Citation : 2021 Latest Caselaw 3456 Kant
Judgement Date : 21 October, 2021
1
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 21ST DAY OF OCTOBER 2021
PRESENT
THE HON'BLE MR. JUSTICE ALOK ARADHE
AND
THE HON'BLE MR.JUSTICE S. VISHWAJITH SHETTY
COMAP NO.31 OF 2021
BETWEEN:
LARSEN AND TOUBRO LIMITED
(CONSTRUCTION DIVISION)
NO.19, KUMARA KRUPA ROAD
1ST AND 2ND FLOORS
BENGALURU - 560 001.
REPRESENTED HEREIN BY ITS
AUTHORISED SIGNATORY
MR. C.A. VENKATESH.
... APPELLANT
(BY MR. R.V.S. NAIK, SR. COUNSEL FOR
MR. VIDUR NAIR AND
MR. T. SURYANARAYANA, ADVS.,)
AND:
1. GEODESIC TECHNIQUES PRIVATE LIMITED
NO.4, 4TH CROSS
PEENYA INDUSTRIAL ESTATE
1ST STAGE, PEENYA
BANGALORE - 560 058
REPRESENTED BY ITS
MANAGING DIRECTOR
MR. SRINIDHI ANANTHARAMAN.
2
2. JUSTICE R.V. RAVEENDRAN (RETD.)
SOLE ARBITRATOR
NO.8/2, KRISHNA ROAD
BASAVANAGUDI
BANGALORE - 560 004.
... RESPONDENTS
(BY MR. S. SRIRANGA, ADV., C/R1)
---
THIS COMAP IS FILED UNDER SECTION 13(1A) OF
COMMERCIAL COURTS ACT, 2015 R/W SECTION 37 OF THE
ARBITRATION AND CONCILIATION ACT, 1996, PRAYING TO
CALL FOR RECORDS IN COM.A.S. NO.80/2016 AS WELL AS
THE ARBITRAL RECORDS WHICH ARE BEFORE THE TRIAL
COURT. SET ASIDE THE IMPUGNED JUDGMENT AND DECREE
DATED 05.12.2020 PASSED BY THE LXXXIII ADDL. CITY
CIVIL AND SESSIONS JUDGE, BENGALURU (CCH-84) (TRIAL
COURT) (ANNEXURE-A) DISMISSING COM.A.S.NO.80/2016 &
ETC.
THIS COMAP COMING ON FOR FINAL HEARING, THIS
DAY, ALOK ARADHE J., DELIVERED THE FOLLOWING:
ORDER
This appeal takes an exception to judgment dated
05.12.2020 passed by the Commercial Court by which
objections preferred by the appellant under Section 34
of the Arbitration and Conciliation Act, 1996 (hereinafter
referred to as 'the Act' for short) have been dismissed.
2. Facts leading to filing of this appeal briefly
stated are that the appellant is a private limited
company and is engaged in the business of construction
and of primarily designing and building steel structures.
The appellant was awarded a contract of Engineering
Procurement and Construction Contract for expansion of
Bangalore International Airport Limited (hereinafter
referred to as 'the BIAL' for short) on 31.05.2011. The
scope of the work involved Engineering Procurement and
Construction work of three storied RCC Structure,
Structural Steel Roof with Roof coverings on east - west
and southern sides of existing terminal building and
steel canopy on the northern side. The appellant sub
contracted the structural Steel Roof work to the
respondent for a consideration of Rs.110 Crores. A letter
of intent dated 29.09.2011 (Ex.C3) was issued. The
aforesaid letter of intent was amended on 15.10.2011.
3. Thereafter, a tripartite agreement dated
25.01.2012 (Ex.R1) was executed between BIAL, the
appellant and the respondent viz., the sub contractor.
Under the agreement, the respondent had to complete
the work within 10 months from 04.10.2011 i.e., upto
03.08.2012. The possession of the site was handed over
to the appellant on 31.08.2013.
4. During the execution of the work, in order to
secure the progress of the work, the appellant and the
respondent agreed that the appellant would secure the
structural steel and consumables required by the
respondent for the contract work and that the appellant
may engage the services of other sub contractors in this
behalf on payment of requisite charges by the
Respondent.
5. However, there was delay in completion of
the work. The disputes arose between the parties.
Thereupon the respondent filed an application under
Section 11(6) of the Arbitration and Conciliation Act,
1996 seeking appointment of an . The aforesaid
application was allowed by this court by an order dated
03.09.2014 and a sole was appointed. The proceeding
before the commenced on 13.12.2014. The parties filed
respective pleadings and adduced oral and documentary
evidence. The appellant examined three of its officers as
RW1 to RW3 and adduced documents viz., Ex.R1 to
Ex.R72 in evidence, whereas, the respondent examined
three of its officers as CW1 to CW3 and tendered
documents viz., EX.C1 to Ex.C278 in evidence.
6. The arbitral tribunal passed an award on
06.02.2016 and directed the appellant to pay a sum of
Rs.5,32,83,419/- along with interest at the rate of 18%
per annum and cost of Rs.12,00,000/- as well as stamp
duty of Rs.3,26,985/- paid by respondent No.1 on the
award under the Karnataka Stamp Act, 1957. The
appellant filed objections under Section 34 of the Act
before the Commercial Court. The Commercial Court
vide judgment dated 05.12.2020 has dismissed the
objections preferred by the appellant. In the aforesaid
factual background, this appeal has been filed.
7. Learned Senior counsel for the appellant
while inviting the attention of this court to objections
preferred by the appellant under Section 34 of the Act
submitted that though various objections were raised,
the Commercial Court in a cryptic and cavalier manner
without adverting to the objections raised by the
appellant has dismissed the petition under Section 34 of
the Act. It is further submitted that while passing the
impugned judgment, the Commercial Court has neither
adverted tot eh grounds nor the contentions raised by
the appellant. It is also argued that interest at the rate
of 18% has been awarded for pendente lite and for a
period thereafter, without assigning any reasons, which
cannot be sustained in the eye of law. Learned Senior
counsel has taken us through the impugned judgment of
the Commercial Court and has submitted that the
matter deserves to be remitted to the Commercial Court
for decision on the objections preferred by the appellant
afresh. In support of aforesaid submissions, reliance has
been placed on decisions in 'SSANYONG
ENGINEERING AND CONSTRUCTION COMPANY
LIMITED VS. NATIONAL HIGHWAYS AUTHORITY
OF INDIA', (2019) 15 SCC 131, 'DYNA
TECHNOLOGIES PVT. LTD. VS. CROMPTON
GREAVES LTD.', 2019 SCC ONLINE SC 1656, 'V4
INFRASTRUCTURE PRIVATE LIMITED VS. JINDAL
BIOCHEM PRIVATE LIMITED', FAO (OS) (COMM)
107/2018, 'ASSOCIATE BUILDERS VS. DELHI
DEVELOPMENT AUTHORITY', (2015) 3 SCC 49,
'P.SHEIK BATCHA ROWTHER AND OTHERS VS.
N.R.ALAGAPPAN SERVAI', AIR 1959 MAD 12,
'ORIENTAL STRUCTURAL ENGINEERS PRIVATE
LIMITED VS. STATEOF KERALA', (2021) 6 SCC 150
and 'UNION OF INDIA VS. WARSAW ENGINEERS
AND OTHERS', COMAP NO.25/2021.
8. On the other hand, learned counsel for the
respondent submitted that a division bench of this court
in UNION OF INDIA VS. WARSAW ENGINEERS
supra in para 12 has held that there is a two stage
process in considering the challenge under Section 34 of
the Act. It is pointed out that first stage is that a Judge
should advert to the grounds agitated at the time of
hearing and thereafter, he has to examine whether
grounds urged are available under Section 34(2)(a) of
the Act and if such grounds are available, to consider
each and every ground. It is also submitted that in para
7 of the judgment, the Commercial Court has adverted
to the grounds raised and in para 21 has recorded a
finding that no ground enumerated under Section
34(2)(a) of the Act for interference with the award
passed by the is made out. It is further submitted that
the judgment passed by the Commercial Court is in
consonance with the principles laid down by division
bench of this court in WARSAW ENGINEERS supra. It is
further submitted that the grounds raised in this appeal
do not fall within the ambit of Section 34(2)(a) of the
Act. In support of aforesaid submissions, reliance has
been placed on decisions in 'NATIONAL HIGHWAYS
AUTHORITY OF INDIA VS. M.HAKEEM & ANR.',
2021 SCC ONLINE SC 473, 'PATEL ENGINEERING
LTD VS. NORTH EASTERN ELECTRIC POWER
CORPORATION LTD.,', (2020) 7 SCC 167,
'SSANGYONG ENGINEER AND CONSTRUCTION
COMPANY LTD. VS. NATIONAL HIGHWAYS
AUTHORITY OF INDIA', (2019) 15 SCC 131,
'NATIONAL HIGHWAYS AUTHORITY OF INDIA VS.
ITD CEMENTATION INDIA LTD.', (2015) 14 SCC 21,
'ASSOCIATE BUILDERS VS. DELHI DEVELOPMENT
AUTHORITY', (2015) 3 SCC 49, and 'NATIONAL
HGIHWAYS AUTHORITY OF INDIA VS. R.N. SHETTY
& COMPANY', 2014 SCC ONLINE DEL 3392.
9. We have considered the submissions made
by learned counsel for the parties and have perused the
record. The scope of interference with an award passed
by an arbitrator is confined to the grounds mentioned in
Section 34(2) of the Act. One more ground has been
incorporated to challenge the award by Amendment Act
2015 with effect from 23.10.2015 viz., 'Public Policy of
India'. The scope of interference with an arbitral award
is well settled. In this connection, reference may be
made to decision of Supreme Court in 'DYNA
TECHNOLOGIES PVT. LTD. supra, wherein in
paragraphs 24 and 25 of the aforesaid decision, it has
been held as under:
24. There is no dispute that Section 34 of the Arbitration Act limits a challenge to an award only on the grounds provided therein or as interpreted by various Courts. We need to be cognizant of the fact that arbitral awards should not be interfered with in a casual and cavalier manner, unless the Court comes to a conclusion that the perversity of the award goes to the root of the matter without there being a possibility of alternative
interpretation which may sustain the arbitral award. Section 34 is different in its approach and cannot be equated with a normal appellate jurisdiction. The mandate under Section 34 is to respect the finality of the arbitral award and the party autonomy to get their dispute adjudicated by an alternative forum as provided under the law. If the Courts were to interfere with the arbitral award in the usual course on factual aspects, then the commercial wisdom behind opting for alternate dispute resolution would stand frustrated.
25. Moreover, umpteen number of judgments of this Court have categorically held that the Courts should not interfere with an award merely because an alternative view on facts and interpretation of contract exists. The Courts need to be cautious and should defer to the view taken by the Arbitral Tribunal even if the reasoning provided in the award is implied unless such award portrays perversity unpardonable under Section 34 of the Arbitration Act.
10. A division bench of this court in UNION OF
INDIA VS. M/S WARSAW ENGINEERS AND
ANOTHER vide judgment dated 17.04.2021 has held as
follows:
12. We have also referred to the decision of the Apex Court which holds that the scope of interference is confined to specific grounds which are available under Section 34 of the said Act of 1996. It is also well settled that the Court should not interfere with an award merely because another view on facts and interpretation of contract exists. When a Judge dealing with the petition under Section 34 of the said Act of 1996 hears the petition on merits, firstly, he must advert to the grounds agitated at the time of hearing in support of the petition under Section 34 of the said Act of 1996. He has to examine whether the grounds urged are available under sub-section (2) and sub-
section (2A) of Section 34 of the said Act of 1996. If the grounds pleaded are
available under Section 34 of the said Act of 1996, the next step will be to consider each and every ground pressed into service on merits and to come to conclusion whether the grounds have been established.
13. Therefore, it is necessary for a Judicial Officer dealing with the petition under Section 34 of the said Act of 1996 to precisely record the submissions made by the counsel for the petitioner in support of the petition under Section 34 of the said Act of 1996. It is also necessary to precisely record the submissions made by way of reply to the specific grounds pleaded by the petitioner. It is not necessary to make verbatim reproduction of oral or written submissions. The gist of every ground agitated and reply to it by the rival party needs to be incorporated. This helps the Judges to deal with every ground urged.
14. Thereafter, each and every ground will have to be separately
considered. It is necessary for the Judicial Officer to firstly consider whether the ground agitated is covered by any of the grounds set out under Section 34 of the said Act of 1996. If according to the learned Judge the ground agitated is not available for challenge in accordance with Section 34 of the said Act of 1996, the Judicial Officer will have to record the reasons for the said conclusion. If he is of the view that the ground agitated is available under Section 34 of the said Act of 1996, he will have to consider whether the said ground is established and record reasons in that behalf.
15. Now coming to the issue of decisions relied upon by the parties, it is not necessary for the Judicial Officer to quote the relevant parts of the said decisions. What is more important is that the judgment should show that the Judicial Officer has adverted to the ratio of the judgment. Only after adverting the ratio of the judgment, the Judicial Officer can come to a conclusion whether the same
can be applied to the facts of the case before him.
16. Thus, while dealing with the petition under Section 34 of the said Act of 1996, for arriving at a correct conclusion, the Judicial Officer, as stated earlier, must precisely record the submissions canvassed in support of the petition and the submissions canvassed for opposing the petition. It is not necessary to reproduce the submissions verbatim. The substance of the grounds urged must be briefly recorded. As a remedy of an appeal is available against the judgment and order in a petition under Section 34 of the said Act of 1996, recording of the submissions made across the Bar helps the Appellate Court to decide the appeal properly. If the submissions are not properly recorded, it gives a scope to an argument that a particular submission was made before the concerned Court but the same has not been considered. If such submissions are made, as per the settled
law, the Appellate Court has to relegate the aggrieved party to the same Court for making an appropriate application as the Appellate Court cannot decide what transpired before the Court which has passed the impugned order.
17. In the present case, we find that the submissions made in support of the petition under Section 34 of the said Act of 1996 are not properly recorded. There is a cursory reference to only one or two submissions in paragraph 17 of the judgment.
18. As stated earlier, the jurisdiction under Section 34 of the said Act of 1996 is not an appellate jurisdiction. The exercise of jurisdiction is confined to the grounds set out in Section 34 of the said Act of 1996.
19. In the facts of the case, we find that after having gone through the impugned judgment and order, it is very difficult for us to know what were the
precise submissions made in support of the petition and for opposing the petition. As the submissions are not properly recorded, the learned Judge has dealt with the issue in a very cryptic manner.
11. It is well settled in law that reason is the
heartbeat of every conclusion and absence of reasons
renders the orders lifeless. The requirement of assigning
reasons ensures transparency and fairness in decision
making. The reasons act as a link between the mind of
the decision maker and the issue, which arises for
determination. The Supreme Court has emphasized the
requirement of new recording of reasons in support of
the conclusions in 'BHAGAT RAJA VS. UNION OF
INDIA AND OTHERS', AIR 1967 SC 1606, and it has
been held that reasons recorded in support of the
conclusions must be explicit and intelligible. It has
further been held that reasons have to be proper,
relevant, germane and should deal with arguments
advanced, points raised and issues involved. The
requirement of assigning the reasons also helps the
appellate court in ascertaining as to the grounds, which
weighed with the authority in coming to a particular
conclusion. [See: 'VISHNU DEV SHARMA VS.
STATEOF U.P. & ORS', (2008) 3 SCC 172].
12. Now we may advert to the impugned
judgment. Paragraphs 1 to 6 contain the narration of
facts. In paragraph 7 of the impugned judgment
reference has been made to main grounds of challenge
to the impugned award. Paragraph 8 refers to the
averments contained in statement of objections.
Paragraphs 9 and 10 refers to points for consideration.
In paragraphs 12 to 17 again facts have been stated . In
paragraphs 17 to 20, the Commercial Court has referred
to certain admitted facts and other facts. In paragraphs
21 to 26, the point for consideration has been answered.
From close scrutiny of paragraphs 21 to 26 of the
judgment, it is evident that neither the contentions nor
the grounds raised by the appellant have been dealt
with by the Commercial Court. Thus, the Commercial
Court without assigning any reasons in a cryptic and a
cavalier manner has recorded the conclusion that the
award passed by the cannot be considered as erroneous
or opposed to Public Policy of India. It has further been
held that the appellant has failed to make out any
cogent grounds to set aside the arbitral award and the
award passed by the is neither perverse, unfair nor
unreasonable. From close scrutiny of paragraphs 21 to
26, it is evident that the Commercial Court has not
assigned any reasons for recording the conclusions. The
Commercial Court has also not dealt with various
contentions and grounds raised in the petition under
Section 34 of the Act.
13. The Commercial Court, therefore, cannot
record the conclusion without assigning reasons that no
ground for interference under Section 34 of the Act is
made out. In paragraph 14 of the judgment in Warsaw
Engineers, a division bench of this court has held that
each and every ground has to be separately considered
to find out whether it is covered by any of the grounds
set out under Section 34 of the Act. However, the
aforesaid exercise cannot be carried out without
assigning the reasons.
14. The Commercial Court without considering
the ratio of the judgments relied upon by the parties has
simply recorded the conclusion that the judgments relied
upon by the appellants are not applicable to the facts of
the case. The Commercial Court has not assigned any
reasons for recording a conclusion that the grounds for
interference under Section 34 of the Act is not made
out. Therefore, though this court is conscious of the fact
that normally the appellate court could be slow to pass
an order of remand, yet in the facts of the case, we are
left with no option but to remand the case as no reasons
have been assigned by the Commercial Court for
arriving at the conclusion that grounds as enumerated
under Section 34 of the Act are not made out.
15. For the aforementioned reasons, the
judgment dated 05.12.2020 passed in COM
A.S.No.80/2016 is quashed and the matter is remitted
to the Commercial Court. The parties shall appear before
the Commercial Court on 28.10.2021 for fixing the date
of hearing. It will not be necessary for the Commercial
Court to issue notice to the parties of the date fixed by
it. Taking into account the fact that the petition was
filed in the year 2016, the Commercial Court shall make
an endeavor to conclude the proceeding within a period
of four months from the date of appearance of the
parties.
In view of the disposal of the main appeal itself, all
pending applications do not survive for consideration.
Accordingly, the same are disposed of.
In the result, the appeal is disposed of.
Sd/-
JUDGE
Sd/-
JUDGE SS
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!