Citation : 2021 Latest Caselaw 5913 Kant
Judgement Date : 10 December, 2021
1
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 10th DAY OF DECEMBER, 2021
BEFORE
THE HON'BLE MR. JUSTICE ANANT RAMANATH HEGDE
WRIT PETITION NO.40691/2017 (GM-BWSSB)
BETWEEN:
RAMKY INFRASTRUCTURE LIMITED,
RAMKY HOUSE, SITE NO.25-30,
2ND CROSS, RAGHAVENDRA NAGARA,
HENNUR RING ROAD,
KALAYANA NAGARA POST,
BENGALURU - 560 043,
REPRESENTED BY ITS
AUTHORIZED SIGNATORY
MR. VENKATA MANIKANTH REDDY ... PETITIONER
(BY SRI. SURESH BABU B.N. ADV.)
AND:
1. BENGALURU WATER SUPPLY
AND SEWERAGE BOARD,
III FLOOR, CAUVERY BHAVAN
BENGALURU - 560 009
REPPRESENTED BY ITS CHAIRMAN
2. THE CHIEF ENGINEER (PROJECTS)
BENGALURU WATER SUPPLY
AND SEWERAGE BOARD,
III FLOOR, CAUVERY BHAVAN
BENGALURU - 560 009. ... RESPONDENTS
(BY SRI. K.B. MONESH KUMAR, ADVOCATE FOR R1 & R2)
2
THIS PETITION IS FILED UNDER ARTCLES 226 AND 227 OF THE
CONSTITUTION OF INDIA PRAYING TO QUASH THE ORDER DATED:
13.04.2017 ISSUED BY THE RESPONDENT NO.2 VIDE ANNEXURE-A
AND ETC.,
THIS PETITION COMING ON FOR PRELIMINARY HEARING - B
GROUP THIS DAY, THE COURT MADE THE FOLLOWING:
ORDER
The challenge to Annexure-A, marked to the petition,
essentially poses the following question:
Whether Bangalore Water Supply and
Sewerage Board, in the absence of any award/decree
fixing the liability on its contractor, can appropriate
and adjust the amount payable to contractor,
towards its claim for interim damages?
2. The answer to the question is firm 'no'. And the
reasons set out in this judgment are not far to seek.
3. The facts giving rise to this question and necessary
to answer the said question can be summarized as under :-
The 1st respondent-board entrusted the work of certain
underground drainage facility to the petitioner. Annexure-B
dated: 21.10.2015, is a certificate issued by 1st respondent-
board certifying the completion of work by the petitioner.
Annexure-C is another certificate issued on the same date, by
the 1st respondent-Board, to the effect that system is taken over
by the Board after completion of work. From these two
certificates referred above, it appears that work was
satisfactorily completed on 10.02.2014 and system is taken over
by the Board on 10.02.2014 itself.
4. These being the facts, an unfortunate incident took
place on 6th March 2017. Three persons deployed to fix the
issue of overflow in the drainage, died while carrying out the
repair work. This drainage admittedly was constructed by the
petitioner. According to respondents defective work carried out
by the petitioner and omission to take necessary precautionary
measures, before labourers were deployed to carry out repair
work, resulted in death of three labourers. On 7th March 2017,
complaint was lodged and FIR was also registered to probe into
the matter.
5. In the backdrop of above said incident, Annexure-A
the impugned notice dated: 13.04.2017, is issued by the 2nd
respondent. From the reading of Annexure-A, it is noticed that
2nd respondent acting on behalf of 1st respondent-board, is
alleging that the work carried out by the petitioner was
defective. It is also forthcoming from Annexure-A, that three
notices (dated 21.01.2016, 18.11.2016 and 02.03.2017) were
issued by the Board, calling upon the petitioner to rectify the
defects in the underground drainage. The copies of the notices
referred above are not produced by the respondents. The
petitioner, disputes the receipt of above said notices.
6. The respondents trace the cause of death of three
persons to the negligent act of the petitioner. Accordingly
issued notice at Annexure-A and claimed that the 1st respondent-
board is entitled to interim damages of Rs.1.00 crore. The last
paragraph of the impugned Annexure-A dated: 13.04.2017,
reads as under :-
"For all the above causes of defective works, negligence while executing the work has been noted with displeasure. Board is constrained to claim a
damage (sic) of Rs.1.00 Crore as interim relief for all the damages (sic) and negligence of your firm."
7. In response to the challenge to notice at Annexure-A
in this writ petition, respondents have filed statement of
objection. Paragraph No.7 of statement of objection, reveals
that 1st respondent-Board has adjusted Rs.1.00 Crore towards
interim damages, from the amount payable to the petitioner. In
paragraph No.8 of the statement of objection, it is further stated
that Rs.30.00 Lakhs is deducted from the amount payable to the
petitioner and the said amount of Rs.30.00 Lakhs is paid to the
family members of three persons who died in the accident
referred above. However it is not clear from the records placed
before the Court, as to whether Rs.30.00 Lakhs is paid from
Rs.1.00 Crore deducted or whether Rs.30.00 Lakhs is deducted
in addition to Rs.1.00 Crore which is *appropriated towards
interim damages. The relevant portion of the said statement of
objection is extracted hereunder:-
"............and hence it necessitated in deducting an interim damage (sic) of Rs.1.00 crore and stopped the payment of bills of the petitioner by adjusting the same towards interim damage.(sic).
*corrected vide court order dated 07/01/2022
8. The relevant portion of paragraph No.8 reads as
under :-
"......... and hence it necessitated in deducting a sum of Rs.30,00,000/- from the bills of the petitioner and paid compensation to the family members of deceased persons."
9. In the backdrop of the above said facts, legality of
Annexure-A is examined in this petition. Heard learned counsel
for the parties.
10. The learned counsel for the petitioner raised
following contentions.
a. Though Annexure-A is in the form of notice declaring
intention to claim Rs.1.00 Crore towards interim damages, the
respondents have withheld amount due to the petitioner in
respect of some other work carried out by the petitioner and
without there being any adjudication on the liability of the
petitioner, respondents have appropriated Rs.1.00 Crore towards
interim damages.
b. The work carried out by the petitioner is not
defective. No objection is raised in respect of the work when
completion certificate was issued in 2015.
c. Respondents have no authority to withhold the
amount payable to the petitioner in respect of some other works
carried out by the petitioner and same cannot be appropriated
towards liability which is yet to be adjudicated.
d. The unauthorized act of the respondents
appropriating Rs.1.00 Crore is made known to the petitioner only
when statement of objection is filed in this petition. There is no
adjudication either as to the allegation of negligence of the
petitioner or as to interim damages alleged to be payable to
respondents.
e. Assuming that the respondents are empowered to
decide on quantum of damages payable to the 1st respondent,
then also said action of appropriating of Rs.1.00 Crore towards
interim damages is erroneous as the petitioner was not all heard
before quantifying the damages.
f. The unfortunate death of three workers who died on
06.03.2017, cannot be attributed to the work carried out by the
petitioner as the work was completed satisfactorily in February
2014 itself. The learned counsel for the petitioner also referred
to Annexures-B and C, the certificates issued by the 1st
respondent/board certifying satisfactory completion of work
entrusted to the petitioner and urged that the cause of death of
three labourers cannot be linked to alleged defective
underground drainage work.
11. In addition to this, so far as payment of Rs.30.00
lakhs said to have been made to the family members of three
persons who died in the accident, the learned counsel for the
petitioner would submit that the petitioner will not claim said
amount of Rs.30.00 Lakhs. He would submit that the petitioner
has willingly agreed to pay the said amount on humanitarian
consideration without admitting the liability. It is his further
contention that the said amount of Rs.30.00 lakhs is paid by the
1st respondent-board from the amount payable to the petitioner.
Thus according to him, said payment it is nothing but payment
made by the petitioner. And on this basis, it is contended that
there is no monetary loss to the respondents towards payment
of Rs.30.00 Lakhs paid to the family members of labourers. And
based on the above said contentions it is urged that Annexure-A
be quashed.
12. On the other hand the learned counsel for the
respondents justifying the notice at Annexure-A, and subsequent
act of deducting and appropriating Rs.1.00 Crore towards interim
damages, would submit on the following lines.
a. That on account of negligent act and sub-standard work carried out by the petitioner, the underground drainage was not properly functioning and
petitioner is bound to compensate the 1st respondent-board.
b. The death of the labourers is directly attributable to
the defective construction of underground drainage and omission
on the part of the petitioner in not taking proper safety
measures before labourers were deployed to carry out the repair
work. Thus according to respondents the petitioner is liable to
pay damages.
c. It is within the authority of 1st respondent-board to
assess the damages and appropriate the amount payable to the
petitioner towards damages payable to 1st respondent/board.
d. Since three labourers died in the manhole
constructed by the petitioner compensation of Rs.30.00 Lakhs is
paid to the dependents of deceased labourers and as such 2nd
respondent/board is entitled to deduct Rs.30.00 Lakhs from the
amount payable to the petitioner.
e. Alternatively it is urged that the Annexure-A dated:
13.04.2017, is only a notice and not an order fixing damages as
such as the petitioner is required to show cause to the said
notice. On this premise it is urged that the petition is premature.
13. On these grounds, the learned Counsel for the
respondent prayed to dismiss the writ petition.
14. This Court considered the rival contentions and
materials placed before it.
15. The claim of the respondents is based on alleged
tortious act committed by the petitioner. The person who claims
damages on account of tortious act of another or on account of
breach of any contract for that matter, has to establish the
tortious act or breach of contract as the case may be. On
establishing the same, the claimant is required to establish the
loss suffered on account of the tortious act or breach of contract.
On proof of these two facts, one is entitled to appropriate
damages to be quantified in accordance with law governing
damages. However there may be cases, where without proof of
actual loss one may be entitled to nominal damages on proof of
tortious act or breach of contract. Nevertheless even in such
cases, the proof of tortious act or breach of contract is a must.
These factors are to be established before the competent Court
or authority invested with the jurisdiction to decide such claim.
In the instant case no such exercise is carried out.
16. The 1st respondent-board after issuing notice at
Annexure-A, which only declares its intention to claim interim
damages of Rs.1.00 Crore, has not taken recourse to seek
remedy before competent Court/Authority to establish its claim
for damages. On the other hand, without any adjudication of
liability of the petitioner, 1st respondent/board has appropriated
damages of Rs.1.00 Crore from the amount payable to the
petitioner.
17. At this juncture, it is appropriate to quote two
fundamental principles of natural justice ingrained in our
jurisprudence namely:-
a) No one shall be judge in his own cause.
b) No one shall be condemned un-heard.
18. The act of the 1st respondent appropriating Rs.1.00
Crore from the account of petitioner, violates both the above
said principles of natural justice. The 1st respondent has played
all-in-one role of the Prosecutor and Judge. This is
impermissible.
19. Unless action is initiated in a manner known to law,
to recover alleged damages payable to the 1st respondent-board,
the Board cannot appropriate the amount belonging to the
petitioner towards its claim in the manner so done. The
procedure adopted by the Board is not only unknown to
jurisprudence in our country, but is also in gross violation of
principles of natural justice. Hence, Annexure-A though
contended to be a show cause notice, on account of subsequent
act has assumed the character and colour of unjust
award/decree. Hence, Annexure-A is liable to be quashed and
accordingly quashed.
20. It is relevant to state that Rs.30.00 Lakhs is said to
be paid by the 1st respondent to the family members of the
deceased labourers. The said amount is paid from the amount
of the petitioner lying with the 1st respondent. In other words,
Rs.30.00 Lakhs is paid by the petitioner and not by 1st
respondent-board. The 1st respondent, thus cannot claim that it
has suffered monetary loss of Rs.30.00 Lakhs and cannot lay a
claim over the said amount. Thus, the claim of 1st respondent-
board relating to loss of Rs.30.00 lakhs is untenable.
21. It is also noticed that petitioner has only prayed to
quash Annexure-A and has not sought any further specific relief
for refund of the amount. However, admittedly the 1st
respondent-board has appropriated the money payable to the
petitioner towards its claim for damages. Since this act of 1st
respondent-board appropriating the amount towards interim
damages is held to be illegal and without jurisdiction, the
consequential order for refund of the amount to the petitioner
shall follow even in the absence of specific prayer in the petition.
The necessary declaration is also granted to the effect that
appropriation of money payable to the petitioner towards interim
damages is illegal. Since amount is withheld and utilised by the
1st respondent-board without any authority of law, the board is
also bound to pay interest on the said amount. The rate of
interest payable shall be @ 5% p.a. which is the prevailing
interest rate charged by the nationalised banks.
22. If the direction for release of the amount is not
issued, it may lead to further litigation to recover the amount
referred above, which is not only undesirable but has to be
necessarily prevented. The Court's power to mould the relief in
appropriate cases, to meet the ends of justice is well recognized.
This case easily falls in the said category.
23. Accordingly, the following:-
ORDER
(i) The impugned notice bearing No.
BWSSB/CE(P)/ACE(CMC)/50/2017-18 dated 13.04.2017,
marked at Annexure-A issued by the 2nd respondent is
quashed.
(ii) The act of respondents withholding and
appropriating the money from the amount payable to
the petitioner is declared as illegal.
(iii) The 1st respondent-Board shall release the
amount withheld and payable to petitioner (except
Rs.30.00 Lakhs which is said to be paid to the family
of deceased three labourers) along with interest at the
rate of 5% per annum on the said amount, with effect
from 13.04.2017 till the date of payment to the
petitioner.
(iv) However, it is made clear that in this writ
petition, what is adjudicated is the legality of the
process through which the interim damages of Rs.1.00
Crore is sought to be recovered as damages. Thus the
right of the respondent-Board if any, against the
petitioner, to claim interim damages/damages from
the petitioner, in respect of claim made in the
Annexure-A is not decided in this petition.
(v) It is open to the 1st respondent-Board to
avail appropriate remedy, if advised in law, for alleged
breaches/wrong if any, committed by the petitioner in
connection with work referred in Annexure-A, If any
such action is initiated before competent
Court/Authority, such claim shall be adjudicated in
accordance with law, without being influenced by the
order quashing Annexure-A.
The writ petition is allowed. There is no order as
to cost.
Sd/-
JUDGE
Brn/hd
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!