Citation : 2021 Latest Caselaw 1747 Kant
Judgement Date : 16 March, 2021
1
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
R
DATED THIS THE 16TH DAY OF MARCH 2021
PRESENT
THE HON'BLE MR. JUSTICE ALOK ARADHE
AND
THE HON'BLE MR.JUSTICE NATARAJ RANGASWAMY
W.A. NO.3070 OF 2018 (LB-BMP)
IN
W.P. NO.13214 OF 2018 (LB-BMP)
BETWEEN:
FLORIANA ESTATE APARTMENT OWNERS
WELFARE ASSOCIATION
(REG.NO.154/05-06)
#53, SARJAPURA ROAD
KORAMANGALA 3RD BLOCK
BENGALURU-560034
REP. BY ITS AUTHORISED SIGNATORY.
... APPELLANT
(BY MR. VIVEK S. REDDY, SR. COUNSEL A/W
MR. DILLI RAJAN, ADV., FOR
MR. K.N. SUBBA REDDY, ADV.,)
AND:
1. THE COMMISSIONER
BENGALURU DEVELOPMENT AUTHORITY
BENGALURU.
2. THE COMMISSIONER
BBMP, BENGALURU.
3. THE JOINT DIRECTOR OF TOWN PLANNING-SOUTH
(PREVIOUSLY JOINT DIRECTOR OF TOWN PLANNING)
B.B.M.P., BENGALURU.
2
4. THE ASSISTANT DIRECTOR OF TOWN PLANNING
BANGALORE SOUTH
B.B.M.P, BENGALURU.
5. M/S KOLTE PATIL DEVELOPERS LIMITED
BEING A COMPANY INCORPORATED UNDER THE
COMPANIES ACT 1956, HAVING ITS
REGISTERED OFFICE AT NAVIPETH
DISTRICT JALAGAON
MAHARASHTRA 048.
REPRESENTED BY ITS DIRECTOR
SRI. NARESH PATIL
AGED ABOUT 54 YEARS
HAVING THE ABOVE SAID ADDRESS
AS MENTIONED IN THE CAUSE TITLE.
CORPORATE OFFICE AT:
#121, 10TH FLOOR
THE ESTATE, DICKENSON ROAD
BESIDE MANIPAL CENTRE
BENGALURU-560001.
6. M/S. ANKIT ENTERPRISES
(A REGISTERED PARTNERSHIP FIRM)
HAVING OFFICE AT # 121, 10TH FLOOR
THE ESTATE, DICKENSON ROAD
BESIDE MANIPAL CENTRE
BENGALURU-560001.
REPRESENTED BY ITS PARTNERS
SRI. RAJESH PATIL
AND SRI. NARESH PATIL
AGED ABOUT 54 YEARS
HAVING THE ABOVE SAID ADDRESS
AS MENTIONED IN THE CAUSE TITLE.
... RESPONDENTS
(BY MR. K.N. PUTTEGOWDA, ADV., FOR R2-R4
MR. K. KRISHNA, ADV., FOR R1
MR. G.L. VISHWANATH, ADV., FOR R5 & R6
MR. ASHOK HARANAHALLI, SR. COUNSEL A/W
MR. VINAYAKA B, ADV., FOR R5)
---
3
THIS W.A. IS FILED UNDER SECTION 4 OF THE KARNATAKA
HIGH COURT ACT, PRAYING TO SET ASIDE THE ORDER DATED
25.9.2018 IN WP 13214/2018 (LB-BBMP) AND ALLOW THE WRIT
PETITION AS PRAYED FOR.
THIS WRIT APPEAL HAVING BEEN HEARD AND RESERVED
FOR JUDGMENT, COMING ON FOR PRONOUNCEMENT OF
JUDGMENT, THIS DAY, ALOK ARADHE J., DELIVERED THE
FOLLOWING:
JUDGMENT
In this intra court appeal under Section 4 of the
Karnataka High Court Act, 1961 the appellants have
assailed the validity of the order dated 25.09.2018
passed by the learned Single Judge by which writ
petition preferred by the appellant has been dismissed
with cost of Rs.1 Lakh. In order to appreciate the
appellant's challenge to the impugned order, few facts
need mention, which are stated infra:
2. The appellant is an Association of Apartment
Owners viz., M/s Flourina Estate Apartment Owners
Welfare Association. The respondent No.5 is a builder
(hereinafter referred to as 'the builder' for short)
whereas, respondent No.6 is a partnership firm
(hereinafter referred to as 'the firm' for short), which
deals in real estate business. One Smt.Rukmini Devi
Prasad was the owner of land bearing Sy.No.53/1
measuring 5607.22 square meters and land bearing
Sy.No.53/2 measuring 5953.05 square meters, situate
at Jakkasandra, Koramangala, Bangalore. The aforesaid
Smt.Rukmini Devi Prasad applied for change of land use
and permission to change the land use was granted on
19.09.1994 in respect of land bearing Sy.No.53/1 and
Sy.No.53/2 from industrial sector to residential purpose
under Section 15(1) of the Karnataka Town and Country
Planning Act, 1961 for Group Housing Scheme.
Thereafter, the builder applied for sanction of a Group
Housing Scheme which was approved by Joint Director,
Town and Country Planning vide order dated
16.02.2001. The aforesaid sanction plan was approved
in respect of land bearing Sy.No.53/2 with two approach
roads which were to be used as exit and entry points
which were of 6 meters in width. The Builder thereafter
constructed a residential complex viz., M/s Flourina
Estate Apartment Owners Welfare Association and on
completion of the construction, occupancy certificates
were issued by Joint Director of Town and Country
Planning on 19.01.2004 and 22.11.2004 respectively.
Thereafter, the Khata was bifurcated by the Assistant
Revenue Officer, Koramangala by which the land bearing
Sy.No.53/1 and Sy.No.53/2 was sub divided on
26.09.2005. Thereafter the builder obtained sanction for
a separate building plan from Joint Director, Town and
Country Planning for construction of commercial
complex in front of land bearing Sy.No.53/1. A sale
deed was executed by the owner of Sy.No.53/1 and
Sy.No.53/2 viz., Smt.Rukmini Devi Prasad Verma and
Mr.C.A.Joseph in favour of respondent No.6 viz.,
partnership firm and in the aforesaid sale deed, the
respondent No.5, builder was a consenting party to the
sale deed.
3. One of the resident's of M/s Flourina Estate
Apartment Owners Welfare Association viz., Ashok
Kumar Pati challenged the sanction plan dated
26.09.2005 in a writ petition viz., W.P.No.18396/2006.
In the aforesaid writ petition, the builder filed a memo
and furnished an undertaking that it would not raise any
construction according to the building plan, which was
under challenge on 28.08.2009. Thereafter, by a
communication dated 24.05.2010, the Joint Director,
Town and Country Planning, Bruhat Bangalore
Mahanagara Palike (hereinafter referred to as 'the BBMP'
for short) asking whether the bifurcation certificate is
required to be obtained from Bangalore Development
Authority (hereinafter referred to as 'the Authority' for
short) before issuance of sanction plan. A reply was sent
on 21.06.2010 to the aforesaid query by the Town
Planning member of Authority stating that prior order of
bifurcation of site is necessary in accordance with
Bangalore Development Authority bye laws but as the
possession has already been granted, the opinion was
withheld. Another communication was sent by the Joint
Director, Town and Country Planning, BBMP on
30.07.2010 in which a query was raised whether
sanction plan can bee issued on based on special notice
for bifurcation of Khatha issued on 26.02.2005.
Thereafter, sanction to the building plan by the Assistant
Director, Town Planning , BBMP to construct club house,
which was later on withdrawn and occupancy certificate
was denied based on objections of the appellant.
Thereafter, the Commissioner, BBMP and Joint Director,
BBMP sanctioned yet another building plan on
23.03.2011 to construct commercial building in front of
portion bearing Sy.No.53/1.
4. Another writ petition was filed viz.,
W.P.No.49732/2012 by some of the residents viz.,
Amith Bannerjee and 16 others in which challenge was
made to the sanction plan dated 23.03.2011. The
aforesaid writ petition was decided by the learned Single
Judge by an order dated 26.03.2013 and following
directions were issued:
(i) Though I see no reason to quash the impugned NOC and the sanction plan, the third respondent is directed to reconsider the compliance regarding means of access by re- visiting item-10B(1) of the NOC dated 23.01.2009 by recording satisfaction with regard to width of the abutting road by adopting the method for determination as discussed and indicated in paragraphs 24 to 27 of this order.
(ii) On such determination, if the
requirement is satisfied, the NOC dated
23.01.2009 granted shall be reaffirmed or else necessary reasoned order be passed in that regard.
(iii) The said exercise shall be completed by the third respondent within two weeks from the date of receipt of a copy of this order.
(iv) Until the said exercise is completed by the third respondent, the respondents No.4 to 6 shall not proceed with the construction.
(v) if the NOC is re-affirmed by the
shall thereafter ensure that the construction is proceeded only in accordance with the requirements of the NOC and sanction plan.
(vi) The petitions are disposed of with the above directions.
5. The Department of Fire and Emergency
Services of BBMP sent a communication dated
09.04.2014 recommending the acceptance of change of
width of the road on the eastern side of the property
from 6 meters to 9 meters. The firm applied for sanction
of a building plan, which was approved by Joint Director,
Town and Country Planning, BBMP on 21.09.2016 for
construction of front portion on Sy.No.53/1. In response
to the application filed by member of the appellant
Association under the provisions of Right to Information
Act, 2005 the Joint Director, Town and Country
Planning, BBMP stated that no fresh or modified plan
was issued to the builder in respect of Sy.No.53/1 and
Sy.No.53/2. The aforesaid sanction plan was challenged
by the appellant in a writ petition before the learned
Single Judge viz., W.P.No.13214/2018. The said writ
petition was dismissed by the learned Single Judge vide
order dated 25.09.2018 on the ground that the
appellant Association is out to misuse and abuse the
process of law by launching spree of litigation against
the builders. It was further held that at every stage, the
appellant has invoked the writ jurisdiction of this court
to ensure that construction being raised under a duly
sanctioned plan is hampered one way or other. It was
also held that not only two writ petitions were filed by
appellant and were disposed of by this court but also
two civil suits are pending trial. It was also held that
BBMP has already considered the entire matter and has
sanctioned the building plan in accordance with bye laws
and Rules and the practices adopted by the appellant
deserves to strongly deprecated and put down with iron
hands of justice. Accordingly, the writ petition was
dismissed with exemplary cost of Rs.1 Lakh to be
deposited by the appellant. In the aforesaid factual
background, this appeal has been filed.
6. Learned Senior counsel for the appellant
submitted that Sy.No.53/1 and Sy.No.53/2 measuring
11,560 square meters of Jakkasandra Village, Begur
Hobli, Sarjapur Road, Koramangala comprises composite
property. It is pointed out while referring to Annexure-C
to the writ petition that the builder developed the said
property and in the year 2001, obtained composite plan
for both survey numbers and constructed a residential
apartment on land bearing property No.53/1 and sold
the same to 103 members of the appellant Association.
It is also pointed out that occupancy certificate was
granted in respect of property No.53/1 and 53/2 on
16.01.2004 and 22.11.2004 by which ingress and
aggress was provided by way of roads measuring 6 feet
in width on the property on either side. It is also urged
that in the year 2016, the firm by suppressing the fact
of the sanction plan obtained on 16.02.2001, once again
the got a plan sanctioned on 21.09.2016. It is further
submitted that the aforesaid sanction plan was issued in
violation of Section 17 of the Town and Country Planning
Act, as well as building bye laws and zoning regulations.
It is also urged that without seeking modification of the
whole sanction plan BBMP could not have accorded
sanction to the new plan in the year 2016. It is also
pointed out that the partners in the firm are the same
who were directors in the builder.
7. It is further submitted that the subsequent
building plan issued on 21.09.2016 has been obtained
by suppression of facts and by playing fraud. It is
further submitted that ingress and aggress which was
provided by roads of 6 meters in width has been taken
away by the new plan and therefore, sanction plan
constitutes violation of the old plan and Regulations of
the BBMP Bye laws. It is submitted that there is no
bifurcation under Section 17 of the Act and in statement
of objections filed in writ petition No.7807/2019
pertaining to same sanction plan, the BBMP has
admitted the aforesaid facts. It is also pointed out that
new master plan Regulation of 2015 stipulates that
there must be minimum road of 30 meters width for
developing plot of the size of 4000 to 20000 square
meters and such a big size requires 30 meters road in
width compulsorily and the same cannot be developed
without adherence to section 17 of the Town and
Country Planning Act, 1961. it is further submitted that
the firm has unjustly enriched itself by obtaining the
plan and has converted the excess road area to its
development land which effectively means that it has
been granted 3.2 width FAR and has sold the earlier
road to the purchaser.
8. It is also urged that no right to register Khata
can arise until and unless a plot has been sub divided
under Section 17 of the Town and Country Planning Act,
1961 and a Khata cannot be secured without adherence
to Section 17 of the Act. It is also urged that from
perusal of Clause 3.2.10 of the Bangalore Mahanagara
Palike Building Bye Laws, it is evident that Section 17 of
the Act applies to the plot as well and is not confined in
its operation to layout alone. It is also pointed out that
aforesaid clause mentions the documents, which are
required to be obtained from the applicant who seeks
sanction of the plan. Reference has also been made to
clause 3.8 of the Revised Master Plan, 2015 and it has
been contended that means of access to high rise
building has to be provided on a thorough fare of 12
meters in width and this road has to be approved by the
Authority and maintained by the local Authority. It is
also submitted that the firm has illegally developing the
front portion and has thereby diminished the rights of
the residents in hind portion of the property viz., land
bearing property No.53/1. It is further submitted that
right to develop the land is a constitutional right as
guaranteed under Article 300A of the Constitution of
India. In support of aforesaid submissions, reliance has
been placed on decisions in DIPAK KUMAR
MUKHERJEE VS. KOLKATA MUNICIPAL
CORPORATION AND OTHERS, (2013) 5 SCC 336,
T.VIJAYALAKSHMI AND OTHERS VS. TOWN
PLANNING MEMBER AND ANOTHER, (2006) 8 SCC
502, DECISION OF ALLAHABAD HIGH COURT IN
EMERALD COURT OWNER RESIDENT WELFARE
ASSOCIATION VS. STATE OF U.P. THRU SECY. AND
OTHERS, AND DECISION OF THIS COURT IN
J.VENKATESH VS. COMMISSIONER, B.B.M.P., 2016
SCC ONLINE KAR 8293, SMT.NEHA VS. THE
COMMISSIONER AND OTHERS, W.P.NO.27012/12
DATED 23.08.2012.
9. On the other hand, learned counsel for
respondent No.6 - firm submitted that respondent No.6
is the absolute owner and is in possession of land of
Sy.No.53/1 situated Jakkasandra Village, Begur Hobli,
Bangalore South Taluk. It is further submitted that the
aforesaid land has been purchased by the firm vide
registered sale deed dated 31.1.2007 and the khata in
respect of said property is in the name of the firm. It is
pointed out that the firm is constructing a residential
apartment as per the plan sanctioned on 21.09.2016. It
is also submitted that the firm has constructed 5 floors
and has registered the project with Real Estate
Regulatory Authority. It is also urged that appellant has
no locus standi to question the sanction plan as the
Apartment complex in respect of which appellant has
claimed right is situated on Sy.No.53/2 and its residents
have undivided share in Sy.No.53/2. It is pointed out
from the record that land has been sanctioned in favour
of the firm in respect of land bearing Sy.No.53/1 and
land bearing Sy.No.53/1 and Sy.No.53/2 are distinct
parcels of land having been bifurcated in the year 2004
and challenge made by the appellant to the bifurcation
has not been successful and appellant is in no way
aggrieved with the issuance of the plan dated 29.9.2016
sanctioned in favour of the firm. It is also urged that
writ of certiorari cannot be invoked to quash the
permission granted by the Corporation as the same can
be issued against action of judicial or quasi judicial
bodies for exercise of quasi judicial power. It is
contended that issuance of sanction plan is permission /
licence granted by the BBMP under Section 299 of the
Karnataka Municipal Corporation Act which is in the
nature of administrative power of BBMP. Therefore, the
writ of certiorari cannot be issued to quash the sanction
plan.
10. It is also contended that the appellant has
not exhausted the alternative remedy as the appellant
has not made any complaint to the BBMP before
approaching this Court. It is also pointed out that BBMP
has the power to issue notice under Section 308 and
321 of the Karnataka Municipal Corporation Act to the
person putting up such a construction if it deems fit and
such matters have to be contested before Karnataka
Appellate Tribunal or by way of a civil suit. It is also
pointed that during the pendency of this writ appeal the
appellant has made a representation before the BBMP in
the year 2019 in which grievance was made with regard
to the sanction plan which has been questioned before
the learned Single Judge. The BBMP has, on the basis of
the complaint, made by the appellant, has issued notice
to the firm to stop construction. The aforesaid
communication is subject matter of W.P.No.7807/2019
and is pending before the learned Single Judge,
therefore, this appeal is prematured. It is also urged
that the appellant is in the habit of filing frivolous
petitions to ensure that the firm does not put up
construction on the property and the appellant is
meddlesome interloper without any genuine grievance.
11. It is also pointed out that the appellant had
challenged the sanction plan dated 16.02.2001 in
W.P.No.49732/2012 on the ground that apartment
complex provided for 6 meter drive way for entry from
Sarjapur Road and a separate 6 meter exit drive way
but entry and exit to the apartment is only through a
single drive way of 9 meters, the aforesaid drive way did
not comply with fire safety norms and therefore NOC
issued by Fire Force Department is invalid. The said writ
petition was dismissed on 26.03.2013, wherein learned
Single Judge of this court held that there is no reason to
quash the sanctioned plan and directed the Fire Force
Department to ensure compliance regarding NOC by re
visiting the property and to re affirm the NOC if the
same is satisfactory. The Fire Force Department has re
affirmed the NOC issued vide letter dated 26.04.2014
and therefore, the challenge to the plan dated
26.02.2001 has been failed. It is also pointed out that in
W.P.No.24071/2017 Association sought a writ of
mandamus to adhere to the sanction plan dated
26.02.2001 and to direct the builder to complete the
construction of the retention wall in Sy.No.53/1 an
Sy.No.53/2. The aforesaid writ petition was disposed of
by learned Single Judge of this court vide order dated
10.01.2018 holding that retention wall has been
constructed by builder and the same is subject matter of
challenge in W.A.No.769/2018. It is also submitted that
O.s.No.2926/2018 against the Association for a
permanent injunction is pending restraining it from
interfering with the said property as well as
O.S.no.2552/2018 which is a suit filed by the appellant
seeking the relief of permanent injunction which pertains
to Sy.No.53/2 only and fortifies the fact that Sy.No.53/1
and 53/2 are distinct parcels of land.
12. It is submitted that total sital area of 53/1
and 53/2 prior to bifurcation was 11560.27 square
meters and the apartment complex is constructed only
on a total erstwhile sital area and remaining portion of
the erstwhile 53/1 and 53/2 is lying south of the area on
which apartment complex has been constructed have
been further bifurcated and assigned new No.53/1. The
area on which apartment has been constructed is
5953.05 square meters and has been assigned new
No.53/2. The bifurcation has come into force on
01.10.2004. It is also pointed out that the apartment
complex has been constructed and the site has been
bifurcated and assigned new number 53/1 has been
stated in the sale deed executed in favour of the
members of the appellant Association. It is also pointed
out that the bifurcation was called in question by the
appellant and the challenge was repelled by the joint
commissioner some time in the year 2015 and 2016 and
it has attained finality. It is further submitted that
belated challenge to bifurcation is not permissible at this
stage. It is also argued that the appellant has not
demonstrated any prejudice which has caused to it on
account of bifurcation of the remaining land over which
it does not have any right.
13. It is also contended that there has never
been two drive ways of 6 meters each to approach the
apartment complex and there has always been a drive
way of 9 meters from the eastern side of the apartment.
The learned Single Judge has refused to quash the
sanction plan and the order passed by the learned Single
Judge in W.P.No.49732/2012 dated 26.02.2013 has
attained finality. It is also argued that there is drive way
of 9 meters which means that the owners of the
apartment complex have an access to the main road
i.e., Sarjapur Road and FAR is determined on the basis
of public road available to approach the apartment
complex and not the means of access of 9 meters. It is
submitted that the builder has constructed the
apartment complex as per the sanction plan dated
16.02.2001 and therefore, the contention of the
appellant that the firm has suppressed the sanction plan
dated 16.02.2001 to secure the impugned plan is wholly
untenable. It is also submitted that it is incorrect to
state that firm was created only to develop the property
and to secure the plan. It is lastly urged that the writ
appeal deserves to be dismissed with exemplary cost. It
is also pointed out that the decision of the Allahabad
High court relied upon by learned Senior counsel for the
appellant has been stayed by the Supreme Court vide
order dated 05.05.2014 passed in SLP (CC)
No.6754/2014 (DHIRENDER SHARMA AND ORS.
VS. EMERALD COURT OWNERS RES. WEL. ASSOC.
AND ORS.). In support of aforesaid submissions,
reliance has been placed on decision of the Supreme
Court in GREATER KAILASH II WELFARE
ASSOCIATION VS. DLF UNIVERSAL LTD. AIR 2007
SC 1938 AND A DECISION OF THE DIVISION
BENCH OF THE DELHI HIGH COURT IN DLF
UNIVERSAL LTD. VS. GREATER KAILASH II
WELFARE ASSOCIATION, 127 (2006) DLT 131.
14. We have considered the submissions made
on both sides and perused the record. Before proceeding
further we may refer to the well settled legal principles.
The law recognizes the right of person to construct
residential houses in the residential area subject to the
terms and conditions of the statute governing the same.
The Town Planning legislations are regulatory in nature.
The right to property of a person would include right to
construct a building. An illegal and unauthorized
construction of building and other structures not only
violate the municipal laws and the concept of land
development of the particular area but also affect
fundamental rights and constitutional rights of other
persons. In Dipak Kumar Mukherjee supra, the Supreme
Court has taken note of menace of illegal and
unauthorized construction of buildings and other
structures in different parts of the country and has held
that such an activity has acquired monstrous proportion.
It is well settled proposition that in administrative
matter the court should ordinarily defer the decision to
the administrators unless decision is clearly illegal and
shockingly arbitrary and the court cannot sit in appeal
over the decision of the executive. The doctrine of Res
Judicata and Constructive Res Judicata as enshrined in
section 11 of the Code of Civil Procedure applies to the
writ proceeding as well.
15. After having noticed the legal position we
may advert to the facts of the case in hand. The issues
which arise for consideration in this appeal in view of
submissions made at the bar are as follows:
i) Whether a composite plan was prepared in respect of lands situate in survey no. 53/1 and 53/2 which show the exit and entry road of six meters each?
ii) Whether the plan which was sanctioned on 21.09.2016 was obtained by
suppression of earlier sanctioned plan dated 16.02.2001?
iii) Whether the sanctioned plan dated 21.09.2016 has been issued in violation of section 17 of Karnataka Town and Country Planning Act, 1961, the building bye laws, and zoning regulations?
iv) Whether there has been a bifurcation of the plot under section 17 of the Act?
v) Whether the writ petition filed by the association was barred on the principles of Constructive Res Judicata and Res Judicata?
vi) Whether this court can examine the validity of the sanction plan in this proceeding which emanates from an order passed by the learned single judge in exercise of powers under article 226 of the Constitution?
16. The learned single judge has dismissed the
writ petition and has assigned the following reasons for
dismissing the writ petition preferred by the appellant:
8. Having heard the learned counsel for the parties, this court is of the considered opinion that the petitioner-Association seems to be out to misuse and abuse the process of law by launching of spree of litigation against these private Respondents-Builders. At every stage, they have ensured by invoking the Court jurisdiction that the construction being raised under a duly sanctioned plan is hampered one way or the other. Not only two writ petitions came to be filed by them and were disposed of by this Court, but the two civil suits are also pending trial and the issue remains. One, namely, the construction being raised by Respondent No.5-M/s Kolte Patil Developers Limited. The competent public body namely BBMP has already considered the entire matter and sanctioned the building plan in accordance with the bye laws and Rules and at least once, upon the specific direction of the learned Single Judge of this Court.
17. Thus from perusal of para 8 as well as the
order passed by the learned single judge it is evident
that learned single judge without adverting to the issues
raised by the appellant has dismissed the writ petition.
In other words, there is no finding on merits of the
issues raised by the appellant.
[
18. It has rightly been contended by learned
counsel for respondent no. 6, while referring to division
bench decision of Delhi High Court in DLF Universal
Limited supra, which has been affirmed by the Supreme
Court in Greater Kailash Part II Welfare Association and
Ors., this court cannot sit in an appeal over the decision
by an executive authority and the decision in
administrative matters should be referred to the
judgment of the administrators. We may refer to
relevant extract of para 76 of the order passed by the
division bench of Delhi High Court in DLF Universal
Limited supra which was referred to by learned counsel
for respondent no. 6 which reads as under:
"In administrative matters the Court should Therefore ordinarily defer to the judgment of
the administrators unless the decision is clearly illegal or shockingly arbitrary".
19. We are aware of the fact that the power of
remand has to be exercised sparingly, rarest of rare
cases and when the writ petition has not been heard on
merits [See: 'TOWN HOUSE BUILDING CO-
OPERATIVE SOCIETY LTD. V. SPECIAL DEPUTY
COMMISSIONER, AIR 1988 KARNATAKA 312 (FB)].
Even though prima facie we find the submission made
by learned counsel for respondent No.6 that the
controversy raised by association has to be put to rest,
however in peculiar facts and circumstances of the fact
we are unable to do so as the learned single judge has
not dealt with matter on merits and we cannot sit in
appeal in respect of a decision taken by an
administrative authority with regard to sanction of a
map, particularly when determination of aforesaid issue
requires factual adjudication which cannot be done in
this summary proceeding. So far as issue No.5 whether
the writ petition filed by the association was barred on
the principles of res judicata or constructive res judicata,
suffice it to say that in the earlier writ petition, the
subsequent building plan was not in question and the
appellant was informed by communications dated
20.03.2017 and 24.05.2017 by the Joint Director of
Town Planning, BBMP that in reply to the application
under the Right to Information Act, 2005 that no fresh
or modified plan was issued to the builder. Therefore, it
appears that the fact of issuance of the subsequent plan
on 21.09.2016 was not in the knowledge of the
appellant in previous round of litigation. Therefore, the
we hold that the writ petition was not barred by either
on the principles of res judicata or constructive res
judicata. In the peculiar facts of the case since the
issues referred to supra namely issue nos. (i) to (iv) and
(vi) involve factual adjudication, we cannot deal with the
issue of validity of the sanction plan dated 21.09.2016.
20. We may hasten to add here that the
appellant has a remedy under Section 308 and 321 of
the Karnataka Municipal Corporation Act, 1976. Section
308 and 321 of the Act read as under:
"308. Power of Commissioner to require alteration of work.- (1) If the Commissioner finds that the work,-
(a) is otherwise than in accordance with the plans or specifications which have been approved; or
(b) contravenes any of the provisions of this Act or any rule, bye-law, order or declaration made under this Act, he may by notice require the owner of the building within a period state either,-
(i) to show cause why such alterations should not be made; or
(ii) to make such alterations as may be specified in the said notice with the object of bringing the work into conformity with the said plans, specifications or provisions.
(2) If the owner does not show cause as aforesaid he shall be bound to make the alterations specified in such notice.
(3) If the owner shows cause as aforesaid the Commissioner shall by an order cancel the notice issued under sub-section(1) or confirm the same subject to such modifications as he may think fit.
"321. Demolition or alteration of buildings or well work unlawfully commenced, carried on or completed.- (1) If the Commissioner is satisfied,-
(i) that the construction or re-construction of any building or hut or well,-
(a) has been commenced without obtaining his permission or where an appeal or reference has been made to the standing committee, in contravention of any order passed by the standing committee; or
(b) is being carried on, or has been completed otherwise than in accordance with the plans or particulars on which such permission or order was based; or
(c) is being carried on, or has been completed in breach of any of the provisions of this Act or of any rule or bye-law made under this Act or of any direction or requisition lawfully given or made under this Act or such rules or bye-laws; or
(ii) that any alternation required by any notice issued under Section 308, have not been duly made; or
(iii) that any alteration of or addition to any building or hut or any other work made or done for any purpose into, or upon any building or hut, has been commenced or is being carried on or has been completed in breach of Section 320,
he may make a provisional order requiring the owner of the building to demolish the work done, or so much of it as, in the opinion of the Commissioner, has been unlawfully executed, or make such alterations as may, in the opinion of the Commissioner, be necessary to brig the work into conformity with the Ac, rules, bye-laws, directions or requisitions as aforesaid, or
with the plans or particulars on which such permission or orders was based and may also direct that until the said order is complied with the owner or builder shall refrain from proceeding with the building or well or hut.
(2) The Commissioner shall serve a copy of the provisional order made under sub-section(1) on the owner or builder of the building or hut or well together with a notice requiring him to show cause within a reasonable time to be named in such notice why the order should not be confirmed.
(3) If the owner or builder fails to
show cause o the satisfaction of the
Commissioner, the Commissioner may
confirm the order, with any modification he may think fit and such order shall then be binding on the owner.
(4) If the construction or reconstruction of any building or hut is commenced contrary to the provisions of Section 300 or 314 and the Commissioner is of the opinion that immediate action should
be taken, then notwithstanding anything contained in this Act, a notice to be given under sub-Section (2) shall not be of less duration than twenty-four hours and shall be deemed to be duly served if it is affixed in some conspicuous part of the near such building or hut accompanied by beat of drum, and upon such affixation and publication, all persons concerned shall be deemed, to have been duly informed of the matters stated therein."
21. In the obtaining factual matrix of the case
and in view of preceding analysis, we quash the order
dated 25.09.2018 passed by the learned single judge
and relegate the appellant to take recourse to remedy
provided to it under section 308 and 321 of the Act, if
not already availed of. It is made clear that this court
has not expressed any opinion on merit of the case. At
this stage, the undertaking furnished by respondent
No.6 with regard to the construction during the
pendency of the appeal on 30.04.2019 is worth
mentioning the relevant extract, which reads as under:
Per contra, Sri.G.L.Vishwanath,
learned counsel for respondent No.6
contended that the construction is being made by respondent No.6 strictly in accordance with the sanctioned plan issued by the BBMP on 21.09.2016. He further contended that there were several litigations pending between the parties and two suits filed by them are also pending and the present petitioners had earlier filed W.P.No.48732/2012 and connected petitions to quash the sanctioned plan dated 23.03.2011 issued by BBMP and also the NOC dated 23.01.2009. The learned Single Judge by an order dated 26.03.2013, disposed of the writ petitions with certain observations. The said order passed by the learned Single Judge has reached finality. Therefore, he opposed the interim prayer.
22. Since, we have relegated the appellant to the
statutory remedy, it is directed that construction if any
made by the respondent no. 6 on the land in question
shall be at the risk and consequences of respondent No.
6 and it shall also not be entitled to claim equity in
respect of construction made by it from 30.04.2019 till
the decision is taken by the competent authority under
section 308 and 321 of the Act. Needless to state that
the appellant shall raise a grievance if any before the
competent authority under section 308 and 321 of the
Karnataka Municipal Corporation Act, 1976 within a
period of two weeks from the date of receipt of certified
copy of this order and the competent authority after
affording an opportunity of hearing to the parties shall
decide the issues which may be raised by the appellants
without being influenced by any of the observations
contained in this order within three months therefrom.
In the result, the appeal is disposed of.
Sd/-
JUDGE
Sd/-
JUDGE
SS
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!