence available

on record especially, the cross-examination of P.W.1, which

has been found that sum of Rs.1,68,305/- is retained by

the plaintiff, was actually payable to defendant as

retention money in respect of supply of two specialized

machinery.

26. Admittedly, retention money is retained by the

plaintiff for the successful working of the two special

purpose machinery. There is no whisper in the plaint or

any correspondence made by the plaintiff that two of the

specialized machinery are not working properly nor it is

precised to the drawings, complied by the plaintiff. Under

such circumstances, plaintiff is bound to repay sum of

Rs.1,68,305/- retained by it on the same logic of 'Doctrine

of Unjust Enrichment'.

27. Taking note of these peculiar aspects of the

matter and amount of Rs.1,68,305/- being retained and

- 26 -

NC: 2023:KHC:45596

not paid in time, it should also carry interest and in the

absence of any contract to the contrary, a sum of

Rs.1,68,305/- is to be given retention out of sum of

Rs.3,31,800/- and the defendant is bound to pay a sum of

Rs.1,63,495/-.

28. However, in the absence of any contract to the

contrary, ordered interest at the rate of 9% would act as

false on the part of defendant in repaying the amount.

29. Modifying the interest at the rate of 6% at sum

of Rs.1,63,495/- from 14.05.1990 till its realization would

meet ends of justice. Accordingly, point Nos.2 to 4 are

answered in affirmative.

REG. POINT No.5:

30. In view of the findings of this Court on point

Nos.1 to 4 as above, following:

ORDER

(i) Appeal is allowed in part.

- 27 -

NC: 2023:KHC:45596

(ii) Decree of the Trial Court is modified as under:

Plaintiff is entitled to a sum of

Rs.1,63,495/- from the defendant at the

rate of 6% from 14.05.1990 till its

realization.

(iii) Office is directed to pass modified decree.

    (iv)    No order as to costs.




                                              Sd/-
                                             JUDGE

KAV

 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter