Citation : 2023 Latest Caselaw 787 Jhar
Judgement Date : 17 February, 2023
IN THE HIGH COURT OF JHARKHAND AT RANCHI
C. M. P. No. 958 of 2022
-----
Prem Kumar ... .... Petitioner Versus Steel Authority of India Limited/Bokaro Steel Plant represented by its Chief Executive Officer & Anr. ... .... Opp. Parties
-----
CORAM: HON'BLE MR. JUSTICE GAUTAM KUMAR CHOUDHARY
-----
For the Petitioner : M/s Rahul Kr. Gupta & Rahul Lamba, Advocates For the Opp. Parties : M/s Shresth Gautam & Abhijeet Tushar, Advocates
-----
Oral Order 04 / Dated : 17.02.2023
1. The instant petition has been filed for an appropriate order in the nature of Certiorari for quashing the order dated 7.11.2022 in Original Suit No.48 of 2016 whereby the petition for adducing evidence under O 18 R 17 r/w Section 151 of the CPC has been rejected.
2. The petitioner had earlier filed Money Suit No.45/83 which was decreed in his favour vide order dated 9.4.1992 and the respondent was directed to refund the advance amount of Rs. 2,03,822.50 with interest @ 12%, pursuant to it the amount was refunded, but as per the petitioner the security amount was still lying with the Respondent .
3. The petitioner find another Original Suit No. 48 of 2016 for specific performance of contract in which the learned Court below allowed amendment petition vide order dated 30.8.22 which are as under "34A. That without prejudice to the above and also to the prayer of the Plaintiff seeking specific performance of the contract for delivery to the Plaintiff of 495.450 MT of the concerned materials, being the used and old conveyor belts, at the contracted rate of Rs. 6650 per MT plus sales tax, the Plaintiff humbly submits that if the Defendants would have performed its contractual obligation of delivery the 495.450 MT of the concerned material, which is old and used conveyor belts, at the contracted price of Rs.6650 per MT plus sales tax, then the Plaintiff would have sold the said material in the market to third parties and the Plaintiff would have made profit being the amount of market price of such material reduced by the purchase price of the Plaintiff from the Defendant. However, as the Defendants have failed to deliver the said materials to the Plaintiff, the Plaintiff has suffered the direct loss of said profit which the Plaintiff shall have made by selling the said material to third parties.
34B. That it is humbly submitted that the Plaintiff had requested the Defendants vide its said letter dated 18.09.2015 to deliver 495.450 MT of the concerned materials, being the used and old conveyor belts, at the contracted rate of Rs. 6650 per MT plus sales tax. However, the Defendants did not deliver the said materials to the Plaintiff. The rate at which the Plaintiff could have sold the said materials to third parties during September 2015 to early 2016 is Rs.35,000 per MT. Accordingly, the Plaintiff would have made a profit of Rs.35000 - Rs. 6650 per MT which comes to Rs.28,350 per MT. The total profit which the Plaintiff would have earned is Rs.28350 per MT x 495.450 MT which comes to Rs. 1,40,46,007. Thus, the Plaintiff has suffered a clear loss of earning or profit of Rs.1,40,46,007 because of the non-performance of the contractual obligation of the Defendants to supply 495.450 MT of the concerned materials, being the used and old conveyor belts, at the contracted rate of Rs. 6650 per MT plus sales tax. The Plaintiff is entitled to be compensated by the Defendants for the said loss of Rs. 1,40,46,007. 34C. That in additional to the above, it is humbly submitted that the Plaintiff was waiting for almost 36 years since 06.08.1980 to take delivery of 495.450 MT of the concerned materials, being the used and old conveyor belts, from the Defendant. The Plaintiff because of the non-delivery by the Defendants, could not sell the said materials to the buyers or customers of the Plaintiffs. The plaintiff because of this non-delivery to his customers suffered loss of reputation, good will and mental harassment. The said long wait of 36 years has caused huge loss to the Plaintiff. The Plaintiff has wasted valuable period of 36 years only because of the non- performance of the contractual obligation by the Respondents. The plaintiff is entitled to a compensation of Rs.20,00,000 for the loss of reputation, goodwill and mental harassment.
34D. That the Defendants, since 28.01.1980, on one side are enjoying the security deposit amount of Rs.50,000 given by the Plaintiff and on the other side the Defendants are not performing their contract obligations of delivering the said materials to the Plaintiff. The defendants cannot partly rely on the contract which favours them and not perform the other part of the contract where they have contractual obligations. Therefore, by way of compensation, the Plaintiff is also entitled to payment by the Respondent of interest @ 18% per annum compounded annually on the said amount of Rs.50,000 since 28.01.1980 along with the principle amount of Rs. 50,000 till the date of actual payment to the Plaintiff."
4. Corresponding amendments in relief portion was also allowed.
5. After the amendment, the plaintiff moved the court below under Section 18 Rule 17 read with Section 151 CPC in the original suit seeking to recall the plaintiff witness no. 1 Naresh Prasad Lodha. The petition has been rejected by the court below for the reason that the petition was filed at a belated stage of argument as the case has been recalled earlier for judgment after the amendment petition was filed.
6. It is submitted by learned counsel for the petitioner that after having permitted the amendment in the plaint, it was necessary for the ends of justice to prove certain documents in reference to the amended pleadings. Reliance has been placed on (2011) 11 SCC 275 wherein it has been held that the matter for consideration is whether the evidence sought to be produced either assist in clarifying the evidence led on the issue or led to effective adjudication. Learned counsel for the respondent-SAIL has raised no objection provided the respondent is also given opportunity for rebuttal of evidence.
7. Object of Order XVIII Rule 17 C.P.C. is to permit a party to adduce into evidence by recalling any witness to ensure that all relevant and best materials are allowed to be brought on record, which could effectively, conclusively help in finally adjudicating the dispute between the parties. Here, in the present case a substantial amendment has been allowed by the learned Court below by which pleadings for damages have been incorporate in the suit. A pleading without evidence is of no avail. Therefore, the prayer of the petitioner to recall P.W.2, is allowed to prove the relevant documents within one month from the date of receipt of order by the Court below subject to the payment of cost Rs.5,000/-.
The O.P. No.2 will also have opportunity to adduce evidence in rebuttal. Instant Civil Miscellaneous Petition is allowed.
(Gautam Kumar Choudhary, J.) AKT
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!