Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Aadyaarush Power Projects Pvt . ... vs State Of Karnataka
2021 Latest Caselaw 3352 Kant

Citation : 2021 Latest Caselaw 3352 Kant
Judgement Date : 20 September, 2021

Karnataka High Court
Aadyaarush Power Projects Pvt . ... vs State Of Karnataka on 20 September, 2021
Author: M.Nagaprasanna
                          1



     IN THE HIGH COURT OF KARNATAKA AT BENGALURU

      DATED THIS THE 20TH DAY OF SEPTEMBER, 2021      R
                       BEFORE

       THE HON'BLE MR. JUSTICE M. NAGAPRASANNA

         WRIT PETITION No.52028/2018 (GM-KEB)
                         C/W
         WRIT PETITION No.57898/2017 (GM-KEB)
         WRIT PETITION No.30716/2018 (GM-KEB)
         WRIT PETITION No.7358/2020 (GM-KEB)
         WRIT PETITION No.7675/2020 (GM-KEB)
         WRIT PETITION No.7698/2020 (GM-KEB)
         WRIT PETITION No.7724/2020 (GM-KEB)
         WRIT PETITION No.7782/2020 (GM-KEB)
         WRIT PETITION No.7930/2020 (GM-KEB)
         WRIT PETITION No.12611/2020 (GM-KEB)
         WRIT PETITION No.12637/2020 (GM-KEB)
         WRIT PETITION No.12644/2020 (GM-KEB)

IN WRIT PETITION No.52028/2018

BETWEEN:

AADYAARUSH POWER PROJECTS PVT. LTD.,
A COMPANY REGISTERED UNDER COMPANIES ACT,2013,
HAVING ITS REGISTERED OFFICE AT 139/12,
5TH MAIN ROAD, CHAMRAJPET,
BENGALURU - 560 018
REPRESENTED BY ITS DIRECTOR,
MR. AMARTHYA RAJASHEKARAPPA.
                                     ... PETITIONER
(BY SRI MANMOHAN P.N., ADVOCATE )

AND:

1.     STATE OF KARNATAKA
       DEPARTMENT OF ENERGY,
                         2



     VIKASA SOUDHA,
     DR.B.R.AMBEDKAR STREET,
     BENGALURU - 560 001
     REPRESENTED BY ITS
     CHIEF SECRETARY.

2.   BANGALORE ELECTRICITY SUPPLY
     COMPANY LTD.,
     A COMPANY REGISTERED UNDER
     COMPANIES ACT, 1956,
     HAVING ITS REGISTERED OFFICE AT
     K.R.ROAD, BENGALURU - 560 001
     REPRESENTED BY ITS
     MANAGING DIRECTOR.

3.   KARNATAKA RENEWABLE ENERGY
     DEVELOPMENT LTD.,
     A COMPANY REGISTERED UNDER
     COMPANIES ACT, 1956,
     HAVING ITS REGISTERED OFFICE
     AT NO.39, SHANTHIGRUHA,
     BHARATH SCOUTS & GUIDES BUILDING,
     PALACE ROAD, GANDHI NAGAR,
     BENGALURU - 560 001
     REPRESENTED BY ITS
     MANAGING DIRECTOR.

4.   KARNATAKA POWER
     TRANSMISSION CORPORATION LTD.,
     A COMPANY REGISTERED UNDER
     COMPANIES ACT, 1956,
     HAVING ITS REGISTERED OFFICE
     AT KAVERI BHAVAN, K.G.ROAD,
     BENGALURU - 560 009
     REPRESENTED BY ITS
     MANAGING DIRECTOR.

5.   KARNATAKA ELECTRICITY
     REGULATORY COMMISSION
     NO.16, C-1, MILLERS TANK BED AREA,
                           3



     VASANTH NAGAR,
     BENGALURU - 560 052
     REPRESENTED BY ITS SECRETARY.
                                 ... RESPONDENTS

(BY SMT.M.C.NAGASHREE, AGA FOR R1;
    SRI S.SRIRANGA, ADVOCATE FOR R2;
    SRI B.N.PRAKASH, ADVOCATE FOR R5;
    NOTICE TO R3 & 4 DISPENSED WITH VIDE ORDER
    DATED 06/12/2018)

     THIS WRIT PETITION IS FILED UNDER ARTICLES 226
AND 227 OF THE CONSTITUTION OF INDIA PRAYING TO
ISSUE A WRIT OF CERTIORARY AND QUASH THE
COMMUNICATION DATED 16.3.2017 ISSUED BY R-5 AT
ANNEX-S; ISSUE A WRIT OF CERTIORARY AND QUASH
THE COMMUNICATION DATED 05.04.2017 ISSUED BY R-5
AT ANNEX-T;

IN WRIT PETITION No.57898/2017

BETWEEN:

1.   SRI H.V.THIMMAIAH
     S/O LATE VEERAPPA
     AGED ABOUT 72 YEARS
     NO.76, HARIABBE, HIRIYUR TALUK,
     CHITRADURGA DISTRICT - 577 598.

2.   M/S B.G.SUN SOLAR HIRIYUR PRIVATE LIMITED
     HAVING ITS REGISTERED OFFICE AT
     NO.368, 2ND MAIN, BEML LAYOUT
     1ST STAGE, BASAVESHWARANAGAR
     BENGALURU - 560 079
     REPRESENTED BY ITS DIRECTOR
     MR.V.G.ANGADI.
                                    ... PETITIONERS

(BY SRI SUNIL P.P., ADVOCATE)
                          4



AND:

1.     THE STATE OF KARNATAKA,
       REPRESENTED BY
       THE ADDITIONAL CHIEF SECRETARY
       ENERGY DEPARTMENT
       VIKASASOUDHA,
       BENGALURU - 560 001.

2.     KARNATAKA ELECTRICITY REGULATORY
       COMMISSION
       6TH & 7TH FLOOR, MAHALAKSHMI CHAMBERS
       NO.9/2. M.G.ROAD
       BENGALURU - 560 001
       REPRESENTED BY ITS SECRETARY.

3.     THE KARNATAKA RENEWABLE ENERGY
       DEPARTMENT LTD.,
       NO.39, "SHANTHIGRUHA"
       BHARATH SCOUTS &
       GUIDES BUILDING
       OPP.: THE CHIEF
       POST MASTER GENERAL OFFICE
       PALACE ROAD,
       BENGALURU - 560 001
       REPRESENTED BY THIS
       MANAGING DIRECTOR.

4.     BENGALURU ELECTRICITY SUPPLY
       COMPANY LIMITED,
       A COMPANY REGISTERED
       UNDER THE PROVISIONS OF
       COMPANIES ACT, 1956 HAVING ITS
       REGISTERED OFFICE AT K.R.CIRCLE ,
       BENGALURU - 560 001
       REPRESENTED BY ITS MANAGING DIRECTOR.

5.     THE GENERAL MANAGER (ELE)
       POWER PURCHASE, BESCOM
                         5



     K.R.CIRCLE
     BENGALURU - 560 001.

6.   THE CHIEF ENGINEER ELECTY.
     TRANSMISSION ZONE, KPTCL
     SIDDAGANGA COMPLEX , BH ROAD
     TUMAKURU - 527 107.

7.   THE EXECUTIVE ENGINEER
     220 KV SRS, KPTCL,
     HIRIYUR - 577 598.
                                   ... RESPONDENTS

(BY SMT.M.C.NAGASHREE, AGA FOR R1;
    SRI B.N.PRAKASH, ADVOCATE FOR R2;
    SRI MURUGESH V.CHARATI, ADVOCATE FOR R3;
    SRI SHAHBAAZ HUSAIN, ADVOCATE FOR R4, R6 & 7;
    R-5 SERVED)

     THIS WRIT PETITION IS FILED UNDER ARTICLES 226
AND 227 OF THE CONSTITUTION OF INDIA PRAYING TO
QUASH THE COMMUNICATION/LETTER DTD 07.07.2017
AT ANNX-Z, ISSUED BY THE R-2; QUASH THE
COMMUNICATION/LETTER DTD 01.08.2017, ISSUED BY
THE R-1 VIDE ANNEXURE-Z1.

IN WRIT PETITION No.30716/2018

BETWEEN:

M/S S.G.ARAKERI SOLAR POWER
PRIVATE LIMITED
HAVING ITS REGISTERED
OFFICE AT:NO.658/8, 2ND FLOOR,
1ST "C" MAIN ROAD,
40TH CROSS, 8TH BLOCK,
JAYANAGARA, BENGALURU - 560 082
REPRESENTED BY ITS DIRECTOR
SRI ISHWAR HEGDE.
                                      ... PETITIONER
                          6



(BY SRI GANAPATI BHAT VAJRALLI, ADVOCATE)

AND:

1.     THE STATE OF KARNATAKA
       REPRESENTED BY ITS CHIEF SECRETARY,
       ROOM NO.320,3RD FLOOR,
       VIDHANA SOUDHA,
       DR AMBEDKAR VEEDI,
       BENGALURU-560 001

2.     THE ADDITIONAL CHIEF SECRETARY
       GOVERNMENT OF KARNATAKA,
       ENERGY DEPARTMENT,
       ROOM NO.236, 2ND FLOOR,
       VIKASA SOUDHA,
       DR AMBEDKAR VEEDI
       BENGALURU - 560 001.

3.     KARNATAKA ELECTRICITY
       REGULATORY COMMISSION
       NO.16, C-1, MILLERS BED AREA,
       VASANTHNAGAR,
       BENGALURU - 560 052
       REPRESENTED BY ITS CHAIRMAN.

4.     M/S HUBLI ELECTRICITY SUPPLY
       COMPANY LIMITED (HESCOM)
       OFFICE AT:NAVANAGAR, P.B.ROAD,
       HUBBALLI - 580 025
       REPRESENTED BY ITS
       MANAGING DIRECTOR.

5.     M/S KARNATAKA RENEWABLE ENERGY
       DEVELOPMENT LIMITED,
       NO.39,"SHANTHIGRUHA"
       BHARATH SCOUTS AND GUIDES
       BUILDING, PALACE ROAD,
       BENGALURU - 560 003.
                                  ... RESPONDENTS
                           7



(BY SMT.M.C.NAGASHREE, AGA FOR R1 AND R2;
    SRI B.N.PRAKASH, ADVOCATE FOR R3;
    SRI SHAHBAAZ HUSAIN, ADVOCATE FOR R4;
    SRI MURUGESH V.CHARATI, ADVOCATE FOR R5)

     THIS WRIT PETITION IS FILED UNDER ARTICLES 226
AND 227 OF THE CONSTITUTION OF INDIA PRAYING TO
QUASH THE IMPUGNED DIRECTION DATED 05.04.2017,
ISSUED BY THE 3RD RESPONDENT, AS PER ANNEXURE-Q
AND LETTER DATED 07.07.2017, ISSUED BY THE 3RD
RESPONDENT AS PER ANNEXURE-T AND ETC.,

IN WRIT PETITION No.7358/2020

BETWEEN:

M/S SAAKESHA SOLAR ENERGY PRIVATE LIMITED
HAVING ITS REGISTERED OFFICE AT
NO.658/8, 2ND FLOOR, F, 1ST 'C' MAIN ROAD,
40TH CROSS, 8TH BLOCK, JAYANAGAR,
BENGALURU - 560 082,
REPRESENTED BY ITS DIRECTOR,
SRI ISHWAR HEGDE.
                                         ... PETITIONER

(BY SRI GANAPATI BHAT VAJRALLI, ADVOCATE)

AND:

1.     M/S BANGALORE ELECTRICITY SUPPLY
       COMPANY LIMITED (BESCOM)
       OFFICE AT K.R.CIRCLE,
       BENGALURU - 560 001,
       REPRESENTED BY ITS
       MANAGING DIRECTOR.

2.     KARNATAKA POWER TRANSMISSION
       CORPORATION LIMITED
       CAVERI BHAVAN,
       BENGALURU - 560 001,
                         8



     REPRESENTED BY ITS
     MANAGING DIRECTOR.

3.   THE KREDL
     SHANTHI GRUHA, NO.39,
     BHARATH SCOUTS AND
     GUIDES BUILDING,
     OPPOSITE THE CHIEF
     POST MASTER GENERAL OFFICE,
     PALACE ROAD, BENGALURU - 560 001.

4.   THE DEPUTY COMMISSIONER
     DISTRICT ADMINISTRATIVE BHAVAN,
     SHIDLAGATTA ROAD,
     CHIKKABALLAPUR - 562 101.

5.   KARNATAKA ELECTRICITY
     REGULATORY COMMISSION
     NO.16, C-1, MILLARS BED AREA,
     VASANTHNAGAR,
     BENGALURU - 560 052,
     REPRESENTED BY ITS CHAIRMAN.

                                     ... RESPONDENTS

(BY SRI S.SRIRANGA, ADVOCATE FOR R1 AND R2;
    SRI MURUGESH V.CHARATI, ADVOCATE FOR R3;
    SMT.M.C.NAGASHREE, AGA FOR R4;
    SRI B.N.PRAKASH, ADVOCATE FOR R5)

     THIS WRIT PETITION IS FILED UNDER ARTICLES 226
AND 227 OF THE CONSTITUTION OF INDIA PRAYING TO
QUASH THE IMPUGNED ORDER DATED 30.08.2018 IN
O.P.NO.161/2017 PASSED BY THE R-5 AS PER
ANNEXURE-H AND ALLOW THE O.P.NO.161/2017 BY
GRANTING AN AMOUNT OF RS.8.40/- PER UNIT AS PER
THE PPA AND ETC.,
                         9



IN WRIT PETITION No.7675/2020

BETWEEN:

M/S GAVI RANGA SOLARS PRIVATE LIMITED
HAVING ITS REGISTERED
OFFICE AT NO.658/8,
2ND FLOOR, F, 2ND 'C' MAIN ROAD,
40TH CROSS, 8TH BLOCK,
JAYANAGAR,
BENGALURU - 560 082,
REPRESENTED BY ITS DIRECTOR,
SRI ISHWAR HEGDE.
                                     ... PETITIONER
(BY SRI GANAPATHY BHAT VAJRALLI, ADVOCATE
    (PHYSICAL HEARING))

AND:

1.     M/S CHAMUNDESHWARI ELECTRICITY SUPPLY
       CORPORATION LIMITED (CESC, MYSORE),
       NO.29, VIJAYANAGAR 2ND STAGE,
       HINKAL, MYSURU - 570 017
       REPRESENTED BY ITS
       GENERAL MANAGER (COMMERCIAL)

2.     M/S BANGALORE ELECTRICITY SUPPLY
       COMPANY LIMITED (BESCOM),
       OFFICE AT: K.R.CIRCLE,
       BENGALURU - 560 001,
       REPRESENTED BY ITS
       MANAGING DIRECTOR.

3.     KARNATAKA POWER TRANSMISSION
       CORPORATION LIMITED
       CAVERI BHAVAN,
       BENGALURU - 560 001,
       REPRESENTED BY ITS
       MANAGING DIRECTOR.
                         10



4.   THE KREDL
     SHANTHI GRUHA, NO.39,
     BHARATH SCOUTS AND
     GUIDES BUILDING,
     OPPOSITE THE CHIEF
     POST MASTER GENERAL OFFICE,
     PALACE ROAD, BENGALURU - 560 001
     REPRESENTED BY
      ITS MANAGING DIRECTOR.

5.   KARNATAKA ELECTRICITY REGULATORY
     COMMISSION
     NO.16, C-1, MILLERS BED
     AREA, VASANTHNAGAR,
     BENGALURU-560 052,
     REPRESENTED BY ITS CHAIRMAN.

6.   THE DEPUTY COMMISSIONER
     DISTRICT ADMINISTRATIVE BHAVAN,
     SHIDLAGATTA ROAD,
     CHIKKABALLAPUR-562101.
                                  ... RESPONDENTS

(BY SRI S.SRIRANGA, ADVOCATE FOR R1.
    R2 & R3 ARE SERVED
    SRI.MURUGESH V.CHARATI, ADVOCATE FOR R4;
    SRI B.N.PRAKASH, ADVOCATE FOR R5;
    SMT.M.C.NAGASHREE, AGA FOR R6 (PHYSICAL
    HEARING))

     THIS WRIT PETITION IS FILED UNDER ARTICLES 226
AND 227 OF THE CONSTITUTION OF INDIA PRAYING TO
QUASH THE IMPUGNED ORDER DTD.28.8.2018 IN
O.P.NO.163/2017 PASSED BY THE R-5 AS PER
ANENXURE-H AND ALLOW THE O.P.NO.163/2017 BY
GRANTING AN AMOUNT OF RS.8.40/- PER UNIT AS PER
THE PPA AND ETC.,
                           11



IN WRIT PETITION No.7698/2020

BETWEEN:

M/S LRK SOLAR POWER PRIVATE LIMITED
HAVING ITS REGISTERED OFFICE AT
NO.658/8, 2ND FLOOR, F, 1ST 'C' MAIN ROAD,
40TH CROSS, 8TH BLOCK, JAYANAGAR,
BENGALURU - 560 082
REPRESENTED BY ITS DIRECTOR
SRI ISHWAR HEGDE.
                                         ... PETITIONER
(BY SRI GANAPATHI BHAT VAJRALLI, ADVOCATE)

AND:

1.     M/S. BANGALORE ELECTRICITY SUPPLY
       COMPANY LIMITED (BESCOM)
       OFFICE AT K.R.CIRCLE,
       BENGALURU - 560 001.
       REPRESENTED BY ITS MANAGIR DIRECTOR

2.     KARNATAKA POWER TRANSMISSION
       CORPORATION LIMITED
       CAVERI BHAVAN, BENGALURU - 560 001
       REPRESENTED BY ITS MANAGING DIRECTOR.

3.     THE KREDL
       SHANTHI GRUHA, NO.39,
       BHARATH SCOUTS AND GUIDES BUILDING,
       OPPOSITE THE CHIEF POST MASTER
       GENERAL OFFICE,
       PALACE ROAD, BENGALURU - 560 001.

4.     THE DEPUTY COMMISSIONER
       DISTRICT ADMINISTRATIVE BHAVAN,
       SHIDLAGATTA ROAD,
       CHIKKABALLAPUR - 562 101.
                           12



5.     KARNATAKA ELECTRICITY REGULATORY
       COMMISSION
       NO.16, C-1, MILLERS BED AREA,
       VASANTHNAGAR,
       BENGALURU - 560 052
       REPRESENTED BY ITS CHAIRMAN.
                                     ... RESPONDENTS

(BY SRI SHAHBAAZ HUSAIN, ADVOCATE FOR R1 & R2;
    SRI MURUGESH V.CHARATI, ADVOCATE FOR R3;
    SMT.M.C.NAGASHREE, AGA FOR R4;
    SRI B.N.PRAKSH, ADVOCATE FOR R5)

     THIS WRIT PETITION IS FILED UNDER ARTICLES 226
AND 227 OF THE CONSTITUTION OF INDIA PRAYING TO
QUASH THE IMPUGNED ORDER DATED 27.09.2018 IN
O.P.NO.165/2017 PASSED BY THE R-5 AS PER
ANNEXURE-H AND ALLOW THE O.P.NO.165/2017 BY
GRANTING AN AMOUNT OF RS.8.40/- PER UNIT AS PER
THE PPA AND ETC.,

IN WRIT PETITION No.7724/2020

BETWEEN:

M/S MNR SOLAR ENERGY PRIVATE LIMITED
HAVING ITS REGISTERED OFFICE AT
NO.658/8, 2ND FLOOR, F, 1ST 'C' MAIN ROAD,
40TH CROSS, 8TH BLOCK, JAYANAGAR,
BENGALURU - 560 082,
REPRESENTED BY ITS DIRECTOR,
SRI.ISHWAR HEGDE.
                                         ... PETITIONER

(BY SRI GANAPATI BHAT VAJRALLI, ADVOCATE)

AND:

1.     M/S BANGALORE ELECTRICITY SUPPLY
       COMPANY LIMITED (BESCOM)
                          13



     OFFICE AT: K.R.CIRCLE,
     BENGALURU - 560 001,
     REPRESENTED BY ITS
     MANAGING DIRECTOR.

2.   KARNATAKA POWER
     TRANSMISSION CORPORATION LIMITED
     CAVERI BHAVAN,
     BENGALURU - 560 001,
     REPRESENTED BY ITS
     MANAGING DIRECTOR.

3.   THE KREDL
     SHANTHI GRUHA, NO.39,
     BHARATH SCOUTS AND
     GUIDES BUILDING,
     OPPOSITE THE CHIEF POST
     MASTER GENERAL OFFICE,
     PALACE ROAD, BENGALURU - 560 001.

4.   THE DEPUTY COMMISSIONER
     DISTRICT ADMINISTRATIVE BHAVAN,
     SHIDLAGATTA ROAD,
     CHIKKABALLAPUR - 562 101.

5.   KARNATAKA ELECTRICITY
     REGULATORY COMMISSION
     NO.16, C-1, MILLERS BED AREA,
     VASANTHNAGAR,
     BENGALURU-560 052,
     REPRESENTED BY ITS CHAIRMAN.

                                     ... RESPONDENTS

(BY SRI SHAHBAAZ HUSAIN, ADVOCATE FOR R1 AND R2;
    SRI MURUGESH V.CHARATI, ADVOCATE FOR R3
    SMT.M.C.NAGASHREE, AGA FOR R4;
    SRI B.N.PRAKASH, ADVOCATE FOR R5)
                           14



     THIS WRIT PETITION IS FILED UNDER ARTICLES 226
AND 227 OF THE CONSTITUTION OF INDIA PRAYING TO
QUASH THE IMPUGNED ORDER DATED 21.08.2018 IN
O.P.NO.158/2017 PASSED BY THE R-5 AS PER
ANNEXURE-H AND ALLOW THE OP NO.158/2017 BY
GRANTING AN AMOUNT OF RS.8.40/- PER UNIT AS PER
THE PPA AND ETC.,

IN WRIT PETITION No.7782/2020

BETWEEN:

M/S NADAGOUDA ENERGIES PRIVATE LIMITED
HAVING ITS REGISTERED OFFICE AT
NO.658/8, 2ND FLOOR, F, 1ST 'C' MAIN ROAD,
40TH CROSS, 8TH BLOCK, JAYANAGAR,
BENGALURU - 560 082
REPRESENTED BY DIRECTOR
SRI ISHWAR HEGDE.
                                         ... PETITIONER
(BY SRI GANAPATI BHAT VAJRALLI, ADVOCATE)

AND:

1.     M/S. HUBLI ELECTRICITY SUPPLY COMPANY
       LIMITED (HESCOM)
       OFFICE AT NAVANAGAR, HUBLI - 580 025
       REPRESENTED BY ITS
       MANAGING DIRECTOR.

2.     KARNATAKA POWER TRANSMISSION CORPORATION
       LIMITED
       CAVERI BHAVAN, BENGALURU - 560 001
       REP BY ITS MANAGING DIRECTOR

3.     THE KREDL
       SHANTHI GRUHA NO.39,
       BHARATH SCOUTS AND GUIDES BUILDING,
       OPPOSITE THE CHIEF POST MASTER GENERAL
       OFFICE,
                           15



     PALACE ROAD, BENGALURU - 560 001.

4.   THE DEPUTY COMMISSIONER
     DISTRICT ADMINISTRATIVE BHAVAN,
     SHIDLAGATTA ROAD,
     CHIKABALLAPUR-562 101

5.   KARNATAKA ELECTRICITY REGULATORY
     COMMISSION
     NO.16, C-1, MILLERS BED AREA,
     VASANTHNAGAR,
     BENGALURU-560 052
     REPRESENTED BY ITS
     CHAIRMAN.

                                      ... RESPONDENTS

(BY SRI HOMESH KIRAN N., ADVOCATE FOR R1 AND R2;
    SRI MURUGESH V.CHARATI, ADVOCATE FOR R3;
    SMT.M.C.NAGASHREE, AGA FOR R4;
    R5 SERVED))

     THIS WRIT PETITION IS FILED UNDER ARTICLES 226
AND 227 OF THE CONSTITUTION OF INDIA PRAYING TO
QUASH THE IMPUGNED ORDER DTD.25.9.2018 IN
O.P.NO.155/2017 PASSED BY THE R-5 AS PER
ANNEXURE-H AND ALLOW THE O.P.NO.155/2017 BY
GRANTING AN AMOUNT OF RS.8.40/- PER UNIT AS PER
THE PPA AND ETC.,

IN WRIT PETITION No.7930/2020

BETWEEN:

M/S CHOWDESHWARI SOLAR ENERGY
PRIVATE LIMITED
HAVING ITS REGISTERED OFFICE AT
NO.658/8, 2ND FLOOR, F, 1ST 'C' MAIN ROAD,
40TH CROSS, 8TH BLOCK, JAYANAGAR,
BENGALURU - 560 082,
                           16



REPRESENTED BY ITS DIRECTOR,
SRI.ISHWAR HEGDE.
                                         ... PETITIONER
(BY SRI GANAPATHI BHAT VAJRALLI, ADVOCATE)
AND:

1.     M/S BANGALORE ELECTRICITY SUPPLY
       COMPANY LIMITED (BESCOM)
       OFFICE AT: K.R.CIRCLE,
       BENGALURU - 560 001,
       REPRESENTED BY ITS
       MANAGING DIRECTOR.

2.     KARNATAKA POWER TRANSMISSION
       CORPORATION LIMITED
       CAVERI BHAVAN, BENGALURU - 560 001,
       REPRESENTED BY ITS
       MANAGING DIRECTOR.

3.     THE KREDL
       SHANTHI GRUHA, NO.39,
       BHARATH SCOUTS AND GUIDES BUILDING,
       OPPOSITE THE CHIEF POST MASTER GENERAL
       OFFICE, PALACE ROAD,
       BENGALURU - 560 001.
       REPRESENTED BY ITS MANAGING DIRECTOR.

4.     THE DEPUTY COMMISSIONER
       DISTRICT ADMINISTRATIVE BHAVAN,
       SHIDLAGATTA ROAD,
       CHIKKABALLAPUR - 562 101

5.     KARNATAKA ELECTRICITY
       REGULATORY COMMISSION
       NO.16, C-1, MILLAES BED AREA,
       VASANTHNAGAR,
       BENGALURU-560 052,
       REPRESENTED BY ITS CHAIRMAN
                                       ... RESPONDENTS
                           17



(BY SRI SHAHBAAZ HUSAIN, ADVOCATE FOR R1 AND R2;
    SRI MURUGESH V.CHARATI, ADVOCATE FOR R3;
    SMT.M.C.NAGASHREE, AGA FOR R4;
    SRI B.N.PRAKASH, ADVOCATE FOR R5)

     THIS WRIT PETITION IS FILED UNDER ARTICLES 226
AND 227 OF THE CONSTITUTION OF INDIA PRAYING TO
QUASH THE IMPUGNED ORDER DATED 28.08.2018 IN
O.P.NO.164/2017 PASSED BY THE R-5 AS PER
ANNEXURE-H AND ALLOW THE OP.NO.164/2017 BY
GRANTING AN AMOUNT OF RS.8.40/- PER UNIT AS PER
THE PPA AND ETC.,

IN WRIT PETITION No.12611/2020

BETWEEN:

M/S. LPD SOLAR POWER PRIVATE LIMITED
HAVING ITS REGISTERED OFFICE AT
NO.658/8, 2ND FLOOR, F, 1ST 'C' MAIN ROAD,
40TH CROSS, 8TH BLOCK, JAYANAGAR,
BENGALURU - 560 082
REPRESENTED BY ITS DIRECTOR
SRI.ISHWAR HEGDE.
                                         ... PETITIONER

(BY SRI GANAPATHI BHAT VAJRALLI, ADVOCATE)

AND:

1.     M/S BANGALORE ELECTRICITY SUPPLY COMPANY
       LIMITED (BESCOM)
       OFFICE AT K.R.CIRCLE,
       BENGALURU - 560 001
       REPRESENTED BY ITS
       MANAGIANG DIRECTOR.

2.     KARNATAKA POWER TRANSMISSION
       CORPORATION LTD.,
       CAVERI BHAVAN, BENGALURU - 560 001
                         18



     REPRESENTED BY
     ITS MANAGING DIRECTOR.

3.   THE KREDL
     SHANTHI GRUHA, NO.39,
     BHARATH SCOUTS AND GUIDES BUILDING,
     OPPOSITE THE CHIEF POST MASTER
     GENERAL OFFICE,
     PALACE ROAD, BENGALURU - 560 001.

4.   THE DEPUTY COMMISSIONER
     DISTRICT ADMINISTRATIVE BHAVAN,
     SHIDLAGATTA ROAD,
     CHIKKABALLAPUR - 562 101.

5.   KARNATAKA ELECTRICITY
     REGULATORY COMMISSION
     NO.16, C-1, MILLERS BED AREA,
     VASANTHNAGAR,
     BENGALURU - 560 052
     REPRESENTED BY ITS CHAIRMAN.
                                     ... RESPONDENTS

(BY SRI SHAHBAAZ HUSAIN, ADVOCATE FOR R1 AND R2;
    SRI MURUGESH V.CHARATI, ADVOCATE FOR R3;
    SMT.M.C.NAGASHREE, AGA FOR R4;
    SRI B.N.PRAKASH, ADVOCATE FOR R5)

     THIS WRIT PETITION IS FILED UNDER ARTICLES 226
AND 227 OF THE CONSTITUTION OF INDIA PRAYING TO
QUASH THE IMPUGNED ORDER DATED 27.09.2018 IN
O.P.NO.166/2017 PASSED BY THE R-5 AS PER
ANNEXURE-H AND ALLOW THE O.P.NO.166/2017 BY
GRANTING AN AMOUNT OF RS.8.40/- PER UNIT AS PER
THE PPA AND ETC.,
                           19



IN WRIT PETITION No.12637/2020

BETWEEN:

M/S SRI UGRAPPA SOLAR PRIVATE LIMITED
HAVING ITS REGISTERED OFFICE AT
NO.658/8, 2ND FLOOR, F, 1ST 'C' MAIN ROAD,
40TH CROSS, 8TH BLOCK, JAYANAGAR,
BENGALURU - 560 082,
REPRESENTED BY ITS DIRECTOR,
SRI ISHWAR HEGDE.
                                         ... PETITIONER
(BY SRI GANAPATHI BHAT VAJRALLI, ADVOCATE)

AND:

1.     M/S BANGALORE ELECTRICITY SUPPLY
       COMPANY LIMITED (BESCOM)
       OFFICE AT: K.R.CIRCLE,
       BENGALURU - 560 001,
       REPRESENTED BY ITS
       MANAGING DIRECTOR.

2.     KARNATAKA POWER TRANSMISSION
       CORPORATION LIMITED
       CAVERI BHAVAN,
       BENGALURU - 560 009,
       REPRESENTED BY ITS
       MANAGING DIRECTOR.

3.     THE KREDL
       SHANTHI GRUHA, NO.39,
       BHARATH SCOUTS AND
       GUIDES BUILDING,
       OPPOSITE THE CHIEF
       POST MASTER GENERAL OFFICE,
       PALACE ROAD,
       BENGALURU - 560 001.
                           20



4.   DEPUTY COMMISSIONER
     DISTRICT ADMINISTRATIVE BHAVAN,
     SHIDLAGATTA ROAD,
     CHIKKABALLAPUR - 562 101.

5.   KARNATAKA ELECTRICITY
     REGULATORY COMMISSION
     NO.16, C-1, MILLERS BED AREA,
     VASANTHNAGAR,
     BENGALURU - 560 052,
     REPRESENTED BY ITS CHAIRMAN.
                                      ... RESPONDENTS

(BY SRI SHAHBAAZ HUSAIN, ADVOCATE FOR R1 & R2;
    SRIMURUGESH V.CHARATI, ADVOCATE FOR R3;
    SMT.M.C.NAGASHREE, AGA FOR R4
    SRI B.N.PRAKASH, ADVOCATE FOR R5)

     THIS WRIT PETITION IS FILED UNDER ARTICLES 226
AND 227 OF THE CONSTITUTION OF INDIA PRAYING TO
QUASH THE IMPUGNED ORDER DATED 29.05.2018 IN
O.P.NO.148/2017 PASSED BY THE R-5, AS PER
ANNEXURE-H AND ALLOW THE O.P. NO. 148/2017 BY
GRANTING AN AMOUNT OF RS 8.40/- PER UNIT AS PER
THE PPA AND ETC.,

IN WRIT PETITION No.12644/2020

BETWEEN:

M/S POORVAJ SOLAR ENERGY PRIVATE LIMITED
HAVING ITS REGISTERED OFFICE AT:
NO.658/8, 2ND FLOOR, F, 1ST 'C' MAIN ROAD,
40TH CROSS, 8TH BLOCK, JAYANAGAR,
BENGALURU - 560 082
REPRESENTED BY ITS DIRECTOR
SRI ISHWAR HEGDE.
                                         ... PETITIONER
(BY SRI GANAPATHY BHAT VAJRALLI, ADVOCATE)
                           21



AND:

1.     M/S. BANGALORE ELECTRICITY
       SUPPLY COMPANY LIMITED (BESCOM)
       OFFICE AT: K.R.CIRCLE,
       BENGALURU - 560 001
       REPRESENTED BY
       MANAGING DIRECTOR.

2.     KARNATAKA POWER TRANSMISSION
       CORPORATION LIMITED
       CAVERI BHAVAN,
       BENGALURU - 560 009
       REPRESENTED BY
       MANAGING DIRECTOR.


3.     THE KREDL
       SHANTHI GRUHA, NO.39,
       BHARATH SCOUTS AND GUIDES BUILDING,
       OPPOSITE THE CHIEF POST MASTER
       GENERAL OFFICE,
       PALACE ROAD, BENGALURU - 560 001
       REPRESENTED BY ITS MANAGING DIRECTOR.

4.     THE DEPUTY COMMISSIONER
       DISTRICT ADMINISTRATIVE BHAVAN,
       SHIDLAGATTA ROAD,
       CHIKKABALLAPUR - 562 101.

5.     KARNATAKA ELECTRICITY
       REGULATORY COMMISSION
       NO.16, C-1, MILLERS BED AREA,
       VASANTHNAGAR,
       BENGALURU - 560 052
       REPRESENTED BY CHAIRMAN.
                                       ... RESPONDENTS

(BY SRI SHAHBAAZ HUSAIN, ADVOCATE R1 AND R2
    SRI MURUGESH V.CHARATI, ADVOCATE FOR R3;
                               22



      SMT.M.C.NAGASHREE, AGA FOR R4;
      SRI B.N.PRAKASH, ADVOCATE FOR R5)

     THIS WRIT PETITION IS FILED UNDER ARTICLES 226
AND 227 OF THE CONSTITUTION OF INDIA PRAYING TO
QUASH THE IMPUGNED ORDER DATED 28.08.2018 IN
O.P.NO.167/2017 PASSED BY THE R-5, AS PER
ANNEXURE-H AND ALLOW THE O.P. NP. 167/2017 BY
GRANTING AN AMOUNT OF RS 8.40/- PER UNIT AS PER
THE PPA AND ETC.,


     THESE WRIT PETITIONS HAVING BEEN HEARD AND
RESERVED FOR ORDERS ON 24.06.2021, COMING ON
FOR PRONOUNCEMENT THIS DAY, THE COURT MADE THE
FOLLOWING :-
                             ORDER

Assemblage of these petitions raise a challenge to

the order passed by the Karnataka Electricity

Regulatory Commission1 in rejecting Original Petition

No.214 of 2017 filed before it by the petitioners and

directing that the petitioners shall be entitled to a

particular tariff. Since facts are common in all these

petitions, facts obtaining in Writ Petition No.52028 of

2018 are referred to in this order for the sake of

convenience.

1 'Commission' for short

2. Succinctly stated, the facts germane for

consideration of the lis are as follows:-

Government of Karnataka on 22-05-2014

introduced a solar policy to be availed between 2014

and 2021 with the object of harnessing the potential of

solar resources in the State. In furtherance of the policy

of the State, Karnataka Renewable Energy Development

Limited2 issued a notification inviting online

applications for facilitating development of renewable

energy on 09.10.2014. The petitioners, in all these

cases, applied pursuant to the notification issued by

KREDL. In Writ Petition No.52028 of 2018, a letter of

award was issued in favour of one Sri Bommappa

Kenchikoppa for development of two megawatts (mw)

solar power plant by a letter of award dated 16.03.2015.

Before the plant could be commissioned and even the

process of harnessing solar resources to begin, the

'KREDL' for short

holder of award died bequeathing his entire property in

favour of his grandson, the petitioner herein.

3. On 26.08.2015, a power purchase agreement

was entered into between the petitioner and the

Bangalore Electric Supply Company Limited3 ('BESCOM'

for short). The power purchase agreement so entered

into between the petitioner and BESCOM was approved

by the Commission on 01.09.2015 pursuant to which,

the petitioner applied to KPTCL for evacuation approval

on 05.08.2016. Pending such approval, the petitioner

also applied before the Deputy Commissioner,

Davangere for conversion of land in Sy.No.67 measuring

10 acres for the purpose. After submission of such

application for conversion KPTCL issued an order of

approval of temporary evacuation on payment of

process fee and payment for evacuation on 19.09.2016.

This resulted in supplemental power purchase

agreement between the petitioner and the 2nd 3 'BESCOM' for short

respondent on 28.09.2016. After the supplemental

power purchase agreement, the petitioner applied for a

no objection from Soratur Grama Panchayat, Honnali

Taluk, Davengere.

4. On 19.10.2016 the Deputy Commissioner

before whom the conversion application was pending

accorded conversion after obtaining NOC from Soratur

Grama Panchayat. Thereafter the 1st respondent/

Government directed all ESCOMS to form a three

member committee to consider extension requests of

farmers holding lands for a period of 3 months. The

communication was sent to all ESCOMS on 24.11.2016.

On 06.01.2017 the petitioner requested BESCOM to

grant extension of scheduled date of commissioning of

the project by 6 months on account of force majeure.

The BESCOM on receipt of such request from the

petitioner and the like, directed the petitioner to submit

documents in support of the claim for extension of the

project.

5. On 27.02.2017 the petitioner again requested

along with all the documents extension of scheduled

date of commissioning of the project by six months.

Pending all such applications for extension - one from

the farmers and the other from the petitioner and the

like, KREDL informed all ESCOMS by its

communication dated 16.03.2017 that requests for

extension of time should not be considered as a routine

exercise except under extraordinary conditions to be

proved by the project developer within the scope of the

power purchase agreement. The Commission issued

another letter/direction directing BESCOMs to advice

the petitioner and all those who were in possession of

such power purchase agreements to file a petition before

it with all necessary documents seeking approval for

extension of time. This direction of the Commission was

issued on 05.04.2017.

6. On 16.06.2017 BESCOM approved the request

of the petitioner for scheduled date of commissioning of

the solar power project by 6 months on account of force

majeure reasons subject to any damages to be payable

and the tariff to be approved by the Commission. The

Government on 23.06.2017 addressed a communication

to KREDL observing that Government has accepted the

plea of ESCOMs in the matter of extension of time to

achieve commissioning of solar project under farmers'

scheme invoking force majeure conditions of the power

purchase agreement and also requested the

Commission to approve such extension of time.

7. On 07.07.2017 the Commission again issued

directives to ESCOMS directing them not to grant

extension of time without the prior approval of the

Commission. On 09.08.2017 BESCOM in terms of the

direction issued by the Commission directed the

petitioner and the like to seek approval from the

Commission for extension of scheduled date of

commissioning. Pending such approval, a provisional

interconnection approval was accorded by BESCOM and

commissioning certificate was also issued confirming

that solar power plant of the petitioner was

commissioned. After all the aforesaid proceedings, the

petitioner filed original petition as was directed by

BESCOM before the Commission in O.P.No.214 of 2017

seeking approval of scheduled date of commissioning.

The Commission by its order dated 09.10.2018

dismissed original petition and directed to pay damages

and liquidated damages as per clauses of the power

purchase agreement and also directed that the tariff

applicable to the petitioner would be Rs.4.36 per unit as

opposed to Rs.8.40 per unit and agreed to by the parties

under the power purchase agreement. It is this order

dated 09.10.2018 and the like, even or odd, that is

called in question by all the petitioners in these

petitions.

8. Heard Sri Manmohan P.N. learned counsel

appearing for the petitioners in most of the petitions,

Sri Ganapathi Bhat Vajralli, learned counsel appearing

for few of the petitioners, Sri S.Sriranga, learned

counsel appearing for KPTCL, Sri Shahbaaz Husain,

learned counsel appearing for BESCOM and KPTCL,

Smt. M.C. Nagashree, learned High Court Government

Pleader for the State, Sri B.N.Prakash, learned counsel

for the Commission and Sri Murugesh.V.Charati,

learned counsel for KREDL.

9. The learned counsel Sri Manmohan P.N who

has led the arguments in the case would urge the

following contentions, that the Commission had no

jurisdiction to intervene in the matter in exercise its

inherent power under Regulations 11 and 14 of the

Karnataka Electricity Regulatory Commission (General

and Conduct of Proceedings) Regulations, 2000; that

inherent powers of the Commission would not enable it

to determine the tariff once an agreement has been

signed between the petitioners and BESCOM; that

power of the Commission is restricted to the period prior

to execution of the power purchase agreement and not

after that; that the Commission had no jurisdiction to

alter or modify terms of the agreement; that letters

issued by the Commission directing cases to be filed

before it for extension would amount to being a Judge in

its own cause; that the parties having appeared before

the Commission cannot confer jurisdiction upon the

Commission to decide the issue after it had no

jurisdiction under the Act; that the Commission has not

proceeded with an open mind as the Commission had

pre-judged the issue by directing ESCOMS not to grant

extension of scheduled date of commissioning the

project.

9.1. The learned counsel would place reliance

upon the following judgments:

(i) GUJARAT URJA VIKAS NIGAM LIMITED v.

SOLAR SEMICONDUCTOR POWER COMPANY

(INDIA) PRIVATE LIMITED AND ANOTHER -

(2017) 16 SCC 498;

(ii) BESCOM v. KONARK POWER PROJECTS

LIMITED AND ANOTHER - (2016) 13 SCC 515;

(iii)   RAGHU      INFRA            PRIVATE      LIMITED     AND

        ANOTHER             v.     C.E.S.C.     AND    ANOTHER

        (W.P.No.51518-51519/2016                 decided      on

        27-08-2019 by this Court);

(iv)    ASIAN   FAB         TECH     LIMITED     v.   CESC   AND

        ANOTHER

(W.P.No.51365 of 2016 decided on 27-08-2019 by

this Court);

(v) CHENNAMANGATHIHALLI SOLAR POWER

PROJECT LLP AND ANOTEHR v. BESCOM AND

ANOTHER

(Appeal No.351 of 2018 decided on 14-09-2020 by

the APTEL);

(vi) A.U.KURESHI v. HIGH COURT OF GUJARAT

AND ANOTHER - (2009) 11 SCC 84;

(vii) MOHD. YUNUS KHAN v. STATE OF UTTAR

PRADESH AND OTHERS - (2010) 10 SCC 539;

(viii) SIEMENS LIMITED v. STATE OF

MAHARASHTRA AND OTHERS - (2006) 12 SCC

33 and

(ix) COMMITTEE OF MANAGEMENT AND ANOTHER

v. VICE CHANCELLOR AND OTEHRS

- (2009) 2 SCC 630.

10. The other learned counsel has toed the lines of

argument of Sri Manmohan P.N., learned counsel.

11. On the other hand, learned counsel Sri

S.Sriranga, appearing for the respondent KPTCL and

BESCOM would at the outset submit that petitioners

have an alternative and efficacious remedy of filing an

appeal before the Appellate Tribunal for Electricity

constituted under Section 111 of the Electricity Act,

2003 and the impugned order passed by the

Commission cannot be questioned before this Court.

Without prejudice to the issue of maintainability, the

learned counsel would also submit that the Commission

had jurisdiction to direct what it has done and the order

passed by the Commission is unassailable and would

place reliance upon judgments in cases of:

(i) ALL INDIA POWER ENGINEERS FEDERATION

LIMITED v. SASAN POWER LIMITED

- (2017) 1 SCC 487;

(ii) TATA POWER COMPANY LIMITED v. RELIANCE

ENERGY LIMITED - (2009) 16 SCC 659;

(iii) GUJARAT URJA VIKAS NIGAM LIMITED v.

TARINI INFRASTRUCTURE AND OTHERS -

(2016) 8 SCC 743;

(iv) P.SINGARAVLEAN AND OTHERS v. DISTRICT

COLLECTOR, TIRUPUR AND OTHERS -

(2020) 3 SCC 133;

(v) GUJARAT URJA VIKAS NIGAM LIMITED v.

EMCO LIMITED AND ANOTHER -

(2016) 11 SCC 182;

(vi)    EARTH SOLAR PRIVATE LIMIED v. PUNJAB

        STATE        ELECTRICITY         REGULARTORY

        COMMISSION AND ANOTEHR

- (Appeal No.169 of 2015 decided on 11-01-2019);

(vii) RELIANCE INFRASTRUCTURE LIMITED v.

STATE OF MAHARASHTRA - (Civil Appeal

No.879 of 2019 decided on 21-01-2019);

(viii) A.P. TRANSCO v. SAI RENEWABLE POWER (P)

LIMITED - (2011) 11 SCC 34;

(ix) VATSALA BELLARY v. KREC AND OTHERS -

(W.P.No.35569 of 2018); and

(x) GRAPHITE INDIA v. KERC AND OTHERS

(W.P.No.12576 of 2018 decided on 21-06-2018).

12. I have given my anxious consideration to the

rival submissions made across the bar and have

perused the material on record.

13. The facts narrated hereinabove would not need

reiteration as they are not in dispute. To consider the

contentions advanced by respective parties as aforesaid,

the prayers in the writ petition that is taken for

reference are to be noticed. The prayers that are sought

in Writ Petition No.52028 of 2018 read as follows:

(i) Issue a writ of certiorari and quash the communication dated 16-03-2017 bearing No.KERC/ S/F-31/VOL- ALL/16-17/2763 issued by the 5th respondent (Produced as Annexure-S);

             and

     (ii)    Issue a writ of certiorari and quash the
             communication       dated      5-04-2017
             bearing     No.KERC/        S/F-31/VOL-
             ALL/16-17/55 issued by the 5th

respondent (Produced as Annexure-T); and

(iii) Issue a writ of certiorari and quash the communication dated 07-07-2017 bearing No.KERC/ S/F-31/VOL- ALL/17-18/541 issued by the 5th

respondent (Produced as Annexure-V);

and

(iv) Issue a writ of certiorari and quash the communication dated 16-06-2017 bearing No.CM(Ele.)/PP/BESCOM /DGM-1/AGM-1/BC-39/F-/17-18/3627

-33 issued by the 2nd respondent insofar as subjects the extension of SCOD to the condition that the tariff applicable and the liquidated damages to be paid if any is subject to Hon'ble KERC/GOK approval (Produced as Annexure-F); and

(v) Issue a writ of certiorari and quash the communication dated 09-08-2017 bearing NO. GM (Ele)/PP/BESCOM/ DGM-1/AGM-1/BC-39/F-17-18/ 6810 issued by the 2nd respondent (Produced as Annexure-X); and

(vi) Issue a writ of certiorari and quash the order dated 9-10-2018 passed in O.P.No.214 of 2017 passed by the 5th respondent (Produced as Annexure-AB); and

(vii) Issue a writ of mandamus directing the 2nd respondent to pay the tariff of Rs.8.40 kwh to the petitioner as per the Power Purchase Agreement dated 26- 08-2015 (Produced as Annexure-C; and

(viii) Pass such other orders as deemed fit in the facts and circumstances of the case, in the interest of justice and equity."

In furtherance of the solar policy of the State

notification was issued by KREDL and the petitioner

was issued a letter of award for development of MW

solar power plant. Certain clauses of the power

purchase agreement dated 26-08-2015 entered into

between the petitioner and BESCOM are germane to be

noticed and are accordingly extracted herein for the

purpose of ready reference:

"Article-I: Definitions

1.1 For all purposes of this Agreement, unless the context otherwise requires the following words and expressions shall have the respective meanings set forth below:

... ... ... ...

(xii) "Effective Date" shall mean date of signing of this Agreement by the parties:

... ... ... ...

(xxviii)"Scheduled Commissioning Date"

shall mean 18 (eighteen) months from the Effective Date.

(xxix) "State loan dispatch Centre" means the State Load Despatch Centre established as per the Act;

(xxx) "State transmission Utility" or "STU" shall mean Karnataka Power

Transmission Corporation Limited or KPTCL.

(xxxi) "Tariff Payment" shall mean the payments to be made under Monthly Bills as referred to in Clause 6.3 and the relevant Supplementary Bills.

5.1 Tariff payable:

The SPD shall be entitled to receive the Tariff of Rs.8.40 per KWH based on the KERC tariff order S/03/1 dated 10-10-2013 in respect of SPD's Solar PV projects in terms of his agreement for the period between COD and the Expiry Date. However, subject to Clause 2.5, if there is a delay in commissioning of the Project beyond the Scheduled Commissioning Date and during such period there is a variation in the KERC Tariff, then the applicable Tariff for the projects shall be the lower of the following:

(i) Rs.8.40 per kwh.

(ii) Varied tariff applicable as on the date of Commercial Operation.

Article-8 FORCE MAJEURE

8.1 Definitions:

In this Article, the following terms shall have the following meanings:

8.2 Affected Party:

An affected party means BESCOM or the SPD whose performance has been affected by an event of Force Majeure.

8.3 Force Majeure Events:

a) Neither Party shall be responsible or liable for or deemed in breach hereof because of any delay or failure in the performance of its obligations hereunder (except for obligations to pay money due prior to occurrence of Force Majeure events under this Agreement) or failure to meet milestone dates due to any event or circumstance (a "Force Majeure Event") beyond the reasonable control of the Party affected by such delay or failure, including the occurrence of any of the following:

i. Acts of God;

        ii.    Typhoons,    floods,   lightning,
               cyclone,   hurricane,    drought,

famine, epidemic, plague or other natural calamities;

iii. Strikes, work stoppages, work slowdowns or other labour dispute which affects a Party's ability to perform under this Agreement;

iv. Acts of war (whether declared or undeclared), invasion or civil unrest;

v. Any requirement, action or omission to act pursuant to any judgment or order of any court or judicial authority in India (provided such requirement, action or omission to act is not due to the breach by the SPD or BESCOM, of any law or any of their respective obligations under this Agreement);

vi. Inability despite complying with all legal requirements to obtain, renew or maintain required licenses or Legal Approvals;

vii. Fire, Earthquakes, explosions, accidents, landslides;

viii. Expropriation and/or compulsory acquisition of the Project in whole or in part;

  ix.    Chemical      or        radioactive
         contamination        or   lionizing
         radiation; or

  x.     Damage to or breakdown of

transmission facilities of either Party;

b) The availability of the above item (a) to excuse a Party's obligations under this Agreement due to a Force Majeure Event shall be subject to the following limitations and restrictions:

i. The non-performing Party gives the other Party written notice describing the particulars of the Force Majeure Event as son as practicable after its occurrence;

ii. The suspension of performance is of no greater scope and of no longer duration than is required by the Force Majeure Event.

iii. The non-performing Party is able to resume performance of its obligations under this Agreement, it shall give the other Party written notice to that effect;

iv. The Force Majeure Event was not caused by the non-performing Party's negligent or intentional acts, errors or omissions, or by its negligence/failure to comply with any material law, or by any material breach or default under this Agreement;

v. In no event shall a Force Majeure Event excuse the obligations of a Party that are required to be completely performed prior to the occurrence of a Force Majeure Event.

        ...           ...                ...          ...

12.10          Amendments:




This Agreement shall not be amended, changed, altered or modified except by a written instrument duly executed by an authorized representative of both Parties. However, BESCOM may consider any amendment or change that the Lenders may require to be made to this Agreement subject to the approval of the Commission.

(Emphasis added)

Clause (xxviii) of the definitions would define 'Scheduled

Commissioning Date' to be 18 months from the effective

date. Clause (xii) thereof defines 'Effective Date" would

mean the date of signing of the agreement between the

parties. The 'Conditions Precedent' are dealt with under

Article-2. Damages for delay to be paid by the Developer

are dealt with under Clause 2.2. Extensions of time are

depicted in Clause 2.5. In terms of Clause 2.5.6 the

result of extensions would be the scheduled

commissioning date and expiry date would be

determined afresh which shall be the scheduled

commissioning date and the expiry date for the

purposes of the agreement. Tariff payable in terms of

the agreement is dealt with under Clause 5.1 which

determines agreed tariff to be Rs.8.40 per kWh. Force

Majeure is dealt with under Article 8. One such clause

depicts inability despite complying with all legal

requirements to obtain, renew or maintain required

licenses. It is in terms of the aforesaid agreement that

the entire issue now springs and is to be considered.

14. In terms of the agreement, the petitioner

applied for evacuation approval from the hands of

KPTCL and conversion from the hands of Deputy

Commissioner and no objection from the hands of

Soratur Gram Panchayat. The approval was granted on

different dates and a supplemental power purchase

agreement was also entered into between the parties.

Since the issue now is with regard to delay in scheduled

date of commissioning, the reasons behind the delay is

required to be noticed.

15. The petitioners in all these cases requested

BESCOM for extension of scheduled commissioning

date enclosing the dates on which steps have been

taken by the petitioners seeking several statutory

approvals which were held at the hands of Government.

First representation of the kind was given on 1st

February 2017 and the second representation of the

kind was given on 27th February 2017. In reply, what

the 1st petitioner got was a communication dated

15-04-2017 from BESCOM which reads as follows:-

"Sir,

Sub: Power Purchase Agreement of 2 MW Tuggalahalli village, Honnali Taluk, Davangere District, Karnataka State of Sri AmarthyaRajashekarappa - reg Extension of Scheduled Commissioning date.

Ref: 1. PPA executed with BESCOM on 26.08.2015.

2. Your letter dated 06-01-2017, 1.2.2017 & 27.2.2017

3. KERC letter No.KERC/S/F-

31/Vol-1ll/16-17/55 dated 05-04- 2017.

--

Hon'ble KERC vide letter cited under ref.(3), have informed that , the Commission has the jurisdiction of legal scrutiny of validity of the extension of time granted in any case by an ESCOM.

Such proceedings being a part of judicial functions of the Commission require reasonable opportunity to be given to both parties of the PPA to present their case.

In this regard, Hon'ble Commission directs all the ESCOMs to advice the concerned SPD/SPVs under Land Owners/ Farmers Scheme to file a petition before the Commission with all relevant grounds/documents for seeking approval for any extension of the Commissioning date. (copy of the letter is enclosed).

I am directed to request you, to file a petition before the Hon'ble Commission forth, with all relevant grounds/ documents for seeking approval for any extension of the Commissioning date."

(Emphasis added)

The communication furnished by BESCOM was based

upon the letter issued by the Commission on

16-03-2017 which reads as follows:

"No.KERC/S/F-31/Vol-All/16-17/ Dated:16- 03-2017

The Managing Director, BESCOM/MESCOM/ESCOM/HESCOM/ GESCOM.

Sir, Sub: Extension of time to achieve COD of the Solar Projects - reg.

Ref. 1.BESCOM letter NO.GM(Ele)/PP/ BESCOM/DGM-1/AGM-1/BC-39/F.. dated 9thJanuary, 2007.

2.KERC letter No.KERC/S/F-31/Vol- 41/15-16/148 dated 04-05-2015.

--

It has come to the notice of the Commission that the BESCOM in its letter cited under reference, has granted extension of time of six months to achieve COD for the 10 MW Solar Project, beyond the time allowed in the PPA without altering the terms of the original PPA. The PPA was approved by the Commission vide its letter cited under

Ref.2 above. The Commission has noted that BESCOM has not obtained prior approval of the Commission regarding the extension of time. The reasons and justification for the extension of time are not forthcoming from the letter of BESCOM.

The Commission has also observed that in certain instances, ESCOMs have granted extension of time to achieve commercial operation of the solar projects from the originally agreed scheduled commissioning date, without altering the terms and conditions of the PPA.

Since the extension of time by ESCOMs without altering the terms of the original PPA will have impact on the Tariff payable by the ESCOMs, the Commission has the jurisdiction of legal scrutiny of validity of the extension of time granted.

The Solar Projects are expected to be completed in the time bound manner in order to ensure that not only the anticipated solar

power generation accrues to the grid to meet the planned demand but also to ensure that the capital cost of the developer is as per assumption mode for calculating the Tariff offer and any extension of time will have for reaching tariff implications affecting the end consumers. In view of rapid changes in the market conditions of photovoltaic plants, resulting in sustained reduction in their cost. Extension of time should not be considered as a routine exercise except under extra-ordinary conditions to be proved by the project developer, within the scope of the original PPA.

I am directed to inform all ESCOMs to not to allow any extension of time beyond the Scheduled Commissioning date (COD) if any, as per the original PPA without obtaining prior opinion of this Commission."

(Emphasis added) The Commission clearly directed ESCOMs not to allow

any extension of time beyond the scheduled

commissioning date without obtaining prior approval of

the Commission. The Commission again communicates

on 05.04.2017 with regard to extension of time for

scheduled commissioning of the project. The letter dated

05.04.2017 reads as follows:

"No.KERC/S/F-31/Vol-All/16-17/55 Date:5-04-2017

The Managing Director, BESCOM/MESCOM/CESC/HESCOM/GESCOM Sir,

Sub: Request for Commission's approval for Supplementary PPAs executed to incorporate extension of time to achieve COD at the Solar Projects under landowners/farmers scheme - Reg. Ref: KERC letter No.KERC/S/F-31/Vol-

All/16-17/2763 dated 17-03-2017.

--

The Commission is receiving for approval several Supplementary PPAs executed in respect of Solar Projects under Land Owners/Farmers' Scheme. Such supplemental PPAs mainly seek to extend time to the developers to achieve CoD beyond

the date specified in the original PPAs. The ESCOM concerned has stated that a Committee formed with its Director Technical as Chairman, as directed by the Government in Energy Department to resolve the issue of granting extension of CoD by considering Article 2.5 and 8 of the PPA, has decided to grant extension of time for achieving scheduled commissioning of the project as requested by the developer.

2. The Commission has noted that, the grounds cited to grant extension of time and the duration of such extension vary from case to case. However, the proceedings of the said Committee and the proposal of the ESCOMs which are not supported by any documents and independent findings, are inadequate to enable the Commission to take a decision in the matter.

3. As already clarified in the Commission's letter dated 17-03-2017 cited under reference the Commission has the jurisdiction of legal scrutiny of the extension of time granted in any case by an ESCOM. Such proceedings

being a part of judicial functions of the Commission require reasonable opportunity to be given to both parties of the PPA to present their case.

     4.    Hence,        I        am     desired      by         the
     Commission              to     inform        that           the

Commission directs all the ESCOMs to advice the concerned SPD/SPVs under Land Owners/Farmers Scheme to file a petition before the Commission with all relevant grounds/documents for seeking approval for any extension of the commissioning date. It may also be noted, this direction of the Commission applies to even such cases where the ESCOMs have not entered into Supplementary PPAs following the decision of the Committee to grant extension of commissioning date."

(Emphasis added)

It is here that the marrow of the lis lies. In paragraph 4

of the communication the Commission directs all

ESCOMs to advice the petitioner and the like to file a

petition before it with all relevant grounds and

documents seeking approval of any extension of

commissioning date. It further directs that this direction

of the Commission would apply even to such cases

where ESCOMs have not entered into supplementary

power purchase agreement. The Commission again on

07.07.2017 directed all ESCOMs not to send any

proposal for approval of the Commission till petitions

are filed by the petitioners and like before the

Commission. The said communication dated

07.07.2017 reads as follows:

"No.KERC/S/F-31/Vol-All/17-187/541 Date:07.07.2017 The Managing Director, BESCOM/MESCOM/CESC/HESCOM/GESCOM Sir, Sub: Extension of time for SCOD in respect of 1 to 3 MWs Solar Power Plants in Karnataka, under Farmers category. - Reg.

      Ref: i)           Govt.letter No.EN 67 VSC 2017 dated
                        23.06.2017




     ii)    KERC            letter       No.KERC/S/F-

31/Vol.All/17-18/212 dated 09-05- 2017.

iii) Govt. letter No: EN 67 VSC 2017 dated 25.04.2017.

(iv) KERC letter No.KERC/S/F-31/Vo-

All/16-17/65 dated 05-04-2017.

(v) KERC letter No.KERC/S/F-31/Vol-

All/16-17/2763 dated 17-03-2017.

(vi) Govt.letter No.EN 75 VSC 2016 date 24.11.2016

--

Please refer to the letter dated 23-06-2017 cited under reference (1) RECEIVED FROM THE Energy Department, GoK, wherein the Government has stated that, it has accepted the views of the ESCOMs, in the matter of extension of time to achieve CoD of the Solar Projects under farmers' scheme invoking Force Majeure conditions of the PPA and hence has requested the Commission to approve such extension of time for achieving CoD.

I am directed to inform you that, the action of the ESCOMs to permit the developers to commission the projects beyond the original scheduled CoD as per PPA, has been approved by the Commission, which however, has noted that the tariff applicable in each case needs

to be examined on merits of each individual case.

I am also directed to inform you that, the ESCOMs may advice the concerned SPD/SPVs under Land Owners/ Farmers scheme to file a petition, each before the Commission with all the relevant grounds/documents for justifying their claims for extension of time under Force majeure conditions of the PPA.

Further, the ESCOMs are hereby directed not to send any SPPA in respect of these cases for approval of the Commission, till the petition(s) filed by the SPDs/SPVs before the Commission, is/are disposed of.

(Emphasis added)

From the correspondences between BESCOMs and the

Commission, Government of Karnataka also requested

the Commission to extend time for the reasons

communicated in the letter dated 23.06.2017. The letter

of the Government to the Commission dated

23.06.2017 reads as follows:-

"From:

The Additional Chief Secretary to Government, Energy Department, Bangalore.

To:

The Secretary, Karnataka Electricity Regulatory Commission, 6th& 7th Floor, Mahalakshmi Chambers, No.9/2, M.G.Road, Bengaluru-560 001.

Sir,

Sub: Extension of time for SCOD in respect of 1 to 3 MWs Solar Power Plants in Karnataka under Farmers Category - reg.

Ref: 1. Government same file No.Letter dated 23.04.2017.

2. Your letter No.KERC/S/F-

31/Vol.A11/17-18/ 212 D:09-05-2017.

3. MD, CESC DO.letterNo.CESC/MD/GM (coml.) RA 2/17-18/DO-63 D:11-05-

4. MD, HESCOM letter No.HESCOM/GM(T)/EE/ (RA)/AEE/17- 18/3624 D: 15-05-2017.

       5.    MD,            GESCOM             letter
             NO.GESCOM/CEE(CP)/EE/              AEE

(PTC)2016-17/7945 D:16-05-2017

6. MD, MESCOM Letter No.MESCOM/MD/PS/99 D. 17-05-

2017.

--

In inviting kind reference to the above, for the Government proposal under ref (1) regarding

considering approval to the extension of COD of Solar Power Projects of capacity 1 to 3 MW under land owning farmers category in BESCOM, the Hon'ble Commission vide reference (2), has requested the Government to furnish the details of similarly placed cases in the other ESCOMs, in order to take view in the matter.

In this regard, other ESCOMs have also submitted their request on the subject matter. The ESCOM wise details of the projects under land owner Farmers is as below:

... ... ... ....

As per the above table, out of 304 MW PPA signed, 131 MW projects have been commissioned within SCOD. Extension of time has been issued by ESCOMs for 129 MW capacity. Proposals to an extent of 31 MW capacity is pending at ESCOMs level, since the Hon'ble Commission has directed all ESCOMs not to allow any extension of time beyond the schedule COD, without obtaining prior opinion of the Commission.

From the proposals submitted by all ESCOMs it is clear that the reasons for delay in execution of the project are common and

the main reasons for considering the extension of SCOD are as below:

a. Delay in getting land conversions. b. Delay in getting evacuation approval, Bay extension approval, CEIG approval etc.

c. Delay in financial closure due to delay in the above mentioned permits. d. Delay due to demonetization of the Indian Currency.

e. Delay in getting Railway Crossing approval f. Delay in getting MEI switchgears.

The Managing Directors of CESC, HESCOM, GESCOM and MESCOM vide letters under ref (3), (4) (5) & (6) have explained the reasons for giving extension of SCOD and summed up saying that this scheme under farmers category is brought into effect with the approval of the Solar Policy by the Cabinet. Government considers it as a preferred and prestigious one. Further, it is standalone scheme in the energy sector not only in Karanata but also in the entire country.

Particularly the following are brought to the notice of the Hon'ble Commission:

1. The ESCOMs have constituted Committees under the Chairmanship of the respective Directors (Technical) to scrutinize and recommend the eligible cases for giving extensions of SCOD and based on the scrutiny and recommendations of the Commission the respective ESCOMs have given extensions as required under Clause 8.3

(b) of the PPA.

2. The extensions are given under Force Majeure as per 8.3 (a) (vi) of the PPA which read as:"Inability despite complying with all legal requirements to obtain renew and maintain required licenses or Legal Approvals."

Hence ESCOMs have given extensions of COD on identical reasons under PPA clause 2.5 (Extension of time) and Article 8 (Force Majeure). In all these cases extensions of COD is given by ESCOMs upto 6 (six) months from the date of SCOD as per PPA Clause 2.5 and Article 8 clearly mentioning that all other terms and conditions shall remain unaltered at the KERC approved rate of unit as laid down in

the terms and conditions of PPA in consideration of the investment made by the farmer.

Accordingly, the reasons given by and the opinion of MD's of CESC, HESCOM, GESCOM and MESCOM are acceptable to the Government (Copies enclosed). In view of the above, I am directed to request the Hon'ble Commission to consider approval to the extension of COD of Solar Power Projects of capacity 1 to 3 MW under land owning famers category.

(Approved by Hon'ble Energy Minister)."

(Emphasis added)

BESCOM communicates to the petitioner on 09.08.2017

that the petitioner will become liable for difference in

tariff and liquidity damages pertaining to delayed

commissioning of the project. Here, the BESCOM

directs the petitioner to file cases before the

Commission forthwith justifying the claim for extension

of time under force majeure conditions. The

Government of India also noticed that not only in

Karnataka but in several places due to factors beyond

control of the developers the project could not be

commissioned and, therefore, directed Energy

Department of Government of Karnataka to grant six

months extension of time to solar projects. The

communication dated 09.04.2018 from the Ministry of

New and Renewable Energy, Government of India to the

Government of Karnataka reads as follows:

"To The Additional Chief Secretary, Energy Department, Govt. of Karnataka, Room NO.236, 2nd Floor, Vikas Soudha, Dr. B.R.Ambedkar Street, Bangalore, Karnataka E-mail: [email protected]

Subject: Request to restore the original tariff of Rs.8.40 per unit for 1-3 MW solar power plants commissioned under the Land Owned farmers Scheme of Karnataka.

--

Sir, This Ministry has received a letter from Association for Land Owned Farmers Solar Power Plants, Karnataka on above subjects. Letter is enclosed for reference.

2. Points highlighted in letter are given below as:

a. Govt. of Karnataka has implemented a Land Owned Farmers Scheme with 1-3 MW solar plants. Under this scheme, PPA of 304 MW was signed. Out of 304 MW, PPA for 283 MW was signed with Rs.8.4 per unit tariff. Out of 283 MW, only 131 MW were commissioned within schemed commissioning date (SCOD).

b. However, ESCOMs have granted 6 months extension for 162 MW solar projects for commissioning of these capacities under Force Majeure Article 8a(vi) of the PPA. These extensions were given due to many reasons beyond the solar power developers' control viz., Demonetisation, Cyclone effect, inordinate delay in NA conversion, power evacuation approvals, safety approval by CEIG and other required statutory approvals.

c. KERC has taken a different stand. The commission has asked all farmers/PPA holders to file petition explaining the reasons for extension. The final judgment on few petitions clearly indicates that the commission has taken the unilateral decision to lower the tariff from Rs.8.40 to Rs.6.51 or Rs.4.36. Due to this, over 57% of the commissioned capacities are facing a threat of survival of bankruptcy.

3. As you are aware that the Government of India has set a target of setting up 100 GW solar capacities by 2022. While all efforts are being made to achieve this target through its various Schemes,

the solar power developers need to be given adequate confidence to maximize development of solar power capacity in the State. The stand taken by KERC on above matters would create an uncertainty for the investors and demotivate the investors from investing in solar sector.

4. In view of above, it is requested that Government of Karnataka may take up the above matter with KERC under Section 108 of the Electricity Act, 2003".

(Emphasis added)

16. With all the aforesaid correspondences,

communications, approvals and extension of time, the

petitioner, as was directed, approached the Commission

for extension of time in O.P.No.214 of 2017. Prayer that

was sought by the petitioner before the Commission

reads as follows:

"A) Approve the extension granted by the respondent to new scheduled commissioning date viz., 25 August, 2017 th

accorded by the 1st respondent vide its letter dated 6th June, 2017 produced as Annexure-P12.

B) Direct the respondent to make payment for the delivered energy under the PPA dated 26thAugust, 2015 produced as Annexure- P2 and the supplemental agreement dated 28th September, 2016 produced as

Annexure-P5, at the rate of Rs.8.40 per unit from the Commercial Operation Date of the petitioner's product for the entire term of the PPA.

C) Pass such other and incidental orders, including an order as to costs as may be deemed appropriate under the facts and circumstances of the present case."

The Commission claiming to be considering the case of

the petitioner observed that there was no force majeure

event for the petitioner to contend that they could not

commission the project and rejected the claim of the

petitioner for extension of scheduled date of

commissioning by the following order:

"(a) It is declared that the petitioner is not entitled to any of the reliefs, sought for in the petition.

(b) The petitioner is entitled to a tariff of Rs.4.36 (Rupees four and paise thirty-six) only per unit, the varied tariff, as applicable on the date of commissioning of the petitioner's plant, as fixed by the Commission in the order dated 12-04-2017 for the term of the PPA, as per Article 5.1 of the PPA; and

(c) The petitioner is also liable to p[ay damages, as provided under Articles 2.2 and 2.5.7 of the PPA."

Identical orders are passed in all these cases.

17. The issue now remains for consideration is,

whether the Commission could have directed BESCOM

to direct the petitioners and the like to approach the

Commission for extension of time. Having solicited

petitions being filed before the Commission, whether the

Commission has acted as a Judge in its own cause. One

acting as a Judge in his own cause is a hue of bias as

bias has manifold hues and shades, one of which is 'no

man can be a judge of its own cause'. To consider

whether the Commission has acted as a Judge in its

own cause, it is germane to notice the judgments of the

Constitutional Courts on the issue of bias, its forms and

hues.

18. One of the cardinal principles of natural

justice is 'nemo debetesse judex in propria causa' (no

man shall be a judge in his own cause). The deciding

authority must be impartial and without bias. The Rule

that bias vitiates any findings is a rule of natural

justice. It is trite law that official bias or bias of the

subject matter is one of the limbs of bias. To appreciate

the said principle on the touchstone of official bias or

bias to the subject-matter, the test is whether there was

a real likelihood of a bias even though such bias has not

in fact taken place. It is apposite to refer DE SMITH IN

HIS JUDICIAL REVIEW OF ADMINSITRATIVE

ACTION4, wherein the author observes that a real

likelihood of bias means at least substantial possibility

of bias.

19. In HALSBURY'S LAWS OF ENGLAND5, it has

been indicated that the test of bias is whether a

reasonable intelligent man, fully appraised of all the

circumstances, would feel a serious apprehension of

bias.

(1980 Edn.) at page 262

4thEdn., Vol.2 para 551

20. The Divisional Court of the Kings Bench, in

R.V. SUNDERLAND JUSTICES6, has held that the

Court will have to judge the matter as a reasonable man

would judge of any matter in the conduct of his own

business.

21. Later, Divisional Court of the Kings Bench,

in R.V. SUNDERLAND JUSTICES7, has again held in

answer to the question whether there was a real

likelihood of bias depends not upon what actually was

done but upon what might appear to be done.

22. The aforesaid principle is reiterated in

acceptance by the Apex Court in MANAK LAL v.

DR.PREM CHAND8 wherein the Hon'ble Apex Court has

held that the test is not whether in fact, bias has

affected the judgment; the test always is and must be

weather a litigant could reasonably apprehend that a

(1901) 2 KB 357, 373,

1923 All ER 233,

AIR 1957 SC 425

bias attributable to a Member of the Tribunal must have

operated against him in the final decision of the

Tribunal. It is in this sense that it is often said that

justice must not only be done but must also appear

to be done.

23. The aforesaid principles with regard to bias are

considered, iterated and elaborated by the Hon'ble Apex

Court in the subsequent judgment in the case of

K. PARTHASARATHI VS. STATE OF ANDHRA

PRADESH9 wherein the Apex Court in paragraphs 14,

15 and 16 has held as follows:

"14. The test of likelihood of bias which has been applied in a number of cases is based on the "reasonable apprehension" of a reasonable man fully cognizant of the facts. The courts have quashed decisions on the strength of the reasonable suspicion of the party aggrieved without having made any finding that a real likelihood of bias in fact existed (see R. v. Huggins [(1895) 1 QB 563] ;R. v. Sussex, JJ., ex. p.

(1974) 3 SCC 459

McCarthy [(1924) 1 KB 256] ; Cottle v. Cottle [(1939) 2 All ER 535] ; R. v. Abingdon, JJ. ex. p. Cousins [(1964) 108 SJ 840] .) But in R. v. Camborne, JJ. ex. p Pearce [(1955) 1 QB 41 at 51] the Court, after a review of the relevant cases held that real likelihood of bias was the proper test and that a real likelihood of bias had to be made to appear not only from the materials in fact ascertained by the party complaining, but from such further facts as he might readily have ascertained and easily verified in the course of his inquiries.

15. The question then is: whether a real likelihood of bias existed is to be determined on the probabilities to be inferred from the circumstances by court objectively, or, upon the basis of the impressions that might reasonably be left on the minds of the party aggrieved or the public at large.

16. The tests of "real likelihood" and "reasonable suspicion" are really inconsistent with each other. We think that the reviewing authority must make a determination on the basis of the whole evidence before it, whether a reasonable man would in the circumstances infer that there is

real likelihood of bias. The Court must look at the impression which other people have. This follows from the principle that justice must not only be done but seen to be done. If right minded persons would think that there is real likelihood of bias on the part of an inquiring officer, he must not conduct the enquiry; nevertheless, there must be a real likelihood of bias. Surmise or conjecture would not be enough. There must exist circumstances from which reasonable men would think it probable or likely that the inquiring officer will be prejudiced against the delinquent. The Court will not inquire whether he was really prejudiced. If a reasonable man would think on the basis of the existing circumstances that he is likely to be prejudiced, that is sufficient to quash the decision [see per Lord Denning, H.R. in Metropolitan Properties Co. (F.G.C.) Ltd. v. Lannon [(1968) 3 WLR 694 at 707]] We should not, however, be understood to deny that the Court might with greater propriety apply the "'reasonable suspicion" test in criminal or in proceedings analogous to criminal proceedings."

(Emphasis supplied)

The case at hand will have to be judged on the

touchstone of law with regard to bias as laid down by

the Apex Court in the afore-extracted judgment.

24. It is also germane to notice the decisions of the

Apex Court in the case of A.U. KURESHI v. HIGH

COURT OF GUJARAT10 - and MOHD. YUNUS KHAN v.

STATE OF U.P.11 -. In the case of A.U.KURESHI the

Apex Court has held as follows:

10. It is an accepted principle of natural justice that a person should not be a judge in his or her own cause. In common law, this principle has been derived from the Latin maxim--nemo debetesse judex in propria sua causa. A reasonable permutation of this principle is that no Judge should adjudicate a dispute which he or she has dealt with in any capacity, other than a purely judicial one. The failure to adhere to this principle creates an apprehension of bias on the part of the said Judge.

(2009) 11 SCC 84

(2010) 10 SCC 539

11. It would be useful to refer to the observations of P.N. Bhagwati, J. in Ashok Kumar Yadav v. State of Haryana [(1985) 4 SCC 417 : 1986 SCC (L&S) 88] : (SCC p. 418) "One of the fundamental principles of our jurisprudence is that no man can be a judge in his own cause. The question is not whether the Judge is actually biased or [has] in fact [decided] partially but whether the circumstances are such as to create a reasonable apprehension in the mind of others that there is a likelihood of bias affecting the decision. If there is a reasonable likelihood of bias it is 'in accordance with natural justice and common sense that the [Judge] likely to be so biased should be incapacitated from sitting'. The basic principle underlying this rule is that justice must not only be done but must also appear to be done."

In the case of MOHD. YUNUS KHAN the Apex Court has

held as follows:

"25. The legal maxim nemo debetesse judex in propria causa (no man shall be a judge in his own cause) is required to be observed by all judicial and quasi-judicial authorities as non-observance thereof is treated as a violation of the principles of natural justice. (Vide Secy. to Govt., Transport Deptt. v. MunuswamyMudaliar [1988 Supp SCC 651: AIR 1988 SC 2232], Meenglas Tea Estate v. Workmen [AIR 1963 SC 1719] and Mineral Development Ltd. v. State of Bihar [AIR 1960 SC 468].)

26. This Court in A.U. Kureshi v. High Court of Gujarat [(2009) 11 SCC 84: (2009) 2 SCC (L&S) 567] placed reliance upon the judgment in Ashok Kumar Yadav v. State of Haryana [(1985) 4 SCC 417: 1986 SCC (L&S) 88] and held that no person should adjudicate a dispute which he or she has dealt with in any capacity. The failure to observe this principle creates an apprehension of bias on the part of the said person. Therefore, law requires that a person should not decide a case wherein he is interested. The question is not whether the person is actually biased but whether the

circumstances are such as to create a reasonable apprehension in the minds of others that there is a likelihood of bias affecting the decision.

27. The existence of an element of bias renders the entire disciplinary proceedings void. Such a defect cannot be cured at the appellate stage even if the fairness of the appellate authority is beyond dispute. (Vide S. Parthasarathi v. State of A.P. [(1974) 3 SCC 459: 1973 SCC (L&S) 580: AIR 1973 SC 2701] and Tilak Chand MagatramObhan v. Kamala Prasad Shukla [1995 Supp (1) SCC 21: 1995 SCC (L&S) 251].) (Emphasis supplied)

25. In the light of the law laid down by the Apex

Court in the afore-extracted judgments if the

orders/communications of the Commission is noticed, it

would without doubt get vitiated on account of

Commission soliciting and directing BESCOM not to

issue any extension orders and to direct all the

petitioners to approach the Commission. It is coercing

the petitioners to come before the Commission as it has

already looked into the file and decided to direct that

BESCOM should not issue any orders and that it would

decide the case if it is brought before it.

26. In my considered view, there cannot be a

better example of bias of the subject matter or official

bias on the part of the Commission, to have already pre-

judged the issue, directing the parties to come before it

and decide the issue re-affirming what it had already

decided on hand. It is like saying "you come before

me; I'll adjudicate, else wither none shall

adjudicate"

27. The contentions of the learned counsel

appearing for the respondent/BESCOM and the

Commission are unacceptable, as it is a clear case of

official bias or bias of the subject matter on the part of

the Commission. The contention with regard to

judgments concerning bias, quoted (supra), that, they

are all of service jurisprudence and would not be

applicable to the facts of the case at hand is also

rejected, for the reason that bias is that principle of

natural justice which permeates into every sphere of

law, be it any kind of jurisprudence. Therefore, the first

leg of proceedings before the Commission gets vitiated.

It is, thus, the Commission did not proceed with an

open mind to consider the case of the petitioners as the

Commission had issued plethora of directions/ letters to

act in a particular manner.

Jurisdiction of the Commission:

28. The contention of the learned counsel for the

petitioners is that the Commission has no jurisdiction to

determine tariff and once an agreement is signed

between the parties, the power of the Commission is

restricted to the period prior to execution of PPA and

once PPA has been signed, the Commission cannot

invoke its inherent jurisdiction to issue and modify the

terms and conditions of the Agreement or intervene with

regard to the obligations to be discharged by the parties.

28.1. It is also his contention that there is no

dispute between the petitioners and the BESCOM. The

Commission has no jurisdiction to decide the case

where there is no dispute under Section 86 of the Act.

29. These submissions are unacceptable for the

reason that the agreement entered into between the

parties clearly indicates the role of the Commission

particularly with regard to amendments. Article 12.10

of the Agreement extracted (supra) directs that the

agreement would not be amended and if amended by

way of changes being made in the agreement, they

would be subject to approval of the Commission.

30. The very agreement also stipulates the

scheduled commissioning date and the effective date.

The effective date would mean signing of the agreement

by the parties and the scheduled commission date

would be 18 months from such effective date. With the

action of the petitioners submitting representations to

BESCOM and the Government of Karnataka or the

Government directing extension to be made on several

factors would without doubt result in change of

scheduled commissioning date, which would be an

amendment to the PPA arrived at between the parties.

31. Tariff was also determined by the Commission

in the cases at hand. In terms of the agreement Article

5.1 (supra) deals with a particular tariff which also

depicts that if there is a delay in commissioning of the

project beyond the scheduled commissioning date, the

tariff would vary. The varied tariff has a direct link with

the scheduled commissioning date. If the scheduled

commissioning date would vary, resulting in variance of

tariff this would again become subject matter of

approval by the Commission. On a plain reading of the

said clauses of the PPA, the jurisdiction of the

Commission cannot be taken away. But, the act of the

Commission in directing or soliciting cases to be filed

before it and deciding the cases are such acts of the

Commission which cannot be countenanced.

32. I therefore, decline to accept the contention of

the petitioners that there is no dispute arisen for the

Commission to intervene or the petitioners to approach

the Commission. The dispute is not with regard to

interpretation of the agreement insofar as it concerns to

the parties of the agreement but, it is the events that

would lead to an amendment to the agreement that

confers jurisdiction on the Commission, not to solicit,

but to the petitioners or the parties to the PPA to

approach the Commission in terms of Section 86 of the

Act, which deals with functions of the Commission.

Section 86 of the Act reads as follows:

"86. Functions of State Commission:- (1) The State Commission shall discharge the following functions, namely:-

(a) determine the tariff for generation, supply, transmission and wheeling of electricity, wholesale, bulk or retail, as the case may be, within the State:

Provided that where open access has been permitted to a category of consumers under section 42, the State Commission shall determine only the wheeling charges and surcharge thereon, if any, for the said category of consumers;

(b) regulate electricity purchase and procurement process of distribution licensees including the price at which electricity shall be procured from the generating companies or licensees or from other sources through agreements for purchase of power for distribution and supply within the State;

(c) facilitate intra-State transmission and wheeling of electricity;

(d) issue licences to persons seeking to act as transmission licensees, distribution licensees and electricity traders with respect to their operations within the State;

(e) promote co-generation and generation of electricity from renewable sources of energy by providing suitable measures for connectivity with the grid and sale of electricity to any person, and also specify, for purchase of electricity from such sources, a percentage of the total consumption of electricity in the area of a distribution licensee;

(f) adjudicate upon the disputes between the licensees, and generating companies and to refer any dispute for arbitration;

(g) levy fee for the purposes of this Act;

(h) specify State Grid Code consistent with the Grid Code specified under clause (h) of sub-section (1) of section 79;

(i) specify or enforce standards with respect to quality, continuity and reliability of service by licensees;

(j) fix the trading margin in the intra-State trading of electricity, if considered, necessary; and

(k) discharge such other functions as may be assigned to it under this Act.

(2) The State Commission shall advise the State Government on all or any of the following matters, namely :-

(i) promotion of competition, efficiency and economy in activities of the electricity industry;

(ii) promotion of investment in electricity industry;

(iii) reorganization and restructuring of electricity industry in the State;

(iv) matters concerning generation, transmission , distribution and trading of electricity or any other matter referred to the State Commission by that Government.

(3) The State Commission shall ensure transparency while exercising its powers and discharging its functions.

(4) In discharge of its functions, the State Commission shall be guided by the National Electricity Policy, National Electricity Plan and tariff policy published under Section 3."

(Emphasis supplied)

Functions of the Commission as depicted under Section

86 of the Act confer manifold jurisdiction on it and one

of which, undoubtedly is the controversy in the case at

hand.

33. On a plain reading of Section 86 of the Act,

action of the Commission was without jurisdiction to

have solicited cases. But, the obligation of the parties to

the PPA is to approach the Commission for redressal of

the controversy. Though it is not a dispute as defined

under Section 86(1)(b) of the Act, it is the power of the

Commission to regulate the price of sale and purchase

of electricity under Section 86(1)(b) of the Act from

generating company and distribution of licensees

through agreements i.e, PPA.

34. It is apposite to notice the judgment of the

Apex Court in the case of ALL INDIA POWER

ENGINEER FEDERATION AN OTHERS v. SASAN

POWER LIMITED12 wherein the Apex Court holds as

follows:

"25. It is thus clear that if there is any element of public interest involved, the court

(2017) 1 SCC 487

steps in to thwart any waiver which may be contrary to such public interest.

26. On the facts of this case, it is clear that the moment electricity tariff gets affected, the consumer interest comes in and public interest gets affected. This is in fact statutorily recognised by the Electricity Act in Sections 61 to 63 thereof. Under Section 61, the appropriate Commission, when it specifies terms and conditions for determination of tariff, is to be guided inter alia by the safeguarding of the consumer interest and the recovery of the cost of electricity in a reasonable manner. For this purpose, factors that encourage competition, efficiency and good performance are also to be heeded. Under Section 62 of the Act, the appropriate Commission is to determine such tariff in accordance with the principles contained in Section 61. The present case, however, is covered by Section 63, which begins with a non obstante clause stating that notwithstanding anything contained in Section 62, the appropriate Commission shall adopt the tariff if such tariff has been

determined through a transparent process of bidding in accordance with the Guidelines issued by the Central Government. The Guidelines dated 19-1-2005 issued by the Central Government under Section 63 make it clear that such Guidelines are framed with the following objectives in mind:

"These Guidelines have been framed under the above provisions of Section 63 of the Act. The specific objectives of these Guidelines are as follows:

(1) Promote competitive procurement of electricity by distribution licensees;

(2) Facilitate transparency and fairness in procurement processes;

(3) Facilitate reduction of information asymmetries for various bidders;

(4) Protect consumer interests by facilitating competitive conditions in procurement of electricity;

(5) Enhance standardisation and reduce ambiguity and hence time for materialisation of projects;

(6) Provide flexibility to suppliers on internal operations while ensuring certainty on availability of power and tariffs for buyers.

xx xx xx xx

31. All this would make it clear that even if a waiver is claimed of some of the provisions of the PPA, such waiver, if it affects tariffs that are ultimately payable by the consumer, would necessarily affect public interest and would have to pass muster of the Commission under Sections 61 to 63 of the Electricity Act. This is for the reason that what is adopted by the Commission under Section 63 is only a tariff obtained by competitive bidding in conformity with Guidelines issued. If at any subsequent point of time such tariff is increased, which increase is outside the four corners of the PPA, even in cases covered by Section 63, the legislative intent and the language of Sections 61 and 62

make it clear that the Commission alone can accept such amended tariff as it would impact consumer interest and therefore public interest.

(Emphasis supplied)

The Apex Court in the afore-extracted judgment

considered power of the regulatory commission and the

change in the agreements which cannot pass muster

without the Commission being privy to such change.

35. The Apex Court, little earlier to the afore-

extracted judgment, in the case of GUJARAT URJA

VIKAS NIGAM LIMITED v. TARINI INFRASTURE

LIMITED13 has held as follows:

"17. As already noticed, Section 86(1)(b) of the Act empowers the State Commission to regulate the price of sale and purchase of electricity between the generating companies and distribution licensees through agreements for power produced for distribution and supply. As

(2016) 8 SCC 743

held by this Court in V.S. Rice & Oil Mills v. State of A.P. [V.S. Rice & Oil Mills v. State of A.P., AIR 1964 SC 1781], K. Ramanathan v. State of T.N. [K. Ramanathan v. State of T.N., (1985) 2 SCC 116: 1985 SCC (Cri) 162] and D.K. Trivedi & Sons v. State of Gujarat [D.K. Trivedi & Sons v. State of Gujarat, 1986 Supp SCC 20] the power of regulation is indeed of wide import. The following extracts from the reports in the above cases would illuminate the issue:

17.1.V.S. Rice & Oil Mills v. State of A.P. [V.S. Rice & Oil Mills v. State of A.P., AIR 1964 SC 1781]: (AIR p. 1787, para 20) "20. Then it was faintly argued by Mr Setalvad that the power to regulate conferred on the respondent by Section 3(1) cannot include the power to increase the tariff rate; it would include the power to reduce the rates. This argument is entirely misconceived. The word "regulate" is wide enough to confer power on the respondent to regulate either by increasing the rate, or decreasing the rate, the test being what is it that is necessary or

expedient to be done to maintain, increase, or secure supply of the essential articles in question and to arrange for its equitable distribution and its availability at fair prices."

17.2.K. Ramanathan v. State of T.N. [K.

Ramanathan v. State of T.N., (1985) 2 SCC 116 : 1985 SCC (Cri) 162] : (SCC pp. 130-31, paras 18-19) "18. The word "regulation" cannot have any rigid or inflexible meaning as to exclude "prohibition". The word "regulate" is difficult to define as having any precise meaning. It is a word of broad import, having a broad meaning, and is very comprehensive in scope. There is a diversity of opinion as to its meaning and its application to a particular state of facts, some courts giving to the term a somewhat restricted, and others giving to it a liberal, construction. The different shades of meaning are brought out in Corpus Juris Secundum, Vol. 76 at p. 611:

'"Regulate" is variously defined as meaning to adjust; to adjust, order, or govern by rule, method, or established mode; to adjust or control by rule, method, or established mode, or governing principles or laws; to govern; to govern by rule; to govern by, or subject to, certain rules or restrictions; to govern or direct according to rule; to control, govern, or direct by rule or regulations.

"Regulate" is also defined as meaning to direct; to direct by rule or restriction; to direct or manage according to certain standards, laws, or rules; to rule; to conduct; to fix or establish; to restrain; to restrict.'

See also: Webster's Third New International Dictionary, Vol. II, p. 1913 and Shorter Oxford Dictionary, Vol. II, 3rd Edn., p. 1784.

19. It has often been said that the power to regulate does not necessarily include the power to prohibit, and ordinarily the word "regulate" is not

synonymous with the word "prohibit". This is true in a general sense and in the sense that mere regulation is not the same as absolute prohibition. At the same time, the power to regulate carries with it full power over the thing subject to regulation and in absence of restrictive words, the power must be regarded as plenary over the entire subject. It implies the power to rule, direct and control, and involves the adoption of a rule or guiding principle to be followed, or the making of a rule with respect to the subject to be regulated. The power to regulate implies the power to check and may imply the power to prohibit under certain circumstances, as where the best or only efficacious regulation consists of suppression. It would therefore appear that the word "regulation" cannot have any inflexible meaning as to exclude "prohibition". It has different shades of meaning and must take its colour from the context in which it is used having regard to the purpose and object of the legislation, and the Court must necessarily keep in

view the mischief which the legislature seeks to remedy."

(Emphasis supplied)

The role of the Commission and its power to regulate is

delineated in the aforementioned judgments. In the

light of the judgments of the Apex Court, the

Commission cannot be kept in the dark when the effect

is amendment to the PPA. Therefore, I decline to accept

the contention of the learned counsel for the petitioners

that the Commission has no jurisdiction to entertain the

dispute.

36. Insofar as the contention that alternative

remedy of appeal is to be filed by the petitioners in

terms of Section 111 of the Act is concerned, the issue

need not merit any consideration, in the light of

preceding analysis with regard to action of the

Commission being vitiated and the jurisdiction of the

Commission being upheld. The contention of filing an

appeal before the Appellate Authority in terms of

Section 111 of the Act is not gone into.

37. For the foregoing reasons, I hold that the

action of the Commission in soliciting petitions to be

filed before it after having pre-judged the issue is in

violation of every known canon of principles of natural

justice and is vitiated by bias; the jurisdiction of the

Commission cannot be taken away on the plea of the

petitioners that parties cannot confer jurisdiction;

parties have not conferred jurisdiction, the jurisdiction

is conferred by the Act and the PPA between the parties.

38. In the result, I pass the following:

ORDER

(a) All the writ petitions are allowed, the impugned orders passed by the Commission in all these cases stand quashed.

(b) These matters are remitted back to the hands of the Commission for appropriate resolution of the dispute bearing in mind the observations made in the course of the order

with regard to the controversy brought before it.

(c) The Commission shall also consider all subsequent events that have taken place after passage of the impugned orders, while passing orders afresh, in the case now remitted.

(d) Parties to the lis are at liberty to place on record all such documents that would advance their cause.

(e) The Commission shall consider the claims of the petitioners and pass appropriate orders within six months from the date of receipt of a copy of this order.

(f) Interim orders granted and subsisting, if any, in all these cases shall continue to operate till the Commission takes up the case for consideration of an interim prayer, if sought for by the petitioners.

(g) All the contentions, except the ones decided in this order, of both the parties are kept open.

Sd/-

JUDGE

bkp CT:MJ

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter