Wednesday, 20, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Sr.No. 09 vs Union Of India And Others
2026 Latest Caselaw 762 J&K

Citation : 2026 Latest Caselaw 762 J&K
Judgement Date : 13 February, 2026

[Cites 2, Cited by 0]

Jammu & Kashmir High Court

Sr.No. 09 vs Union Of India And Others on 13 February, 2026

                                                                     Sr.No. 09
                                                                              2026:JKLHC-JMU:344
       HIGH COURT OF JAMMU & KASHMIR AND LADAKH
                         AT JAMMU
 CJ Court
                 Case No. : Arb P No. 08/2026
                                                Date of Pronouncement : 13.02.2026
                                                          Uploaded on : 13.02.2026

 M/s V 6 Infrastructure Pvt. Ltd.                       ..... Appellant/Petitioner(s)

                              Through: Mr. Anil Mahajan, Advocate

                         Vs


 Union of India and others                                       ..... Respondent(s)

                              Through: Mr. Vishal Sharma, DSGI with
                                       Mr. Eishan Dadhichi, CGSC and
                                       Mr. Suman Sudan, Advocate

 Coram:           HON'BLE THE CHIEF JUSTICE
                                         ORDER
 (ORAL)

1. The present petition has been filed under Section 11(6) of the Arbitration and Conciliation Act, 1996, seeking appointment of an arbitrator.

2. The petitioner is a Private Limited Company, registered under the provisions of the Companies Act, participated in the tendering process initiated by the respondents for "construction of AF School Building at AF Station, Jammu" and having been declared to be the successful bidder was allotted the contract for an amount of Rs.10,87,40,530/- vide CA No. CEAFU-20/2018-19 issued by the respondents. Accordingly, a Contract Agreement was executed, wherein the date of commencement of the work was fixed as 04.02.2018 with extended date of completion as 30.06.2022. The petitioner, accordingly, executed the work and completed the same on 30.06.2022. However, the respondents failed to release the payment for work already executed.

3. It is contended that the agreement entered into between the parties contains an Arbitration Clause which provides that during the subsistence of the contract, the parties shall approach the Dispute Resolution Board (DRB) for redressal of the disputes, if any, within three months from the date either party gives the notice. Therefore, in terms of the said Clause, the petitioner, vide letter dated 17.11.2025, called upon the Chairman Chief Engineer, Northern Command

2026:JKLHC-JMU:344

C/O 56 APO stating that since the disputes have arisen between the parties, as such, the same be resolved through Dispute Resolution Board. In response to the said letter, the Chairman Engineer, vide letter dated 13.01.2026, communicated to the petitioner that it is not possible for the HQ to constitute the DRB.

4. It is urged that since the respondents failed to accede to the request of the petitioner and also having failed to release the payment in favour of the petitioner, the petitioner was constrained to invoke arbitration Clause 70 of IAWF 2249 General Conditions of the Contract, seeking appointment of an arbitrator for dispute resolution vide letter dated 06.04.2024. It is further urged that respondent- department vide letter dated 08.11.2024 asked the petitioner to forward a signed copy of the agreement for appointment of an arbitrator which was, accordingly, forwarded but till filing of the present petition, the respondents have failed to appoint an arbitrator. And, therefore, the petitioner has been left with no choice but to seek indulgence of this Court under Section 11 (6) of the Arbitration and Conciliation Act, through the medium of petition at hand seeking appointment of an independent arbitrator.

5. It is urged that since the respondent-department has failed to release the payment despite notice dated 06.04.2024 and neither agreed for settlement of the disputes through arbitration nor directed appointment of an arbitrator. Hence, the petition at hand.

6. Heard. Notice.

7. Served with advance copy of the petition, Mr. Eishan Dadhichi, CGSC, present in Court, accepts notice.

8. The existence of the arbitration clause, as aforesaid, and its invocation by the petitioner vide notice dated 06.04.2024 is not disputed.

9. Thus, having argued the matter at some length and in the given circumstances, learned counsel for the respondents, as always, fairly submits that let an arbitrator be appointed. But since the claim that is sought to be made by the petitioner is vehemently disputed/denied, it is submitted that respondents be granted liberty to raise all possible pleas/objections before the arbitral tribunal/ arbitrator in this regard.

10. In the given facts and circumstances, coupled with statement made at the Bar by learned counsel for the respondents, the petition is allowed. Accordingly, with the consent of learned counsel for the parties,

2026:JKLHC-JMU:344

Mr. Arvind Kumar Arora, DG, Pers, MES, is appointed as the sole arbitrator. Who shall proceed with the matter in accordance with the provisions of the Act. And to make an award within the time provided in the Act itself after charging the prescribed fee along with incidental expenses to be shared by the parties.

11. Registry to send a copy of this order to the learned arbitrator.

12. Disposed of.

                           (                                       (ARUN PALLI)
                                                                  CHIEF JUSTICE
 Jammu :
 13.02.2026
 Pawan Chopra/Secy





 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter