Citation : 2022 Latest Caselaw 9979 Kant
Judgement Date : 30 June, 2022
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 30TH DAY OF JUNE, 2022
PRESENT
THE HON'BLE MR. JUSTICE P.S.DINESH KUMAR
AND
THE HON'BLE MR. JUSTICE C.M. POONACHA
COMAP NO.251/2021
BETWEEN
MR. MAAZ AHMED SHARIEF
S/O AZIZ SHARIEF
R/AT NO. 548, 8TH MAIN
4TH BLOCK, KORAMANGALA
BENGALURU -560034
...APPELLANT
(BY SRI H.RAMACHANDRA, ADVOCATE)
AND
1. M/S PURUVANKARA PROJECTS LTD.,
(PRESENTLY KNOWN AS
M/S PURUVANKARA LTD.)
A COMPANY INCORPORATED UNDER
THE PROVISIONS OF COMPANIES ACT 1956
HAVING ITS REGISTERED OFFICE
AT NO. 130/1, ULSOOR ROAD,
BENGALURU -560042.
2. MR. RIYAZ AHMED SHARIEF
S/O AZIZ SHARIEF
AGED ABOUT YEARS
R/AT NO. 85, TAREEN BLOCK
3RD BLOCK, JAYANAGAR
BENGALURU -560011
...RESPONDENTS
(BY SRI SANJAY NAIR, ADVOCATE FOR R1)
2
THIS COMAP IS FILED UNDER SECTION 13(1-A) OF THE
COMMERCIAL COURTS ACT, 2015, PRAYING TO SET ASIDE THE
IMPUGNED ORDER PASSED IN COMMERCIAL A.S.NO.149/2018
PASSED BY THE HON'BLE LXXXVII ADDL. CITY CIVIL AND
SESSIONS JUDGE (EXCLUSIVE DEDICATED COMMERCIAL
COURT) AT BENGALURU (CCH-88) DATED 01.07.2021
CONSEQUENTLY AWARD IN CMP NO.83/2006 DATED
17.12.2012 PASSED BY THE SOLE ARBITRATOR IS ALSO LIABLE
TO BE SET ASIDE AND TO REMAND THE CASE TO THE HON'BLE
SOLE ARBITRATOR.
THIS COMAP COMING ON FOR ADMISSION ON
16.06.2022 AND HAVING BEEN HEARD AND RESERVED FOR
JUDGMENT, THIS DAY POONACHA J., PRONOUNCED THE
FOLLOWING:
JUDGMENT
This Appeal is filed challenging the judgment dated
01.07.2021 passed in Commercial AS No.149/2018 filed
under Section 34 of the Arbitration and Conciliation Act,
1996 (hereinafter referred to as the 'Act' for short) as well
as the Arbitral Award dated 17.12.2012 passed in CMP
No.83/2006.
2. The Appellant herein was arrayed as
Respondent No.2 before the Sole Arbitrator and he is
Plaintiff No.2 before the Commercial Court. Respondent
No.1 herein was Claimant before the Sole Arbitrator and
Defendant/Respondent before the Commercial Court.
Respondent No.2 herein was arrayed as Respondent No.1
before the Sole Arbitrator and Plaintiff No.1 before the
Commercial Court. It is also pertinent to note herein that
Commercial AS No.149/2018 filed before the Commercial
Court was filed by the Appellant herein as well as
Respondent No.2, whereas the present appeal has been
filed only by the Appellant who was Plaintiff No.2 before
the Commercial Court. Appellant is represented as the
GPA holder of the Respondent No.2.
3. For the sake of convenience, the parties will be
referred to as per their ranking before the Sole Arbitrator.
4. The Claimant filed the claim petition before the
Sole Arbitrator seeking for specific performance of the
Agreement dated 24.02.2003 and for the other reliefs.
The Sole Arbitrator vide Award dated 17.12.2012 ordered
that the Claimant was entitled for specific performance of
the Agreement dated 24.02.2003 and Sale Deed was
required to be executed by the Respondents in favour of
the Claimant, as also to deliver original title deeds and put
the Claimant in possession on receipt of the balance sale
consideration from the Claimant at the rate of Rs.310 per
sq.ft.
5. The Respondents being aggrieved by the
Arbitral Award, filed Commercial AS No.149/2018. The
Claimant contested the said proceedings. The Commercial
Court, after giving an opportunity to all the parties, vide its
judgment dated 01.07.2021, dismissed the application
filed by Respondents. Hence this appeal under Section 37
of the Act.
6. Learned counsel for the Appellant, in support
of this Appeal, urged the following contentions:
(a) that the document that was sought to be relied
upon by the Sole Arbitrator was insufficiently stamped and
hence, the same could not be relied upon by the Sole
Arbitrator;
(b) that the Appellant did not have sufficient
opportunity to put forth his case before the Sole Arbitrator;
(c) that the MOU dated 24.02.2003 was not a
registered document and having regard to Section
17(1)(a) of the Indian Registration Act, 1908 (hereinafter
referred to as "the Act, 1908" for short), the document
can be looked into only for collateral purposes and the Sole
Arbitrator gravely erred in considering the said document
in its entirety and ordering specific performance of the
same; and
(d) that the Commercial Court erred in not
exercising its jurisdiction under Section 34 of the Act in
interfering with the Award made by the Sole Arbitrator.
7. Per contra, the learned counsel for Respondent
No.1 contended:
(a) that the document which the Appellant is
alleging to be insufficiently stamped was not produced
either before the Sole Arbitrator or before the Commercial
Court or in this Appeal in a manner known to law and
hence, it is not open to the Appellant to put forth the said
contention regarding insufficiency of stamping in the
present Appeal for the first time;
(b) that the contention regarding insufficiency of
stamp is put forth before this Court for the first time and
the said contention was not put forth either before the Sole
Arbitrator or before the Commercial Court. Under the
circumstances, the Appellant is not entitled to put forth the
said contention regarding insufficiency of stamping in the
present Appeal for the first time;
(c) notwithstanding the fact that the contention
regarding insufficiency of stamping of the document is not
liable to be considered by this Court, no possession was
handed over under the said document, the stamp duty
paid is sufficient and the said document is not a
compulsorily registerable document as contemplated under
Section 17(1)(a) of the Indian Registration Act, 1908;
(d) that the Application filed under Section 34 for
setting aside the Arbitral Award made by the Sole
Arbitrator was barred by time; and
(e) that the Commercial Court, while considering
the Application filed under Section 34 of the Act
challenging the Award made by the Sole Arbitrator, has
followed the settled principles of law regarding the scope
of interference in Arbitral Awards and has rightly rejected
the Application filed under Section 34 of the Act.
8. We have given our anxious consideration to
the contentions put forth by the learned counsel for the
respective parties and perused the material on record.
9. Having regard to the contentions put forth by
the counsel for the respective parties, the point that arises
for our consideration is, "Whether the Commercial Court
erred in law in dismissing the Application filed under
Section 34 of the Act and in not interfering with the
Arbitral Award made by the Sole Arbitrator"?
10. The counsel for the Appellant has vehemently
contended that no sufficient opportunity was provided to
the Respondents before the Sole Arbitrator to contest the
claim made by the Claimant. It is pertinent to note that
the same contention was urged by the Appellant before the
Commercial Court and the Commercial Court has
considered the contentions of the parties in detail with
regard to the said aspect of the matter, more particularly
in paragraphs 13, 15, 17, 18 and 19 of the judgment dated
01.07.2021 and rightly rejected the said contention
because, it is forthcoming from the material on record that
Respondents had entered appearance and represented by
an Advocate before the learned Arbitrator, but they failed
to file any statement even after a lapse of more than nine
months. Hence, we find no good ground to interfere with
the finding recorded by the Commercial Court on this
aspect.
11. The other aspect that has been recorded by
the Commercial Court is, the application filed under
Section 34 of the Act was barred by limitation. It is
relevant to note that the Arbitral Award was passed on
17.12.2012 and the application under Section 34 of the Act
was preferred on 13.07.2018.
12. Section 34(3) of the Act specifically stipulates
that an application for setting aside the Award is required
to be made within three months. The proviso to Section
34(3) of the Act provides a further period of thirty days
within which an application under Section 34 could be
entertained provided, sufficient cause is demonstrated that
the applicant was prevented from making such application
within the stipulated time. The proviso further mandates
that beyond the said further period of thirty days, the
application cannot be entertained. As noticed by the
Commercial Court, the settled proposition of law as held in
the case of P.Radha Bai v. Ashok Kumar and another,
reported in (2019) 13 SCC 445, whereunder the Hon'ble
Supreme Court has held that the Arbitration Act being a
"special law" a specific period of limitation is stipulated
under Section 34(3) of the Act and there is no provision
under the Limitation Act dealing with challenging an Award
passed under the Arbitration Act, the provisions of the
Limitation Act cannot be applied for the purpose of
extending the period of limitation beyond what is
prescribed under Section 34(3) of the Act. Having noticed
the said aspect of the matter, the Commercial Court has
recorded a categorical finding that the application filed
under Section 34 of the Act is barred by time. The
Appellant has not been able to demonstrate as to how the
said finding on the aspect of limitation is erroneous or bad
in law and liable to be interfered with. Under the
circumstances, the said finding with regard to limitation as
recorded by the Commercial Court does not call for
interference.
13. At the time of arguments, counsel for the
Appellant vehemently contended that the MOU dated
24.02.2003 is insufficiently stamped and the same was
required to be impounded and this aspect is not looked
into by the Sole Arbitrator as well as the Commercial
Court. Counsel for the Appellant also relied on the
following judgments in support of the said contention;
1) N.N.Global Mercantile Pvt.Ltd., v.
Indo Unique Flame Ltd., and Ors., reported in (2021) 4 SCC 379; and
2) Widescreen Holdings Private Limited & Anr., Etc., v. Religare Finvest Limited & Anr., Etc., reported in 2022 LiveLaw (SC) 435.
14. It is to be noted that the contention regarding
insufficiency of payment of stamp duty on the MOU dated
24.02.2003 was not raised either before the Sole
Arbitrator or before the Commercial Court.
Notwithstanding the same, it is to be noted that the stamp
duty payable on the MOU at the relevant point of time i.e.,
the date of the MOU as per Article 5(iii)(e)(iv) of the
Karnataka Stamp (Amendment) Act, 1995, was Rs.200/-.
Hence, the said MOU dated 24.02.2003 is sufficiently
stamped. Under the circumstances, the decisions relied
upon by the counsel for the Appellant are inapplicable to
the facts of the present case.
15. Section 17 of the Act, 1908 stipulates the
documents of which registration is compulsory. Section
17(1) of the Act, 1908 stipulates the documents which are
compulsorily registerable. Section 17(1)(a) of the Act,
1908 applies to the documents where the benefit of part
performance is sought to be taken. Section 17(2) of the
Act, 1908 lists out the documents where Section
17(1)(a)(b) and (c) shall not apply. The learned counsel
for the Appellant is unable to demonstrate how Section 17
of the Act, 1908 will apply in the present case in respect of
the MOU in question. Under the circumstances, the said
contention put forth by the learned counsel for the
Appellant is also liable to be rejected.
16. It is also noticed by the Commercial Court that
a memo was filed furnishing a copy of the order sheet in
EP No.1764/2013, which discloses that after the Award has
been executed and a copy of the Sale Deed which was
executed pursuant to the Arbitral Award was furnished
before the Commercial Court and that the Claimant had
taken possession of the property by depositing the
consideration amount of Rs.1,22,66,190/- on 30.01.2019
itself.
17. The scope of interference under Section 37 of
the Act has been the subject matter of various judicial
pronouncements [(1) SSANGYONG Engineering and
Construction Company Limited v. National Highways
Authority of India (NHAI), reported in (2019) 15 SCC
131; (2) Patel Engineering Limited v. North Eastern
Electric Power Corporation Limited, reported in (2020)
7 SCC 167;(3) PSA SICAL Terminals Pvt. Ltd., v. Board
of Trustees of V.O Chidambranar Port Trust Tuticorin
and Others, reported in 2021 SCC OnLine SC 508; and
(4) Delhi Airport Metro Express Private Limited v.
Delhi Metro Rail Corporation Limited, reported in
(2022) 1 SCC 131)]. Considering the settled proposition of
law, as laid down in the aforementioned judgments, we are
of the considered opinion that the Commercial Court has
rightly exercised its jurisdiction under Section 34 of the Act
and refused to interfere with the Arbitral Award dated
17.12.2012 passed by the Sole Arbitrator. The Commercial
Court has considered the application filed under Section 34
of the Act by noticing the settled proposition of law with
regard to the scope of interference contemplated under
Section 34 of the Act and correctly appreciated the
relevant aspects of the matter and rightly refused to
interfere with the Award passed by the Sole Arbitrator.
Thus the Appellant has failed to demonstrate that the
judgment dated 01.07.2021 passed in Commercial AS
No.149/2018 warrants interference by this Court under
Section 37 of the Act.
18. It is open to the Appellant to participate in
EP.No.1764/2013 and agitate the same in accordance with
law.
19. In view of the above, this appeal must fail and
it is accordingly dismissed.
In view of the dismissal of the appeal, IA.3/2021
does not survive for consideration and is accordingly,
disposed of.
No costs.
Sd/-
JUDGE
Sd/-
JUDGE nd
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!