Citation : 2021 Latest Caselaw 1935 Kant
Judgement Date : 21 April, 2021
COMAP. No.53 OF 2021
1
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 21ST DAY OF APRIL, 2021
PRESENT
THE HON'BLE MR. ABHAY S. OKA, CHIEF JUSTICE
AND
THE HON'BLE MR. JUSTICE SURAJ GOVINDARAJ
COMAP. No.53 OF 2021
BETWEEN:
CAPACITE INFRAPROJECTS LTD
A COMPANY LIMITED BY SHARES
HAVING ITS REGISTERED OFFICE AT
605-607, SHRIKANT CHAMBERS
PHASE-1, 6TH FLOOR, ADJACENT TO
R.K. STUDIOUS, SION-TROMBAY ROAD
CHEMBUR, MUMBAI - 400 070
ALSO AT: NO. 1112, 11TH FLOOR
BARTON CENTRE, MAHATMA GANDHI
ROAD, BENGALURU- 560 001
REP BY ITS AUTHORISED
SIGNATORY MR. GOVINDRAJAN M KONAR ... APPELLANT
(BY SRI. DHYAN CHINNAPPA, SENIOR COUNSEL FOR
SRI. SRINANDAN.K, ADVOCATE OF S.K. LAW CHAMBERS-PH)
AND:
1. M/S SIDDHA SHEKA DEVELOPERS LLP
A LIMITED LIABILITY PARTNERSHIP HAVING
ITS ADDRESS AT 1/1 NV HOUSE
1ST FLOOR, H-SIDDIAH ROAD
BENGALURU, KARNATAKA
INDIA
REP. BY ITS PARTNERS
2. UNION BANK OF INDIA
HAVING ITS BRANCH OFFICE AT
MID CORPORATE BRANCH, MUM(S)
COMAP. No.53 OF 2021
2
UNION BANK BHAVAN
39, VIDHAVAN BHAVAN MARG
NARIMAN POINT, MUMBAI - 400 021
REP. BY ITS MANAGING DIRECTOR ... RESPONDENTS
(BY SRI. UDAYA HOLLA, SENIOR COUNSEL FOR
SRI. SANJAY H. SETHIYA AND
MS. PRITHVI S. HEGDE, ADVOCATES OF
LAW SQUARE FOR C/R1-PH)
THIS APPEAL IS FILED UNDER SECTION 13(1A) OF THE
COMMERCIAL COURTS ACT, 2015 READ WITH SECTION 37(1)(B) OF
THE ARBITRATION AND CONCILIATION ACT, 1996 READ WITH
ORDER XLIII RULE 1(R) OF THE CPC 1908, PRAYING TO SET ASIDE
THE ORDER DATED 12.03.2021 PASSED BY THE LEARNED LXXXII
ADDITIONAL CITY CIVIL AND SESSIONS JUDGE, (COMMERCIAL
JUDGE) (CCH-83) AT BENGALURU IN COMM. A.A.NO.22/2020 VIDE
ANNEXURE-W AND I.A.NO.1, FILED BY THE APPELLANT AND
CONSEQUENTLY ALLOW IA.NO.1 AND THE SECTION 9
APPLICATION FILED UNDER THE ARBITRATION AND CONCILIATION
ACT, 1996 AND ETC.
*****
THIS APPEAL COMING ON FOR HEARING AND HAVING BEEN
RESERVED FOR ORDERS ON 05.04.2021, THIS DAY,
SURAJ GOVINDARAJ J., PRONOUNCED THE FOLLOWING:
JUDGMENT
1. The Appellant is before this Court seeking for
setting aside the order dated 12.03.2021 passed
by the learned LXXXII Additional City Civil and COMAP. No.53 OF 2021
Sessions Judge (Commercial Judge) (CCH-83),
Bangalore in Comm.A.A.No.22/2020 dismissing
I.A.No.1 filed by the Appellant under Section 9 of
the Arbitration and Conciliation Act, 1996 and
also seeking for allowing the said application.
2. The Appellant had filed A.A.No.22/2020 under
Section 9 of the Arbitration and Conciliation Act,
1996 seeking for an injunction restraining the
respondent No.1 either by itself or through its
agents, employees, officers, representatives,
consultants from taking any action, steps dealing
with encashing the Bank Guarantee No.49570
IGI 0029618 as also restraining respondent
No.2-Bank from honouring the Bank Guarantee
and ad-interim reliefs in respect thereto.
FACTS:
3. The Appellant, who was the applicant in A.A.No.22/2020 COMAP. No.53 OF 2021
3.1. Appellant who is a contractor who had been
awarded a contract for Rs.21,80,69,997/-
by Respondent No.1 on 12th December
2015 to carry out the civil work for the
purpose of construction of an apartment
building called 'Marquis' at Bull Temple
Road, Basavanagudi, Bangalore.
3.2. A letter of award was issued on 13th June
2016, mobilisation advance of 10% of the
contract value was agreed to be released to
the applicant in two tranches to facilitate
the applicant to perform the contract.
3.3. Clause 4.1 of the Letter of Award deals
with the mobilisation advance, which is
reproduced hereunder for easy reference:
"4.1. Mobilisation Advance: An interest-free recoverable Mobilisation Advance of 10% of the Contract Sum will be released to you in the following COMAP. No.53 OF 2021
trances against submission of equal amount of Bank Guarantees from reputed private banks.
The first tranche of 5% of Contract Sum shall be released on acceptance of Letter of Award by the Contractor and on submission of Bank Guarantee, amounting to 5% of Contract Sum i.e. Rs.1,09,03,500 valid till date of Virtual Completion.
The Second tranche of 5% of Contract Sum Rs.1,09,03,500 shall be released against submission of Bank Guarantee for equal amount and against successful mobilisation of Plant and Machinery.
4.2. Mobilisation Advance will be recovered from 3rd Running Account (RA) Bill on prorate basis and shall be recovered in total on or before 80% of work is completed." (emphasis supplied)
3.4. Respondent No.1 advanced a sum of
Rs.1,09,03,500/- as the first tranche of
mobilisation advance, which was secured
by the Appellant by way of two Bank
Guarantees dated 3rd March 2016 for a sum
of Rs.59,03,500/- and Rs.50,00,000/-, COMAP. No.53 OF 2021
which were initially valid till 29 th December
2016.
3.5. In October 2016, the second tranche of the
mobilisation advance of Rs.1,09,03,500/-
was advanced which was secured by Bank
Guarantee dated 13th October 2016 for a
sum of Rs.1,09,03,500/- issued by the
second respondent herein.
3.6. Subsequent thereto, apart from the Bank
Guarantee, independent performance Bank
Guarantee was also made available by the
Appellant to Respondent No. 1 for a sum of
Rs.43,60,000/-.
3.7. The Appellant commenced and continued
the work under the contract and raised
various Running Account Bills (RA Bills). In
the said RA Bills, a portion of the COMAP. No.53 OF 2021
mobilisation advance was deducted, and as
such, each time a Bank Guarantee was
extended. The amount covered under the
Bank Guarantee was progressively
reduced, taking into consideration the
amount adjusted.
3.8. In December 2019, certain disputes arose
between the Appellant and Respondent No.
1-employer. The parties agreed to reduce
the total value of the contract from
Rs.21,80,69,997 to Rs.13,96,00,000/- and
thereafter, the Appellant renewed the Bank
Guarantee on 31st December 2019 only for
a sum of Rs.56,28,324/-.
3.9. The Appellant contends that in February
2020 instead of making payment of the
balance amount due to the Appellant, COMAP. No.53 OF 2021
Respondent No. 1 invoked the mobilisation
Bank Guarantee, which came to be
informed by the Respondent No.2-Bank to
the Appellant and it is in such
circumstances that the Appellant filed the
above application in A.A.No.22/2020
seeking for aforesaid reliefs.
4. The Respondent No. 1-employer, on being
served with notice, entered appearance and filed
its objections contending that
4.1. The Respondent No. 1-employer has made
payments of several amounts from time to
time to the various suppliers of the
Appellant, labourers, sub-contractors,
electricity dues, etc.
4.2. The Appellant, instead of completing the
work by 31st March 2018, had demobilised COMAP. No.53 OF 2021
from the site in January 2020, all the men
and machinery were removed from the
site, and as such, the employer was
required to engage the services of another
contractor to complete the works allotted
to the Appellant.
4.3. On account of the demobilisation, the
Respondent No. 1-employer was left with
no option but to invoke the Bank
Guarantee provided by the Appellant
towards mobilisation advance paid by the
Respondent No. 1-employer.
4.4. The Respondent No.1-employer further
contended that the invocation of the Bank
Guarantee was proper and correct in terms
of the Bank Guarantee issued. The
Respondent No. 1-employer had all rights COMAP. No.53 OF 2021
to invoke and/or encash the Bank
Guarantee and, as such, sought for
dismissal of the application filed by the
Appellant.
5. The trial Court, on consideration of the matter,
vide its order dated 12th March 2021,
5.1. Dismissed the application on the ground
that the Bank Guarantee was unconditional
and irrevocable Bank Guarantee.
5.2. No injunction could be issued restraining
the invocation of the same. Though it has
been contended by the Appellant that only
a sum of Rs.14.17 lakhs remains to be
adjusted from mobilisation advance, the
Respondent No. 1 - employer had
contended that a sum of Rs.1,43,65,390/-
had been paid by Respondent No. 1 to COMAP. No.53 OF 2021
various suppliers and contractors of the
Appellant. Therefore, the invocation could
be made for the entire amount covered
under the Bank Guarantee.
5.3. There are no grounds made out by the
Appellant for grant of an injunction
restraining the invocation of the Bank
Guarantee. The Bank Guarantee being
unconditional, no injunction order could be
granted and as such, dismissed the
application.
5.4. It is aggrieved by the said order that the
Appellant is before this Court.
6. Sri. Dhyan Chinnappa learned Senior counsel
instructed by Sri. Srinandan K., learned counsel
appearing for the Appellant submitted that:
COMAP. No.53 OF 2021
6.1. The Bank Guarantee, which has been
issued in the present case, is only related
to the mobilisation advance issued by
Respondent No. 1-employer and does not
cover any aspect. If the Bank Guarantee
had to be invoked, it could have been only
invoked in respect of the balance due on
the head of account of mobilisation and
nothing more.
6.2. The unadjusted mobilisation advance
covered by the Bank Guarantee is only
Rs.14.17 lakhs. Therefore, the entire Bank
Guarantee could not have been enchased.
The contract value is for a sum of
Rs.21,80,69,997/- as regards which a sum
of Rs.2,18,04,000/- had been advanced
towards which the Bank Guarantee had
been issued. Subsequent to the adjustment COMAP. No.53 OF 2021
of the mobilisation advance from various
RA bills, the same came to be reduced. As
such, the only Bank Guarantee which was
in operation was for a sum of
Rs.56,28,324/-. The unadjusted
mobilisation advance being only
Rs.14,17,633/-, a Bank Guarantee for a
sum of Rs.56,28,324/- could not be
encashed.
6.3. The letter invoking the Bank Guarantee
does not indicate the amounts due by the
Appellant to Respondent No. 1-employer.
There is no mention of the amounts in the
said invocation letter. As such, invoking the
entire Bank Guarantee for a paltry amount
due is improper and, therefore, ought to be
injuncted. In this regard, he relies upon the
following decisions:
COMAP. No.53 OF 2021
6.3.1. Hindustan Construction Co. Ltd. v.
State of Bihar, (1999) 8 SCC 436, more particularly, Paras 9 and 21 thereof:
9. What is important, therefore, is that the bank guarantee should be in unequivocal terms, unconditional and recite that the amount would be paid without demur or objection and irrespective of any dispute that might have cropped up or might have been pending between the beneficiary under the bank guarantee or the person on whose behalf the guarantee was furnished. The terms of the bank guarantee are, therefore, extremely material. Since the bank guarantee represents an independent contract between the Bank and the beneficiary, both the parties would be bound by the terms thereof. The invocation, therefore, will have to be in accordance with the terms of the bank guarantee, or else, the invocation itself would be bad.
21. As pointed out above, bank guarantee constitutes a separate, distinct and independent contract. This contract is between the Bank and the defendants. It is independent of the main contract between HCCL and the defendants. Since the bank guarantee was furnished to the Chief Engineer and there is no definition of "Chief Engineer" in the bank guarantee nor is it provided therein that "Chief Engineer" would also include Executive Engineer, the bank guarantee could be invoked by none except the Chief Engineer. The invocation was thus wholly wrong and the Bank was under no obligation to pay the amount covered by COMAP. No.53 OF 2021
the "performance guarantee" to the Executive Engineer.
6.3.2. Standard Chartered Bank v. Heavy Engg. Corpn. Ltd., (2020) 13 SCC 574
23. The settled position in law that emerges from the precedents of this Court is that the bank guarantee is an independent contract between Bank and the beneficiary and the Bank is always obliged to honour its guarantee as long as it is an unconditional and irrevocable one. The dispute between the beneficiary and the party at whose instance the Bank has given the guarantee is immaterial and is of no consequence. There are, however, exceptions to this rule when there is a clear case of fraud, irretrievable injustice or special equities. The Court ordinarily should not interfere with the invocation or encashment of the bank guarantee so long as the invocation is in terms of the bank guarantee.
6.4. Though copies of several other decisions
have been produced, they have not been
relied on by the learned Senior counsel. He
limits his reliance on the aforesaid
decisions.
6.5. On the above basis, he submits that the
trial Court ought to have injuncted COMAP. No.53 OF 2021
Respondent No. 1-employer from invoking
the Bank Guarantee and second
respondent - Bank from honouring any
such invocation.
7. Sri. Udaya Holla learned Senior counsel
instructed by Sri. Sanjay H.Sethiya, learned
counsel appearing for Respondent No. 1-
employer would submit that
7.1. The Bank Guarantee which has been issued
is an unconditional Bank Guarantee.
Admittedly, there are disputes between the
parties as regards which the Appellant has
invoked the arbitration clause.
7.2. The Appellant has not completed the works
awarded to the Appellant; instead
demobilised its men and machinery from
the worksite. Hence, Respondent No. 1-
COMAP. No.53 OF 2021
employer was constrained to make
payment of various amounts of monies to
the suppliers/sub-contractors of the
Appellant, which Respondent No. 1-
employer is entitled to recover.
7.3. It is in this background that the Bank
Guarantee has been invoked by
Respondent No. 1-employer.
7.4. The entire reading of either the application
under Section 9 as also the present
memorandum of appeal would not indicate
any allegation of fraud as against the
employer-Respondent No. 1, and as such,
there is no embargo on the Respondent No.
1-employer from invoking the Bank
Guarantee. The Bank Guarantee being a
commercial instrument executed in favour COMAP. No.53 OF 2021
of Respondent No. 1-employer, Respondent
No. 1 could invoke the same which cannot
be injuncted by a Court of law. In this
regard, he relies upon the following
decisions:
7.4.1. U.P. Cooperative Federation Ltd., vs. Singh Consultants and Engineers (P) Ltd., (1988) 1 SCC 174, more particularly, Paras 21 and 35 thereof, which are reproduced hereunder for easy reference:
21. In the instant case, the learned Judge has proceeded on the basis that this was not an injunction sought against the Bank but this was the injunction sought against the Appellant. But the net effect of the injunction is to restrain the Bank from performing the bank guarantee. That cannot be done. One cannot do indirectly what one is not free to do directly. But a maltreated man in such circumstances is not remedyless. The respondent was not to suffer any injustice which was irretrievable. The respondent can sue the Appellant for damages. In this case, there cannot be any basis for apprehension that irretrievable damages would be caused if any. I am of the opinion that this is not a case in which injunction should be granted. An irrevocable commitment either in the form of confirmed bank guarantee or irrevocable letter of credit cannot be interfered with except in case of fraud or in case of question of apprehension of irretrievable injustice has been made out. This is the well settled principle of the law in COMAP. No.53 OF 2021
England. This is also a well settled principle of law in India, as I shall presently notice from some of the decisions of the High Court and decisions of this Court.
35. Mr. Tarkunde submitted before us that in this case the grievance of the Appellant was that there was delay in performance and defective machinery had been supplied. He submitted that if at this stage Appellant was allowed to enforce the bank guarantee, damage would be done. He submitted before us that Appellant could not be permitted to take advantage of illegality by invoking the bank guarantee. But in my opinion these contentions cannot deter us -- in view of the principle well settled that there should not be interference in trade. This is not a case where irretrievable injustice would be done by enforcement of bank guarantee. This is also not a case where a strong prima facie case of fraud in entering into a transaction was made out. If that is the position, then the High Court should not have interfered with the bank guarantee.
7.4.2. Vinitech Electronics Private Ltd vs. HCL Infosystems Ltd., (2008) 1 SCC 544 more particularly, Paras 11 and 12 thereof, which are reproduced hereunder for easy reference:
11. The law relating to invocation of bank guarantees is by now well settled by a catena of decisions of this Court. The bank guarantees which provided that they are payable by the guarantor on demand is considered to be an unconditional bank guarantee. When in the course of commercial dealings, unconditional guarantees have been given or accepted the beneficiary is entitled to realise such a bank guarantee in terms thereof irrespective of any pending disputes. In U.P. State Sugar COMAP. No.53 OF 2021
Corpn. v. Sumac International Ltd. this Court observed that: (SCC p. 574, para 12)
"12. The law relating to invocation of such bank guarantees is by now well settled. When in the course of commercial dealings an unconditional bank guarantee is given or accepted, the beneficiary is entitled to realise such a bank guarantee in terms thereof irrespective of any pending disputes. The Bank giving such a guarantee is bound to honour it as per its terms irrespective of any dispute raised by its customer. The very purpose of giving such a bank guarantee would otherwise be defeated. The courts should, therefore, be slow in granting an injunction to restrain the realisation of such a bank guarantee. The courts have carved out only two exceptions. A fraud in connection with such a bank guarantee would vitiate the very foundation of such a bank guarantee. Hence if there is such a fraud of which the beneficiary seeks to take advantage, he can be restrained from doing so. The second exception relates to cases where allowing the encashment of an unconditional bank guarantee would result in irretrievable harm or injustice to one of the parties concerned. Since in most cases payment of money under such a bank guarantee would adversely affect the Bank and its customer at whose instance the guarantee is given, the harm or injustice contemplated under this head must be of such an exceptional and irretrievable nature as would override the terms of the guarantee and the adverse effect of such an injunction on commercial dealings in the country. The two grounds are not necessarily connected, though both may coexist in some cases."
12. It is equally well settled in law that bank guarantee is an independent contract COMAP. No.53 OF 2021
between Bank and the beneficiary thereof. The Bank is always obliged to honour its guarantee as long as it is an unconditional and irrevocable one. The dispute between the beneficiary and the party at whose instance the Bank has given the guarantee is immaterial and of no consequence. In BSES Ltd. v. Fenner India Ltd. this Court held: (SCC pp. 733-34, para 10)
"10. There are, however, two exceptions to this rule. The first is when there is a clear fraud of which the Bank has notice and a fraud of the beneficiary from which it seeks to benefit. The fraud must be of an egregious nature as to vitiate the entire underlying transaction. The second exception to the general rule of non-intervention is when there are 'special equities' in favour of injunction, such as when 'irretrievable injury' or 'irretrievable injustice' would occur if such an injunction were not granted. The general rule and its exceptions has been reiterated in so many judgments of this Court this Court, correctly declared that the law was 'settled'."
7.4.3. BSES Ltd (Now Reliance Energy Ltd.) vs. Fenner India Ltd and Another (2006) 2 SCC 728 Paras 9 and 10 thereof, which are reproduced hereunder for easy reference:
The rule and its exceptions
9. Mr Rohatgi, learned Senior Counsel for the Appellant, urged that the settled law in this country is that a bank guarantee is an independent contract between the Bank and the beneficiary thereof. Accordingly, irrespective of any dispute between the beneficiary and the party at whose instance the Bank has given the guarantee, the Bank is obliged to honour its guarantee, as long as the guarantee is unconditional and COMAP. No.53 OF 2021
irrevocable. Our attention was drawn to the judgment of this Court in U.P. Coop. Federation Ltd. v. Singh Consultants and Engineers (P) Ltd.. It was pointed out in that case that a bank guarantee must be honoured in accordance with its terms as the Bank, which gives the guarantee, is not concerned with the relations between the supplier and the customer. Neither is the Bank concerned with the question whether any of them have failed in their contractual obligations or not. In other words, the Bank must pay according to the tenor of its guarantee, on demand, without proof or condition.
10. There are, however, two exceptions to this rule. The first is when there is a clear fraud of which the Bank has notice and a fraud of the beneficiary from which it seeks to benefit. The fraud must be of an egregious nature as to vitiate the entire underlying transaction. The second exception to the general rule of non-intervention is when there are "special equities" in favour of injunction, such as when "irretrievable injury" or "irretrievable injustice" would occur if such an injunction were not granted. The general rule and its exceptions has been reiterated in so many judgments of this Court, that in U.P. State Sugar Corpn. v. Sumac International Ltd., this Court, correctly declared that the law was "settled"
7.4.4. U.P.State Sugar Corporation vs. Sumac International Ltd, (1997)1 SCC 568. Paras 12 and 16 thereof, which are reproduced hereunder for easy reference:
12. The law relating to invocation of such bank guarantees is by now well settled. When in the course of commercial dealings an unconditional bank guarantee is given or COMAP. No.53 OF 2021
accepted, the beneficiary is entitled to realise such a bank guarantee in terms thereof irrespective of any pending disputes. The Bank giving such a guarantee is bound to honour it as per its terms irrespective of any dispute raised by its customer. The very purpose of giving such a bank guarantee would otherwise be defeated. The courts should, therefore, be slow in granting an injunction to restrain the realisation of such a bank guarantee. The courts have carved out only two exceptions. A fraud in connection with such a bank guarantee would vitiate the very foundation of such a bank guarantee. Hence if there is such a fraud of which the beneficiary seeks to take advantage, he can be restrained from doing so. The second exception relates to cases where allowing the encashment of an unconditional bank guarantee would result in irretrievable harm or injustice to one of the parties concerned. Since in most cases payment of money under such a bank guarantee would adversely affect the Bank and its customer at whose instance the guarantee is given, the harm or injustice contemplated under this head must be of such an exceptional and irretrievable nature as would override the terms of the guarantee and the adverse effect of such an injunction on commercial dealings in the country. The two grounds are not necessarily connected, though both may coexist in some cases. In the case of U.P. Coop. Federation Ltd. v. Singh Consultants and Engineers (P) Ltd. which was the case of a works contract where the performance guarantee given under the contract was sought to be invoked, this Court, after referring extensively to English and Indian cases on the subject, said that the guarantee must be honoured in accordance with its terms. The Bank which gives the guarantee is not COMAP. No.53 OF 2021
concerned in the least with the relations between the supplier and the customer; nor with the question whether the supplier has performed his contractual obligation or not, nor with the question whether the supplier is in default or not. The Bank must pay according to the tenor of its guarantee on demand without proof or condition. There are only two exceptions to this rule. The first exception is a case when there is a clear fraud of which the Bank has notice. The fraud must be of an egregious nature such as to vitiate the entire underlying transaction. Explaining the kind of fraud that may absolve a bank from honouring its guarantee, this Court in the above case quoted with approval the observations of Sir John Donaldson, M.R. in Bolivinter Oil SA v. Chase Manhattan Bank (All ER at p. 352): (at SCC p. 197)
"The wholly exceptional case where an injunction may be granted is where it is proved that the Bank knows that any demand for payment already made or which may thereafter be made will clearly be fraudulent. But the evidence must be clear both as to the fact of fraud and as to the Bank's knowledge. It would certainly not normally be sufficient that this rests on the uncorroborated statement of the customer, for irreparable damage can be done to a bank's credit in the relatively brief time which must elapse between the granting of such an injunction and an application by the Bank to have it charged."
This Court set aside an injunction granted by the High Court to restrain the realisation of the bank guarantee.
16. Clearly, therefore, the existence of any dispute between the parties to the COMAP. No.53 OF 2021
contract is not a ground for issuing an injunction to restrain the enforcement of bank guarantees. There must be a fraud in connection with the bank guarantee. In the present case we fail to see any such fraud. The High Court seems to have come to the conclusion that the termination of the contract by the Appellant and his claim that time was of the essence of the contract, are not based on the terms of the contract and, therefore, there is a fraud in the invocation of the bank guarantee. This is an erroneous view. The disputes between the parties relating to the termination of the contract cannot make invocation of the Bank guarantees fraudulent. The High Court has also referred to the conduct of the Appellant in invoking the bank guarantees on an earlier occasion on 12-4-1992 and subsequently withdrawing such invocation. The Court has used this circumstance in aid of its view that the time was not of the essence of the contract. We fail to see how an earlier invocation of the bank guarantees and subsequent withdrawal of this invocation make the bank guarantees or their invocation tainted with fraud in any manner. Under the terms of the contract it is stipulated that the respondent is required to give unconditional bank guarantees against advance payments as also a similar bank guarantee for due delivery of the contracted plant within the stipulated period. In the absence of any fraud the Appellant is entitled to realise the bank guarantees.
7.4.5. Himadri Chemicals Industries Limited vs. Coal Tar Refining Co., (2007) 8 SCC 110 more particularly, Paras 11 and 13 thereof, which are reproduced hereunder for easy reference:
11. Except under these circumstances, the courts should not readily issue injunction COMAP. No.53 OF 2021
to restrain the realisation of a bank guarantee or a letter of credit. So far as the first exception is concerned i.e. of fraud, one has to satisfy the Court that the fraud in connection with the bank guarantee or letter of credit would vitiate the very foundation of such a bank guarantee or letter of credit. So far as the second exception is concerned, this Court has held in that decision that it relates to cases where allowing encashment of an unconditional bank guarantee would result in irretrievable harm or injustice to one of the parties concerned. While dealing with the case of fraud, this Court in U.P. Coop. Federation Ltd. v. Singh Consultants and Engineers (P) Ltd. held as follows: (SCC p. 197, para 53)
The fraud must be of an egregious nature such as to vitiate the entire underlying transaction.
(emphasis supplied)
While coming to a conclusion as to what constitutes fraud, this Court in the above case quoted (at SCC p. 197, para 54) with approval the observations of Sir John Donaldson, M.R. in Bolivinter Oil SA v. Chase Manhattan Bank, All ER at p. 352g-h which is as follows:
"The wholly exceptional case where an injunction may be granted is where it is proved that the Bank knows that any demand for payment already made or which may thereafter be made will clearly be fraudulent. But the evidence must be clear, both as to the fact of fraud and as to the Bank's knowledge. It would certainly not normally be sufficient that this rests on the uncorroborated statement of the customer, for irreparable damage can be done to a COMAP. No.53 OF 2021
bank's credit in the relatively brief time which must elapse between the granting of such an injunction and an application by the Bank to have it discharged."
(emphasis supplied)
13. So far as the second exception is concerned, this Court in U.P. State Sugar Corpn. v. Sumac International Ltd. as considered herein earlier, at SCC para 14 on pp. 575-76 observed as follows:
"14. On the question of irretrievable injury which is the second exception to the rule against granting of injunctions when unconditional bank guarantees are sought to be realised the Court said in the above case that the irretrievable injury must be of the kind which was the subject-matter of the decision in Itek Corpn. case. In that case an exporter in USA entered into an agreement with the Imperial Government of Iran and sought an order terminating its liability on stand by letters of credit issued by an American bank in favour of an Iranian bank as part of the contract. The relief was sought on account of the situation created after the Iranian revolution when the American Government cancelled the export licences in relation to Iran and the Iranian Government had forcibly taken 52 American citizens as hostages. The US Government had blocked all Iranian assets under the jurisdiction of United States and had cancelled the export contract. The Court upheld the contention of the exporter that any claim for damages against the purchaser if decreed by the American courts would not be executable in Iran under these circumstances and realisation of the bank guarantee/letters of credit would cause irreparable harm to the plaintiff. This contention was upheld. To avail COMAP. No.53 OF 2021
of this exception, therefore, exceptional circumstances which make it impossible for the guarantor to reimburse himself if he ultimately succeeds, will have to be decisively established. Clearly, a mere apprehension that the other party will not be able to pay, is not enough. In Itek case there was a certainty on this issue. Secondly, there was good reason, in that case for the Court to be prima facie satisfied that the guarantors i.e. the Bank and its customer would be found entitled to receive the amount paid under the guarantee."
(emphasis supplied)
7.4.6. Daewoo Motors India Ltd. v. Union of India (2003) 4 SCC 690 more particularly, Paras 10 and 13 thereof, which are reproduced hereunder for easy reference:
10. It is too well settled a proposition to admit of detailed reasoning that for encashment of bank guarantee, the Bank cannot have any valid resistance, except, of course, in a case of fraud. The clause in the bank guarantee, on which Mr Chidambaram relies, reads as under:
"We, Times Bank Ltd., PTI Building, Parliament Street, New Delhi 110 001 do hereby unconditionally and irrevocably agree to pay the President of India on demand without any demur or protest the amount due and payable under the abovesaid bond not exceeding Rs 4,80,00,000 (Rupees four crores eighty lakhs only) by way of loss or damage caused or suffered by the President of India by reason of non-fulfilment of the export obligation under the abovesaid notification or by reason of any breach of any of the terms and conditions of the COMAP. No.53 OF 2021
abovesaid bond by M/s daewoo motors india limited."
13. From a perusal of the above clauses, it is abundantly clear that the bank guarantee furnished by the Bank is an unconditional and absolute bank guarantee. The Bank has rendered itself liable to pay the cash on demand by the President of India "notwithstanding any dispute raised by M/s Daewoo Motors India Limited in any proceeding before any court or tribunal". It is worth noticing that the clause in the bank guarantee specifically provides that the demand made by the President of India shall be conclusive as regards the amount due and payable by the Bank under this guarantee and the liability under the guarantee is absolute and unequivocal. In the face of the clear averments, it is trite to contend that the bank guarantee is a conditional bank guarantee. Therefore, the Bank has no case to resist the encashment of the bank guarantee. Inasmuch as we have held that the bank guarantee is an unconditional bank guarantee, the case of Hindustan Construction Co. Ltd. v. State of Bihar is of no avail to the Appellant.
7.5. In the case of 'Hindustan Construction'
(supra), the Bank Guarantee was not an
unconditional Bank Guarantee whereas in
the present case, it is unconditional Bank
Guarantee and as such, he submits that
the dicta of the Apex Court in 'Hindustan COMAP. No.53 OF 2021
Construction' (supra) would not be
applicable to the present facts and
circumstances.
7.6. On the above grounds, he submits that the
order passed by the trial Court is just and
proper and does not require any
interference.
8. Heard Sri. Dhyan Chinnappa learned Senior
counsel instructed by Sri. Srinandan K., learned
counsel appearing for the Appellant and Sri.
Udaya Holla learned Senior counsel instructed by
Sri. Sanjay H.Sethiya learned counsel appearing
for the Respondent No. 1 - employer.
Respondent No.2 being a formal party, notice
has been dispensed with.
COMAP. No.53 OF 2021
9. On the basis of the submission made by both the
counsel and the documents on record, the points
that would arise for our determination are:
9.1. Whether the Appellant had made out a case for grant of injunction restraining the invocation of the mobilisation advance Bank Guarantee?
9.2. Whether the order of the trial court suffers from any infirmity requiring interference by this Court?
9.3. What order?
10. Answer to Point No.1: Whether the Appellant had made out a case for grant of injunction restraining the invocation of the mobilisation advance Bank Guarantee?
10.1. The facts and contentions of the Appellant
are stated hereinabove. Suffice it to say
that according to the Appellant,
mobilisation advance remaining to be
adjusted was only a sum of Rs.14,17 lakhs
and Bank Guarantee for a sum of COMAP. No.53 OF 2021
Rs.56,28,324/- could not be encashed. It is
further contended that mobilisation Bank
Guarantee could only be invoked insofar as
remaining unadjusted mobilisation advance
and therefore, invocation ought to have
been only restricted to the said amount.
10.2. Admittedly, the contract as initially
awarded was for a sum of
Rs.21,80,69,997/- as regards which the
mobilisation advance for a sum of
Rs.2,18,04,000/- had been advanced which
had been secured by the Bank Guarantees.
Subsequent thereto, under various RA bills,
the amounts advanced as mobilisation
advance was deducted in RA bills, and as
such, on 13.12.2019, the Bank Guarantee
was renewed only for a sum of
Rs.56,28,324/-.
COMAP. No.53 OF 2021
10.3. The Bank Guarantee as issued in the year
2016 continues to be in force, and no
particular amount has been adjusted. The
only dispute now remaining is that
according to the Appellant, the amount due
is only Rs.14,17,633/- on account of
mobilisation advance, whereas Respondent
No. 1-employer contends that the entire
Bank Guarantee could be encashed by
Respondent No. 1.
10.4. The contention of the Appellant is that as of
the date of the invocation, only an amount
of Rs.14.17 lakhs remains to be adjusted,
and the entire Bank Guarantee could not
have been invoked and encashed.
10.5. Per contra, the contention of Sri. Udaya
Holla, learned Senior Counsel appearing for COMAP. No.53 OF 2021
Respondent No. 1, is that the Bank
Guarantee had been invoked in a proper
and required manner, and neither the Bank
nor the Appellant can contend that the
Bank Guarantee cannot be invoked. The
Bank Guarantee being a commercial
document, has to be given a commercial
meaning. The purpose of issuance of a
Bank Guarantee will be defeated if an
injunction is granted restraining the
invocation of the Bank Guarantee.
10.6. Sri. Dhyan Chinnappa, learned Senior
counsel, has relied upon the Hindustan
Construction's case (supra) to contend
that invocation of the Bank Guarantee has
to be made in a manner provided under the
Bank Guarantee. If the same is not done in
that particular manner, then the invocation COMAP. No.53 OF 2021
is held to be bad and requires to be set
aside. He has also relied upon the decision
of the Apex Court in the case of Standard
Chartered Bank (supra) to contend that
even as regards invocation of Bank
Guarantee, an injunction order could be
granted.
10.7. Sri. Udaya Holla learned Senior counsel by
relying upon the decision in the case of
Daewoo Motors (supra) has contended
that the Hindustan Construction's case is
not applicable to the present facts since, in
Hindustan Construction's case, the Bank
Guarantee was not an unconditional Bank
Guarantee whereas in the present case is
an unconditional Bank Guarantee. Be that
as it may, he submits that the respondent
has invoked the Bank Guarantee in terms COMAP. No.53 OF 2021
of the said Bank Guarantee. Therefore,
even on facts, the Hindustan
Construction case is not applicable to the
present facts. He has also relied upon
several other decisions extracted
hereinabove that there cannot be an
injunction restraining the invocation of the
Bank Guarantee. It is in the above facts
that the present point needs to be
considered.
10.8. Admittedly, there was a contract entered
into between the Appellant as the
Contractor and the respondent as an
employer for a value of Rs.21,80,69,997/-.
In the said contract, an amount equivalent
to 10% of the contract value was released
as mobilisation advance to the Appellant
amounting to Rs.2,18,04,000/-. Thereafter, COMAP. No.53 OF 2021
a portion of the mobilisation advance was
adjusted from time to time under various
Running Account bills. Though initially Bank
Guarantee had been issued for a sum of
Rs.2,18,04,000/-, subsequently on 31st
December 2019, an amount under the
Bank Guarantee was reduced to
Rs.56,28,324/-. It is only thereafter the
disputes commenced between the
Appellant and the respondent and the Bank
Guarantee was invoked by the respondent.
10.9. In view of the above, it is clear that until
the date of issuance of the Bank
Guarantee, the amount adjusted have
already been taken into consideration while
issuing the Bank Guarantee. Though it is
contended that the amounts due as on the
date of the invocation of the Bank COMAP. No.53 OF 2021
Guarantee on account of the mobilisation
advance is less than that covered by the
Bank Guarantee, the same cannot be
adjudicated by a Court of law at the
interlocutory stage. The same can only be
adjudicated after trial. Even if the Bank
Guarantee is invoked for a higher amount
than what is due, the same could always be
adjudicated and appropriate orders can be
passed after trial.
10.10. It is not the case of the Appellant that
fraud is played by the respondent. The only
case of the Appellant is that the amount
actually due is less than that covered by
the Bank Guarantee. The issuance of the
Bank Guarantee is also not in dispute.
COMAP. No.53 OF 2021
10.11. We are of the considered opinion that the
Bank Guarantee is required to be paid on
demand, it being the foundation of the
commercial dealings and/or commercial
contracts, any injunction restraining the
invocation of the Bank Guarantee would
have a cascading negative effect on
business transactions. The purpose of
issuance of a Bank Guarantee is that the
same may be invoked by the person to
whom it is issued and the Bank is required
to honour the same. Any dispute as such
between the parties can neither be decided
by the Bank nor by any Court in
interlocutory proceedings.
10.12. In the present case, admittedly, the
disputes between the parties are being
referred to Arbitration, Arbitration clause COMAP. No.53 OF 2021
already having been invoked. Any and all
contentions of the Appellant as regards the
wrongful or improper invocation of the
Bank Guarantee can be adjudicated by the
Arbitrator as and when appointed.
10.13. The only exception for invocation of the
Bank Guarantee being "fraud" and the
same not even having been raised in the
present matter, we find no reason to
injunct the invocation of the Bank
Guarantee.
10.14. Hence, we answer Point No.1 by holding
that the Appellant has not made out a case
for grant of injunction restraining the
invocation of the mobilisation advance
Bank Guarantee.
COMAP. No.53 OF 2021
11. Answer to Point No.2: Whether the order of the trial court suffers from any infirmity requiring interference by this Court?
11.1. The trial Court has considered all the above
aspects in its well-reasoned order. The trial
Court having taken into consideration that
the Bank Guarantee was unconditional one,
there being amounts due on the part of the
Appellant to the respondent, as on the date
of the invocation of the Bank Guarantee,
the Bank Guarantee was valid and
subsisting has refused the order of
injunction as sought for by the Appellant.
11.2. We find no reason to interfere with the
well-reasoned order passed by the trial
Court.
11.3. Hence, we answer Point No.2 by holding
that the order passed by the trial Court COMAP. No.53 OF 2021
does not suffer from any infirmity requiring
interference by this Court.
12. Answer to Point No.3: What order?
12.1. In the result, the above appeal stands dismissed. No costs.
Sd/-
CHIEF JUSTICE
Sd/-
JUDGE
Prs* COMAP. No.53 OF 2021
CJ & SGRJ: COMAP No.53/2021 21.04.2021
ORDER
1. After the judgment was pronounced in open Court, the
learned counsel appearing for the appellant submitted
that the appellant is ready to deposit the entire amount
covered by the Bank Guarantee and prays for extension
of the interim order passed earlier to enable the
appellant to approach the Apex Court.
2. In view of the said submission made, the operation of
the interim order passed earlier is extended by a period
of four weeks from today subject to deposit being made
by the appellant of the entire amount covered by the
Bank Guarantee within one week from today.
3. Needless to state that if the amount is not deposited
within one week from today, this order of extension of
the interim order will stand automatically vacated.
COMAP. No.53 OF 2021
4. As and when the amount is deposited, the Registry to
deposit the same in a Fixed Deposit in any of the
Nationalised Banks in the name of the Court and renew
it from time to time until further orders.
5. Since this order has been passed in the presence of
both the learned counsel, there is no need for receipt of
certified copy of the order for due compliance.
Sd/-
CHIEF JUSTICE
Sd/-
JUDGE
bkv*
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!