Citation : 2022 Latest Caselaw 2202 Jhar
Judgement Date : 23 June, 2022
1
IN THE HIGH COURT OF JHARKHAND AT RANCHI
Arbitration Application No.08 of 2020
Modi Projects Limited, a Company registered under the provisions of
the Indian Companies Act, 1956, having its registered office at 3rd
Floor, Shivani Apartment, 23-Lansdown Terrace, Koltata, P.O. and
P.s.-Kolkata, District-Kolkata 700026 and having its Corporate office at
Kanke Road, Ranchi-834008, Jharkhand through one of its Directors
Pradip Modi, Aged about-63 years, son of Late Sita Ram Modi,
Resident of -9/1, Basant Vihar, Kanke Road, P.O. & P.S. Gonda,
District-Ranchi. ......... Petitioner
1. East Central Railway through its General Manager, having its office
at Diggikalam Hajipur P.O. P.S. & Dist Hajipur Bihar 844101
2. The Chief Administrative Officer (con), East Central Railway,
Mahendru Ghat P.O. P.S. Mahendru Ghat Dist Patna Bihar-800004
3. The Chief Engineer (con)/(South), East Central Railway, Mahendru
Ghat P.O. P.S. Mahendru Ghat Dist Patna Bihar-800004
4. Dy. Chief Engineer (con), East Central Railway, Barkakana P.O. P.S.
Barkakana Dist Ramgarh-829102 ......... Respondents
CORAM : HON'BLE MR. JUSTICE SUJIT NARAYAN PRASAD
---------
For the Petitioner : Mr. Shresth Gautam, Advocate : Mr. Rajarshi Singh, Advocate : Mr. Abhijeet Tushar, Advocate For the Resp.-Railway : Mr. Prashant Pallav, A.S.G.I.
---
13/23.06.2022 The instant application has been filed invoking the
jurisdiction conferred under Section 11(6) of the Arbitration and
Conciliation Act, 1996, (hereinafter referred to as the 'Act'), 1996
for appointment of Arbitrator, in view of the Arbitration Clause
as contained under Clause 64 (1) (i) of the Contract.
2. The brief facts of the case, as per the pleading made in the
application, required to be enumerated, are as hereunder:-
It is the case of the petitioner/applicant that in terms of the
notice inviting tender bearing Tender Notice No.05 of 2013-14
(Open)/South and Tender No.22 of 2013-14 (Open)/South, which
has been issued for the Construction of Syphon Bridges at Km
195.715 and Km 196.610, provision of catch water drain from Km
179.500 to Km 199.47 and other associated drainage/water
crossing works in Barkakana-Ranchi section in connection with
Koderma-Ranchi new BG Rail line Project.
The petitioner/applicant being an eligible tenderer applied
for the same and after due process of law, the work order for the
aforesaid construction work was awarded to the petitioner, vide
letter dated 27.09.2013. An agreement was executed between the
petitioner and the respondents for the aforesaid Construction of
Syphon Bridges at Km 195.715 and Km 196.610, provision of
catch water drain from Km 179.500 to Km 199.47 and other
associated drainage/water crossing works in Barkakana-Ranchi
section in connection with Koderma-Ranchi new BG Rail line
Project, which is having Arbitration Clause as under Clause 64 (1)
(i), in view of the applicability of the General Conditions of
Contract, 2008.
The further fact of the case is that as per the contract, the
time of completion of work was 6 months, i.e., 26.03.2014 and
value of work was Rs.5,77,39,523/30. The petitioner/applicant
immediately upon issuance of work order and execution of the
agreement, invested and mobilized men and machines at the
worksite for commencement of the work.
The petitioner/applicant has submitted a bank guarantee,
as per the condition stipulated in the agreement within the
stipulated period.
The further fact of the case is that in terms of the agreement,
the respondents were required to provide approved drawings of
two Syphon bridges immediately after the issuance of LoA which
was to be used for undertaking the construction of work but
according to the petitioner/applicant, even after lapse of time
given for completion of work, the approved drawings were not
provided even after repeated requests.
It is the grievance of the petitioner/applicant that it is due
to the non-performance of the condition of the agreement by not
providing encumbrance free site, details of drainage/water
crossing works, within the time schedule and as such, the work
could not have been commenced. However, extension was
granted to the petitioner and by that time, only 10-12 per cent of
the total contract value of the work could have been completed.
But no payments were being made for execution of work which
caused financial hindrance to the petitioner/applicant in
completion of the work, which fact has been brought to the notice
of the concerned authority and it was agreed to fore-close the
contract and to that effect, a request was made by the petitioner
vide letter dated 07.09.2017 also requesting therein to arrange
release of performance bank guarantee as also for making
payments of the final bill at an early date. The respondents have
not given any heed to such request in spite of the repeated
request made in this regard and as such, a notice under Clause 63
of the General Condition of Contract, 2008 of the agreement, has
been given for justified action on the part of the respondent.
The final account including claims in the matter of
Construction of Syphon Bridges at Km 195.715 and Km 196.610,
provision of catch water drain from Km 179.500 to Km 199.47 and
other associated drainage/water crossing works in Barkakana-
Ranchi section in connection with Koderma-Ranchi new BG Rail
line Project was submitted by the petitioner but the same has also
not been considered.
3. Finally, the petitioner/applicant when after the dispute
having not been settled, has made a request vide letter dated
16.11.2019 by invoking the condition stipulated under Clause 64
of the General Condition of Contract, for appointment of
Arbitrator, so that, the dispute may be resolved. But, no action
has been taken on behalf of the respondents, therefore, the instant
application has been filed praying therein for appointment of sole
Arbitrator. Thereafter, a notice was issued to the concerned
respondent, in pursuant thereto, appearance has been made on
behalf of the Railway, who on earlier occasion, was represented
by Mr. Jalisur Rahman, who has taken the plea of applicability of
the General Condition of Contract, 2016, which contains a
provision of appointment of Arbitrator who has been named in
the GCC, 2016.
4. Mr. Rahman, learned counsel appearing for the Railway
has relied upon the judgment rendered by the Hon'ble Apex
Court in the case of Central Organization for Railway
Electrification Vrs. ECI-SPIC-SMO-MCML (JV) a Joint Venture
Company, reported in (2020) 14 SCC 712, wherein, the Hon'ble
Apex Court has considered the applicability of the General
Condition of Contract which contains a Clause as under Clause
64 (3) (b) and has laid down that after issuance of notification
dated 16.11.2016 by the Railway Board modifying the Clause 64
of the General Condition of Contract, by which, the Arbitral
Tribunal shall consist of sole Arbitrator who shall be a Gazetted
Officer of the Railway not below the JA Grade nominated by the
General Manager and as such, submission has been made that
after modification of the General Condition of Contract by way of
the notification dated 16.11.2016, there is no question of
application of General Condition of Contract which contains a
provision of Arbitration Clause as under Clause 64 (2) (a),
wherein, it has been stipulated for appointment of independent
sole Arbitrator and hence, it was submitted that the instant
application is fit to be dismissed on the aforesaid ground alone.
5. In response to the same, Mr. Shresth Gautam, learned
counsel appearing for the petitioner/applicant has submitted that
even accepting the General Condition of Contract was modified
by virtue of notification dated 16.11.2016, the same cannot be a
ground for rejection of the instant application, reason being that
the contract or the work in question was executed at the time of
existence of the General Condition of Contract, 2008.
It has further been submitted that the General Condition of
Contract which was notified on 16.11.2016 cannot have its
retrospective application for deciding the issue of appointment of
Arbitrator giving go-by to the condition stipulated in the General
Condition of Contract, 2008, the period under which the
agreement has been executed.
6. It requires to refer herein that due to change in the panel of
the Railway, Mr. Prashant Pallav, learned Assistant Solicitor
General of India, has taken over the case and has argued the case
at length.
7. Mr. Pallav, learned A.S.G.I., in response to the submission
made on behalf of the learned counsel for the
petitioner/applicant about retrospective application of the
modified General Condition of Contract, notified on 16.11.2016
and what will be its effect in the contract executed during the
period of existence of the General Condition of Contract, 2008
and has submitted at bar that there is no question of retrospective
application of the modified General Condition of Contract which
has been notified on 16.11.2016, subsequent to the date of
execution of agreement in question, which admittedly has been
issued in course of subsistence period of the General Condition of
Contract, 2008.
8. This Court has heard the learned counsel for the parties.
9. The bone of contention on the objection which earlier was
made about the applicability of the General Condition of
Contract modified on 16.11.2016, which contains a Clause for
appointment of Arbitrator, who will be a Gazetted Officer of the
Railway not below the rank of JA grade nominated by the
General Manager.
10. The issue was raised that once the General Condition of
Contract, notified on 16.11.2016, has came into existence, the
effect of the General Condition of Contract, 2008, the period
under which, the contract has been entered into, will lose its
force.
11. The position of law is well settled that if the parties have
entered into a contract, in pursuant to the condition of contract,
the condition stipulated under the said contract will only be
applicable having not been affected by the subsequent
modification in the condition of contract, otherwise, the
imposition of the modified condition in the already existing
contract will prejudice the interest of the party and it will be said
to be unilateral insertion of an agreement due to the substitution
of the condition of the earlier contract.
12. It is not in dispute that when the party entered into a
contract, the same binds both the parties if the contract is bilateral
and there cannot be any change in the condition of contract
unilaterally.
Herein, the proposition which has been put-forth on earlier
occasion on behalf of the counsel appearing for the respondent
Railway that the moment the General Condition of Contract
which has been notified on 16.11.2016 has came into being, the
condition contained in the earlier General Condition of Contract,
2008 will ipso-facto lose its force, but, this Court is not in
agreement with such proposition, for the reason that, if such
proposition will be accepted then the Clause which was already
existed on the date of contract entered in between the parties, will
be allowed to be substituted without any knowledge on the part
of the said party who is going to be adversely affected.
13. However, Mr. Pallav, learned A.S.G.I., has submitted that
there cannot be a retrospective applicability of the General
Condition of Contract by deeming the condition already existing
in the earlier contract to be redundant.
14. This Court, on appreciation of the aforesaid submission is
of the view that sole dispute about the applicability of the
subsequent General Condition of Contract notified on 16.11.2016
will not be applicable in the facts of the given case, rather the
General Condition of Contract, 2008 will have its implication and
as such, the Arbitration Clause is to be considered on the basis of
the Arbitration Clause existing in the General Condition of
Contract, 2008.
For ready reference, Clause 64(1) of the General Condition
of Contract, 2008 reads as under:-
"64 (1) (i)-Demand for Arbitration In the event of any dispute or difference between the parties hereto as to the construction or operation of this contract, or the respective rights and liabilities of the parties on any matter in question, dispute or difference on any account or
as to the withholding by the Railway of any certificate to which the contractor may claim to be entitled to, or if the Railway fails to make a decision within 120 days, then and in any such case, but except in any of the "excepted matters" referred to in Clause 63 of these conditions, the contractor, after 120 days but within 180 days of his presenting his final claim on disputed matters shall demand in writing that the dispute or difference be referred to arbitration.
64 (1) (ii)-The demand for arbitration shall specify the matters which are in question, or subject of the dispute or difference as also the amount of claim item wise. Only such dispute(s) or difference(s) in respect of which the demand has been made, together with counter claims or set off, given by the Railway, shall be referred to arbitration and other matters shall not be included in the reference. 64 (1) (ii)-(a) The Arbitration proceedings shall be assumed to have commenced from the day, a written and valid demand for arbitration is received by the Railway.
(b) The claimant shall submit his claim stating the facts supporting the claims along with all the relevant documents and the relief or remedy sought against each claim within a period of 30 days from the date of appointment of the Arbitral Tribunal.
(c) The Railway shall submit its defence statement and counter claim(s), if any, within a period of 60 days of receipt of copy of claims from Tribunal thereafter, unless otherwise extension has been granted by Tribunal.
(d) The place of arbitration would be within the geographical limits of the Division of the Railway where the cause of action arose or the Headquarters of the concerned Railway or any other place with the written consent of both the parties.
64 (1) (iii)- No new claim shall be added during proceedings by either party. However, a party may amend or supplement the original claim or defence thereof during the course of arbitration proceedings subject to acceptance by Tribunal having due regard to the delay in making it. 64 (1) (iv)-If the contractor(s) does/do not prefer his/their specific and final claims in writing within a period of 90 days of receiving the intimation from the Railways that the final bill is ready for payment, he/they will be deemed to have waived his/their claim(s) and the Railway shall be discharged and released of all liabilities under the contract in respect of these claims."
For ready reference, Clause-64(3) of the General Condition
of Contract, 2014 as notified vide notification dated 16.11.2016
reads as under:-
"64. (3) Appointment of arbitrator:
* * * * *
64. (3)(a)(ii) In case not covered by Clause 64(3)(a)(i), the Arbitral Tribunal shall consist of a panel of three gazette railway officers not below JA Grade or two railway gazette officers not below JA Grade and a retired railway officer, retired not below the rank of SAG officer, as the arbitrators. For this purpose, the Railways will send a panel of at least four (4) names of gazette railway officers of one or more departments of the Railways which may also include the name(s) of retired railway officer(s) empanelled to work as railway arbitrator to the contractor within 60 days from the day when a written and valid demand for arbitration is received by the GM........"
15. Learned counsel for the respondents has not raised any
other point in opposition.
16. This Court, in consequence of the aforesaid finding is of the
view that the instant application is fit to be allowed, accordingly,
the instant application stands allowed.
17. Learned counsel for the parties have suggested the name of
Hon'ble Mr. Justice (Retd.) Pramath Patnaik, Former Judge of this
Court, to act as Sole Arbitrator and as such, the same is being
accepted.
18. Considering the aforesaid suggestion, this Court, therefore,
appoints Hon'ble Mr. Justice (Retd.) Pramath Patnaik, Former
Judge of this Court, presently residing at Plot No.11-2D/780/52,
CDA Sector-11 (Near Hanuman Temple) Cuttack, Odisha-753014,
[email protected], to act as sole Arbitrator for
resolution of dispute between the parties.
19. The proposed Arbitrator is required to submit a
declaration in terms of Section 12 of Arbitration and Conciliation
Act, 1996.
20. Learned Arbitrator would be free to lay down fees and
other expenses towards conduct of the arbitration proceedings,
however, keeping into account the ceiling prescribed under
Schedule IV of the Act of 1996 as amended.
21. Learned Arbitrator would endeavour to conclude the
proceedings preferably within the period of six months, also
taking into regard the mandate of the Legislature under Section
29-A of the Act of 1996.
22. Let photocopy of the entire pleadings along with copy of
the entire order sheet be sent to the learned Arbitrator by the
Registry.
23. Pending Interlocutory Application(s), if any, stands
disposed of.
(Sujit Narayan Prasad, J.)
A.F.R.-Rohit/-
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!