Monday, 04, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Union Of India Through The Secretary vs Jsw Steel Ltd
2025 Latest Caselaw 6363 Jhar

Citation : 2025 Latest Caselaw 6363 Jhar
Judgement Date : 13 October, 2025

Jharkhand High Court

Union Of India Through The Secretary vs Jsw Steel Ltd on 13 October, 2025

Author: Sujit Narayan Prasad
Bench: Sujit Narayan Prasad
                                                    2025:JHHC:31616-DB




     IN THE HIGH COURT OF JHARKHAND AT RANCHI
                L.P.A. No.67 of 2023
                                       ------
1.     Union of India through the Secretary, Ministry of Coal,
Government of India, having its office at 120, 1st floor, F-wing,
Shahstri Bhawan, P.O. & P.S.-New Delhi, District-New Delhi
2.     The Nominated Authority, Ministry of Coal, Government of
India, having its office at 120, 1st floor F-wing, Shahstri Bhawan, P.O.
& P.S.-Shastri Bhawan, District-New Delhi
                           ....      ....             Respondents/Appellants
                         Versus
1. JSW Steel Ltd., a Company Incorporated under the Companies
     Act, 1956, having its registered office at JSW Center, Bandra
     Kurla Complex, P.O. & P.S. Bandra East District Mumbai, and it's
     Project Office at B-236, Ground Floor, Road No.3, Ashok Nagar,
     P.O. Ashok Nagar, P.S. Argora, District-Ranchi, through its
     authorized representative and Associate Vice President-Projects,
     Sri Dhananjay Kumar Sinha, son of Sri Upendra Nath Sinha, aged
     about 55 years, resident of Flat No.201, Shakti Apartment,
     Ashokpuram, P.O. Ashok Nagar, P.S. Argora, District Ranchi.
2. Dhananjay Kumar Sinha, son of Sri Upendra Nath Sinha, aged
     about 55 years, resident of Flat No.201, Shakti Apartment,
     Ashokpuram, P.O. Ashok Nagar, P.S. Argora, District Ranchi.
                    ....        ....            Petitioners/Respondents
                           With
                   L.P.A. No.61 of 2023
                                  ------
1.     Union of India through the Secretary, Ministry of Coal,
Government of India, having its office at 120, 1st floor, F-wing,
Shahstri Bhawan, P.O. & P.S.-New Delhi, District-New Delhi
2.     Nominated Authority, Ministry of Coal, Government of India,
having its office at 120, 1st floor F-wing, Shahstri Bhawan, P.O. &
P.S.-Shastri Bhawan, District-New Delhi
                           ....      ....             Respondents/Appellants
                                  Versus


                            1
                                                          LPA Nos.67 & 61 of 2023
                                             2025:JHHC:31616-DB




1. JSW Steel Ltd., a Company Incorporated under the Companies
     Act, 1956, having its registered office at JSW Center, Bandra
     Kurla Complex, P.O. & P.S. Bandra East District Mumbai, and it's
     Project Office at B-236, Ground Floor, Road No.3, Ashok Nagar,
     P.O. Ashok Nagar, P.S. Argora, District-Ranchi, through its
     authorized representative and Associate Vice President-Projects,
     Sri Dhananjay Kumar Sinha, son of Sri Upendra Nath Sinha, aged
     about 55 years, resident of Flat No.201, Shakti Apartment,
     Ashokpuram, P.O. Ashok Nagar, P.S. Argora, District Ranchi.
2. Dhananjay Kumar Sinha, son of Sri Upendra Nath Sinha, aged
     about 55 years, resident of Flat No.201, Shakti Apartment,
     Ashokpuram, P.O. Ashok Nagar, P.S. Argora, District Ranchi.
                    ....       ....   Petitioners/Respondents


CORAM : HON'BLE MR. JUSTICE SUJIT NARAYAN PRASAD
        HON'BLE MR. JUSTICE ARUN KUMAR RAI
                    ------
        For the Appellants  : Mr. Prashant Pallav, DSGI
                              Ms. Shivani Jaluka, Advocate
       For the Respondents : Mr. Indrajit Sinha, Advocate
                              Mr. Rohitashya Roy, Advocate
                              Mr. Vibhor Mayank, Advocate
                              Mr. Shivam Kumar, Advocate
                              Ms. Oishi Das, Advocate
                           ------
C.A.V. on 23.09.2025               Pronounced on 13/10/2025

Per Sujit Narayan Prasad, J.

Prayer

1. Both these appeals, preferred by the Union of India under

Clause-10 of the Letters Patent, are directed against the common

order/judgment dated 06.12.2022 passed in W.P.(C) No.1128 of

2020 (impugned in L.P.A. No.67 of 2023) and W.P.(C) No.1126 of

2020 (impugned in L.P.A. No.61 of 2023), whereby and

whereunder, the writ petitions have been disposed of by quashing

LPA Nos.67 & 61 of 2023 2025:JHHC:31616-DB

the show cause notices issued by the Deputy Secretary being the

Nominated Authority, Ministry of Coal, Govt. of India with a liberty

to pass order afresh.

Factual Matrix

2. Since, similar facts and prayers have been made in both the

cases as such for the sake of convenience, the brief facts of one

of the cases, i.e., L.P.A. No.67 of 2020 arising out of W.P.(C)

No.1128/2020, is being referred hereinbelow.

3. The brief facts of the case, as per the pleading made in the writ

petition [W.P.(C) No.1128/2020], requires to be enumerated,

which read as under: -

(i) It is the case of the writ petitioner that the petitioner is

a company registered under the Companies Act, 1956.

(ii) The petitioner proposes to set up an integrated steel

plant in Jharkhand. The State of Jharkhand and the petitioner had

entered into a Memorandum of Understanding on 09.11.2005 in

terms of which the Government of Jharkhand had assured to

provide all assistance to the petitioner inter alia in acquiring land,

getting mining lease etc.

(iii) The Hon'ble Apex Court vide its judgment dated

25.08.2014 and 24.09.2014 passed in Manohar Lal Sharma vs.

The Principal Secretary & Ors., (2014) 9 SCC 516, had de-

allocated 214 Coal Blocks which were previously allocated by the

Ministry of Coal, Government of India including the Moitra Coal

Block which allocated to the prior allottee.

LPA Nos.67 & 61 of 2023 2025:JHHC:31616-DB

(iv) Subsequent to the aforesaid judgment, an ordinance

was promulgated by his Excellency the President of India, being

Coal Mines (Special Provisions) Ordinance, 2014.Thereafter, the

Coal Mines (Special Provisions) Act, 2015 was brought into force

retrospectively from 21.10.2014 and in terms thereof the Central

Government has also framed Coal Mines (Special Provisions)

Rules, 2014.

(v) After passing of the Act by the Parliament, fresh

bidding was conducted for allocation of the different Coal Blocks

in which the petitioner had also participated. In the auction, Moitra

Coal Block was allocated to the petitioner.

(vi) Pursuant thereof, an agreement was executed

between His Excellency the President of India, acting through the

Central Government represented by the Nominated Authority and

the petitioner on 17.03.2015 in terms of Rule- 13(5) of the Coal

Mines (Special Provisions) Rules, 2014 and the said agreement

is termed as "Coal Mines and Development and Protection

Agreement".

(vii) Pursuant to the aforesaid agreement, the petitioner

was required to furnish a bank guarantee of Rs.

1,715,803,210.00 in terms of Clause 6.1 of the agreement, the

petitioner accordingly furnished a bank guarantee of Rs.

1,715,803,210.00 dated 26.03.2015.

(viii) The Government of India through Office of Nominated

Authority, Ministry of Coal, issued a vesting order no.

LPA Nos.67 & 61 of 2023 2025:JHHC:31616-DB

104/21/2015/NA dated 22.04.2015 in terms of Section 8(4) of the

Act of 2015, read with Rule 7(2)(b) and Rule 13(1) of the Rules of

2014, in favour of the petitioner by virtue of which all rights, title

and interest of the prior allottee in and over the land (including

land compensatory afforestation) and mine infrastructure of the

prior allottee vested in the petitioner free from all encumbrances.

(ix) The Moitra Coal Block was earlier allocated to M/s

Jayaswal Neco Industries Ltd. For the purpose of working the

coal block, the prior allottee had purportedly acquired 242.55

acres of land within the coal block area comprised within 10

villages in the District of Hazaribagh within the State of

Jharkhand.

(x) The prior allottee had also acquired a total area of

266.17 acres of land in the district of Dhanbad, Garhwa, Gumla

and Palamau for the purpose of Compensatory Afforestation.

(xi) The said CMDPA was amended on 06.05.2015

whereby the efficiency parameter was rescheduled.

(xii) In terms of the provisions of Section 8(4) of the Act of

2015, once a vesting order is issued in terms of Rule 7(2)(b) and

Rule 13(1) of the Rules of 2014, all the rights, title and interest of

the prior allottee in an over the land and mining infrastructure

stand fully and absolutely transferred and vested in the

successful bidder, i.e., the petitioner free from all encumbrances.

(xiii) Therefore, the land purchased by the prior allottee in

connection to Moitra Coal Project stood statutorily transferred by

LPA Nos.67 & 61 of 2023 2025:JHHC:31616-DB

way of legal fiction in favour of the petitioner.

(xiv) The respondent No. 1 vide its letter dated 19.05.2015

had categorically directed the Chief Secretary, Government of

Jharkhand for transfer of all licenses of the prior allottee in favour

of the successful bidder including mutation of the land without

any delay and with no extra liability.

(xv) After the issuance of the vesting order, the petitioner

made several representations before the concerned respondent

authorities through its letters dated 03.06.2015 and 10.07.2015

requesting the respondent authorities to transfer and mutate the

land held by the prior allottee both within the mining lease area

and land for compensatory afforestation, in favour of the

petitioners, otherwise the petitioner will be rendered incapacitated

to comply with the efficiency parameter contained in Schedule-E

of the CMDPA.

(xvi) The State of Jharkhand in order to resolve the issue

relating to transfer and mutation of the vested land, constituted a

committee headed by the Chief Secretary of the State, which in a

meeting held on 10.08.2015 had proposed to realize stamp duty

and registration charges by executing a registered deed of

transfer.

(xvii) While the decision regarding payment of registration

fee and stamp duty was pending, the petitioner vide its letter

dated 04.09.2015 had apprised the State of Jharkhand that the

vesting order is issued in terms of Rule-7(2)(b) and Rule-13(1) of

LPA Nos.67 & 61 of 2023 2025:JHHC:31616-DB

the Coal Mines (Special Provision) Rules, 2014 as per which the

land and mining infrastructure stand fully and absolutely

transferred and vested in favour of the successful bidder, i.e., the

petitioner.

(xviii) The respondent No. 1 once again through its letter

being letter No. F. No. 13016/36/2015-CA-III dated 13.10.2015

clarified that the entire land owned by the prior allottee whether

the same was previously owned and/or acquired by the

government and transferred to the prior allottee or purchased by

the prior allottee have directly vested in favour of successful

bidder, i.e., the petitioner in the present case as per Section 8(4)

read with Section 3(1)(p) of the Act of 2015 and the same is

required to be transferred and mutated in favour of the successful

allottee without any extra liability.

(xix) In the said letter dated 13.10.2015, the respondent

No. 1 had specifically mentioned that any guideline which

stipulates payment of sum to the Government on the basis of

assessment of present value of land are not applicable in the

case of vesting done under the Coal Mines Special Provision Act.

It was also stated that the special act has an overriding effect on

any other law which is inconsistent with or in contravention to the

provision of the Coal Mines Special Provision Act as such the

same will prevail over any rules or guidelines.

(xx) The petitioner made a representation dated

24.11.2015 before the Ministry of Coal, Government of India that

LPA Nos.67 & 61 of 2023 2025:JHHC:31616-DB

the Government of Jharkhand is intending to take a decision to

charge stamp duty and registration fee for the transfer of land

from the prior allottee to the petitioner ignoring the fact that the

same has already been vested upon the petitioner by legal fiction

and an Act of legislature, as such the decision to that effect will be

totally inconsistent and contrary to the notification issued by the

Ministry of Coal.

(xxi) The Govt. of Jharkhand through Department of Land

Revenue, Registration and Land Reforms issued notification

no.5281 dated 26.11.2015 specifying that the land owned by the

prior allottee will be transferred and mutated in favour of the

successful bidder, i.e., the petitioner on payment of registration

fee and stamp duty over the present valuation of the land.

(xxii) The petitioner made a representation dated

10.03.2016 requesting the concerned respondent for their

intervention and support on expeditious transfer and mutation of

the land in favour of the petitioner. The petitioner has specifically

informed that delay in transfer and mutation of the vested land

will adversely affect in achieving the milestone.

(xxiii) It is the case of the petitioner that the respondents

have not responded to the representations made by the

petitioner. In spite of repeated requests and representations

made by the petitioner, the Govt. of Jharkhand failed to take any

positive step for complying with the clarification issued by the

Ministry of Coal, Govt. of India and the petitioner did not receive

LPA Nos.67 & 61 of 2023 2025:JHHC:31616-DB

any favourable response from the State of Jharkhand till

25.05.2016.

(xxiv) The State of Jharkhand vide its letter dated

25.05.2016 issued the direction after notification dated

26.11.2015 directing the petitioner to get the vested land

transferred by way of a registered transfer deed and on payment

of requisite stamp duty.

(xxv) In order to avoid any further delay, the petitioner was

compelled and constrained to enter into transfer of land vide 10

deeds of transfer executed on payment of the demanded stamp

duty and registration charges. Therefore, the transfer of vested

land within the mining lease area was affected by executing

registered transfer deeds on 30.05.2016 on payment of stamp

duty and registration fee.

(xxvi) Meanwhile, the Deputy Commissioner, Hazaribagh

has issued a communication dated 02.01.2016 wherein the

petitioner has been informed that prior to mutation of the vested

land, a permission under Section 49 of the CNT Act is required to

be obtained and a proceeding under Section 49 of the CNT Act

will be initiated with respect to the vested land and in this regard,

the Circle Officer, Barkagaon, Hazaribagh had issued notice(s) to

several persons who were the original owners of the land.

(xxvii) The transfer and mutation of land for compensatory

afforestation being major pre-requisite for achieving Stage-II

Forest Clearances and subsequent execution of mining lease, the

LPA Nos.67 & 61 of 2023 2025:JHHC:31616-DB

petitioner made several representations before the concerned

authorities for expediting the matter of transfer and mutation.

However, the petitioner failed to fetch any favourable response

from the concerned respondents.

(xxviii) The petitioner had also represented before the

concerned respondent for their intervention and support in

achieving the Efficiency Parameter No.9, i.e., Forest Clerance

and subsequent achievement of Efficiency Parameter No.12, i.e.,

Grant of Mining Lease well before eleven months from the

schedule date of completion, i.e., on 24.03.2016. However, the

concerned respondents never replied to the same.

(xxix) The mining lease thereafter granted to the petitioner

on 31.10.2019 but the same has not been executed. However,

the respondents in their endeavour to shift the entire blame upon

the petitioner started issuing show cause notices to the petitioner

for not meeting the time schedule as provided under the

efficiency parameter.

(xxx) In this regard, the respondent nos.1 and 2 issued the

first show cause notice dated 21.03.2017 for not meeting the

timeline with respect to Forest Clerance. The said show cause

notice was replied by the petitioner.

(xxxi) Without considering the aforesaid reply of the

petitioner, respondent nos.1 and 2 had again issued a show

cause notice dated 19.02.2018 for not meeting the time schedule.

The respondent nos.1 and 2 further informed the petitioner that

LPA Nos.67 & 61 of 2023 2025:JHHC:31616-DB

the petitioner is liable for an appropriation of 5 per cent of bank

guarantee constituting performance security as per clause 6.3

and 10.3 of the CMDPA. The said cause notice was again replied

by the petitioner vide its letter dated 03.08.2019.

(xxxii) Thereafter, petitioner state that the aforesaid show

cause notices is illegal and without jurisdiction. The petitioner has

challenged the aforesaid show cause notices in the separate writ

proceedings.

(xxxiii) The petitioner has been served with another show

cause notice dated 24.07.2019 blaming the petitioner for not

being able to meet the time schedule as provided under the

efficiency parameter contained in CMDPA. Consequently, the

respondents have arbitrarily and unreasonable informed the

petitioner that the petitioner is liable for an appropriation of 17 per

cent of the bank guarantee constituting performance security as

per clause 6.3 and 10.3 of the CMDPA.

(xxxiv) Being aggrieved with the aforesaid, writ petitions

being W.P.(C) Nos.1126, 1127 and 1128 of 2020 have been filed

and the same have been allowed by the learned Single Judge of

this Court, which is the subject matter of the instant appeals.

Submissions of the learned counsel for the Appellants-U.O.I.

4. Mr. Prashant Pallav, learned counsel for the appellants-U.O.I. has

taken the following grounds in assailing the impugned judgment: -

(i) Learned Single Judge has not taken into

consideration the fact that the terms and

LPA Nos.67 & 61 of 2023 2025:JHHC:31616-DB

conditions as referred under Clause 6.2 of the

Coal Mine Development and Production

Agreement (in short 'CMPDA') for Moitra Coal

Mine has not properly been appreciated, reason

being that, due show cause notice has been

issued as required to be issued under Clause 6.3

of the Agreement and as such, there was no

need to have an opportunity at the stage of

determination, as referred under Clause 6.2 of

the Agreement.

(ii) It has been contended that the writ petitioners

have submitted to the jurisdiction of the

Nominated Authority, in pursuance to the show

cause notice issued in the light of Clause 6.3 of

the Agreement without raising the issue of non-

compliance of the issue of determination, as

referred under Clause 6.2 of the Agreement.

(iii) The ground has been taken that once the

respondents-writ petitioners have submitted to

the jurisdiction of the concerned authority, it is not

available for the respondents-writ petitioners to

take the ground that merely because the

determination is not there, as required to be there

under Clause 6.2 of the Agreement, the decision

so taken by the authority, suffers from infirmity.

LPA Nos.67 & 61 of 2023 2025:JHHC:31616-DB

(iv) The ground has been taken that the authority

while considering the response furnished on

behalf of the writ petitioners in pursuance to the

show cause notice issued in terms of Clause 6.3

of the Agreement, has taken into consideration

the issue of waiver or appropriation depending

upon the factual aspect, as also, depending upon

the said response. Therefore, the issue is still left

open by the authority and after getting the report

from the State, the issue either of waiver or

appropriation is to be considered and in case, the

State will not forward its report, then, the

Nominated authority will decide the issue of

waiver or appropriation of amount, therefore, it

cannot be said that any prejudice has been

caused to the writ petitioner.

(v) Learned counsel for the appellant, based upon

the aforesaid grounds, has submitted that the

learned Single Judge since has not taken into

consideration these aspects of the matter, hence,

the impugned order requires interference.

Submissions of the learned counsel for the Respondents-writ

petitioners

5. Per contra, Mr. Indrajit Sinha, learned counsel for the

respondents-writ petitioners has submitted that it is a case where

LPA Nos.67 & 61 of 2023 2025:JHHC:31616-DB

the terms and conditions of the bilateral contract in pursuance to

the Coal Mine Development and Production Agreement has not

been complied with, which aspect of the matter has been taken

into consideration by the learned Single Judge and based upon

the same, the order impugned passed by the authority, has been

interfered with.

6. The contention which has been raised of no prejudice having

been caused to the writ petitioners, cannot be said to be

acceptable and it is not acceptable at all, reason being that, when

the terms and conditions of the contract is available, then, it is the

bounden duty of the parties to comply with the terms and

conditions of the contract, there cannot be any go-by to the terms

and conditions of the agreement.

7. It has been contended that in the agreement, it has been taken

care of, the opportunity is to be provided to the respondents-writ

petitioners before taking the decision of the appropriation of the

performance security at two stages, i.e., at the stage of condition

stipulated under Clause 6.2 and 6.3 of the Agreement. Clause 6.2

provides the issue of determination of the laches committed on

the part of the respondents-writ petitioners and on the basis of

such determination, the penal action is required to be taken in

view of the terms and conditions stipulated under Clause 6.3 of

the Agreement.

8. The argument therefore has been advanced that directly taking

action in view of the provision of Clause 6.3 after issuance of

LPA Nos.67 & 61 of 2023 2025:JHHC:31616-DB

show cause notice to the writ petitioners, the vital right of the

issue of determination as required to be there in view of Clause

6.2 of the Agreement, has been taken away and thereby, the

petitioners have been deprived to have one opportunity to put

their defence.

9. Learned counsel, based upon the aforesaid grounds, has

submitted that if the learned Single Judge after taking into

consideration these issues, has interfered with the impugned

judgment by passing the judgment dated 06.12.2022 (impugned

in the instant memo of appeals), the same cannot be said to

suffer from an error.

Response of the learned counsel for the appellants-U.O.I.

10. Learned counsel for the appellants has submitted, in response to

the argument, that once the respondents-writ petitioners have

submitted to the jurisdiction of the authority, the issue of non-

compliance of the condition stipulated under Clause 6.2 is not

available to be agitated and the same is not having force, reason

being that, even if the response has been given but the terms and

conditions of the contract, cannot be diluted merely on account of

furnishing the reply in terms of Clause 6.3 of the Agreement.

Analysis

11. We have heard the learned counsel for the parties and gone

through the finding recorded by the learned Single Judge in the

impugned judgment.

12. This Court, on consideration of the arguments advanced on

LPA Nos.67 & 61 of 2023 2025:JHHC:31616-DB

behalf of the parties and the pleading as available in the paper

book as also the finding recorded by the learned Single Judge,

needs to consider the following issues;

(i) Whether merely because the respondents-writ

petitioners have submitted to the jurisdiction of the

authority in terms of the show cause notice issued

under Clause 6.3, they are seized to agitate the

deprivation of their right to be heard at the time of

determination, as required to be there under Clause

6.2 of the Agreement.

(ii) Whether skipping from the consideration of the issue

of determination as per the condition stipulated under

Clause 6.2 of the Agreement, if the appellants

straightaway take the recourse of Clause 6.3, will it be

said to be proper on the part of the appellants and in

these circumstances, will it not be said to cause the

prejudice to the writ petitioners.

13. Both the issues are interlinked and as such, the same are being

taken up together.

14. But, before considering the aforesaid issues, this Court is of the

view that the settled position of law on the issue of deviation from

the terms and conditions of the Contract, needs to be referred

herein.

15. It is the settled position of law that terms and condition of the

contract is strictly to be adhered to and any condition contained

LPA Nos.67 & 61 of 2023 2025:JHHC:31616-DB

therein, if allowed to be flouted, the same to be contrary to the

terms and conditions and will amount to re-writing the terms and

conditions of the contract.

16. The Hon'ble Apex Court in the case of Rakesh Kumar Verma

Vrs. HDFC Bank Ltd., 2025 INSC 473 has categorically

observed that a concluded contract pre supposes the

existence of at least two parties with mutual rights and

obligations and once a concluded contract comes into

existence, it is axiomatic that such rights and obligations of the

parties are governed by the terms and conditions thereof.

17. Further, it requires to refer herein the settled position of law

that once the parties have accepted the terms and conditions

of lease or any agreement, it binds the parties and there

cannot be any breach of terms and conditions. Reference in

this regard may be made to the judgment rendered by the

Hon'ble Apex Court in the case of Tamil Nadu Electricity

Board and Another vs. N. Raju Reddiar and Another,

reported in (1996) 4 SCC 551 wherein it has been held that it

must be borne in mind that the agreement between the parties

was a written agreement and therefore the parties are bound

by the terms and conditions of the agreement.

18. Further, the law is well settled that once the terms and

conditions of the agreement have been accepted by the

parties, it is not available to them to assail the same, reference

LPA Nos.67 & 61 of 2023 2025:JHHC:31616-DB

in this regard may be made to the judgment rendered by

Hon'ble Apex Court in the case of Panna Lal and Others v.

State of Rajasthan and Others, reported in (1975) 2 SCC

633 wherein it has been held that the licensee having

voluntarily accepted the contract and after having fully

exploited to its advantage the contract to the exclusion of

other, cannot resile from the contract and cannot challenge the

terms either on the ground of inconvenient

19. It requires to refer herein the settled position of law that if any

terms and conditions have been agreed upon by the parties

the same cannot be relaxed by the High Court sitting

under Article 226 of the Constitution of India otherwise it will

amount to re-write the terms and conditions of contract as has

been held in the case of Union Territory of Pondicherry and

Ors Vs. P.V. Suresh and Ors., reported in (1994) 2 SCC 70

wherein at paragraph 11 it has been held that the Court has no

jurisdiction to alter the terms or rewrite the contract between

the parties, for ready reference the same is being quoted as

under:

"11. In the circumstances of this case, .......................... Otherwise, the Court has no jurisdiction to alter the terms or rewrite the contract between the parties."

20. In the case of Polymat India (P) Ltd. and Anr. Vs. National

Insurance Co. Ltd. and Ors., reported in (2005) 9 SCC 174

LPA Nos.67 & 61 of 2023 2025:JHHC:31616-DB

wherein, the Hon'ble Apex Court by taking aid of the judgment

rendered in the case of United India Insurance Co. Ltd. Vs.

M.K.J. Corp., reported in (1996) 6 SCC 428 has been pleased

to observe that "after the completion of the contract, no

material alteration can be made in its terms except by mutual

consent".

21. Adverting to the factual aspect of the present case, in the

premises of the settled position of law that there cannot be any

deviation from the terms and conditions once the contract has

been entered in between the parties, the relevant conditions of

the agreement, which is relevant for the present lis require

reference in the present context are Clause 6.2 and Clause 6.3,

for ready reference, the same are being quoted as under:-

"6.2 Events for appropriation of the Performance Security 6.2.1. The Performance Security may be appropriated by the Nominated Authority upon occurrence of any of the following events (the "Appropriation Event"), to be determined by the Nominated Authority in its sole discretion:

(a) failure of the Successful Bidder to provide the duly acknowledged duplicate copy of the Vesting Order as required under Clause 4.6;

(b) failure of the Successful Bidder to make payment of the first instalment, second instalment or the third instalment of the Upfront Amount within the specified in Clause 3.1(b), Clause 5.2.2 or Clause 5.2.3, respectively;

(c) failure of submission of Commencement Plan within the time specified in Clause 5.1.1.

(d) failure of the Successful Bidder to comply with the Efficiency Parameters as required under Clause 10;

(e) any change in Control or transfer of right, title or interest in the Coal Mine which is not in conformity with Clause 13;

LPA Nos.67 & 61 of 2023 2025:JHHC:31616-DB

(f) failure to make payment of the Monthly Payment in accordance with this Agreement;

(g) any utilization of coal which is in conformity with Clause 8; or

(h) any other breach or non-compliance of any of the provisions of this Agreement including in case of the Warranties being untrue or misleading or incorrect in any manner whatsoever.

6.2.2 Provided however that in the event an Appropriation Even has occurred solely on account of an Event of Force Majeure which could not have been mitigated by the Successful Bidder through Good Industry Practice as provided in Clause 23, then the Performance Security shall not be appropriated for such specific Appropriation Event.

6.3. Manner of appropriation of the Performance Security 6.3.1 Upon occurrence of an Appropriation Event, to be determined by the Nominated Authority, the Nominated Authority shall have the unconditional right to appropriate the Performance Security by providing a written notice to the Successful Bidder in the following proportion:

#       Appropriation Event                         Amount of the
                                                    Performance
                                                    Security
                                                    appropriated
1.      Failure of the Successful Bidder to         Entire
        provide the duly acknowledged               Performance
        duplicate copy of the Vesting Order         Security.
        as required under Clause 4.6
2.      Failure of the Successful Bidder to         An amount equal
        make payment of the first instalment,       to      the     first
        second instalment or the third              instalment, and/or
        instalment of the Upfront Amount            second
        within the time specified in Clause         instalment and/or
        3.1(b), Clause 5.2.2 or Clause 5.2.3,       third instalment of
        respectively                                the         Upfront
                                                    Amount together
                                                    with 12% per
                                                    annum        simple
                                                    interest on such
                                                    amount starting
                                                    from the date on
                                                    which          such
                                                    amount was due
                                                    and until the date
                                                    of appropriation
                                                    of               the
                                                    Performance
                                                    Security.



                                                LPA Nos.67 & 61 of 2023
                                              2025:JHHC:31616-DB




3.       Failure      of     submission  of              An amount equal
         Commencement Plan within the time               to 10% of the
         specified in Clause 5.1.1                       Performance
                                                         Security
4.       Failure of the Successful Bidder to             Such Per cent of
         comply      with   the    Efficiency            the Performance
         Parameters as required under Clause             Security for each
         10                                              failure to comply
                                                         with the Efficiency
                                                         Parameters       as
                                                         specified         in
                                                         SCHEDULE E.
5.       Any change in Control or transfer of            Entire
         right, title or interest in the Coal Mine       Performance
         which is not in conformity with Clause          Security.

6.       Any utilization of coal which is not in         Entire
         conformity with Clause 8                        Performance
                                                         Security.
7.       Failure of the Successful Bidder to             The amount of
         make payment of the Monthly                     Monthly Payment
         Payment                                         due and payable,
                                                         along     with    a
                                                         simple interest of
                                                         twelve per cent
                                                         per         annum
                                                         starting from the
                                                         date on which
                                                         such amount was
                                                         due and until the
                                                         date              of
                                                         appropriation of
                                                         the Performance
                                                         Security.
8.       Any other breach or non-compliance              Such proportion
         with any of the provisions of this              as      may      be
         Agreement, including in case of the             determined by the
         Warranties     being      untrue   or           Nominated
         misleading or incorrect in any manner           Authority in its
         whatsoever.                                     sole discretion.


6.3.2 Any Appropriation Even resulting in appropriation of the entire Performance Security shall be Termination Event for the purposes of Clause 24 (EFFECTIVE DATE, TERM AND TERMINATION) 6.3.3 In the event of a part appropriation of the Performance Security, the Successful Bidder shall be required to: (i) rectify the Appropriation Event; and (ii) top-up the bank guarantee constituting the Performance Security within fifteen Business Days of receipt of a notice under Clause 6.3.1, failure to do so shall be a Termination Event for the purposes of Clause 24 (EFFECTIVE DATE, TERM AND TERMINATION). Appropriation Event except as

LPA Nos.67 & 61 of 2023 2025:JHHC:31616-DB

mentioned in clause 6.2.1 (d) shall be rectified within seven Business Days of receipt of a notice under Clause 6.3.1. Appropriation Event mentioned in clause 6.2.1 (d) shall be rectified within the time specified in SCHEDULE E. 6.3.4 In the event that on account of one or more Appropriation Events, an amount equal to hundred per cent of the Performance Security is appropriated in aggregate in one or more instances, the same shall be Termination Event for the purposes of Clause 24 (EFFECTIVE DATE, TERM AND TERMINATION)."

22. It is evident from the condition stipulated under Clause 6.2 that in

case of any lapses on the part of the second party, the Nominated

Authority is first to determine the liability.

23. Clause 6.3 stipulates that after such determination the initiation

will be taken for appropriation of the performance security.

24. This Court, after going through the condition stipulated under

Clause 6.2 and Clause 6.3, is of the view that both the Clauses

are to be read together, since, the condition stipulated under

Clause 6.3 is the consequence by taking action depending upon

the issue of determination of the liability, as per the condition

stipulated under Clause 6.2 of the Agreement.

25. The word "determined" under Clause 6.2 is having bearing which

means that the issue of liability of the second party is to be

decided for the purpose of taking initiation for appropriation of the

performance security as per the condition stipulated under

Clause 6.3.

26. It cannot be denied and also not disputed that when any liability

is being determined then incumbent upon the authority, would be

to call upon the party against whom any liability is being

determined so as to follow the principle of natural justice.

LPA Nos.67 & 61 of 2023 2025:JHHC:31616-DB

27. At this juncture, Mr. Prashant Pallav, learned counsel appearing

for the appellants-U.O.I. has submitted that there is no reference

of following the principle of natural justice as under Clause 6.2.

28. But, this Court is not impressed with such argument, reason

being that, when the issue of liability is being determined then if

the same is going to lead the civil consequence, which cannot be

assessed at the initial stage, rather, the same can only be

assessed after considering the response of the party concerned

and for which, the mandatory requirement would be to call upon

such party to put-forth his defence.

29. It requires to refer herein that even if there is no statutory

provision requiring an opportunity to be given, in order to follow

the cardinal principle of natural justice, an opportunity of hearing

is to be given to the party concerned who is going to be adversely

affected, reference in this regard may be made to the judgment

rendered by the Hon'ble Apex Court in the case of Mrs. Maneka

Gandhi Vrs. Union of India and Anr., reported in (1978) 1 SCC

248, wherein, the proposition has been laid down that even if

there is no statutory provision requiring an opportunity to be

given, in order to follow the cardinal principle of natural justice, an

opportunity of hearing is to be given to the party concerned who

is going to be adversely affected.

30. Such decision has been given by the Hon'ble Apex Court while

dealing with Section 10(3) of the Indian Passport Act, wherein,

the validity of the said provision was challenged on the ground

LPA Nos.67 & 61 of 2023 2025:JHHC:31616-DB

that there is no provision to provide an opportunity of hearing

before impounding the passport. However, the Hon'ble Apex

Court has upheld the constitutional validity of the said provision,

but has laid down the proposition that even if there is no provision

or stipulation made in the statutory provision, then also, it will be

the bounded duty of the concerned authority to provide

opportunity of hearing before taking any adverse decision, for

ready reference, the relevant paragraph of the said judgment

needs to be referred, which reads as under:-

"9. We may commence the discussion of this question with a few general observations to emphasise the increasing importance of natural justice in the field of administrative law. Natural justice is a great humanising principle intended to invest law with fairness and to secure justice and over the years it has grown into a widely pervasive rule affecting large areas of administrative action. Lord Morris of Borth-y-Gest spoke of this rule in eloquent terms in his address before the Bentham Club: "We can, I think, take pride in what has been done in recent periods and particularly in the field of administrative law by invoking and by applying these principles which we broadly classify under the designation of natural justice. Many testing problems as to their application yet re-remain to be solved. But I affirm that the area of administrative action is but one area in which the principles are to be deployed. Nor are they to be invoked only when procedural failures are shown. Does natural justice qualify to be described as a 'majestic' conception? I believe it does. Is it just a rhetorical but vague phrase which can be employed, when needed, to give a gloss of assurance? I believe that it is very much more. If it can be summarised as being fair-play in action -- who could wish that it would ever be out of action? It denotes that the law is not only to be guided by reason and by logic but that its purpose will not be fulfilled; it

LPA Nos.67 & 61 of 2023 2025:JHHC:31616-DB

lacks more exalted inspiration. And then again, in his speech in the House of Lords in Wiseman v. Borneman, the learned Law Lord said in words of inspired felicity: "... that the conception of natural justice should at all stages guide those who discharge judicial functions is not merely an acceptable but is an essential part of the philosophy of the law. We often speak of the rules of natural justice. But there is nothing rigid or mechanical about them. What they comprehend has been analysed and described in many authorities. But any analysis must bring into relief rather their spirit and their inspiration than any precision of definition or precision as to application. We do not search for prescriptions which will lay down exactly what must, in various divergent situations, be done. The principles and procedures are to be applied which, in any particular situation or set of circumstances, are right and just and fair. Natural justice, it has been said, is only 'fair play in action'. Nor do we wait for directions from Parliament. The common law has abundant riches: there may we find what Byles, J., called 'the justice of the common law' ". Thus, the soul of natural justice is "fair-play in action" and that is why it has received the widest recognition throughout the democratic world. In the United States, the right to an administrative hearing is regarded as essential requirement of fundamental fairness. And in England too it has been held that "fair-play in action" demands that before any prejudicial or adverse action is taken against a person, he must be given an opportunity to be heard. The rule was stated by Lord Denning, MR in these terms in Schmidt v. Secretary of State or Home Affairs -- "where a public officer has power to deprive a person of his liberty or his property, the general principle is that it has not to be done without his being given an opportunity of being heard and of making representations on his own behalf". The same rule also prevails in other Commonwealth countries like Canada, Australia and New Zealand. It has even gained access to the United Nations (vide American Journal of International Law, Vol. 67, p. 479). Magarry, J., describes natural justice "as a distillate of due process of law" (vide Fontaine v. Chastarton16). It is the

LPA Nos.67 & 61 of 2023 2025:JHHC:31616-DB

quintessence of the process of justice inspired and guided by "fair-play in action". If we look at the speeches of the various Law Lords in Wiseman case it will be seen that each one of them asked the question "whether in the particular circumstances of the case, the Tribunal acted unfairly so that it could be said that their procedure did not match with what justice demanded", or, was the procedure adopted by the Tribunal "in all the circumstances unfair?" The test adopted by every Law Lord was whether the procedure followed was fair in all the circumstances and "fair-play in action" required that an opportunity should be given to the taxpayer "to see and reply to the counter-statement of the Commissioners"

before reaching the conclusion that "there is a prima facie case against him". The inquiry must, therefore, always be:

does fairness in action demand that an opportunity to be heard should be given to the person affected?"

31. This Court, therefore, is of the view that merely because there is

no reference to provide an opportunity of hearing to the writ

petitioners under Clause 6.2, the vital right of putting their

defence at the stage of determination of liability cannot be taken

away, otherwise, the same will violate the principle of natural

justice.

32. Clause 6.3 is the consequence of the issue of determination

which is to be done as per the condition stipulated under Clause

6.2 of the Agreement.

33. Initiation which is to be taken under Clause 6.2 of the Agreement

is to be based upon the determination of the liability of

appropriation of the performance security and for which also,

depending upon the outcome of the issue of determination as per

Clause 6.2 of the Agreement, a fresh show cause notice is to be

LPA Nos.67 & 61 of 2023 2025:JHHC:31616-DB

given to the party concerned.

34. However herein, show cause notice has been given in terms of

Clause 6.3 of the Agreement which has been responded by the

respondents-writ petitioners and for that reason, the ground has

been taken that the writ petitioners have submitted to the

jurisdiction of the authority concerned and hence, the writ

petitioners are seized to agitate the issue of non-compliance of

the condition stipulated under Clause 6.2 of the Agreement.

35. This Court, is of the view that merely because the petitioners

have responded to the response given in view of Clause 6.3, they

will not seize in agitating the issue of laches committed on the

part of the appellants in depriving the petitioners in providing the

opportunity of being heard by issuance of show cause notice at

the stage of determination.

36. The issue of natural justice has been held to be instinct and if not

followed, then the same will be said to be in the teeth of Article 14

of the Constitution of India and in that view of the matter, even if

the writ petitioners have submitted to the jurisdiction by

submitting response to show cause notice in terms of Clause 6.3,

the issue of having no opportunity of hearing at the stage of

determination is being in the teeth of Article 14 of the Constitution

of India and hence, the contention which has been raised that

merely because the writ petitioners have submitted to the

jurisdiction of the Nominated Authority in terms of show cause

notice issued under Clause 6.3, will seize to agitate the non-

LPA Nos.67 & 61 of 2023 2025:JHHC:31616-DB

determination of the issue as required to be determined in view of

Clause 6.2 of the Agreement, is having no foundation. Hence,

such argument is hereby, rejected.

37. Further, if the stage of Clause 6.2 and Clause 6.3, the proceeding

is at two stages and if the petitioners will be deprived from their

right to have opportunity at the stage of Clause 6.2 of the

Agreement, then, petitioners will lose one opportunity and

straightaway, the party concerned will have to jump to the stage

of condition stipulated under Clause 6.3 of the Agreement.

38. The law is well settled that if the terms and conditions of the

agreement has been provided, the same are to be adhered to in

strict sense and there cannot be any deviation and if the deviation

will be permitted, then, the same will amount to re-writing the

terms of the Contract, which is not permissible. Otherwise also,

deviating from the terms and conditions will amount to relaxation

in the terms and conditions, which is also not permissible once

the agreement has been entered in between the parties.

39. Accordingly, both the issues are being answered.

40. This Court, adverting to the impugned judgment, has found that

the learned Single Judge has taken into consideration before the

recourse of Clause 6.3, it was mandatory requirement to follow

the condition required under Clause 6.2 with regard to the

performance security, the said consideration has been given in

terms of the condition stipulated in the Agreement.

41. This Court, considering the finding so recorded in the impugned

LPA Nos.67 & 61 of 2023 2025:JHHC:31616-DB

judgment and based upon the discussions made hereinabove, is

of the view that the judgment impugned needs no interference.

42. Accordingly, the instant appeals fail and are, dismissed.

43. Pending interlocutory application(s), if any, stands disposed of.




                                                (Sujit Narayan Prasad, J.)

         I Agree



  (Arun Kumar Rai, J.)                              (Arun Kumar Rai, J.)


    13/10/2025

 Rohit/-A.F.R.

Uploaded on 14.10.2025





                                                                LPA Nos.67 & 61 of 2023
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter