Thursday, 07, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

N.R. Construction Private ... vs The State Of Jharkhand And Others
2023 Latest Caselaw 1946 Jhar

Citation : 2023 Latest Caselaw 1946 Jhar
Judgement Date : 5 May, 2023

Jharkhand High Court
N.R. Construction Private ... vs The State Of Jharkhand And Others on 5 May, 2023
                 IN THE HIGH COURT OF JHARKHAND AT RANCHI

                           Arbitration Appeal No. 13 of 2009

            N.R. Construction private Limited            ...     ...    Appellant
                                     Versus
            The State of Jharkhand and others      ...        ...      Respondents
                                     ---

CORAM :HON'BLE MRS. JUSTICE ANUBHA RAWAT CHOUDHARY

---

For the Appellant : Mr. Indrajit Sinha, Advocate Ms. Puja Agarwal, Advocate For the Respondents : Mr. Sachin Kumar, A.A.G. II

---

13/05.05.2023 Learned counsel for the parties are present.

Arguments of the Appellant

2. Learned counsel for the appellant has submitted that the learned court below has set aside the award by referring to Clause 11 of the agreement by holding that as per clause-11, it was specifically provided that the contractor shall not be entitled for any payment for any additional work unless he has received an order in writing from the in-charge for the additional work in terms of clause 11 of the agreement.

3. The learned counsel submits that the impugned order has been passed by which the award has been set aside by holding that the learned Arbitrator has passed the award by ignoring clause 11 (proviso) of contract/agreement and therefore the learned Arbitrator had travelled beyond his jurisdiction and in the interest of justice the award has been set aside.

4. The learned counsel has submitted that before the learned Arbitrator, neither any ground of jurisdiction was raised nor any reliance was placed upon clause 11 of the contract to show that the sanction for additional work having not been granted in terms of clause 11, no payment was admissible. The learned counsel has also submitted that the specific case of the respondents herein before the learned Arbitrator was that the entire work was already completed. He has referred to paragraph 23 of the award. He has also submitted that before the learned Arbitrator, the respondent had admitted that the appellant was entitled for payment to the extent of a sum of Rs. 14,13,779/-. The learned counsel submits that though the point of

sanction was bone of contention between the parties before the learned arbitrator, but no specific plea regarding point of jurisdiction or any objection with regard to clause 11 of the contract having been raised by the respondents before the learned Arbitrator, such ground could not have been a reason for setting aside the award under Section 34 of the Arbitration and Conciliation, act, 1996. He has also submitted that no reference was even made to clause 11 of the contract in the petition for setting aside the award filed under section 34 of the Act of 1996. The learned counsel submits that new plea could not have been raised for the first time at the stage of argument before the learned court below. He has also submitted that no such plea was raised in the petition filed under Section 34 of the Arbitration and Conciliation Act, 1996 that the learned arbitrator had ignored any term of the contract.

5. The learned counsel has referred to para 17 and 18 of the judgment passed by the Hon'ble Supreme Court reported in (2020) 11 SCC 161 to submit that there cannot be any statutory limitation or bar for the claim in all circumstances. He has submitted that whether the claim was admissible or not is essentially a question of fact and once the work was already done, there was no question of denial of any payment. The learned counsel has submitted that no such plea was raised that the claim, which was made for extra work, was beyond the terms of agreement between the parties and was outside the scope of work before the learned Arbitrator. Although such plea ought to have been raised under Section 16 of the Act of 1996, but neither any such plea was raised under Section 16, nor any such plea was raised before the learned arbitrator at any point of time.

6. He has also relied upon a judgment passed by the Hon'ble Supreme Court reported in (2016) 4 SCC 119 and has submitted that similar clause as that of clause 11, was subject matter of consideration by the Hon'ble Supreme Court. He has referred to paragraph No. 18 of the said judgment to submit that while considering the judgment of the High Court, the Hon'ble Supreme Court has also recorded that while relying upon clause 11 of the contract, the High Court had brushed aside the admission of the witness that extra work was done and the High court was not right in ignoring the same to hold that the admission of a witness cannot have any effect on the contractual

obligation of the parties. It was also pointed out that the respondent of the said case had not raised any plea relying upon clause 11 of the contract.

7. The learned counsel submits that in the present case also, the work was already done and the sanction/ approval was sought for, but it cannot be said that the learned arbitrator has travelled beyond jurisdiction to award the amount on the account of the work already done. Learned counsel submits that the award did not call for any interference within the permissible limit of interference under Section 34 of the Arbitration and Conciliation Act, 1996. He submits that the impugned order is fit to be set-aside.

Arguments of the Respondents.

8. Learned counsel appearing on behalf of the respondents has submitted that the award of the learned arbitrator clearly indicates that no sanction was given for extra work and accordingly the learned court below has rightly set aside the award which was primarily for the claim of the extra work.

9. He has also submitted that the learned Arbitrator had travelled beyond his jurisdiction while passing the award in connection with the extra work.

10. He has submitted that the learned arbitrator had ignored clause 11 of the contract while awarding the amount.

11. The learned counsel has further submitted that merely a statement made by the Executive Engineer before the learned Arbitrator that the work was completed cannot be used as an estoppel against the respondents to take a plea that the work was actually not completed. Learned counsel has submitted that the work was actually not completed and the appellant has been awarded the amount without completion of the work.

12. He has further submitted that so far as argument of the appellant that clause 11 was not referred to or relied upon before the learned Arbitrator is concerned, it was for the learned Arbitrator to refer to the various clauses of the agreement and see whether any amount was admissible on the face of clause 11 of the contract.

13. While referring to the grounds, the learned counsel has stated that it has been specifically raised in the petition under Section 34 of

the Arbitration and Conciliation Act, 1996 at paragraph 13 that the additional amount of claim was never sanctioned/approved by the competent authority and such plea was referable to clause 11 of the contract. The learned counsel has submitted that the learned court below has set aside the award by referring to clause-11 (proviso) of the contract and has rightly held that the learned Arbitrator has travelled beyond his jurisdiction. He has relied upon the judgment passed by the Hon'ble Supreme Court reported in 2022 Live Law (SC) 121, paragraph 40 and 44, to submit that an arbitral tribunal being a creature of contract is bound to act in terms of the contract under which it is constituted and award can be said to be patently illegal where the arbitral tribunal has failed to Act in terms of the contract or has ignored the specific terms of a contract.

14. The learned counsel has further submitted that it is a case where the learned Arbitrator has ignored the specific terms of the contract i.e clause 11 of the agreement. He has also relied upon the judgment reported in (2014) 9 SCC 246 to submit that the said case was relating to excepted matter and it was held that the learned Arbitrator, while deciding the claim specifically excluded from arbitration by the agreement, cannot give an award on such count.

15. Arguments concluded.

16. Post this case for dictation of judgment in open court on 12.05.2023.

(Anubha Rawat Choudhary, J.) Binit

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter