Thursday, 07, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Anvil Energy Private Limited (Formerly ... vs Jharkhand Bijli Vitran Nigam Limited
2026 Latest Caselaw 2005 Jhar

Citation : 2026 Latest Caselaw 2005 Jhar
Judgement Date : 17 March, 2026

[Cites 5, Cited by 0]

Jharkhand High Court

Anvil Energy Private Limited (Formerly ... vs Jharkhand Bijli Vitran Nigam Limited on 17 March, 2026

Author: Rajesh Shankar
Bench: Rajesh Shankar
                                                          2026:JHHC:7222-DB




IN THE HIGH COURT OF JHARKHAND AT RANCHI
              W.P.(C) No.1601 of 2026
                           -----

Anvil Energy Private Limited (formerly known as Anvil Cables Private Limited), having its registered office at 102, Krishna, 224 A.J.C. Bose Road, Kolkata-700017, through its Authorized Signatory, Mr. Jay Prakash Mishra, son of Birendra Kumar Mishra, resident of F3-25C/1 New Haujpur Link Road, P.O. Maheshtala, P.S. Haujpur, District Kolkata-700141.

.......... Petitioner.

-Versus-

1. Jharkhand Bijli Vitran Nigam Limited, through its Chairman-cum- Managing Director, having its office at Engineering Building, HEC, Dhurwa, Ranchi-834002.

2. General Manager (RP), Jharkhand Bijli Vitran Nigam Limited, having its office at Engineering Building, HEC, Dhurwa, Ranchi- 834002.

3. Chief Engineer, Rural Electrification, Jharkhand Bijli Vitran Nigam Limited, having its office at Engineering Building, HEC, Dhurwa, Ranchi-834002.

4. Electrical Superintending Engineer, Electric Supply Circle, JBVNL, Garhwa, P.O., P.S. & District Garhwa-822124.

.......... Respondents.

-----

With

-----

M/s. Sri Gopikrishna Infrastructure Private Limited, having its registered office at 30/B Vengal Rao Nagar, P.O. & P.S. S. R. Nagar, District Hyderabad-500038, through its Authorized Signatory-cum- Manager (Accounts), Mr. Shamshad Ali, son of Late Md. Shafiullah, resident of Raza Colony, Kanta Toli, P.O. G.P.O., P.S. Lower Bazar, District Ranchi-834001.

.......... Petitioner.

-Versus-

1. Jharkhand Bijli Vitran Nigam Limited, through its Chairman-cum- Managing Director, having its office at Engineering Building, HEC, Dhurwa, Ranchi-834002.

2. General Manager (RP), Jharkhand Bijli Vitran Nigam Limited, having its office at Engineering Building, HEC, Dhurwa, Ranchi- 834002.

3. Chief Engineer, Rural Electrification, Jharkhand Bijli Vitran Nigam Limited, having its office at Engineering Building, HEC, Dhurwa, Ranchi-834002.

4. Electrical Superintending Engineer, Electric Supply Circle, Garhwa, P.O., P.S. & District Garhwa-822114.

.......... Respondents.

-----

With

-----

2026:JHHC:7222-DB

M/s. Sri Gopikrishna Infrastructure Private Limited, having its registered office at 30/B Vengal Rao Nagar, P.O. & P.S. S. R. Nagar, District Hyderabad-500038, through its Authorized Signatory-cum- Manager (Accounts), Mr. Shamshad Ali, son of Late Md. Shafiullah, resident of Raza Colony, Kanta Toli, P.O. G.P.O., P.S. Lower Bazar, District Ranchi-834001.

.......... Petitioner.

-Versus-

1. Jharkhand Bijli Vitran Nigam Limited, through its Chairman-cum- Managing Director, having its office at Engineering Building, HEC, Dhurwa, Ranchi-834002.

2. General Manager (RP), Jharkhand Bijli Vitran Nigam Limited, having its office at Engineering Building, HEC, Dhurwa, Ranchi- 834002.

3. Chief Engineer, Rural Electrification, Jharkhand Bijli Vitran Nigam Limited, having its office at Engineering Building, HEC, Dhurwa, Ranchi-834002.

4. Electrical Superintending Engineer, Electric Supply Circle, Deoghar, P.O., P.S. & District Deoghar-814112.

.......... Respondents.

-----

With

-----

M/s. Sri Gopikrishna Infrastructure Private Limited, having its registered office at 30/B Vengal Rao Nagar, P.O. & P.S. S. R. Nagar, District Hyderabad-500038, through its Authorized Signatory-cum- Manager (Accounts), Mr. Shamshad Ali, son of Late Md. Shafiullah, resident of Raza Colony, Kanta Toli, P.O. G.P.O., P.S. Lower Bazar, District Ranchi-834001.

.......... Petitioner.

-Versus-

1. Jharkhand Bijli Vitran Nigam Limited, through its Chairman-cum- Managing Director, having its office at Engineering Building, HEC, Dhurwa, Ranchi-834002.

2. General Manager (RP), Jharkhand Bijli Vitran Nigam Limited, having its office at Engineering Building, HEC, Dhurwa, Ranchi- 834002.

3. Chief Engineer, Rural Electrification, Jharkhand Bijli Vitran Nigam Limited, having its office at Engineering Building, HEC, Dhurwa, Ranchi-834002.

4. Electrical Superintending Engineer, Electric Supply Circle, Deoghar, P.O., P.S. & District Deoghar-814112.

.......... Respondents.

-----

With

-----

M/s. Anvil Cables Private Limited, having its registered office at 102, Krishna, 224 A.J.C. Bose Road, Kolkata-700017, through its Assistant Manager-cum-Authorized Signatory, Mr. Jay Prakash

2026:JHHC:7222-DB

Mishra, son of Birendra Kumar Mishra, resident of F3-25C/1 New Haujpur Link Road, P.O. Maheshtala, P.S. Haujpur, District Kolkata- 700141.

.......... Petitioner.

-Versus-

1. Jharkhand Bijli Vitran Nigam Limited, through its Chairman-cum- Managing Director, having its office at Engineering Building, HEC, Dhurwa, Ranchi-834002.

2. General Manager (RP), Jharkhand Bijli Vitran Nigam Limited, having its office at Engineering Building, HEC, Dhurwa, Rannchi- 834002.

3. Chief Engineer, Rural Electrification, Jharkhand Bijli Vitran Nigam Limited, having its office at Engineering Building, HEC, Dhurwa, Ranchi-834002.

4. Electrical Superintending Engineer, Electric Supply Circle, Deoghar, P.O., P.S. & District Deoghar-814112.

.......... Respondents.

-----

With

-----

M/s. Sri Gopikrishna Infrastructure Private Limited, having its registered office at 30/B Vengal Rao Nagar, P.O. & P.S. S. R. Nagar, District Hyderabad-500038, through its Authorized Signatory-cum- Manager (Accounts), Mr. Shamshad Ali, son of Late Md. Shafiullah, resident of Raza Colony, Kanta Toli, P.O. G.P.O., P.S. Lower Bazar, District Ranchi-834001.

.......... Petitioner.

-Versus-

1. Jharkhand Bijli Vitran Nigam Limited, through its Chairman-cum- Managing Director, having its office at Engineering Building, HEC, Dhurwa, Ranchi-834002.

2. General Manager (RP), Jharkhand Bijli Vitran Nigam Limited, having its office at Engineering Building, HEC, Dhurwa, Ranchi- 834002.

3. Chief Engineer, Rural Electrification, Jharkhand Bijli Vitran Nigam Limited, having its office at Engineering Building, HEC, Dhurwa, Ranchi-834002.

4. Electrical Superintending Engineer, Electric Supply Circle, Jharkhand Bijli Vitran Nigam Limited, Garhwa, P.O., P.S. & District Garhwa-822114.

.......... Respondents.

-----

With

-----

M/s. Sri Gopikrishna Infrastructure Private Limited, having its registered office at 30/B Vengal Rao Nagar, P.O. & P.S. S. R. Nagar, District Hyderabad-500038, through its Authorized Signatory-cum- Manager (Accounts), Mr. Shamshad Ali, son of Late Md. Shafiullah,

2026:JHHC:7222-DB

resident of Raza Colony, Kanta Toli, P.O. G.P.O., P.S. Lower Bazar, District Ranchi-834001.

.......... Petitioner.

-Versus-

1. Jharkhand Bijli Vitran Nigam Limited, through its Chairman-cum- Managing Director, having its office at Engineering Building, HEC, Dhurwa, Ranchi-834002.

2. General Manager (RP), Jharkhand Bijli Vitran Nigam Limited, having its office at Engineering Building, HEC, Dhurwa, Ranchi- 834002.

3. Chief Engineer, Rural Electrification, Jharkhand Bijli Vitran Nigam Limited, having its office at Engineering Building, HEC, Dhurwa, Ranchi-834002.

4. Electrical Superintending Engineer, Electric Supply Circle, JBVNL, Garhwa, P.O., P.S. & District Garhwa-822114.

.......... Respondents.

-----

     CORAM :           HON'BLE THE CHIEF JUSTICE
                   HON'BLE MR. JUSTICE RAJESH SHANKAR
                                -----
     For the Petitioners :       Mr. M. S. Mittal, Sr. Advocate
                                 Mr. Salona Mittal, Advocate
     For the Respondents:        Mr. Sachin Kumar, Advocate
                                 Ms. Aditi Raj, Advocate
                                -----
     Order No.02                                   Date: 17.03.2026

1. Heard learned counsel for the parties.

2. Learned counsel for the parties agree that these writ petitions can

be disposed of by a common order. They point out that the material

facts in all these writ petitions are substantially same, though the

actual quantities or amounts involved may differ. Accordingly, we

propose to dispose of these writ petitions by a common order by

treating W.P.(C) No.1601 of 2026 as the lead case.

3. The petitioner seeks an appropriate writ upon the respondents for

quashing and setting aside the letters issued by the respondents

directing the deduction of certain amounts on account of highly

quoted items.

4. The petitioner argues that such deduction was inconsistent with and

in fact contrary to the terms of the contract between the parties.

2026:JHHC:7222-DB

The petitioner has urged that such deduction was made despite the

fact that the variation in contract price due to change in quantity

was within the prescribed limits and further, the same, was at the

instance of the respondents themselves.

5. Based on the above contention, the petitioner, seeks a writ of

mandamus upon the respondents to refund the deducted amount of

Rs.1,26,17,214.70/- along with interest at the rate of 18% per

annum because according to the petitioner, such deduction was

unilateral, illegal and in violation of the terms of the contract.

6. The issue raised in these petitions is almost identical to the issue

involved in W.P.(C) Nos.5303, 6007 and 2583 of 2025 which were

disposed of by a common judgment and order dated 22nd January,

2026. There, this Court noted that the dispute, similar to the dispute

raised in these Petitions, was a purely contractual dispute and any

resolution of such dispute would involve adjudication into highly

disputed question of facts with regard to excess quantities, if any,

the rates that would apply to such excess quantities, whether the

variation was within the permissible limits or not and which of the

parties was indeed responsible for the variation.

7. In some of these petitions, the respondents have filed returns

disputing the petitioners' claims and raising serious factual disputes.

The returns also point out that the petitioners have an alternative

remedy of resorting to arbitration under the agreement/contract

between the parties.

8. The resolution of the above-referred disputes would undoubtedly

involve adjudication into highly disputed questions of fact. Such an

exercise cannot be ordinarily undertaken when exercising the

2026:JHHC:7222-DB

summary and extraordinary jurisdiction under Article 226 of the

Constitution. This is especially so when at least some of the

Petitioners have undisputedly agreed to resort to arbitration to

resolve such disputes.

9. Mr Mittal, learned senior counsel for the petitioners, pointed out that

arbitration clauses are to be found in the agreements which are the

subject matter of the W.P.(C) Nos. 416, 1105 and 1315 of 2026. He

submitted that, in the agreements that are the subject matter of the

remaining petitions, there is no arbitration clause.

10. The presence or absence of an arbitration clause is not crucial. The

crucial issue is that the disputes raised in all these petitions arise

from allegations and counter-allegations of breaches of the contract

between the parties. Further, any resolution of such disputes would

involve adjudication into highly disputed questions of fact, some of

which are referred to hereinabove.

11. Therefore, it would not be appropriate to attempt to resolve such

disputes in our summary and extraordinary jurisdiction under Article

226 of the Constitution of India. This is more so in cases where the

parties have themselves agreed to resolve such disputes through

arbitration. In cases where the agreements do not contain an

arbitration clause, the petitioners may have to resort to the ordinary

remedy of filing a civil suit to pursue their claims.

12. As noted earlier, in almost identical circumstances, this Court, by its

common judgment and order dated 22nd January, 2026, disposing of

W.P.(C) Nos. 5303, 6007 and 2583 of 2025, declined to entertain

writ petitions but relegated the parties to arbitration. In those cases,

since the parties agreed upon the appointment of an Arbitral

2026:JHHC:7222-DB

Tribunal, with the express consent of the parties, this Court

proceeded to appoint the Arbitral Tribunal so that the disputes could

be resolved expeditiously. The reasoning in our order of 22 nd

January, 2026, will equally apply in the present cases.

13. In Kulchhinder Singh v. Hardayal Singh Brar, (1976) 3 SCC

828, the Hon'ble Supreme Court held that a writ petition is

unavailable to enforce a contract qua contract. The fact that the

respondent was a "State" is not sufficient and an enquiry should be

whether what is sought to be enforced is a statutory duty or

sovereign obligation. The Hon'ble Supreme Court, speaking through

Krishna Iyer, J observed as follows:-

"The writ petition, stripped of embroidery and legalistics,

stands naked as a simple contract between the staff and the

society agreeing upon a certain percentage of promotions to

various posts or an omnibus, all-embracing promise to give a

quota to the existing employees. At its best, the writ petition

seeks enforcement of a binding contract but the neat and

necessary repellant is that the remedy of Article 226 is

unavailable to enforce a contract qua contract. We fail to see

how a supplier of chalk to a government school or cheese to a

government hospital can ask for a constitutional remedy under

Article 226 in the event of a breach of a contract, bypassing the

normal channels of civil litigation. ........... Private law may

involve a State, a statutory body, or a public body in contractual

or tortious actions. But they cannot be siphoned off into the writ

jurisdiction (emphasis supplied)"

2026:JHHC:7222-DB

14. In Divl. Forest Officer v. Bishwanath Tea Co. Ltd., (1981) 3

SCC 238, the petitioner tried to enforce through writ petition the

right to remove timber under a contract. The Hon'ble Supreme

Court did not allow this by observing that ordinarily where a breach

of contract is complained of, a party complaining of such breach

may sue for specific performance of the contract if the contract is

capable of being specifically performed or the party may sue for

damages. Such a suit would ordinarily be cognizable by civil court.

The High Court in its extraordinary jurisdiction would not entertain a

petition either for specific performance of contract or for recovering

damages.

15. In LIC v. Asha Goel (2001) 2 SCC 160, the Hon'ble Supreme Court

held that it cannot be laid down as a general proposition of law that

in no case, the High Court can entertain a writ petition under Article

226 of the Constitution to enforce a claim under a contract for life

insurance. The Hon'ble Supreme Court that the determination of the

question depends upon consideration of several factors like,

whether a writ petitioner is merely attempting to enforce his/her

contractual rights or the case raises important questions of law and

constitutional issues, the nature of dispute raised, the nature of

enquiry necessary for determination of the dispute, etc. While the

jurisdiction of the High Court to entertain a writ petition under

Article 226 of the Constitution cannot be denied altogether, Courts

must bear in mind the self-imposed restriction consistently followed

by the High Courts all these years after the constitutional power

came into existence in not entertaining writ petitions filed for

enforcement of purely contractual rights and obligations which

2026:JHHC:7222-DB

involved disputed questions of facts. The Courts have consistently

take the view that in case where for the determination of the

dispute raised, it is necessary to enquire into facts for determination

of which it may become necessary to record oral evidence a

proceeding under Article 226 of the Constitution is not the

appropriate forum. The position is also well settled that if the

contract entered between the parties provide an alternate forum for

resolution of disputes arising from the contract, then the parties

should approach the forum agreed by them and the High Court in

writ jurisdiction should not permit them to bypass the agreed forum

of dispute resolution.

16. In State of Bihar v. Jain Plastics & Chemicals Ltd., (2002) 1

SCC 216, the petitioner questioned the deduction of an amount

from the final bill to be paid to the petitioner-contractor by alleging

breach of contract by him. The High Court allowed the petition.

However, the Hon'ble Supreme Court, reversing the High Court's

order, held that even if it is possible to decide the question raised in

the petition, based on affidavits and counter-affidavits, it would not

be proper to exercise extraordinary jurisdiction under Article 226 of

the Constitution in cases of alleged breach of contract.

17. As noted above, this is a matter where no public law element is

shown to be involved. Notwithstanding the language used in some

of the petitions alleging unfairness or arbitrariness, these matters

involve alleged breaches of non-statutory contracts. A resolution of

the dispute would involve adjudication of highly disputed questions

of fact. Admittedly, in at least some of the matters, the agreements

contain an arbitration clause. Therefore, upon cumulative

2026:JHHC:7222-DB

consideration of all these factors, we are satisfied that these are not

matters where we should entertain writ petitions or exercise our

extraordinary jurisdiction under Article 226 of the Constitution.

18. For the above reasons, we decline to entertain these petitions.

However, we grant the petitioners liberty to invoke the arbitration

clauses, if any, in their agreements or to resort to the ordinary civil

remedies before the Civil Court for resolution of their disputes, as

have been raised in these petitions.

19. Since this Court has not adjudicated upon the rival disputes on

merits, all contentions of all parties on the merits of the disputes are

left explicitly open to be decided through arbitration and/or the

ordinary civil remedies before the Civil Courts.

20. All these writ petitions are disposed of with liberty in the above

terms. No costs.

(M. S. Sonak, C.J.)

(Rajesh Shankar, J.) 17th March, 2026 Sanjay/Rohit Uploaded on 18.03.2026

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter