Citation : 2025 Latest Caselaw 63 Jhar
Judgement Date : 2 May, 2025
2025:JHHC:13181
IN THE HIGH COURT OF JHARKHAND AT RANCHI
C.M.P. No. 99 of 2025
---
M/s. KMC-ECI(JV) represented through its authorized signatory Peddu Srinivasa Rao son of Late Peddu Venkata Ratnam, the authorized representative of the petitioner company having its principal office at Corporate House, Shilpa Homes Layout, Gachibowli, Hyderabad (Telangana) and having its corporate office at KMC-ECI (JV), Bukru, P.O.& P.S. - Keredari, Hazaribagh ... ... Petitioner Versus
1. The State of Jharkhand through the Principal Secretary, State Highway Authority of Jharkhand, , Ranchi
2. The State Highway Authority of Jharkhand (SHAJ), Ranchi represented by its Chief Executive Officer
3. The Principal Secretary, the State Highway Authority of Jharkhand (SHAJ), Ranchi
4. The Chief Executive Officer, the State Highway Authority of Jharkhand (SHAJ), Ranchi
5. The Member Technical, the State Highway Authority of Jharkhand (SHAJ), Ranchi
6. The Engineer-in-Chief, the State Highway Authority of Jharkhand (SHAJ), Ranchi
7. The Central Bank of India represented by its Senior Branch Manager, having its office at Corporate Finance Branch, Bank Street, P.O. & P.S. - Koti, District- Hyderabad (Telangana)
8. IDBI Bank, represented by its Senior Branch Manager having its office at Specialized Corporate Branch, P.O. & P.S.- Chapel Road, District- Hyderabad (Telangana) .... ... Respondents CORAM: HON'BLE MR. JUSTICE RAJESH SHANKAR For the Petitioner : Mr. Amit Kumar Das, Advocate For the Respondents :
Order No. 10 Dated: 02.05.2025
The present Civil Miscellaneous Petition has been preferred
by the petitioner seeking clarification of the order dated
15.05.2018 passed by this court in W.P.(C) No. 7190 of 2017 to
the effect that the liberty granted to the petitioner in Paragraph
nos. 32, 33 and 35 of the said order to invoke arbitration clause
of the EPC contract agreement i.e., clause- 26 was in relation to
all grievances raised by it including that of termination of its
contract. It has also been prayed to clarify that the findings as
2025:JHHC:13181
well as the factual observations made by this Court in the said
order would not prejudice the case of the parties before the
learned Arbitral Tribunal.
2. Learned counsel for the petitioner submits that the petitioner
had preferred writ petition being W.P.(C) No. 7190 of 2017
challenging the termination order bearing no. 1668 dated
07.12.2017 whereby the State Highways Authority of Jharkhand
(in short, "SHAJ") had taken decision to terminate its contract and
had also prayed for quashing the letter no. 1670 dated
07.12.2017 issued under the signature of the Member (Technical),
SHAJ whereby the Senior Manager, Central Bank of India,
Corporate Finance Branch, Bank Street, Koti Hyderabad had been
directed to encash the bank guarantee deposited by the petitioner
towards the performance security. The said writ petition was
disposed of by this court vide order dated 15.05.2018.
3. It is further submitted that the order dated 15.05.2018
passed by this court in W.P.(C) No. 7190 of 2017 had intended to
grant liberty to the petitioner to raise all the contentions before
the learned Arbitral Tribunal including the question of termination
of contract which would be evident from reading of paragraph
nos. 32 and 35 of the said order, however a doubt has cropped up
from paragraph- 33 of the said order in which the liberty granted
to the petitioner seems to be only in relation to encashment of
the performance bank guarantee deposited by it.
4. It is also submitted that the question with respect to legality
of encashment of the performance security cannot be decided by
2025:JHHC:13181
the learned Arbitral Tribunal unless it also decides the legality of
the termination of contract.
5. Learned counsel for the petitioner further submits that the
petitioner had filed an application being Arbitration Application
No. 11 of 2020 before this Court under Section 11(6) of the
Arbitration and Conciliation Act, 1996 seeking direction to appoint
Arbitrator for resolution of the dispute which was disposed of by a
co-ordinate Bench of this Court vide order dated 23.06.2022
appointing second Arbitrator for resolution of dispute as well as
providing liberty to the parties to raise all the legal issues for
consideration by the Arbitrators in accordance with law which
invariably included the dispute qua termination of contract.
6. It is also submitted that on the one hand, the respondent -
SHAJ has tried to justify the validity of the termination of contract
before the Arbitral Tribunal, however on the other hand, it has
claimed that the matter of termination of contract has already
been decided by this Court in its order dated 15.05.2018 passed
in W.P.(C) No. 7190 of 2017. Thus, the petitioner has been
constrained to approach this Court seeking clarification of the
order dated 15.05.2018. It is expedient in the interest of justice
that the order dated 15.05.2018 passed by this court in W.P.(C)
No. 7190 of 2017 should suitably be clarified to the effect that the
liberty granted to the petitioner in paragraph nos. 32 and 33 of
the said order to invoke arbitration is in relation to all the
grievances of the petitioner including that of termination of
contract.
2025:JHHC:13181
7. Heard learned counsel for the petitioner and perused the
order dated 15.05.2018 passed by this Court in W.P.(C) No. 7190
of 2017, the relevant part of which reads as under: -
"32. Under the aforesaid circumstances, I am of the considered view that after taking decision for termination of contract agreement, the respondent- SHAJ has rightly invoked Clause 23.6.1 of the EPC contract agreement and has encashed/appropriated the performance security as a predetermined compensation. If the petitioner has any grievance, it may invoke Clause 26 of the EPC contract agreement.
33. In view of the discussions made herein above, the present writ petition is disposed of with the following observations:
(i) No interference is warranted with the order of termination contained in Memo no. 1668 dated 07.12.2017 as the same does not suffer from any arbitrariness, unreasonableness, irrationality, biasness and mala fide.
(ii) So far the order of encashment of performance security deposited by the petitioner is concerned, the same is within the competence of the respondent-SHAJ. However, the petitioner is at liberty to invoke clause 26 of the EPC contract agreement."
8. Generally, Civil Miscellaneous Petition (C.M.P.) is filed for
correction of typographical error or omission of a word, etc. in a
judgment or order, however if such a petition is filed seeking
review or modification of an order or judgment, the same cannot
be entertained. The present C.M.P. has been filed seeking
clarification of the order dated 15.05.2018 passed in W.P.(C) No.
7190 of 2017 not because any such clarification is found
necessary, rather the applicant actually wants a review of the
order dated 15.05.2018 passed in W.P.(C) No. 7190 of 2017. I am
of the view that a party cannot be permitted to claim review in
2025:JHHC:13181
the garb of filing a Civil Miscellaneous Petition. Undoubtedly, Civil
Miscellaneous Petition seeking clarification or modification of the
order or judgment touching the merit of the matter is not
maintainable. If any error is apparent on the face of the record,
an application for review can be filed. What cannot be done
directly cannot be permitted to be done indirectly.
9. On perusal of the prayer made in the present C.M.P., it
appears that in the garb of clarification, the petitioner in fact has
sought review of the order dated 15.05.2018 passed in W.P.(C)
No. 7190 of 2017 contending that vide said order, the petitioner
has been granted liberty to invoke arbitration clause of the EPC
contract agreement in relation to all grievances of the petitioner
including termination of contract. The petitioner has further
sought clarification that the findings given by this court in the
said order should not prejudice the case of the parties before the
learned Tribunal. I am of the view that such kind of prayer
cannot be entertained by way of Civil Miscellaneous Petition.
10. Moreover, In the light of the order dated 15.05.2018, the
petitioner invoked the dispute resolution process as contained in
Clause 26 of the EPC Contract and by now the parties have led
their respective evidences in the arbitral proceeding and the
matter is at the stage of argument of the parties.
11. The present C.M.P has been filed on 29.11.2024 i.e., after
about more than six years from the date of order passed in the
aforesaid writ petition without giving any cogent explanation for
committing such an inordinate delay in filing the same. If the
2025:JHHC:13181
petitioner had any doubt in the said order, it should have promptly
approached this Court invoking appropriate jurisdiction. Hence, I
am of the view that the conduct of the petitioner is not bonafide,
rather the present C.M.P. appears to have been filed to delay the
arbitral proceeding which certainly amounts to abuse of the
process of the Court.
12. Otherwise also, the matter is pending before the Arbitral
Tribunal which is competent enough to interpret the order dated
15.05.2018 passed by this Court in W.P.(C) No. 7190 of 2017.
13. The present C.M.P. is accordingly dismissed.
14. This Court takes serious note of the conduct of the petitioner
as it has consumed valuable time of the Court by filing this
frivolous petition. Such attitude of the petitioner is deprecated
and it deserves to be saddled with an exemplary cost.
15. Accordingly, the petitioner shall pay a cost of Rs.50,000/- in
favour of the Jharkhand State Legal Services Authority (JHALSA),
Ranchi within four weeks from today and shall file proof of the
same, failing which the office shall place this case before the
Bench to take appropriate action against it.
(Rajesh Shankar, J.) Ritesh/A.F.R.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!