Monday, 04, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Renew Power Private Limited vs State Of Karnataka
2021 Latest Caselaw 5248 Kant

Citation : 2021 Latest Caselaw 5248 Kant
Judgement Date : 2 December, 2021

Karnataka High Court
Renew Power Private Limited vs State Of Karnataka on 2 December, 2021
Bench: S.R.Krishna Kumar
                            1

                                              ®
     IN THE HIGH COURT OF KARNATAKA, BENGALURU

      DATED THIS THE 2ND DAY OF DECEMBER, 2021

                         BEFORE

     THE HON'BLE MR.JUSTICE S.R.KRISHNA KUMAR

            WRIT PETITION No.5703 OF 2020
                          C/W
     WRIT PETITION NOs.5303 OF 2020, 5341 OF 2020,
       5346 OF 2020, 5347 OF 2020, 5354 OF 2020,
       5357 OF 2020, 5361 OF 2020, 5362 OF 2020,
       5364 OF 2020, 5365 OF 2020, 5368 OF 2020,
       5369 OF 2020, 5371 OF 2020, 5374 OF 2020,
                5375 OF 2020 (GM-KEB)
IN W.P.No.5703 OF 2020
BETWEEN:
1.      RENEW POWER PRIVATE LIMITED
        A COMPANY INCORPORATED UNDER
        THE PROVISIONS OF THE COMPANIES ACT, 2013
        AND HAVING ITS REGISTERED OFFICE AT
        NO.138, ANSAL CHAMBERS II,
        BIKAJI CAMA PLACE, DELHI-110 066
        REPRESENTED BY AUTHORIZED SIGNATORY,
        MR NIKHIL KUMAR Y.S.
2.    M/S RAJAT RENEWABLES LTD
      A COMPANY INCORPORATED UNDER
      THE PROVISIONS OF THE COMPANIES ACT, 2013
      AND HAVING ITS REGISTERED OFFICE AT
      NO.138, ANSAL CHAMBERS II,
      BIKAJI CAMA PLACE, DELHI-110 066
      REPRESENTED BY AUTHORIZED SIGNATORY,
      MR NIKHIL KUMAR Y.S.
                                         ...PETITIONERS
(BY SRI SHODHAN BABU A.M., ADVOCATE
    SRI KUSUM RANGANATH, ADVOCATE
    SMT AMRITA JOSHI, ADVOCATE)
AND:
1.      STATE OF KARNATAKA
        DEPARTMENT OF ENERGY,
                               2




      VIKASA SOUDHA, DR.B.R.AMBEDKAR VEEDHI,
      BANGALORE-560 001
      REPRESENTED BY
      THE ADDITIONAL CHIEF SECRETARY TO GOVERNMENT

2.    HUBLI ELECTRICITY SUPPLY COMPANY LIMITED
      A COMPANY REGISTERED UNDER THE PROVISIONS OF
      COMPANIES ACT, 1956, HAVING ITS REGISTERED
      OFFICE AT P.B.ROAD, NAVANAGAR,
      HUBBALI-580 025
      REPRESENTED BY ITS MANAGING DIRECTOR

3.    THE KARNATAKA POWER TRANSMISSION
      CORPORATION LTD.,
      A COMPANY REGISTERED UNDER THE
      PROVISIONS OF COMPANIES ACT 1956
      HAVING ITS REGISTERED OFFICE AT
      KAVERI BHAVAN, K.G.ROAD,
      BANGALORE-560 009
      REPRESENTED BY ITS
      MANAGING DIRECTOR
                                       ...RESPONDENTS
(BY SRI RAMESH GOWDA A., AGA FOR R1
    SRI SHAHBAAZ HUSAIN, ADVOCATE FOR R2
    SRI S.SRIRANGA, ADVOCATE FOR R3)

       THIS W.P. IS FILED UNDER ARTICLES 226 AND 227 OF
THE CONSTITUTION OF INDIA PRAYING TO DIRECT THE R-2 TO
HONOR ITS PAYMENT OBLIGATIONS UNDER THE PPA, BY
PROCESSING THE INVOICES, DATED 07.08.2019, 06.09.2019,
14.10.2019, 07.11.2019, 10.12.2019, AND 09.01.2019 ANNX-H1 AND
K (COLLY)) AND MAKING A PAYMENT OF A SUM OF
RS.3,63,03,568/- (RUPEES THREE CRORES SIXTY THREE LAKHS
THREE THOUSAND FIVE HUNDRED AND SIXTY EIGHT ONLY) TO
THE PETITIONER NO.2 AND ETC.

IN W.P.No.5303 OF 2020
BETWEEN:
1.    RENEW POWER PRIVATE LIMITED
      A COMPANY INCORPORATED UNDER
      THE PROVISIONS OF THE COMPANIES ACT, 2013
      AND HAVING ITS REGISTERED OFFICE AT
      NO.138, ANSAL CHAMBERS II,
      BIKAJI CAMA PLACE, DELHI-110 066
      REPRESENTED BY AUTHORIZED SIGNATORY,
      MR NIKHIL KUMAR Y.S.
                             3




2.    RENEW WIND ENERGY (SILPA)
      PRIVATE LIMITED
      A COMPANY INCORPORATED UNDER THE PROVISIONS
      OF THE COMPANIES ACT, 2013 AND HVAVING ITS
      REGISTERED OFFICE AT NO.138, ANSAL CHAMBERS II,
      BIKAJI CAMA PLACE, DELHI-110 066
      REPRESENTED BY AUTHORIZED SIGNATORY,
      MR NIKHIL KUMAR Y.S.
                                          ...PETITIONERS
(BY SRI SHODHAN BABU A.M., ADVOCATE
    SRI KUSUM RANGANATH, ADVOCATE
    SMT AMRITA JOSHI, ADVOCATE)

AND:

1.     STATE OF KARNATAKA
       DEPARTMENT OF ENERGY,
       VIKASA SOUDHA, DR.B.R.AMBEDKAR VEEDHI,
       BANGALORE-560 001
       REPRESENTED BY
       THE ADDITIONAL CHIEF SECRETARY
       TO GOVERNMENT

2.     HUBLI ELECTRICITY SUPPLY CO. LTD.,
       A COMPANY REGISTERED UNDER
       THE PROVISIONS OF COMPANIES ACT, 1956,
       HAVING ITS REGISTERED OFFICE AT P.B.ROAD,
       NAVANAGAR, HUBBALI-580 025
       REPRESENTED BY ITS MANAGING DIRECTOR

3.    THE KARNATAKA POWER TRANSMISSION
      CORPORATION LTD.,
      A COMPANY REGISTERED UNDER THE
      PROVISIONS OF COMPANIES ACT 1956
      HAVING ITS REGISTERED OFFICE AT
      KAVERI BHAVAN, K.G.ROAD,
      BANGALORE-560 009
      REPRESENTED BY ITS
      MANAGING DIRECTOR
                                       ...RESPONDENTS
(BY SRI RAMESH GOWDA A., AGA FOR R1
    SRI SHAHBAAZ HUSAIN, ADVOCATE FOR R2
    SRI S.SRIRANGA, ADVOCATE FOR R3)

     THIS W.P. IS FILED UNDER ARTICLES 226 AND 227 OF
THE CONSTITUTION OF INDIA PRAYING TO DIRECT THE R-2 TO
HONOR ITS PAYMENT OBLIGATIONS UNDER THE PPA, BY
PROCESSING THE INVOICES, DATED 06.08.2019, 06.09.2019,
                              4




09.10.2019, 06.11.2019, 06.12.2019, AND 06.01.2020 (ANNXURE-
G1 AND J) AND MAKING A PAYMENT OF RS.34,96,63,750/-
(RUPEES THIRTY FOUR CRORES NINETY SIX LAKHS SIXTY
THREE THOUSAND SEVEN HUNDRED AND FIFTY ONLY) TO THE
PETITIONER NO.2 AND ETC.

IN W.P.No.5341 OF 2020
BETWEEN:
1.     RENEW POWER PRIVATE LIMITED
       A COMPANY INCORPORATED UNDER
       THE PROVISIONS OF THE COMPANIES ACT, 2013
       AND HAVING ITS REGISTERED OFFICE AT
       NO.138, ANSAL CHAMBERS II,
       BIKAJI CAMA PLACE, DELHI-110 066
       REPRESENTED BY AUTHORIZED SIGNATORY,
       MR NIKHIL KUMAR Y.S.

2.    KANAK RENEWABLES LIMITED
      A COMPANY INCORPORATE UNDER
      THE PROVISIONS OF THE COMPANIES ACT, 1956 AND
      HAVING ITS REGISTERED OFFCE AT
      NO.138, ANSAL CHAMBERS II,
      BIKAJI CAMA PLACE, DELHI-110 066
      REPRESENTED BY AUTHORIZED SIGNATORY,
      MR NIKHIL KUMAR Y.S.
                                        ...PETITIONERS
(BY SRI SHODHAN BABU A.M., ADVOCATE
    SRI KUSUM RANGANATH, ADVOCATE
    SMT AMRITA JOSHI, ADVOCATE)

AND:
1.     STATE OF KARNATAKA
       DEPARTMENT OF ENERGY,
       VIKASA SOUDHA, DR.B.R.AMBEDKAR VEEDHI,
       BANGALORE-560 001
       REPRESENTED BY
       THE ADDITIONAL CHIEF SECRETARY
       TO GOVERNMENT

2.     HUBLI ELECTRICITY SUPPLY CO. LTD.,
       A COMPANY REGISTERED UNDER
       THE PROVISIONS OF COMPANIES ACT, 1956,
       HAVING ITS REGISTERED OFFICE AT P.B.ROAD,
       NAVANAGAR, HUBBALI-580 025
       REPRESENTED BY ITS MANAGING DIRECTOR
                              5




3.    THE KARNATAKA POWER TRANSMISSION
      CORPORATION LTD.,
      A COMPANY REGISTERED UNDER THE
      PROVISIONS OF COMPANIES ACT 1956
      HAVING ITS REGISTERED OFFICE AT
      KAVERI BHAVAN, K.G.ROAD,
      BANGALORE-560 009
      REPRESENTED BY ITS
      MANAGING DIRECTOR
                                       ...RESPONDENTS
(BY SRI RAMESH GOWDA A., AGA FOR R1
    SRI SHAHBAAZ HUSAIN, ADVOCATE FOR R2 & R3)

       THIS W.P. IS FILED UNDER ARTICLES 226 AND 227 OF
THE CONSTITUTION OF INDIA PRAYING TO DIRECT THE R-2 TO
HONOR ITS PAYMENT OBLIGATIONS UNDER THE PPA, BY
PROCESSING THE INVOICES, DATED 06.09.2019, 14.10.2019,
07.11.2019, 10.12.2019, 09.01.2019 FOR 23.1 MW AND 6.9.2019,
14.10.2019, 7.11.2019, 10.12.2019, 09.01.2020 FOR 2.1 MW
(ANNEXURE-H1 AND K COLLY) AND MAKING OF PAYMENT OF
RS.8,73,560,740/- (RUPEES EIGHT CRORES SEVENTY THREE
LAKHS FIFTY THOUSAND SEVEN HUNDRED AND FORTY ONLY)
ON THE P.2 AND ETC.

IN W.P.No.5346 OF 2020
BETWEEN:
1.    RENEW POWER PRIVATE LIMITED
      A COMPANY INCORPORATED UNDER
      THE PROVISIONS OF THE COMPANIES ACT, 2013
      AND HAVING ITS REGISTERED OFFICE AT
      NO.138, ANSAL CHAMBERS II,
      BIKAJI CAMA PLACE, DELHI-110 066
      REPRESENTED BY AUTHORIZED SIGNATORY,
      MR NIKHIL KUMAR Y.S.
2.    M/S RAJAT RENEWABLES LTD
      A COMPANY INCORPORATED UNDER
      THE PROVISIONS OF THE COMPANIES ACT, 2013
      AND HAVING ITS REGISTERED OFFICE AT
      NO.138, ANSAL CHAMBERS II,
      BIKAJI CAMA PLACE, DELHI-110 066
      REPRESENTED BY AUTHORIZED SIGNATORY,
      MR NIKHIL KUMAR Y.S.
                                         ...PETITIONERS
(BY SRI SHODHAN BABU A.M., ADVOCATE
    SRI KUSUM RANGANATH, ADVOCATE
    SMT AMRITA JOSHI, ADVOCATE)
                            6




AND:
1.     STATE OF KARNATAKA
       DEPARTMENT OF ENERGY,
       VIKASA SOUDHA, DR.B.R.AMBEDKAR VEEDHI,
       BANGALORE-560 001
       REPRESENTED BY
       THE ADDITIONAL CHIEF SECRETARY TO GOVERNMENT

2.     GULBARGA ELECTRICITY SUPPLY COMPANY LIMITED
       A COMPANY REGISTERED UNDER THE PROVISIONS OF
       COMPANIES ACT, 1956, HAVING ITS REGISTERED
       OFFICE AT STATION ROAD, KALBURGI-585 101
       REPRESENTED BY ITS MANAGING DIRECTOR

3.    THE KARNATAKA POWER TRANSMISSION
      CORPORATION LTD.,
      A COMPANY REGISTERED UNDER THE
      PROVISIONS OF COMPANIES ACT 1956
      HAVING ITS REGISTERED OFFICE AT
      KAVERI BHAVAN, K.G.ROAD, BANGALORE-560 009
      REPRESENTED BY ITS MANAGING DIRECTOR
                                       ...RESPONDENTS
(BY SRI RAMESH GOWDA A., AGA FOR R1
    SRI MURUGESH V.CHARATI, ADVOCATE FOR R2
    SRI SHAHBAAZ HUSAIN, ADVOCATE FOR R3)

       THIS W.P. IS FILED UNDER ARTICLES 226 AND 227 OF
THE CONSTITUTION OF INDIA PRAYING TO DIRECT THE R-2 TO
HONOR ITS PAYMENT OBLIGATIONS UNDER THE PPA, BY
PROCESSING THE INVOICES, DTD.6.9.2019, 14.10.2019,
7.11.2019, 9.12.2019, 9.1.2019, (ANNEXURE-K (COLLY) AND
MAKING OF PAYMENT OF RS.86,47,565/- (RUPEES EIGHT SIX
LAKHS SEVENTY SEVEN THOUSAND FIVE HUNDRED AND SIXTY
FIVE ONLY) ON THE P-2 AND ETC.

IN W.P.No.5347 OF 2020
BETWEEN:
1.     RENEW POWER PRIVATE LIMITED
       A COMPANY INCORPORATED UNDER
       THE PROVISIONS OF THE COMPANIES ACT, 2013
       AND HAVING ITS REGISTERED OFFICE AT
       NO.138, ANSAL CHAMBERS II,
       BIKAJI CAMA PLACE, DELHI-110 066
       REPRESENTED BY AUTHORIZED SIGNATORY,
       MR NIKHIL KUMAR Y.S.
                             7




2.    M/S RAJAT RENEWABLES LTD
      A COMPANY INCORPORATED UNDER
      THE PROVISIONS OF THE COMPANIES ACT, 2013
      AND HAVING ITS REGISTERED OFFICE AT
      NO.138, ANSAL CHAMBERS II,
      BIKAJI CAMA PLACE, DELHI-110 066
      REPRESENTED BY AUTHORIZED SIGNATORY,
      MR NIKHIL KUMAR Y.S.
                                         ...PETITIONERS
(BY SRI SHODHAN BABU A.M., ADVOCATE
    SRI KUSUM RANGANATH, ADVOCATE
    SMT AMRITA JOSHI, ADVOCATE)
AND:
1.     STATE OF KARNATAKA
       DEPARTMENT OF ENERGY,
       VIKASA SOUDHA, DR.B.R.AMBEDKAR VEEDHI,
       BANGALORE-560 001
       REPRESENTED BY
       THE ADDITIONAL CHIEF SECRETARY TO GOVERNMENT

2.     HUBLI ELECTRICITY SUPPLY CO. LTD.,
       A COMPANY REGISTERED UNDER
       THE PROVISIONS OF COMPANIES ACT, 1956,
       HAVING ITS REGISTERED OFFICE AT P.B.ROAD,
       NAVANAGAR, HUBBALI-580 025
       REPRESENTED BY ITS MANAGING DIRECTOR

3.    THE KARNATAKA POWER TRANSMISSION
      CORPORATION LTD.,
      A COMPANY REGISTERED UNDER THE
      PROVISIONS OF COMPANIES ACT 1956
      HAVING ITS REGISTERED OFFICE AT
      KAVERI BHAVAN, K.G.ROAD, BANGALORE-560 009
      REPRESENTED BY ITS MANAGING DIRECTOR
                                       ...RESPONDENTS
(BY SRI RAMESH GOWDA A., AGA FOR R1
    SRI MURUGESH V.CHARATI, ADVOCATE FOR R2
    SRI SHAHBAAZ HUSAIN, ADVOCATE FOR R2 & R3)

       THIS W.P. IS FILED UNDER ARTICLES 226 AND 227 OF
THE CONSTITUTION OF INDIA PRAYING TO DIRECT THE R-2 TO
HONOR ITS PAYMENT OBLIGATIONS UNDER THE PPA, BY
PROCESSING THE INVOICES, DATED 08.07.2019, 07.08.2019,
06.09.2019, 14.10.2019, 07.11.2019, 09.01.2020 (ANNEXURE-H1
AND K) AND MAKING A PAYMENT OF RS.6,59,75,311/- (RUPEES
SIX CRORES FIFTY NINE LAKHS SEVENTY FIVE THOUSAND
THREE HUNDRED AND ELEVEN ONLY) TO THE PETITIONER
NO.2 AND ETC.
                            8




IN W.P.No.5354 OF 2020

BETWEEN:

1.     RENEW POWER PRIVATE LIMITED
       A COMPANY INCORPORATED UNDER
       THE PROVISIONS OF THE COMPANIES ACT, 2013
       AND HAVING ITS REGISTERED OFFICE AT
       NO.138, ANSAL CHAMBERS II,
       BIKAJI CAMA PLACE, DELHI-110 066
       REPRESENTED BY AUTHORIZED SIGNATORY,
       MR NIKHIL KUMAR Y.S.

2.    M/S OSTRO DAKSHIN POWER PVT. LTD.,
      A COMPANY INCORPORATED UNDER
      THE PROVISIONS OF THE COMPANIES ACT 2013
      AND HAVING ITS REGISTERED OFFICE AT
      NO.138, ANSAL CHAMBERS II,
      BIKAJI CAMA PLACE, DELHI-110 066
      REPRESENTED BY AUTHORIZED SIGNATORY,
      MR NIKHIL KUMAR Y.S.
                                         ...PETITIONERS
(BY SRI SHODHAN BABU A.M., ADVOCATE
    SRI KUSUM RANGANATH, ADVOCATE
    SMT AMRITA JOSHI, ADVOCATE)

AND:

1.     STATE OF KARNATAKA
       DEPARTMENT OF ENERGY,
       VIKASA SOUDHA, DR.B.R.AMBEDKAR VEEDHI,
       BANGALORE-560 001
       REPRESENTED BY
       THE ADDITIONAL CHIEF SECRETARY
       TO GOVERNMENT

2.     GULBARGA ELECTRICITY SUPPLY CO. LTD.,
       A COMPANY REGISTERED UNDER THE
       PROVISIONS OF COMPANIES ACT, 1956,
       HAVING ITS REGISTERED OFFICE AT
       STATION ROAD, KALBURGI-585 101
       REPRESENTED BY ITS MANAGING DIRECTOR

3.     THE KARNATAKA POWER TRANSMISSION
       CORPORATION LTD.,
       A COMPANY REGISTERED UNDER THE
       PROVISIONS OF COMPANIES ACT 1956
       HAVING ITS REGISTERED OFFICE AT
       KAVERI BHAVAN, K.G.ROAD,
                              9




      BANGALORE-560 009
      REPRESENTED BY ITS MANAGING DIRECTOR
                                      ...RESPONDENTS
(BY SRI RAMESH GOWDA A., AGA FOR R1
    SRI MURUGESH V.CHARATI, ADVOCATE FOR R2
    SRI S.SRIRANGA, ADVOCATE FOR R3)

       THIS W.P. IS FILED UNDER ARTICLES 226 AND 227 OF
THE CONSTITUTION OF INDIA PRAYING TO DIRECT THE R-2 TO
HONOR ITS PAYMENT OBLIGATIONS UNDER THE PPA, BY
PROCESSING THE INVOICES, DTD.9.9.2019, 9.10.2019, 6.11.2019,
6.12.2019, 9.1.2020, ANENXURE-K (COLLY) AND MAKING A
PAYMENT 57,02,775/- (RUPEES FIFTY SEVEN CRORES TWO
LAKHS THIRTY EIGHT THOUSAND SEVEN HUNDRED AND
SEVENTY FIVE ONLY) ON THE P-2 AND ETC.

IN W.P.No.5357 OF 2020
BETWEEN:
1.     RENEW POWER PRIVATE LIMITED
       A COMPANY INCORPORATED UNDER
       THE PROVISIONS OF THE COMPANIES ACT, 2013
       AND HAVING ITS REGISTERED OFFICE AT
       NO.138, ANSAL CHAMBERS II,
       BIKAJI CAMA PLACE, DELHI-110 066
       REPRESENTED BY AUTHORIZED SIGNATORY,
       MR NIKHIL KUMAR Y.S.

2.    ADYAH SOLAR ENERGY PRIVATE LIMITED
      A COMPANY INCORPORATE UNDER THE PROVISIONS OF
      THE COMPANIES ACT, 2013 AND HAVING ITS
      REGISTERED OFFICE AT
      NO. 138, ANSAL CHAMBERS II,
      BIKAJI CAMA PLACE, DELHI 110 066,
      REPRESENTED BY AUTHORIZED SIGNATORORY, MR.
      NIKHIL KUMAR Y.S.
                                          ...PETITIONERS
(BY SRI SHODHAN BABU A.M., ADVOCATE
    SRI KUSUM RANGANATH, ADVOCATE
    SMT AMRITA JOSHI, ADVOCATE)

AND:

1.     STATE OF KARNATAKA
       DEPARTMENT OF ENERGY,
       VIKASA SOUDHA, DR.B.R.AMBEDKAR VEEDHI,
       BANGALORE-560 001
       REPRESENTED BY
       THE ADDITIONAL CHIEF SECRETARY TO GOVERNMENT
                           10




2.   GULBARGA ELECTRICITY SUPPLY CO. LTD.,
     A COMPANY REGISTERED UNDER THE
     PROVISIONS OF COMPANIES ACT, 1956,
     HAVING ITS REGISTERED OFFICE AT
     STATION ROAD, KALBURGI - 585 101
     REPRESENTED BY ITS MANAGING DIRECTOR

3.    THE KARNATAKA POWER TRANSMISSION
      CORPORATION LTD.,
      A COMPANY REGISTERED UNDER THE
      PROVISIONS OF COMPANIES ACT 1956
      HAVING ITS REGISTERED OFFICE AT
      KAVERI BHAVAN, K.G.ROAD,
      BANGALORE-560 009
      REPRESENTED BY ITS
      MANAGING DIRECTOR
                                       ...RESPONDENTS
(BY SRI RAMESH GOWDA A., AGA FOR R1
    SRI MURUGESH V.CHARATI, ADVOCATE FOR R2
    SRI S.G.PRASHANTH MURTHY, ADVOCATE FOR R3)

       THIS W.P. IS FILED UNDER ARTICLES 226 AND 227 OF
THE CONSTITUTION OF INDIA PRAYING TO DIRECT THE R-2 TO
HONOR ITS PAYMENT OBLIGATIONS UNDER THE PPA, BY
PROCESSING THE INVOICES, DTD. 20.9.2019, 11.10.2019,
19.11.2019,   9.12.2019,   AND    9.1.2020  ANNEXURE-L
COLLECTIVELY AND MAKING PAYMENT OF RS.12,05,54,724/-
(RUPEES TWELVE CRORES FIVE LAKHS FIFTY FOUR
THOUSAND SEVEN HUNDRED TWENTY FOUR ONLY) ON THE P-
2 AND ETC.

IN W.P.No.5361 OF 2020
BETWEEN:

1.   RENEW POWER PRIVATE LIMITED
     A COMPANY INCORPORATED UNDER
     THE PROVISIONS OF THE COMPANIES ACT, 2013
     AND HAVING ITS REGISTERED OFFICE AT
     NO.138, ANSAL CHAMBERS II,
     BIKAJI CAMA PLACE, DELHI-110 066
     REPRESENTED BY AUTHORIZED SIGNATORY,
     MR NIKHIL KUMAR Y.S.

2.   ADYAH SOLAR ENERGY PRIVATE LIMITED
     A COMPANY INCORPORATED UNDER THE PROVISIONS
     OF THE COMPANIES ACT, 2013 AND HAVING ITS
     REGISTERED OFFICE AT
     NO. 138, ANSAL CHAMBERS II,
                               11




      BIKAJI CAMA PLACE, DELHI 110 066,
      REPRESENTED BY AUTHORIZED SIGNATORORY,
      MR. NIKHIL KUMAR Y.S.
                                        ...PETITIONERS
(BY SRI SHODHAN BABU A.M., ADVOCATE
    SRI KUSUM RANGANATH, ADVOCATE
    SMT AMRITA JOSHI, ADVOCATE)

AND:

1.     STATE OF KARNATAKA
       DEPARTMENT OF ENERGY,
       VIKASA SOUDHA, DR.B.R.AMBEDKAR VEEDHI,
       BANGALORE-560 001
       REPRESENTED BY
       THE ADDITIONAL CHIEF SECRETARY TO GOVERNMENT

2.     HUBLI ELECTRICITY SUPPLY COMPANY LIMITED
       A COMPANY REGISTERED UNDER THE PROVISIONS OF
       COMPANIES ACT, 1956, HAVING ITS REGISTERED
       OFFICE AT P.B.ROAD, NAVANAGAR,
       HUBBALI-580 025
       REPRESENTED BY ITS MANAGING DIRECTOR

3.     THE KARNATAKA POWER TRANSMISSION
       CORPORATION LTD.,
       A COMPANY REGISTERED UNDER THE
       PROVISIONS OF COMPANIES ACT 1956
       HAVING ITS REGISTERED OFFICE AT
       KAVERI BHAVAN, K.G.ROAD, BANGALORE-560 009
       REPRESENTED BY ITS MANAGING DIRECTOR
                                        ...RESPONDENTS

(BY SRI RAMESH GOWDA A., AGA FOR R1
    SRI SHAHBAAZ HUSSAIN, ADVOCATE FOR R2 & R3)

       THIS W.P. IS FILED UNDER ARTICLES 226 AND 227 OF
THE CONSTITUTION OF INDIA PRAYING TO DIRECT THE R-2 TO
HONOR ITS PAYMENT OBLIGATIONS UNDER THE PPA, BY
PROCESSING THE INVOICES, DTD. 6.6.2019, 11.6.2019, 9.7.2019,
6.8.2019, 17.9.2019, 10.10.2019, 14.11.2019, 9.12.2019, 9.1.2020
ANNXURE-J1, J AND L COLLECTIVELY AND MAKING A PAYMENT
OF RS.17,84,65,057/- (RUPEES SEVENTEEN CRORES EIGHTY
FOUR LAKHS SIXTY FIVE THOUSAND AND FIFTY SEVEN ONLY)
ON THE P-2 AND ETC.
                            12




IN W.P.No.5362 OF 2020
BETWEEN:
1.     RENEW POWER PRIVATE LIMITED
       A COMPANY INCORPORATED UNDER
       THE PROVISIONS OF THE COMPANIES ACT, 2013
       AND HAVING ITS REGISTERED OFFICE AT
       NO.138, ANSAL CHAMBERS II,
       BIKAJI CAMA PLACE, DELHI-110 066
       REPRESENTED BY AUTHORIZED SIGNATORY,
       MR NIKHIL KUMAR Y.S.

2.    RENEW WIND ENERGY (SIPLA) PRIVATE LIMITED
      A COMPANY REGISTERED UNDER THE PROVISION OF
      THE COMPANIES ACT, 2013 AND HAVING ITS
      REGISTERED OFFICE
      AT NO.138, ANSAL CHAMBERS II,
      BIKAJI CAMA PLACE, DELHI-110 066
      REPRESENTED BY AUTHORIZED SIGNATORY
      MR. NIKHIL KUMAR Y.S
                                          ...PETITIONERS
(BY SRI SHODHAN BABU A.M., ADVOCATE
    SRI KUSUM RANGANATH, ADVOCATE
    SMT AMRITA JOSHI, ADVOCATE)

AND:

1.     STATE OF KARNATAKA
       DEPARTMENT OF ENERGY,
       VIKASA SOUDHA, DR.B.R.AMBEDKAR VEEDHI,
       BANGALORE-560 001
       REPRESENTED BY
       THE ADDITIONAL CHIEF
       SECRETARY TO GOVERNMENT

2.     HUBLI ELECTRICITY SUPPLY COMPANY LIMITED
       A COMPANY REGISTERED UNDER
       THE PROVISIONS OF COMPANIES ACT, 1956,
       HAVING ITS REGISTERED OFFICE AT P.B.ROAD,
       NAVANAGAR, HUBBALI-580 025
       REPRESENTED BY ITS MANAGING DIRECTOR

3.     THE KARNATAKA POWER TRANSMISSION
       CORPORATION LTD.,
       A COMPANY REGISTERED UNDER THE
       PROVISIONS OF COMPANIES ACT 1956
       HAVING ITS REGISTERED OFFICE AT
       KAVERI BHAVAN, K.G.ROAD,
                             13




       BANGALORE-560 009
       REPRESENTED BY ITS
       MANAGING DIRECTOR
                                       ...RESPONDENTS
(BY SRI RAMESH GOWDA A., AGA FOR R1
    SRI SHAHBAAZ HUSSAIN, ADVOCATE FOR R2 & R3)

       THIS W.P. IS FILED UNDER ARTICLES 226 AND 227 OF
THE CONSTITUTION OF INDIA PRAYING TO DIRECT THE R-2 TO
HONOR ITS PAYMENT OBLIGATIONS UNDER THE PPA, BY
PROCESSING THE INVOICES, DATED 06.08.2019, 09.09.2019,
11.10.2019, 07.11.2019, 06.12.2019, 07.01.2020 VIDE ANNX-G1
AND J (COLLECTIVELY) AND MAKING A PAYMENT OF
RS.13,27,61,611/- (RUPEES THIRTEEN CRORES TWENTY SEVEN
LAKHS SIXTY ONE THOUSAND SIX HUNDRED AND ELEVEN
ONLY) TO THE PETITIONER NO.1 AND ETC.

IN W.P.No.5364 OF 2020
BETWEEN:
1.     RENEW POWER PRIVATE LIMITED
       A COMPANY INCORPORATED UNDER
       THE PROVISIONS OF THE COMPANIES ACT, 2013
       AND HAVING ITS REGISTERED OFFICE AT
       NO.138, ANSAL CHAMBERS II,
       BIKAJI CAMA PLACE, DELHI-110 066
       REPRESENTED BY AUTHORIZED SIGNATORY,
       MR NIKHIL KUMAR Y.S.

2.    M/S BIDEAL RENEWABLE PVT. LTD.,
      A COMPANY INCORPORATED UNDER
      THE PROVISION OF THE COMPANIES ACT, 2013
      AND HAVING ITS REGISTERED OFFICE AT
      NO.138, ANSAL CHAMBERS II,
      BIKAJI CAMA PLACE, DELHI-110 066
      REPRESENTED BY AUTHORIZED SIGNATORY,
      MR NIKHIL KUMAR Y.S.
                                         ...PETITIONERS
(BY SRI SHODHAN BABU A.M., ADVOCATE
    SRI KUSUM RANGANATH, ADVOCATE
    SMT AMRITA JOSHI, ADVOCATE)

AND:

1.     STATE OF KARNATAKA
       DEPARTMENT OF ENERGY,
       VIKASA SOUDHA, DR.B.R.AMBEDKAR VEEDHI,
       BANGALORE-560 001
                               14




      REPRESENTED BY THE ADDITIONAL
      CHIEF SECRETARY TO GOVERNMENT

2.    GULBARGA ELECTRICITY SUPPLY CO. LTD.,
      A COMPANY REGISTERED UNDER
      THE PROVISIONS OF COMPANIES ACT, 1956,
      HAVING ITS REGISTERED OFFICE AT
      STATION ROAD, KALBURGI-585 101
      REPRESENTED BY ITS MANAGING DIRECTOR

3.    THE KARNATAKA POWER TRANSMISSION
      CORPORATION LTD.,
      A COMPANY REGISTERED UNDER THE
      PROVISIONS OF COMPANIES ACT 1956
      HAVING ITS REGISTERED OFFICE AT
      KAVERI BHAVAN, K.G.ROAD,
      BANGALORE-560 009
      REPRESENTED BY ITS
      MANAGING DIRECTOR
                                       ...RESPONDENTS
(BY SRI RAMESH GOWDA A., AGA FOR R1
    SRI MURUGESH V.CHARATI, ADVOCATE FOR R2
    SRI S.SRIRANGA, ADVOCATE FOR R3)

       THIS W.P. IS FILED UNDER ARTICLES 226 AND 227 OF
THE CONSTITUTION OF INDIA PRAYING TO DIRECT THE R-2 TO
HONOR ITS PAYMENT OBLIGATIONS UNDER THE PPA, BY
PROCESSING THE INVOICES, DATED 09.07.2019, 07.08.2019,
09.09.2019, 09.10.2019, 06.11.2019, 09.12.2019, 06.01.2020 VIDE
ANNX-H1 AND K (COLLECTIVELY) AND MAKING A PAYMENT OF
RS.29,89,75,310/- (RUPEES TWENTY NINE CRORES EIGHTY
NINE LAKHS SEVENTY FIVE THOUSAND AND THREE HUNDRED
AND TEN ONLY) TO THE PETITIONER NO.1 AND ETC.

IN W.P.No.5365 OF 2020
BETWEEN:
1.    RENEW POWER PRIVATE LIMITED
      A COMPANY INCORPORATED UNDER
      THE PROVISIONS OF THE COMPANIES ACT, 2013
      AND HAVING ITS REGISTERED OFFICE AT
      NO.138, ANSAL CHAMBERS II,
      BIKAJI CAMA PLACE, DELHI-110 066
      REPRESENTED BY AUTHORIZED SIGNATORY,
      MR NIKHIL KUMAR Y.S.

2.    M/S PUGALUR RENEWEABLE PVT. LTD.,
      A COMPANY INCORPORATED UNDER THE PROVISIONS
                            15




      OF THE COMPANIES ACT, 2013 AND HAVING ITS
      REGISTERED OFFICE AT
      THE FUTURA, BLOCK B, 8TH FLOOR,
      NO.334, RAJIV GANDHI SALAI, SHOLINGANALLUR,
      CHENNAI 600 119.
      REPRESENTED BY AUTHORIZED SIGNATORY
      MR. NIKHIL KUMAR Y.S
                                           ...PETITIONERS
(BY SRI SHODHAN BABU A.M., ADVOCATE
    SRI KUSUM RANGANATH, ADVOCATE
    SMT AMRITA JOSHI, ADVOCATE)

AND:

1.     STATE OF KARNATAKA
       DEPARTMENT OF ENERGY,
       VIKASA SOUDHA, DR.B.R.AMBEDKAR VEEDHI,
       BANGALORE-560 001
       REPRESENTED BY
       THE ADDITIONAL CHIEF SECRETARY TO GOVERNMENT

2.     GULBARGA ELECTRICITY SUPPLY CO. LTD.,
       A COMPANY REGISTERED UNDER
       THE PROVISIONS OF COMPANIES ACT, 1956,
       HAVING ITS REGISTERED OFFICE AT
       STATION ROAD, KALBURGI-585 101
       REPRESENTED BY ITS MANAGING DIRECTOR

3.    THE KARNATAKA POWER TRANSMISSION
      CORPORATION LTD.,
      A COMPANY REGISTERED UNDER THE
      PROVISIONS OF COMPANIES ACT 1956
      HAVING ITS REGISTERED OFFICE AT
      KAVERI BHAVAN, K.G.ROAD, BANGALORE-560 009
      REPRESENTED BY ITS
      MANAGING DIRECTOR
                                       ...RESPONDENTS
(BY SRI RAMESH GOWDA A., AGA FOR R1
    SRI MURUGESH V.CHARATI, ADVOCATE FOR R2
    SRI S.SRIRANGA, ADVOCATE FOR R3)

       THIS W.P. IS FILED UNDER ARTICLES 226 AND 227 OF
THE CONSTITUTION OF INDIA PRAYING TO DIRECT THE R-2 TO
HONOR ITS PAYMENT OBLIGATIONS UNDER THE PPA, BY
PROCESSING THE INVOICES, DATED 06.08.2019, 06.09.2019,
09.10.2019, 07.11.2019, 06.12.2019, 06.01.2020 (ANNEXURE-K
(COLLY)) AND MAKING A PAYMENT OF RS.34,98,34,295/-
(RUPEES THIRTY FOUR CRORES NINETY EIGHT LAKHS THIRTY
                            16




FOUR THOUSAND TWO HUNDRED AND NINETY FIVE ONLY) TO
THE PETITIONER NO.2 AND ETC.

IN W.P.No.5368 OF 2020
BETWEEN:
1.     AZURE POWER INDIA PRIVTE LIMITED
       A COMPANY INCORPORATED UNDER
       THE PROVISIONS OF THE COMPANIES ACT,
       1956 AND HAVING ITS REGISTERED OFFICER
       AT 3RD FLOOR, ASSET 301-304 AND 307,
       WORLD MARK 3, AEROCITY,
       NEW DELHI 110 037,
       REP BY ITS AUTHORIZED SIGNATORY,
       MR. NAGARAJA NAIK

2.     AZURE POWER EARTH PRIVATE LIMITED
       A COMPANY INCORPORATED UNDER
       THE PROVISIONS OF THE COMPANIES ACT, 1956
       AND HAVING ITS REGISTERED OFFICER
       AT 3RD FLOOR, ASSET 301-304 AND 307,
       WORLD MARK 3, AEROCITY,
       NEW DELHI 110 037,
       REP BY ITS AUTHORIZED SIGNATORY,
       MR.NAGARAJA NAIK
                                            ...PETITIONERS

(BY SRI SHODHAN BABU A.M., ADVOCATE
    SRI KUSUM RANGANATH, ADVOCATE
    SMT AMRITA JOSHI, ADVOCATE)

AND:

1.     STATE OF KARNATAKA
       DEPARTMENT OF ENERGY,
       VIKASA SOUDHA, DR.B.R.AMBEDKAR VEEDHI,
       BANGALORE-560 001
       REPRESENTED BY
       THE ADDITIONAL CHIEF SECRETARY TO GOVERNMENT

2.     HUBLI ELECTRICITY SUPPLY CO LTD
       A COMPANY REGISTERED UNDER
       THE PROVISIONS OF COMPANIES ACT 1956,
       HAVING ITS REGISTERED OFFICE AT
       P.B. ROAD, NAVANAGAR,
       HUBBALLI -580 025
       REP BY ITS MANAGING DIRECTOR
                               17




3.    THE KARNATAKA POWER TRANSMISSION
      CORPORATION LTD.,
      A COMPANY REGISTERED UNDER THE
      PROVISIONS OF COMPANIES ACT 1956
      HAVING ITS REGISTERED OFFICE AT
      KAVERI BHAVAN, K.G.ROAD, BANGALORE-560 009.
      REPRESENTED BY ITS
      MANAGING DIRECTOR
                                       ...RESPONDENTS
(BY SRI RAMESH GOWDA A., AGA FOR R1
    SRI SHAHBAAZ HUSSAIN, ADVOCATE FOR R2 & R3)

       THIS W.P. IS FILED UNDER ARTICLES 226 AND 227 OF
THE CONSTITUTION OF INDIA PRAYING TO DIRECT THE R-2 TO
HONOR ITS PAYMENT OBLIGATIONS UNDER THE PPA, BY
PROCESSING THE INVOICES, DTD. 6.6.2019, 5.7.2019, 3.8.2019,
7.9.2019, 11.10.2019, 12.11.2019, 9.12.2019, 8.1.2020 ANNEXURE-J
COLLECTIVELY AND MAKING PAYMENT OF RS.26,05,68,575/-
(RUPEES TWENTY SIX CRORE FIVE LAKHS SIXTY-EIGHT
THOUSAND FIVE HUNDRED AND SEVENTY -FIVE ONLY) ON THE
P-2 AND ETC.

IN W.P.No.5369 OF 2020
BETWEEN:
1.    RENEW SOLAR POWER PRIVATE LIMITED
      A COMPANY INCORPORATED UNDER
      THE PROVISIONS OF THE COMPANIES ACT, 2013
      AND HAVING ITS REGISTERED OFFICE AT
      NO.138, ANSAL CHAMBERS II,
      BIKAJI CAMA PLACE, DELHI-110 066
      REPRESENTED BY AUTHORIZED SIGNATORY,
      MR NIKHIL KUMAR Y.S.
2.    RENEW AGNI POWER PRIVATE LIMITED
      A COMPANY INCORPORATE UNDER THE
      PROVISIONS OF THE COMPANIES ACT, 2013 AND
      HAVING ITS REGISTERED OFFICE AT NO. 138,
      ANSAL CHAMBERS II, BIKAJI CAMA PLACE,
      DELHI -110 066,
      REPRESENTED BY AUTHORIZED SIGNATORORY,
      MR. NIKHIL KUMAR Y.S.
                                          ...PETITIONERS
(BY SRI SHODHAN BABU A.M., ADVOCATE
    SRI KUSUM RANGANATH, ADVOCATE
    SMT AMRITA JOSHI, ADVOCATE)
                              18




AND:

1.     STATE OF KARNATAKA
       DEPARTMENT OF ENERGY,
       VIKASA SOUDHA, DR.B.R.AMBEDKAR VEEDHI,
       BANGALORE-560 001
       REPRESENTED BY
       THE ADDITIONAL CHIEF SECRETARY TO GOVERNMENT

2.     HUBLI ELECTRICITY SUPPLY COMPANY LIMITED
       A COMPANY REGISTERED UNDER THE PROVISIONS OF
       COMPANIES ACT, 1956, HAVING ITS REGISTERED
       OFFICE AT P.B.ROAD, NAVANAGAR,
       HUBBALI-580 025
       REPRESENTED BY ITS MANAGING DIRECTOR

3.    THE KARNATAKA POWER TRANSMISSION
      CORPORATION LTD.,
      A COMPANY REGISTERED UNDER THE
      PROVISIONS OF COMPANIES ACT 1956
      HAVING ITS REGISTERED OFFICE AT
      KAVERI BHAVAN, K.G.ROAD, BANGALORE-560 009
      REPRESENTED BY ITS MANAGING DIRECTOR
                                       ...RESPONDENTS
(BY SRI RAMESH GOWDA A., AGA FOR R1
    SRI SHAHBAAZ HUSAIN, ADVOCATE FOR R2 & R3)

       THIS W.P. IS FILED UNDER ARTICLES 226 AND 227 OF
THE CONSTITUTION OF INDIA PRAYING TO DIRECT THE R-2 TO
HONOR ITS PAYMENT OBLIGATIONS UNDER THE PPA, BY
PROCESSING THE INVOICES, DATED 06.08.2019, 05.09.2019,
09.10.2019, 06.11.2019, 06.12.2019 AND 09.01.2019 VIDE ANNX-L
AND MAKING A PAYMENT OF RS.8,41,78,410/- (RUPEES EIGHT
CRORES FORTY ONE LAKHS SEVENTY-EIGHT THOUSAND
FOUR HUNDRED AND TEN ONLY) TO THE PETITIONER NO.2
AND ETC.


IN W.P.No.5371 OF 2020

BETWEEN:
1.     RENEW POWER PRIVATE LIMITED
       A COMPANY INCORPORATE UNDER
       THE PROVISIONS OF THE COMPANIES ACT, 2013
                            19




       AND HAVING ITS REGISTERED OFFICE AT
       NO. 138, ANSAL CHAMBERS II,
       BIKAJI CAMA PLACE, DELHI 110 066,
       REP BY AUTHORIZED SIGNATORY,
       MR. NIKHIL KUMAR Y.S.

2.    RENEW WIND ENERGY (SIPLA) PRIVATE LIMITED
      A COMPANY INCORPORATE UNDER THE PROVISIONS OF
      THE COMPANIES ACT, 2013 AND HAVING ITS
      REGISTERED OFFICE AT
      NO. 138, ANSAL CHAMBERS II,
      BIKAJI CAMA PLACE, DELHI 110 066,
      REP BY AUTHORIZED SIGNATORY,
      MR. NIKHIL KUMAR Y.S.
                                          ...PETITIONERS
(BY SRI SHODHAN BABU A.M., ADVOCATE
    SRI KUSUM RANGANATH, ADVOCATE
    SMT AMRITA JOSHI, ADVOCATE)

AND:

1.     STATE OF KARNATAKA
       DEPARTMENT OF ENERGY,
       VIKASA SOUDHA, DR.B.R.AMBEDKAR VEEDHI,
       BANGALORE-560 001
       REPRESENTED BY
       THE ADDITIONAL CHIEF SECRETARY TO GOVERNMENT

2.     HUBLI ELECTRICITY SUPPLY COMPANY LIMITED
       A COMPANY REGISTERED UNDER
       THE PROVISIONS OF COMPANIES ACT, 1956,
       HAVING ITS REGISTERED OFFICE AT
       P.B.ROAD, NAVANAGAR, HUBBALI-580 025
       REPRESENTED BY ITS MANAGING DIRECTOR

3.    THE KARNATAKA POWER TRANSMISSION
      CORPORATION LTD.,
      A COMPANY REGISTERED UNDER THE
      PROVISIONS OF COMPANIES ACT 1956
      HAVING ITS REGISTERED OFFICE AT
      KAVERI BHAVAN, K.G.ROAD, BANGALORE-560 009
      REPRESENTED BY ITS MANAGING DIRECTOR
                                       ...RESPONDENTS
(BY SRI RAMESH GOWDA A., AGA FOR R1
    SRI SHAHBAAZ HUSAIN, ADVOCATE FOR R2 & R3)

       THIS W.P. IS FILED UNDER ARTICLES 226 AND 227 OF
THE CONSTITUTION OF INDIA PRAYING TO DIRECT THE R-2 TO
                              20




HONOR ITS PAYMENT OBLIGATIONS UNDER THE PPA, BY
PROCESSING     THE    INVOICES,   DTD.9.9.2019,   11.10.2019,
7.11.2019, 6.12.2019, 7.1.2019, ANNEXURE-J COLLECTIVELY AND
MAKING PAYMENT OF RS.14,11,70,7328/- (RUPEES FOURTEEN
CRORES     ELEVEN    LAKHS   SEVENTY   THOUSAND      SEVEN
HUNDRED AND THIRTY EIGHT ONLY) ON THE P-2 AND ETC.


IN W.P.No.5374 OF 2020

BETWEEN:
1.     RENEW POWER PRIVATE LIMITED
       A COMPANY INCORPORATE UNDER
       THE PROVISIONS OF THE COMPANIES ACT, 2013
       AND HAVING ITS REGISTERED OFFICE AT
       NO. 138, ANSAL CHAMBERS II,
       BIKAJI CAMA PLACE, DELHI 110 066,
       REP BY AUTHORIZED SIGNATORY,
       MR. NIKHIL KUMAR Y.S.

2.    KANAK RENEWABLES LIMITED
      A COMPANY INCORPORATE UNDER
      THE PROVISIONS OF THE COMPANIES ACT, 1956
      AND HAVING ITS REGISTERED OFFICE AT
      NO. 138, ANSAL CHAMBERS II,
      BIKAJI CAMA PLACE, DELHI 110 066,
      REP BY AUTHORIZED SIGNATORY,
      MR. NIKHIL KUMAR Y.S.
                                        ...PETITIONERS
(BY SRI SHODHAN BABU A.M., ADVOCATE
    SRI KUSUM RANGANATH, ADVOCATE
    SMT AMRITA JOSHI, ADVOCATE)

AND:

1.     STATE OF KARNATAKA
       DEPARTMENT OF ENERGY,
       VIKASA SOUDHA, DR.B.R.AMBEDKAR VEEDHI,
       BANGALORE-560 001
       REPRESENTED BY
       THE ADDITIONAL CHIEF SECRETARY TO GOVERNMENT

2.     GULBARGA ELECTRICITY SUPPLY CO. LTD.,
       A COMPANY REGISTERED UNDER THE
       PROVISIONS OF COMPANIES ACT 1956,.
       HAVING ITS REGISTERED OFFICE AT
                             21




      STATION ROAD, KALABURGI 585102.
      REP BY ITS MANAGING DIRECTOR

3.    THE KARNATAKA POWER TRANSMISSION
      CORPORATION LTD.,
      A COMPANY REGISTERED UNDER THE
      PROVISIONS OF COMPANIES ACT 1956
      HAVING ITS REGISTERED OFFICE AT
      KAVERI BHAVAN, K.G.ROAD,
      BANGALORE-560 009
      REPRESENTED BY ITS
      MANAGING DIRECTOR
                                       ...RESPONDENTS
(BY SRI RAMESH GOWDA A., AGA FOR R1
    SRI MURUGESH V. CHARATI, ADVOCATE FOR R2
    SRI S.G.PRASHANTH MURTHY, ADVOCATE FOR R3)

      THIS W.P. IS FILED UNDER ARTICLES 226 AND 227 OF
THE CONSTITUTION OF INDIA PRAYING TO DIRECT THE R-2 TO
HONOR ITS PAYMENT OBLIGATIONS UNDER THE PPA, BY
PROCESSING THE INVOICES, DATED 06.09.2019, 14.10.2019,
07.11.2019, 09.12.2019, AND 09.01.2019, (ANNEXURE-K (COLLY))
AND MAKING A PAYMENT OF RS.1,42,26,996/- (RUPEES ONE
CRORE FOURTY TWO LAKHS TWENTY SIX THOUSAND NINE
HUNDRED AND NINETY SIX ONLY) TO THE PETITIONER NO.2
AND ETC.


IN W.P.No.5375 OF 2020

BETWEEN:
1.    RENEW POWER PRIVATE LIMITED
      A COMPANY INCORPORATE UNDER
      THE PROVISIONS OF THE COMPANIES ACT,
      2013 AND HAVING ITS REGISTERED OFFICE
      AT NO. 138, ANSAL CHAMBERS II,
      BIKAJI CAMA PLACE, DELHI 110 066,
      REP BY AUTHORIZED SIGNATORY,
      MR. NIKHIL KUMAR Y.S.

2.    OSTRO MAHAWIND POWER PRIVATE LIMITED
      A COMPANY INCORPORATED UNDER THE
      PROVISIONS OF THE COMPANIES ACT 2013
      AND HAVING ITS REGISTERED OFFICE
                            22




       AT UNIT NO. G-0, GROUND FLOOR,
       MIRA CORPORATE SUITES, 1 AND 2
       ISHWAR INDUSTRIAL ESTATE,
       MATHURA ROAD, NEW DELHI 110 065,
       REPRESENTED BY AUTHORIZED SIGNATORY
       MR. NIKHIL KUMAR Y.S.
                                        ...PETITIONERS

(BY SRI SAJJAN POOVAYYA, SR. ADVOCATE FOR
    SRI SHODHAN BABU A.M., ADVOCATE
    SRI KUSUM RANGANATH, ADVOCATE
    SMT AMRITA JOSHI, ADVOCATE)

AND:

1.     STATE OF KARNATAKA
       DEPARTMENT OF ENERGY,
       VIKASA SOUDHA, DR.B.R.AMBEDKAR VEEDHI,
       BANGALORE-560 001
       REPRESENTED BY
       THE ADDITIONAL CHIEF SECRETARY TO GOVERNMENT

2.     HUBLI ELECTRICITY SUPPLY CO LTD
       A COMPANY REGISTERED UNDER THE
       PROVISIONS OF COMPANIES ACT 1956,
       HAVING ITS REGISTERED OFFICE AT
       PB ROAD, NAVANAGAR, HUBBALI 580 025.
       REP BY ITS MANAGING DIRECTOR

3.     THE KARNATAKA POWER TRANSMISSION
       CORPORATION LTD.,
       A COMPANY REGISTERED UNDER THE
       PROVISIONS OF COMPANIES ACT 1956
       HAVING ITS REGISTERED OFFICE AT
       KAVERI BHAVAN, K.G.ROAD,
       BANGALORE-560 009
       REPRESENTED BY ITS
       MANAGING DIRECTOR
                                        ...RESPONDENTS

(BY SRI RAMESH GOWDA A., AGA FOR R1
    SRI MURUGESH V. CHARATI, ADVOCATE FOR R2
    SRI S.G.PRASHANTH MURTHY, ADVOCATE FOR R3)

       THIS W.P. IS FILED UNDER ARTICLES 226 AND 227 OF
THE CONSTITUTION OF INDIA PRAYING TO DIRECT THE R-2 TO
HONOR ITS PAYMENT OBLIGATIONS UNDER THE PPA, BY
                                23




PROCESSING THE INVOICES, DATED 08.08.2019, 06.09.2019,
09.10.2019, 06.11.2019, 06.12.2019, 06.01.2020 (ANNEXURE-G1
AND J (COLLY)) AND MAKING A PAYMENT OF RS.40,14,13,594/-
(RUPEES       FORTY   CRORES    FOURTEEN    LAKHS    THIRTEEN
THOUSAND FIVE HUNDRED AND NINETY FOUR ONLY) TO THE
PETITIONER NO.2 AND ETC.


      THESE       WRIT      PETITIONS    COMING     ON    FOR
'DICTATING ORDERS' THIS DAY, THE COURT MADE THE
FOLLOWING:-


                             ORDER

These batch of writ petitions which are filed by the

petitioners who are renewable energy generating

companies involved in the business of independent power

production and establishing and operating power plants,

while petitioners in some of the petitions are operating solar

power plants, petitioners in the other petitions are operating

wind power plants. The subject matter of all the petitions

are Power Purchase Agreements (PPAs) entered into

between the petitioners and the various Electricity Supply

Companies (ESCOMs), who are arrayed as respondent

No.2 in these petitions.

2. The details of the petitioners, PPAs, relevant

clauses etc., are as under;-

PETITIONS (WIND) - PPA CLAUSES DETAILS

Sl. WP No. SPV Respond Wind PPA PPA PPA Clause for PPA PPA Dispute Nos. ent / Clause Clause for Payment obligation clause for Clause Redressal ESCOM Solar for Late opening for Mechanis payment Payment Letter of monthly m Clause of Invoice Surcharge Credit Joint Meter Reading 1 5703 of Rajat HESCOM Wind Clause Clause 6.3 / Clause 6.4/Page 44 of Clause Clause Clause 10 2020 Renewa 6.2/ Page Page 44 of Petition / Obligation to 6.5/ Page 7.3/ Page (Lead bles 44 of Petition/ pay 100% of the 45 of 46 of Petition) Petition 1.25% PM disputed amount Petition Petition

2 5303 of Renew HESCOM Wind Clause Clause 6.3 / Clause 6.4/Page 44 of Clause Clause Clause 10 2020 Wind 6.2/ Page Page 44 of Petition/Obligation to 6.5/ Page 7.3/ Page Energy 44 of Petition/ pay 100% of the 45 of 46 of (Sipla) Petition 1.25% PM disputed amount Petition Petition

3 5341 of Kanak HESCOM Wind Clause Clause 6.3 / Clause 6.4/Page 44 of Clause Clause Clause 10 2020 Renewa 6.2/ Page Page 44 of Petition/Obligation to 6.5/ Page 7.3/ Page bles 44 of Petition/ pay 100% of the 45 of 46 of Petition 1.25% PM disputed amount Petition Petition

4 5346 of Rajat GESCOM Wind Clause Clause 6.3 / Clause 6.4/Page 46 of Clause Clause Clause 10 2020 Renewa 6.2/ Page Page 46 of Petition/ Obligation to 6.5/ Page 7.3/ Page bles 46 of Petition/ pay 100% of the 47 of 48 of Petition 1.25% PM disputed amount Petition Petition

5 5347 of Rajat HESCOM Wind Clause Clause 6.3 / Clause 6.4/Page 44 of Clause Clause Clause 10 2020 Renewa 6.2/ Page Page 44 of Petition/ Obligation to 6.5/ Page 7.3/ Page bles 44 of Petition/ pay 100% of the 45 of 46 of Petition 1.25% PM disputed amount Petition Petition

6 5354 of Ostro GESCOM Wind Clause Clause 6.3 / Clause 6.4/Page 44 of Clause Clause Clause 10 2020 Dakshi 6.2/ Page Page 44 of Petition/ Obligation to 6.5/ Page 7.3/ Page n 44 of Petition/ pay 100% of the 45 of 46 of Petition 1.25% PM disputed amount Petition Petition

7 5362 of Renew HESCOM Wind Clause Clause 6.3 / Clause 6.4/Page 44 of Clause Clause Clause 10 2020 Wind 6.2/ Page Page 44 of Petition/ Obligation to 6.5/ Page 7.3/ Page Energy 44 of Petition/ pay 100% of the 45 of 46 of (Sipla) Petition 1.25% PM disputed amount Petition Petition

8 5364 of Bidwal GESCOM Wind Clause Clause 6.3 / Clause 6.4/Page 48 of Clause Clause Clause 10 2020 Renewa 6.2/ Page Page 48 of Petition/ Obligation to 6.5/ Page 7.3/ Page ble 48 of Petition/ pay 100% of the 49 of 51 of Petition 1.25% PM disputed amount Petition Petition 9 5365 of Pugalur GESCOM Wind Clause Clause 6.3 / Clause 6.4/Page 47 of Clause Clause Clause 10 2020 Renewa 6.2/ Page Page 47 of Petition/ Obligation to 6.5/ Page 7.3/ Page ble 47 of Petition/ pay 100% of the 48 of 50 of Petition 1.25% PM disputed amount Petition Petition

10 5371 of Renew HESCOM Wind Clause Clause 6.3 / Clause 6.4/Page 44 of Clause Clause Clause 10 2020 Wind 6.2/ Page Page 44 of Petition/ Obligation to 6.5/ Page 7.3/ Page Energy 44 of Petition/ pay 100% of the 45 of 46 of (Sipla) Petition 1.25% PM disputed amount Petition Petition

11 5374 of Kanak GESCOM Wind Clause Clause 6.3 / Clause 6.4/Page 46 of Clause Clause Clause 10 2020 Renewa 6.2/ Page Page 46 of Petition/ Obligation to 6.5/ Page 7.3/ Page bles 46 of Petition/ pay 100% of the 47 of 48 of Petition 1.25% PM disputed amount Petition Petition

12 5375 of Ostro HESCOM Wind Clause Clause 6.3 / Clause 6.4/Page 45 of Clause Clause Clause 10 2020 Mahawi 6.2/ Page Page 46 of Petition/ Obligation to 6.5/ Page 7.3/ Page nd 45 of Petition/ pay 100% of the 46 of 48 of Petition 1.25% PM disputed amount Petition Petition

PETITIONS (SOLAR) - PPA CLAUSES DETAILS Sl. WP SPV Respondent Win PPA PPA PPA Clause for PPA PPA Dispute Nos. No. ESCOMS d/ Clause Clause for Payment clause for Clause Redressal Solar for Late obligation opening for Mechanis payment Payment Letter of monthly m Clause of Invoice Surcharge Credit Joint Meter Reading 1 5368 Azure HESCOM Solar Clause Clause 13.4 Clause 13.7.1 & Clause Clause Clause 18 of Earth 13.3.1/ / Page 67 13.7.2/Page 68 of 13.6/ Page 10.2/ Page 2020 Power Page 66 of of Petition/ Petition/Obligation 67 of 63 of Petition 1.25% PM to pay 95% of the Petition Petition outstanding invoice amount

2 5357 Adyah GESCOM Solar Clause Clause 13.4 Clause 13.7.1 & Clause Clause Clause 18 of Solar- 13.3.1/ / Page 72 13.7.2/Page 73 of 13.6/ Page 10.2/ Page 2020 Block Page 71 of of Petition/ Petition/Obligation 72 of 68 of 10 Petition 1.25% PM to pay 95% of the Petition Petition outstanding invoice amount

3 5361 Adyah HESCOM Solar Clause Clause 13.4 Clause 13.7.1 & Clause Clause Clause 18 of Solar- 13.3.1/ / Page 69 13.7.2/Page 70 of 13.6/ Page 10.2/ Page 2020 Block Page 68 of of Petition/ Petition/Obligation 69 of 65 of 13 Petition 1.25% PM to pay 95% of the Petition Petition outstanding invoice amount

4 5369 Renew HESCOM Solar Clause Clause 13.4 Clause 13.7.1 & Clause Clause Clause 18 of Agni 13.3.1/ / Page 72 13.7.2/Page 70 of 13.6/ Page 10.2/ Page 2020 Power Page 68 of of Petition/ Petition/Obligation 69 of 65 of Petition 1.25% PM to pay 95% of the Petition Petition outstanding invoice amount

PETITIONERS' CONTENTIONS

(i) The Respondent No.1 is the State of Karnataka,

while the Respondent No. 2 in all the petitions are the

respective Electricity Supply Companies (ESCOMS) which

are statutory distribution licensees constituted under the

Electricity Act, 2003 (herein referred as "the said Act of

2003" for brevity). The Respondent No.2 is a "State" within

the meaning of Article 12 of the Constitution of India. The

Respondent No.3-KPTCL performs the functions of

transmission of power in the entire State of Karnataka

and also construction of stations and transmission

lines and maintenance.

(ii) It is contended that Respondent No.2-ESCOMs

being statutory entities/authorities and instrumentalities of

the State Government and wholly owned by the Govt. of

Karnataka are discharging public, and statutory functions

under the provisions of the said Act of 2003. The

Respondent No.2-ESCOMs have an obligation to act fairly

and reasonably in the discharge of their statutory and

contractual functions. The act of non-payment of admitted

and undisputed dues to the Petitioners-Generators is

contrary to public good, public interest, illegal, unfair,

arbitrary and therefore, contrary to Article 14 of the

Constitution of India.

(iii) The petitioners have entered into PPAs as well

as supplementary agreements with the Respondent No.2-

ESCOMs for periods between 20-30 years. The payment of

tariff approved by the respective State Electricity

Regulatory Commissions, which is the Karnataka Electricity

Regulatory Commissioner (KERC), in accordance with

PPAs is a part of the ESCOM's statutory duty of

procurement of electricity in accordance with the procedure

and the contracts approved by the KERC, as per the KERC

(Conditions of license for ESCOMs) Regulations, 2004. The

Respondent No.2-ESCOMs cannot fulfill its statutory duty

of procurement of electricity without paying the tariff for the

energy procured from the Generators as specified by the

KERC and the PPAs between the parties.

(iv) It is averred that the statutory duty of the

Respondent No.2-ESCOMs to pay the tariff prescribed by

the KERC, in accordance with the terms of the PPA

entered into between the parties also arises from Section

61 of the Electricity Act, 2003 read with Regulation 21 of

the KERC (Conditions of license for ESCOMs) Regulations,

2004, require the ESCOMs to act in accordance with the

process for procurement approved by the Commission and

in accordance with the contracts approved by the

Commission, which specifically states that the tariff

determination process must be in accordance with

commercially sound principles and ensure a reasonable

return on investment of the Generators. It is submitted that

permitting Respondent No.2-ESCOMs to evade this

statutory responsibility by delaying payment of dues for

electricity supplied by the Generators is contrary to Section

61 of the said Act of 2003.

(v) It is contended that the Invoices are issued

pursuant to a joint meter reading exercise and as per the

tariff prescribed under the PPA. Respondent No.2-

ESCOMs has acknowledged the supply and quantum of

electricity, despite which the ESCOMs are arbitrarily

withholding payment of the dues owed to the petitioner.

The quantum of energy supplied by the petitioner and the

tariff is admitted and undisputed by the respondents. The

respondent No.2-ESCOMs therefore is obligated to pay the

petitioner as per the terms of the PPAs entered into

between the parties. The respondent No.2-ESCOMs has

also failed to provide the mandatory security towards non-

payment of the tariff as prescribed under the PPA between

the parties by failing to open irrevocable and revolving

Letter of Credit in favour of the petitioner.

(vi) It is averred that the respondent No.2-ESCOMs

has an obligation to make payment of the Invoices by the

5th day of the immediately succeeding month, in which the

monthly bill/supplementary bill is issued by the petitioner as

per the PPA. The petitioners are entitled to receipt of late

payment surcharge for delays in payment as per the PPA.

The non-payment of the petitioner's undisputed dues under

the terms of the PPA has adversely affected the ability of

the petitioner to proceed with the petitioner's operations,

since the petitioner has an obligation to meet its expenses,

liabilities and debt repayment obligations from the tariff

received for the generation of electricity.

(vii) It is contended that the PPA expressly protects

the rights of the petitioner by providing for payment of 95%

of the Invoice amounts even in the case of a disputed

invoice. The protection given to the petitioner is to ensure

that the Generators are not prejudiced in the midst of

supplying electricity as per the terms of the PPA entered

into between the parties. The Respondent No.2-ESCOMs

can always recover the money from the Generators if there

is excess payment for electricity supplied. However, the

Generators will be severely prejudiced if their invoices are

not honoured by the Respondent No.2-ESCOMs.

Therefore, the non-payment of undisputed dues to the

Petitioner No. 2 for electricity generated and supplied to the

Respondent No. 2-ESCOMs is contrary to the public

interest and public goods, as private generators may refrain

from establishing generation of stations in Karnataka due to

the arbitrary, unfair, and unreasonable actions of

Respondent No. 2-ESCOMs in not honoring their payment

obligations under the settled PPAs.

(viii) It is also contended that the arbitrary,

unreasonable, and unjust negligence of the Respondent

No. 2-ESCOMs of its statutory and contractual obligations

has resulted in grave consequences for the petitioner, as

the petitioner is finding it increasingly difficult to meet its

debt repayment obligations and other liabilities; that the

financing for the petitioner's projects is based primarily on

the timely payment of tariff by Respondent No. 2, as the

petitioner will otherwise be unable to meet its debt

obligations which will have a cascading effect on the

financial health of the Petitioners and on the financial health

of the banks and other financial institutions as well. The

non-payment of statutory, admitted and undisputed dues to

the Petitioner is therefore a matter of great public

importance, especially since electricity is an essential good

for the citizens, that the State Government procures from

entities such as the Petitioner.

(ix) It is averred that supply of electricity is a

fundamental right under Article 21 of the Constitution of

India, as electricity forms a part of meaningful right to

shelter under Article 21 of the Constitution of India.

Respondent no. 2 is therefore discharging the functions of

the State in ensuring that consumers are not prevented

from access to their fundamental right to shelter under

Article 21 of the Constitution of India. The willful default of

Respondent No. 2 in not honoring its payment obligations

has a significant impact on the health of the renewable

energy sector as a whole as Generators will be unable to

continue generation of electricity due to the lack of return

on their costs and investments.

(x) It is contended that the Respondent No.2-

ESCOMs have an obligation to act in a reasonable, fair,

and just manner even in contractual relations, especially

when the state is performing a public function for public

good through private persons. Procurement of electricity for

the purpose of supply to various classes of consumers is a

public function for public good which enables the state to

meet its constitutional obligation of providing meaningful

shelter and enabling commerce and industry. The

Petitioners' credit rating and ability to raise finances for new

projects are dependent on receiving timely payments from

the Respondents as per the terms of the PPA entered into

between the parties and approved by the KERC. The

ESCOMs have an obligation to co-operate with the KERC

in its measures to promote generation of renewable energy,

and it is submitted that delaying payments of admitted dues

to generators of renewable energy is contrary to the

scheme of the Electricity Act, 2003.

(xi) It is averred that the Respondent No. 2 has an

obligation to open and maintain a revolving and irrevocable

letter of credit in favour of the Petitioner in accordance with

the PPA entered into between the Parties. The Respondent

No.2 has failed to open and maintain a revolving and

irrevocable letter of credit in favour of the Petitioner

contrary to the specific terms of the contract, and the non-

compliance with an admitted term of the PPA entered into

between the parties is arbitrary and violative of Article 14 of

the Constitution of India. The irrevocable letter of credit is

the only protection against such instances of non payment

of the tariff dues of the Petitioner, and the Respondents

have to mandatorily maintain an irrevocable LC as per the

terms of the PPA.

(xii) It is contended that the tariff determination

process carried out by the KERC is pursuant to Section 86

(1) (a) read with Sections 61 to 64 of the said Act of 2003.

In the case of renewable energy, the tariff determination

must also take into consideration Section 86(1)(e), which

specifically casts a duty on the KERC to promote

generation of electricity through renewable sources. The

tariff determination and the power procurement process are

both functions regulated by the KERC. The two functions

are intrinsically linked and not severable from each other as

there can be no power procurement without the payment of

tariff as prescribed by the KERC under the said Act of

2003.

(xiii) It is further averred that the provisions of the

PPA that deal with tariff related aspects forms a statutory

obligation and to that extent the tariff obligations are both

statutory and contractual in nature. Therefore, the

Respondent No.2 is not only in breach of its contractual

functions but also in breach of its statutory functions under

the provisions of the said Act of 2003. Respondent No. 2

being a deemed Distribution Licensee under Section 14 of

the Electricity Act, 2003 has a statutory obligation to

maintain capital adequacy, and creditworthiness to meet its

payment obligations. The failure of Respondent No.2 to

honor its undisputed payment obligations in a timely

manner, is therefore arbitrary, contrary to the scheme of the

2003 Act, without any basis and a violation of the terms of

its License under Section 14 read with Section 131 (2) of

the 2003 Act. The non-payment of tariff as per the manner

in which it is prescribed in the PPA, approved by the KERC,

in exercise of its regulatory function under Regulation 21 of

the KERC (Conditions of license for ESCOMs) Regulations,

2004, is arbitrary and violative of Article 14 of the

Constitution of India. The delay in payments of admitted

dues is also contrary to Section 61(h) and 86(1) (e) of the

Electricity Act, 2003, which specifically requires the

appropriate commission, which is the KERC in the present

instance to promote generation of electricity from

renewable sources of energy.

3. The Respondent No.1 - the State and Respondent

No.3 - KPTCL have not filed their statement of objections to

the petition. The Respondent No. 2 - ESCOMs have filed

their statement of objections resisting the petition.

CONTENTIONS OF RESPONDENT No.2-ESCOMs

(i) In addition to denying the various contentions

urged in the petition, Respondent No.2-ESCOMs have

contended that the petitions are not maintainable for the

reason that the petitioners have efficacious alternative

remedy available to address the grievances raised in the

above Petition. Section 86(1)(f) of the Electricity Act, 2003

provides for the Respondent No.2 to adjudicate upon

disputes between a generating company and a distributing

licensee. Section 86(1)(f) is a special and specific provision

of law governing the disputes between a generating

company and a distributing licensee and the KERC has

been specially constituted to adjudicate on such disputes.

All the contentions raised in the petition relate exclusively to

the said PPAs and the actions of the Respondents around

it and not otherwise. The said Act of 2003 establishes a

hierarchy of remedies available to the Petitioner. So also,

the PPAs stipulate that dispute resolution, either by way of

adjudication or arbitration has to be done by the KERC

which has to be approached by the petitioners. It is

therefore contended that in view of availability of equally

effective and alternative remedy for the petitioners to

approach the KERC under Section 86(1)(f) of the said Act

of 2003, the present petitions are liable to be dismissed as

not maintainable.

(ii) It is contended that Government contracts

generally have an impact on public welfare. Considering

the impact of such Government contracts, Article 323-B of

the Constitution provides for establishment of tribunals to

deal with disputes affecting the public at large. If disputes

arising out of non - payment of dues in all government

contracts constituting a violation of a fundamental right are

brought under the purview of the High Court's jurisdiction,

there would be no need for any special tribunals. Article

322-B read with the provisions of the Electricity Act, 2003

are special provisions of law that govern the instant dispute

and mandate the Petitioner to file necessary petition before

the KERC and not by way of the present petitions.

(iii) It is averred that if this Court assumes writ

jurisdiction over the issue at hand, a dangerous precedent

will be set as all the matters under the jurisdiction of the

KERC would be subsumed under the High Court's

jurisdiction. If the KERC, a statutory body, equipped with

technical and legal members, specifically constituted to

deal with intricate disputes arising out of the Power

Purchase Agreements is deprived of its jurisdiction at the

matter in hand on the ground that the act of non-payment of

dues by a government company affects public interest at

large; a negative precedent would be set, encouraging

several litigants to circumvent the remedy readily available

to them before approaching the Writ Courts. Through such

an act of judicial adventurism, the purpose of establishing

special courts and the mechanism for dispute resolution

laid out in the Electricity Act, 2003 would be defeated.

Moreover, the Petitioner's contention that the public interest

is being affected can also be looked into by the KERC, as

the provisions of the Act of 2003 mandates a balance of

public and private interest in adjudication of all disputes. It

is therefore contended that there is no merit in the petitions

and that the same are liable to be dismissed.

REJOINDER OF THE PETITIONERS;

(i) In addition to controverting the various contentions

urged by the Respondent No.2-ESCOMs in the defence,

petitioners have pointed out in their rejoinder that the

Respondent No. 2 has admitted the outstanding amounts

towards the payment of electricity and that there is no

dispute on the issue of outstanding amounts, despite which

the Respondent No. 2 has arbitrarily and repeatedly

withheld payments due to the Petitioners. The issues of

arbitrariness by the State in contractual matters and

violation of Article 14 are required to be adjudicated and

decided by this Hon'ble Court and therefore, the Petitioner

has rightly approached this Court.

(ii) It is contended that the present writ petitions are

maintainable against the State and/or State

instrumentalities in contractual matters especially in cases

such as the present instance, where the State is

consistently acting arbitrarily and delaying payments of

admitted dues to be made to the Petitioners. Petitioners

have placed reliance upon the judgments of the Apex Court

in order to contend that this Court may exercise its

extraordinary jurisdiction under Article 226 of the

Constitution of India in matters, where a party is aggrieved

by the action of a public body or authority especially when

the action or conduct of a public body or authority is high

handed, arbitrary, unjust and unlawful even in contractual

matters and even if there exists an arbitration

clause/agreement in the contract.

(iii) It is also contended that the dues owed to the

Petitioner are undisputed dues. The timely payment of tariff

for electricity supplied is the foundational representation of

the contract entered into with the Respondent No.1-State

and the State owned Distribution Licensees i.e.

Respondent No. 2 herein and that the Petitioner herein has

rightly approached this Hon'ble Court particularly when

Respondent No. 2 does not dispute that the PPAs have an

element of public interest. It is averred that the payments

owed to the Petitioner are undisputed dues towards supply

of electricity to the State of Karnataka and that the quantum

of dues or the electricity supplied is not in dispute, as well

the fact that the obligation to make payment within fifteen

days of the receipt of the invoices is also not in dispute.

The Respondents are also aware that the Petitioners are

dependent on prompt payment of dues. The commercial

feasibility of the Project and the financial health of the

electricity generators depend on the prompt payment of

PPA tariff by the Respondents. It is therefore contended

that there is no merit in any of the contentions urged by

Respondent No.2 and that petitioners are entitled to the

relief's sought for by them in the petitions.

4. Heard Sri.K.G.Raghavan and Sri.Sajjan Poovaya,

learned Senior Counsel appearing for the Petitioners,

learned AGA as well as the learned counsel for

Respondents 2 and 3 and perused the materials on record.

5. In addition to reiterating the various contentions

urged in the petitions and referring to the documents

produced by the petitioners, both the learned senior

counsel for the petitioners submit that indisputably,

petitioners have entered into separate PPAs and

supplementary agreements with the respective ESCOMS

for development of power projects across various places in

Karnataka. Referring to the decisions of the Apex Court,

learned senior counsel submitted that writ petitions are

maintainable even in contractual matters relating to the

PPAs, even though the same contain an arbitration

clause/agreement, particularly when no disputed or

complicated questions of fact or contentious issues arise

for consideration in the petitions.

5.1 Learned senior counsel invited my attention to

the material on record including the relevant clauses in the

PPAs in order to contend that pursuant to joint meter

readings in the presence of both the Petitioner and

Respondent No.2-ESCOMs, despite the Petitioner raising

invoices/bills for payments after conducting the requisite

joint meter readings, the Respondent No.2 did not comply

with its liability to make payment in favour of the petitioner.

It is also submitted that the Respondent No.2 did not raise

any dispute with regard to its liability to make payment nor

took recourse to or resort to the dispute resolution

mechanism stipulated under the PPAs. So also, the

Respondent No.2 did not open a Letter of Credit as

enjoined under the PPAs. It is therefore contended that the

Respondent No.2-ESCOMs cannot avoid or evade to

honour or fulfil their liabilities and obligations under the

PPAs by refusing to make payment, open letter of credit

etc., and consequently, necessary directions are to be

issued to them in this regard.

5.2 Learned senior counsel submit that Section

86(1)(f) of the Act of 2003 Act will apply only if there are

disputes between the Petitioner and Respondent No.2 and

not otherwise. Elaborating their submissions, learned

senior counsel submit that the material on record viz., the

joint meter readings conducted in the presence of the

Petitioner as well as Respondent No 2., the bills/invoices

raised by the Petitioner, complete inaction on the part of the

Respondent to raise any dispute with regard to subject

invoices/bills either prior to filing of the petition or thereafter

clearly establish that there is no dispute between the

Petitioner and Respondent No. 2 as regards their liability to

make payments which requires adjudication/arbitration by

the KERC under Section 86(1)(f); it is therefore contended

that in the absence of any dispute between the Petitioner

and Respondent, the question of the Petitioners seeking

adjudication/resolution of a non-existing dispute before the

KERC does not arise, particularly when the remedy under

Section 86(1)(f) is dependent upon existence of a dispute

between Petitioner and Respondent No. 2, and it is only

existing disputes that can be adjudicated/arbitrated by

KERC under the said provision.

5.3 Learned senior counsel further submit that

alternatively, even assuming but not conceding that

Respondent No.2-ESCOMs can dispute their liability with

regard to payment of the amounts payable to the

Petitioners, the PPAs make it obligatory/mandatory for the

ESCOMs to pay 95%(Solar) and 100%(Wind) of the invoice

amounts upfront to the petitioners before raising a dispute

and consequently, it is necessary that directions are issued

to the Respondent No.2 to pay the dues to the petitioners,

open a monthly irrevocable revolving Letter of Credit in

favour of the petitioners; so also, Respondent No.2-

ESCOMs are to be issued necessary directions to honour

all their obligations towards the petitioners under the PPAs

henceforth, in the future also without driving the Petitioners

to initiate fresh proceedings against the ESCOMs for

repeated defaults committed by them. In support of his

submissions, learned senior counsel has placed reliance

upon the following decisions;

(i) Arkay Energy (Rameswarm) Limited Vs. Tamilnadu Generation & Distribution Company Limited - (2021) 224 Comp Cas 381;

(ii) Union of India & Ors. Vs. Tania Construction Private Limited (2011) 5 SCC 697;

(iii) HarbansalSahnia & Anr. Vs. Indian Oil Corp Ltd & Ors. - (2003) 2 SCC 107;

(iv) Major (Retd) Inder Singh Rekhi Vs. Delhi Development Authority - (1988) 2 SCC 338;

(v) Unitech Limited & Ors Vs. Telangana State Industrial Infrastructure Corporation & Ors - Civil Appeal No.317/2021;

(vi) ABL International Ltd & Anr Vs. Export Credit Guarantee Corporation of India & ors. - (2004) 3 SCC 553;

(vii) Embassy Property Developments Pvt. Ltd Vs. State of Karnataka & ors. - (2020) 13 SCC 308.

6. Per contra, learned counsel for Respondent No.2

while reiterating the various contentions urged in the

statement of objections submitted that writ petition is not

maintainable since the dispute relates to contractual matter

arising out of the PPAs which contain a dispute redressal

mechanism including arbitration and approaching the

KERC; it is submitted that in view of availability of equally

efficacious and alternative remedy of

adjudication/arbitration of disputes under Section 86(1)(f) of

the Act 2003 as well the PPAs, the Petitioners would

necessarily have exhaust their remedy by approaching the

KERC for adjudication/arbitration of their disputes and

without doing so, the Petitioners are not entitled to invoke

the extraordinary jurisdiction of the court in the present

petition. It is contended that the present petitions arising out

of the contractual matters and involving contentious issues

and disputed/complicated questions of law and fact the

same cannot be adjudicated upon by this court in the

present petitions which are liable to be dismissed. In

support of his contentions, learned counsel for Respondent

No.2-ESCOMs relied upon the following decisions:

(i) Gujarat Urja Vikas Nigam V. Essar Power Ltd - (2008) 4 SCC 755;

(ii) Spectrum Power Generation Limited V. TCALO - Appeal No.90/2011 Dated 10.08.2011 by the Electricity Appellate Tribunal;

(iii) Nabha Power Vs. Punjab Power State Corporation

- Appeal No.283/2015 Dated 17.05.2018 by the Electricity Appellate Tribunal;

(iv) Gujarat Urja Vikas Nigam Vs. Solar Semiconductor - (2017) 16 SCC 498;

(v) Tachocline Renewables Vs. KERC -

W.P.No.51696/2017 dated 05.04.2018;

(vi) State of Gujarat Vs. Utility Users Welfare Association - (2018) 6 SCC 21.

7. I have given my anxious consideration to the rival

submissions and perused the material on record.

8. The following points arise for consideration in the

present petitions;

I. Whether the present petitions in relation to a contract i.e., PPAs between the Petitioner and the Respondent No. 2-ESCOMs are maintainable under Article 226 of Constitution of India ?

II. Whether the present petitions are maintainable in view of dispute redressal mechanism contained in the PPAs ?

III. Whether the present petitions are maintainable in view of Section 86(1)(f) of the Electricity Act, 2003 ?

IV. Whether the Petitioners are entitled to the reliefs sought in the petition?

Re: Point No.1

Before adverting to this issue, it is necessary to refer

to certain covenants in the PPAs with regard to joint meter

reading/measurements, raising of invoices, payment of

bills, late payment charges, opening of letters of credit etc.,

(i) As can be seen from the table extracted above,

insofar as the petitioners who are operating solar power

plants are concerned, Clause No.10 of the PPAs stipulates

the procedure for joint meter reading/measurements.

Clause No.13 provides for raising of bills/invoices by the

petitioners and payment by the ESCOMs to them as well

the obligation on the part of the ESCOMs to open revolving

and irrevocable letters of credit in favour of the petitioners.

Clause No.13.7 mandates that even if the ESCOMs dispute

the bills/invoices, the ESCOMs would necessarily have to

pay 95% of the disputed amount to the petitioners as a

mandatory pre-condition and only thereafter, the ESCOMs

would be entitled to pursue the said dispute. Clause No.18

provides for the dispute resolution mechanism.

(ii) Insofar as the petitioners who are operating wind

power plants are concerned, Clause No.7 of the PPAs

stipulates the procedure for joint meter

reading/measurements. Clause No.6 provides for raising of

bills/invoices by the petitioners and payment by the

ESCOMs to them as well the obligation on the part of the

ESCOMs to open revolving and irrevocable letters of credit

in favour of the petitioners. Clause No.6.4 mandates that

even if the ESCOMs dispute the bills/invoices, the

ESCOMs would necessarily have to pay 100% of the

disputed amount to the petitioners as a mandatory pre-

condition and only thereafter, the ESCOMs would be

entitled to pursue the said dispute. Clause No.10 provides

for the dispute resolution mechanism.

(iii) The material on record indicates that in the

instant cases, the Respondent No.2-ESCOMs did not

dispute any of the subject invoices of the petitioners nor

raise any dispute in accordance with the aforesaid clauses

of the PPAs. So also, even after filing of the present

petitions, the ESCOMs did not raise any dispute as regards

their obligation and liability to make payment and open

irrevocable and revolving letters of credit in favour of the

petitioners as per the PPAs; on the other hand, several

payments have been made by the ESCOMs in favour of

some of the petitioners during the pendency of the petitions

thereby admitting their duties, obligations and liabilities

under the PPAs.

(iv) Section 61 of the said Act of 2003, inter-alia,

requires the KERC to ensure that (a) generation,

transmission, distribution and supply of electricity are

conducted on commercial principles; (b) the factors which

would encourage competition, efficiency, economical use of

the resources, good performance, and optimum

investments are promoted; and (c) co-generation and

generation of electricity from renewable sources of energy

is promoted.

(v) In addition to the above, the PPA is approved by

the KERC under Regulation 21.4 of the KERC (Conditions

of license for ESCOMs) Regulations, 2004. The KERC

monitors the PPAs to ensure that the ESCOMs purchase

electrical capacity and/or energy in an efficient and

economical manner under a transparent power

procurement process, and in accordance with the principles

specified under Section 61 of the Act. Therefore, the PPA

has a statutory flavour and is not to be treated as a normal

commercial contract between the Parties.

(vi) The question with regard to the jurisdiction of this

Court to exercise its extraordinary jurisdiction under Article

226 of the Constitution of India in contractual matters in

relation to the PPAs entered into between the petitioners

and Respondent No.2-ESCOMs which is a 'State' within

the meaning of Article 12, is well settled by several

decisions of the Apex Court and this Court. In the case of

Century Spinning and Manufacturing Company Ltd. &

Ors. Vs The Ulhasnagar Municipal Council & Anr.-1970

(1) SCC 58, the Apex Court held as under:

" The High Court may, in exercise of its discretion, decline to ,exercise its extra-ordinary jurisdiction under Art. 226 of the Constitution. But the discretion is judicial : if the petition makes a claim which is frivolous, vexatious, or prima facie unjust, or may not appropriately be tried in a petition invoking extra-ordinary jurisdiction, the Court may decline to entertain the petition. But a party claiming to be aggrieved by the action of a public body or authority on the plea that the action is unlawful, high-handed, arbitrary or unjust, is entitled to a hearing of its petition on the merits. Apparently the petition filed by the Company did not raise any

complicated questions of fact for determination, -and the claim could not be characterised as frivolous, vexatious or unjust. The High Court has given no reasons for dismissing the petition in limine, and on a consideration of the averments in the petition and the materials placed before the Court we are satisfied that the Company was ,entitled to have its grievance against the action of the Municipality, which was prima facie unjust, tried."

(vii) In the case of ABL International Ltd. vs Export

Credit Guarantee Corpn. of India Ltd - (2004) 3 SCC

553, the Apex Court held as under;

" From the above discussion of ours, following legal principles emerge as to the maintainability of a writ petition :-

(a) In an appropriate case, a writ petition as against a State or an instrumentality of a State arising out of a contractual obligation is maintainable.

(b) Merely because some disputed questions of facts arise for consideration, same cannot be a ground to refuse to entertain a writ petition in all cases as a matter of rule.

(c) A writ petition involving a consequential relief of monetary claim is also maintainable.

(viii) In the case of Kumari Shrilekha Vidyarthi

vs State of U.P - (1991) 1 SCC 212, it was held as

under:

".......Applicability of Article 14 to all executive actions of the State being settled and for the same reason its applicability at the threshold to the making of a contract in exercise of the executive power being beyond dispute, can it be said that the State can thereafter cast off its personality and exercise unbridled power unfettered by the requirements of Article 14 in the sphere of contractual matters and claim to be governed therein only by private law principles applicable to private individuals whose rights flow only from the terms of the contract without anything more? We have no hesitation in saying that the personality of the State, requiring regulation of its conduct in all spheres by requirements of Article 14, does not undergo such a radical change after the making of a contract merely because some contractual rights accrue to the other party in addition. It is not as if the requirements of Article 14 and contractual obligations are alien concepts which cannot co-exist. The Preamble of the Constitution of India resolves to secure to all its citizens Justice, social. economic and political; and Equality of status and opportunity. Every State action must be aimed at achieving this goal. Part IV of the Constitution contains `Directives Principles of State Policy which are fundamental in the governance of the country and are aimed at securing social and economic freedoms by appropriate State action which is complementary to individual fundamental rights guaranteed in Part III for protection against excesses of State action to

realise the vision in the Preamble. This being the philosophy of the Constitution, can it be said that it contemplates exclusion of Article-14 non-arbitrariness which is basic to rule of law - from State actions in contractual field when all actions of the State are meant for public good and expected to be fair and just? We have no doubt that the Constitution does not envisage or permit unfairness or unreasonableness in State actions in any sphere of its activity contrary to the professed ideals in the Preamble. In our opinion. it would be alien to the Constitutional Scheme to accept the argument of exclusion of Article 14 in contractual matters. The scope and permissible grounds of judicial review in such matters and the relief which may be available are different matters but that does not justify the view of its total exclusion. This is more so when the modern trend is also to examine the unreasonableness of a term in such contracts where the bargaining power is unequal so that these are not negotiated contracts but standard form contracts between unequals.

There is an obvious difference in the contracts between private parties and contracts to which the State is a party, Private parties are concerned only with their personal interest whereas the State while exercising its powers and discharging its functions, acts indubitably, as is expected of it, for public good and in public interest. The impact of every State action is also on public interest. This factor alone is sufficient to import at least the minimal requirements

of public law obligations and impress with this character the contracts made by the State or its instrumentality. It is a different matter that the scope of judicial review in respect of disputes failing within the domain of contractual obligations may be more limited and in doubtful cases the parties may be relegated to adjudication of their rights by resort to remedies provided for adjudication of purely contractual disputes. However, to the extent, challenge is made on the ground of violation of Article 14 by alleging that the impugned act is arbitrary, unfair or unreasonable, the fact that the dispute also fails within the domain of contractual obligations would not relieve the State of its obligation to comply with the basic requirements of Article 14. To this extent, the obligation is of a public character invariably in every case irrespective of there being any other right or obligation in addition thereto. An additional contractual obligation cannot divest the claimant of the guarantee under Article 14 of non- arbitrariness at the hands of the State in any of its actions.

Thus, in a case like the present, if it is shown that the impugned State action is arbitrary and, therefore, violative of Article 14 of the Constitution, there can be no impediment in striking down the impugned act irrespective of the question whether an additional right, contractual or statutory, if any, is also available to the aggrieved persons.

The State cannot be attributed the sprit personality of Dr. Jekyll and Mr. Hyde in the contractual field so as to impress on it all the characteristics of the State at the threshold while making a contract requiring it to fulfil the obligation of Article 14 of the Constitution and thereafter permitting it to cast off its garb of State to adorn the new robe of a private body during the subsistence of the con- tract enabling it to act arbitrarily subject only to the contractual obligations and remedies flowing from it. It is really the nature of its personality as State which is significant and must characterize all its actions, in what- ever field, and not the nature of function, contractual or otherwise, which is decisive of the nature of scrutiny permitted for examining the validity of its act. The requirement of Article 14 being the duty to act fairly, justly and reasonably, there is nothing which militates against the concept of requiring the State always to so act, even in contractual matters. There is a basic difference between the acts of the State which must invariably be in public interest and those of a private individual, engaged in similar activities, being primarily for personal gain, which may or may not promote public interest. Viewed in this manner, in which we find no conceptual difficulty or anachronism, we find no reason why the requirement of Article 14 should not extend even in the sphere of contractual matters for regulating the conduct of the State activity.

...Unlike a private party whose acts uninformed by reason and influenced by personal predilections in contractual matters may result in adverse consequences to it alone without affecting the public interest, any such act of the State or a public body even in this field would adversely affect the public interest. Every holder of a public office by virtue of which he acts on behalf of the State or public body is ultimately accountable to the people in whom the sovereignty vests. As such, all powers so vested in him are meant to be exercised for public good and promoting the public interest. This is equally true of all actions even in the field of contract. Thus, every holder of a public office is a trustee whose highest duty is to the people of the country and, therefore, every act of the holder of a public office, irrespective of the label classifying that act, is in discharge of public duty meant ultimately for public good. With the diversification of State activity in a Welfare State requiring the State to discharge its wide-ranging functions even through its several instrumentalities, which requires entering into contracts also, it would be unreal and not pragmatic, apart from being unjustified to exclude contractual matters from the sphere of State actions required to be non-arbitrary and justified on the touchstone of Article 14.

Even assuming that it is necessary to import the concept of presence of some public element in a State action to attract Article 14 and permit judicial review, we have no hesitation in saying that the

ultimate impact of all actions of the State or a public body being undoubtedly on public interest, the requisite public element for this purpose is present also in contractual matters. We, therefore, find it difficult and unrealistic to exclude the State actions in contractual matters, after the contract has been made, from the purview of judicial review to test its validity on the anvil of Article 14.

....It is now too well-settled that every State action, in order to survive, must not be susceptible to the vice of arbitrariness which is the crux of Article 14 of the Constitution and basic to the rule of law, the system which governs us. Arbitrariness is the very negation of the rule of law. Satisfaction of this basic tests in every State action is sine qua lion tO its validity and in this respect, the State cannot claim comparison with a private individual even in the field of contract. This distinction between the State and a private individual in the field of contract has to be borne in the mind."

(ix) In its recent decision in the case of Uttar

Pradesh Power Transmission Corporation Limited v.

C.G Power and Industrial Solutions and Limited and

Anr - 2021 SCC OnLine SC 383, the Apex Court reiterated

that a writ petition is maintainable in contractual matters

even if the contract contains an arbitration

clause/agreement. Similarly, in the case of Unitech

Limited & Ors v. Telangana State Industrial

Infrastructure Corporation & Ors - 2021 SCC OnLine SC

99, it was held as under:

" However, to clear the ground, it is necessary to postulate that recourse to the jurisdiction under Article 226 of the Constitution is not excluded altogether in a contractual matter. A public law remedy is available for enforcing legal rights subject to well-settled parameters. 33 A two judge Bench of this Court in ABL International Ltd. v. Export Credit Guarantee Corporation of India7 [ABL International] analyzed a long line of precedent of this Court8 to conclude that writs under Article 226 are maintainable for asserting contractual rights against the state, or its instrumentalities, as defined under Article 12 of the Indian Constitution.....

This exposition has been followed by this Court, and has been adopted by three- judge Bench decisions of this Court in State of UP v. Sudhir Kumar9 and Popatrao Vynkatrao Patil v. State of Maharashtra10. The decision in ABL International, cautions that the plenary power under Article 226 must be used with circumspection when other remedies have been provided by the contract. But as a statement of principle, the jurisdiction under Article 226 is not excluded in contractual matters. (2004) 3 SCC 553 K.N. Guruswamy v. State of Mysore, AIR 1954 SC 592; Gujarat State Financial Corporation. v.

Lotus Hotels (P) Ltd, (1983) 3 SCC 379; Gunwant Kaur v. Municipal Committee, Bhatinda, (1969) 3 SCC 769 2020 Scconline SC 847 Civil Appeal 1600 of 2000 (Supreme Court of India) PART E Article 23.1 of the Development Agreement in the present case mandates the parties to resolve their disputes through an arbitration. However, the presence of an arbitration clause within a contract between a state instrumentality and a private party has not acted as an absolute bar to availing remedies under law. If the state instrumentality violates its constitutional mandate under Article 14 to act fairly and reasonably, relief under the plenary powers of the Article 226 of the Constitution would lie. This principle was recognized in ABL International......Therefore, while exercising its jurisdiction under Article 226, the Court is entitled to enquire into whether the action of the State or its instrumentalities is arbitrary or unfair and in consequence, in violation of Article 14. The jurisdiction under Article 226 is a valuable constitutional safeguard against an arbitrary exercise of state Harbanslal Sahnia v. Indian Oil Corporation Ltd., (2003) 2 SCC 107; Ram Barai Singh & Co. v. State of Bihar & Ors., (2015) 13 SCC 592 power or a misuse of authority. In determining as to whether the jurisdiction should be exercised in a contractual dispute, the Court must, undoubtedly eschew, disputed questions of fact which would depend upon an evidentiary determination requiring a trial. But equally, it is well-settled that the jurisdiction

under Article 226 cannot be ousted only on the basis that the dispute pertains to the contractual arena. This is for the simple reason that the State and its instrumentalities are not exempt from the duty to act fairly merely because in their business dealings they have entered into the realm of contract. Similarly, the presence of an arbitration clause does not oust the jurisdiction under Article 226 in all cases though, it still needs to be decided from case to case as to whether recourse to a public law remedy can justifiably be invoked.

(x) In the instant case, the material on record clearly

discloses that Respondent No.2-ESCOMs have not fulfilled,

discharged or honoured the obligations and duties cast

upon them under the PPAs; on the other hand, during the

pendency of the present petitions, some of the ESCOMs

have paid certain amounts towards the dues claimed by the

petitioners under their invoices. So also, the ESCOMs have

not raised any dispute with regard to their liability to make

payment or the entitlement of the petitioners under the

invoices in addition to not disputing their liability to open

revolving and irrevocable letters of credit in favour of the

petitioners as required under the PPAs. The material on

record and the rival contentions do not give rise to

disputed/complicated questions of fact or contentious

issues. As held by the Apex Court, the failure on the part of

the Respondent No.2-ESCOMs to fulfil, discharge and

honour their duties, obligations and liabilities under the

PPAs clearly establishes that the Respondent No.2-

ESCOMs are acting in an arbitrary, illegal, unfair,

unreasonable, unjust and irrational manner which is

violative of Article 14 of the Constitution of India warranting

interference by this Court in the present petitions. Under

these circumstances, in the facts of the case on hand, I am

of the considered opinion that the petitions are

maintainable.

Accordingly, Point No.1 is answered in favour of the

Petitioners by holding that the present petitions are

maintainable before this Court in the exercise of its

jurisdiction under Article 226 of the Constitution of India.

Re: Point No.2

(i) This point relates to maintainability of the petitions

in the light of dispute redressal mechanism contained in the

PPAs entered into between the petitioners and the

Respondent No.2-ESCOMs. As stated supra, Clause No.18

of the PPAs provide for resolution of disputes as per the

procedure provided therein. A perusal of Clause

No.18(Solar) and Clause No.10(Wind) of the PPAs will

indicate that the petitioners and the Respondent No.2-

ESCOMs have agreed to resolve disputes arising out of the

PPAs by amicable discussions/talks failing which the

parties would have to seek resolution of their disputes

before the KERC by way of arbitration or adjudication. It is

the contention of the ESCOMs that in view of the dispute

resolution mechanism contained in the PPAs, the present

petitions are not maintainable before this Court.

(ii) In this context, it is necessary to state that a

perusal of Clause No.18 of the PPAs will indicate that in

order to invoke the said clause, it is absolutely essential for

an actual dispute to exist between the petitioners and the

Respondent No.2-ESCOMs; in other words, existence of a

dispute is a sine-qua-non for the petitioners or the

ESCOMs to invoke the said clause and seek resolution as

per the procedure provided under Clause No.18(Solar) and

Clause No.10(Wind); it follows there from that in the

absence of any dispute, Clause No.18(Solar) and Clause

No.10(Wind) of the PPAs would not get attracted nor

become applicable and consequently, the question of the

parties invoking the said clause would not arise.

(iii) As stated supra, the material on record indicates

that though procedure prescribed in Clauses 10 and 13 of

the PPAs was followed and joint measurement/meter

readings were recorded in the presence of both petitioners

and Respondent No.2-ESCOMs pursuant to which the

petitioners had raised the subject invoices/bills and called

upon the Respondent No.2 to make payment and open

letters of credit, the Respondent No.2 did not fulfil,

discharge or comply with their contractual obligations and

duties under the PPAs; so also, the Respondent No.2 did

not raise or put forth any dispute with regard to any of the

invoices/bills as required in the aforesaid clauses and on

the other hand, the Respondent No.2 has made certain

payments to the petitioners, that too even after filing of the

present petitions. To put it differently, so long as the

Respondent No.2 did not raise any dispute with regard to

the bills/invoices of the petitioners or the liability of the

Respondent No.2 to make payment to the petitioners,

Clause No.18(Solar) and Clause No.10(Wind) of the PPAs

which provides for a dispute redressal mechanism neither

gets attracted nor is the said clause applicable/invocable by

the petitioner to seek redressal of their grievances. Under

these circumstances, in the absence of any dispute raised

by the Respondent No.2 with regard to any of the amounts

payable to the petitioners under the PPAs, it cannot be said

that the present petitions are not maintainable.

(iv) As stated supra, before either party has to take

steps to seek recourse to the dispute redressal mechanism

provided in the PPAs, it is essential that there exists a

dispute which requires to be resolved; the said dispute

redressal mechanism provides for resolution of disputes by

way of amicable settlement/adjudication/arbitration, as the

case may be, in accordance with the aforesaid Clause

No.18(Solar) and Clause No.10(Wind). It cannot be

gainsaid that dispute resolution by way of amicable

settlement/adjudication/arbitration presupposes existence

of a dispute raised by the Respondent No.2-ESCOMs. In

the case of Major (Retd) Inder Singh Rekhi v. Delhi

Development Authority (1988) 2 SCC 338, the Apex

Court has held that existence of a dispute necessarily

requires an assertion of claim by one party and the denial

of the claim by the other party; in the instant case, in the

absence of any dispute between the petitioner and

Respondent No.2 with regard to the PPAs, the contention

of the Respondent No.2 that the petitions are not

maintainable in view of the dispute resolution mechanism

contained in the PPAs is clearly devoid of merit.

Accordingly, Point No.2 is also answered in favour of

the petitioners by holding that the present petitions are

maintainable before this Court in the exercise of its

extraordinary jurisdiction under Article 226 of the

Constitution of India.

Re: Point No.3

(i) The Respondent No.2-ESCOMs have contended

that the petitions are not maintainable in view of the equally

efficacious and alternative remedy available to the

petitioners under Section 86(1)(f) of the Electricity Act,

2003. In order to appreciate this contention, it is necessary

to extract the said provision which reads as under:

"86. Functions of State Commission - (1) The State Commission shall discharge the following functions, namely:

(a) xxxxxxxxx

(b) xxxxxxxxx

(c) xxxxxxxxx

(d) xxxxxxxxx

(e) xxxxxxxx

(f) adjudicate upon the disputes between the licensees and generating companies and to refer any dispute for arbitration;"

(ii) Reliance is placed upon the aforesaid provision

by the Respondent No.2-ESCOMs in order to contend that

in the light of the remedy available to the petitioners to seek

redressal of their grievances before the KERC as provided

under Section 86(1)(f), the present petitions are not

maintainable. This contention urged on behalf of the

ESCOMs also completely ignores the specific usage of the

word, "dispute" in Section 86(1)(f); recourse to the remedy

available under this provision also presupposes existence

of a dispute between petitioner and the ESCOMs and in the

absence of any dispute in relation to the PPAs, the

question of the petitioner taking recourse to remedies of

adjudication or reference to arbitration by the KERC would

not arise.

(iii) A plain reading of Section 86(1)(f) will indicate

that in order to invoke the said provision, it is absolutely

essential for an actual dispute to exist between the

petitioners and the Respondent No.2-ESCOMs; in other

words, existence of a dispute is a sine-qua-non for the

petitioners to invoke the said provision and seek redressal

of their grievances; it follows there from that in the absence

of any dispute, Section 86(1)(f) would neither get attracted

nor become applicable in the facts of the instant case.

(iv) As stated supra, the material on record indicates

that though procedure prescribed in Clauses 10 and 13 of

the PPAs was followed and joint measurement/meter

readings were recorded in the presence of both petitioners

and Respondent No.2-ESCOMs pursuant to which the

petitioners had raised the subject invoices/bills and called

upon the Respondent No.2 to make payment and open

letters of credit, the Respondent No.2 did not fulfil,

discharge or comply with their contractual obligations and

duties under the PPAs; so also, the Respondent No.2 did

not raise or put forth any dispute with regard to any of the

invoices/bills as required in the aforesaid clauses and on

the other hand, the Respondent No.2 has made certain

payments to the petitioners, that too even after filing of the

present petitions. To put it differently, so long as the

Respondent No.2 did not raise any dispute with regard to

the bills/invoices of the petitioners or the liability of the

Respondent No.2 to make payment to the petitioners,

Section 86(1)(f) neither gets attracted nor is the said

provision applicable/invocable by the petitioner to seek

redressal of their grievances. Under these circumstances,

in the absence of any dispute raised by the Respondent

No.2 with regard to any of the amounts payable to the

petitioners under the PPAs, it cannot be said that the

present petitions are not maintainable.

(v) The judgement of the Hon'ble Supreme Court in

the case of Gujarat Urja Vikas Nigam Limited v. Essar

Power Ltd - (2008) 4 SCC 755 relied upon by the

Respondent No.2 pertains to the powers of the State

Electricity Regulatory Commission under Section 86 (1) of

the Electricity Act to refer disputes to arbitration. So also,

the judgement of the Apex Court in the case of State of

Gujarat v. Utility Users Welfare Association -(2018) 6

SCC 21 pertains to the nature of the functions of the State

Electricity Regulatory Commissions and the need for a

judicial member to possess legal qualifications and to

mandatorily be part of the State Electricity Regulatory

Commissions, to ensure that the adjudicatory functions of

the State Electricity Regulatory Commissions are duly

discharged; both these judgments are clearly inapplicable

to the facts of the instant case given the fact that no dispute

has arisen or been raised between the petitioner and

Respondent No.2-ESCOMs with regard their obligations

and liability to honour the terms and conditions of the

PPAs.

(vi) Similarly, the decision in the Gujarat Urja Vikas

Nigam Limited v. Solar Semiconductor Power

Company (India) Pvt Ltd. -(2017) 16 SCC 498 is also

inapplicable to the facts of the present case, as this

judgement pertains to the scope of inherent powers of the

State Commissions and does not limit the powers of this

Court under Article 226 of the Constitution of India. The

other judgements cited by the Respondent No.2 are

judgements of the Appellate Tribunal for Electricity which

set out the powers of the KERC, and cannot have a bearing

on the writ jurisdiction of this Court.

(vii) As stated supra, before either party has to take

steps to seek recourse to Section 86(1)(f), it is essential

that there exists a dispute which requires to be resolved;

the said provision provides for resolution of disputes by way

of adjudication/arbitration, as the case may be. As held by

the Apex Court in Major (Retd) Inder Singh Rekhi's

case(supra), existence of a dispute necessarily requires an

assertion of claim by one party and the denial of the claim

by the other party; in the instant case, in the absence of

any dispute between the petitioner and Respondent No.2

with regard to the PPAs, the contention of the Respondent

No.2 that the petitions are not maintainable in view of the

Section 86(1)(f) of the Electricity Act, 2003 is clearly devoid

of merit.

Accordingly, Point No.3 is also answered in favour of

the petitioners by holding that the present petitions are

maintainable before this Court in the exercise of its

extraordinary jurisdiction under Article 226 of the

Constitution of India.

Re: Point No.4

(i) The last question that arises for consideration is

with regard to the relief's sought for by the petitioners and

the orders to be passed/directions to be issued in the

petitions. As stated supra, petitioners seek directions to the

Respondent No.2-ESCOMs to pay the outstanding dues

covered under the subject bills/invoices to the petitioners as

well as continue to pay all the amounts in respect of the

bills/invoices raised by the petitioners in future also as per

the PPAs in addition to directions to be issued to open

irrevocable and revolving letters of credit in favour of the

petitioners towards the payments/dues payable by the

ESCOMs. In this context, learned Senior Counsel for the

petitioners submitted that in the interest of all power

generating companies as well as the public at large, it is

essential that general guidelines and suitable/appropriate

directions are issued to all the ESCOMs in the State of

Karnataka to honour, discharge and fulfil their obligations

and duties under the PPAs.

(ii) The material on record indicates that Respondent

No.2's failure to make payments to the Petitioners is a

consistent pattern which has led to a serious impediment

for the Petitioners to carry on their work. Respondent

No.2's failure to make payments in a timely manner has

serious ramifications on the Petitioners' ability to continue

to generate energy, which, needless to say, has a drastic

and large-scale impact on the generation and supply of

renewable energy. It cannot also be gainsaid that

Respondent No.2 collects and receives monies from

consumers for the supply of the energy generated by the

Petitioners and other power generating companies. It is

therefore in public interest and in the interest of preserving

energy reforms that necessary directions are to be issued

to Respondent No.2 to abide by the terms of the PPAs

thereby preventing it from casting aside its solemn

obligations under statutory contracts.

(iii) It is pertinent to point out that the Ministry of New

and Renewable Energy ("MNRE"), granted must-run status

to renewable energy projects vide Office Memorandum,

dated 1.4.2020. The MNRE, in its O.M., dated 1.4.2020,

further stated that the renewable energy generators were to

be paid their dues on time regardless of the Moratorium

granted by the Power Ministry to ESCOMs/Distribution

Licensees in the wake of Covid-19. The MNRE also issued

a letter, dated 6.4.2020, directing the ESCOMs/Distribution

Licensees pan India to open Letters of Credit as per the

terms of the PPA as this is a pan India issue.

(iv) The conduct of the Respondent No. 2 is also

directly contrary to Section 86(1) (e) which requires the

KERC to promote generation of electricity through

renewable sources of energy. The Respondent No.2 has a

duty to act in the object and spirit of Section 86(1) (e) and

aid the function of the KERC in promoting generation of

energy from renewable sources. In Unitech Limited's

case(supra), the Apex Court has also held that investors

who respond to the representations held out by the State

while investing in public projects are legitimately entitled to

assert that the representations must be fulfilled and to

enforce compliance with duties which have been

contractually assumed. It is therefore clear that appropriate

directions are to be issued to the ESCOMs to honour all

their obligations under the PPAs.

(v) Learned counsel for the ESCOMs submitted that

huge amounts due to the ESCOMs have not been paid by

Rural Local Bodies, Urban Local Bodies, State Government

dues, subsidy dues from farmers etc., and this has resulted

in the ESCOMs not being in a position to pay the dues to

the power generating companies including the Petitioners

on time. It is also submitted that in respect of some of the

petitioners, the ESCOMs have either already opened letters

of credit or renewed existing letters of credit; so also, the

ESCOMs have made payments to some of the petitioners

during the pendency of these petitions. Further, learned

counsel for the ESCOMs have also filed various Memos

along with documents in this regard. The said Memos,

documents and submissions of the learned counsel for the

ESCOMs are placed on record.

(vi) In view of the aforesaid facts and circumstances,

I am of the considered opinion that the petitioners are

entitled to the relief's sought for by them in the petitions and

consequently, Respondent No.2-ESCOMs are to be

directed to honour and discharge all their obligations and

liabilities under the PPAs including making payment of the

outstanding dues to the petitioners and to continue to make

timely and prompt payments henceforth in the future also

in; so also, the ESCOMs are to be directed to open / renew

irrevocable and revolving monthly letters of credit in favour

of the petitioners so as to ensure prompt, timely and regular

payments being made to the petitioners. Further, general

guidelines are also to be issued to all the ESCOMs in the

State of Karnataka to honour and discharge all their

obligations and liabilities under the PPAs entered into with

anyone including making payments, opening / renewing

letters of credit etc., in favour of all the power generators.

Accordingly, Point No.4 is answered in favour of the

petitioners by holding that the petitioners are entitled to the

relief's sought for in the petitions and necessary directions

and guidelines are to be issued to the ESCOMs.

9. In the result, I pass the following:

ORDER

(i) All the petitions are hereby allowed;

(ii) The Respondent No.2-ESCOMs in all the

petitions are directed to honour, discharge and fulfil their

duties, obligations and liabilities under the Power Purchase

Agreements(PPAs) entered into between the Petitioners

and Respondent No.2-ESCOMs;

(iii) The Respondent No.2-ESCOMs in all the

petitions are directed to pay and clear all the outstanding

dues payable by the ESCOMs in favour of the petitioners in

relation to all the bills/invoices of the petitioners as on date;

(iv) The Respondent No.2-ESCOMs in all the

petitions are also hereby directed to henceforth make

prompt, regular and timely payments in favour of the

petitioners without any delay in relation to all future

bills/invoices also;

(v) The Respondent No.2-ESCOMs in all the

petitions are also hereby directed to forthwith open / renew

monthly irrevocable letters of credit in terms of the PPAs in

favour of the petitioners for the purpose of enabling and

ensuring payments of all amounts due to the petitioners

from the ESCOMs;

GENERAL GUIDELINES TO BE ISSUED TO ALL ELECTRICITY SUPPLY COMPANIES(ESCOMS) AND THE STATE OF KARNATAKA

(i) All ESCOMs are directed to honour, discharge and

fulfil their duties, obligations and liabilities under the Power

Purchase Agreements(PPAs) entered into between the

Power Generators and ESCOMs;

(ii) All ESCOMs are directed to henceforth make

prompt, regular and timely payments in favour of the power

generators without any delay in relation to all future

bills/invoices of the power generators;

(iii) All ESCOMs are also hereby directed to forthwith

open / renew monthly irrevocable letters of credit in terms

of the PPAs in favour of the power generators for the

purpose of enabling and ensuring payments of all amounts

due to the power generators from the ESCOMs;

(iv) Registry is directed to send a copy of this order to

the following persons:-

a) The Karnataka Electricity Regulatory Commission,

Bengaluru.

b) All Electricity Supply Companies (ESCOMs) in

the entire State of Karnataka.

c) The Principal Secretary, Department of

Energy, State of Karnataka.

d) The Chief Secretary, State of Karnataka.

SD/-

JUDGE

Srl.

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter