Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Ut Of J & K vs Nishat Ahmed
2024 Latest Caselaw 2233 j&K

Citation : 2024 Latest Caselaw 2233 j&K
Judgement Date : 28 October, 2024

Jammu & Kashmir High Court

Ut Of J & K vs Nishat Ahmed on 28 October, 2024

                                                                    Sr. No. 18

       HIGH COURT OF JAMMU & KASHMIR AND LADAKH
                       AT JAMMU

LPA No. 84/2022 in
WP (C) No. 830/2021

1.   UT of J & K                                   .....Appellant(s)/Petitioner(s)
     through its Commissioner/Secretary,
     Public Works Department (R&B),
     Civil Secretariat, Jammu.

2.   The District Development Commissioner,
     Kishtwar.

3.   The Chief Engineer, PMGSY (JKRRDA)
     J & K JKPCC Building, 4th Floor,
     Panama Chowk, Jammu.

4.   The Additional District Development
     Commissioner, (Chairman SOP/SDRF),
     Kishtwar.

5.   The Superintendent Engineer (PMGSY),
     Circle-Batote.

6.   The Executive Engineer (PMGSY),
     PWD (R&B), Kishtwar.

                             Through :- Mr. Ravinder Gupta, AAG
                      v/s
     Nishat Ahmed, Age 40 years,                              .....Respondent(s)
     S/o Mohd. Sikander,
     R/o Village Hullar Lachdayaram-A,
     Tehsil & District Kishtwar.

                             Through :- Mr. Irfaan Khan, Advocate

CORAM: HON'BLE MR. JUSTICE ATUL SREEDHARAN, JUDGE
       HON'BLE MR. JUSTICE MOHD. YOUSUF WANI, JUDGE
                            ORDER (ORAL)

28.10.2024 (Atul Sreedharan-J)

1. The present appeal has been filed by the UT which is aggrieved by

the order dated 02.06.2022 passed by the learned Single Judge in

WP (C) No. 830/2021 titled Nishat Ahmed vs. UT of J & K &

Ors.

2. The brief facts of the case are as follows:

3. The writ petition was filed seeking a direction to the respondents

(hereinafter, to be referred to, as the 'appellants') to release the

payment amounting to Rs. 24.85 Lacs in favour of the petitioner

(hereinafter, to be referred to, as the 'respondent') for executing

the restoration works i.e. (a) Dunadi Bunjwah Road from Kewa Pul

to Kither, (b) Shalimar to Trigam and (c) K K Road Km 6 th to

Shana. These works were assigned to the respondent for execution

by the District Administration. The respondent completed the work

in the year 2016 and then again in the year 2018. The restoration

works were executed from time to time by the respondent as and

when the roads were damaged, the respondent was assigned the task

and he completed the same without any delay in order to ensure

safe transportation on those roads and the appellants assured the

respondent that the payments would be released in his favour.

Thereafter, there were various communications addressed by

different departments of the appellants seeking the release of Rs.

24.85 Lacs so that the same can be paid to the respondent.

4. As the payment was not released despite various communications

with the various departments of UT, the respondent made

representations to the appellant no. 4 for clearing his liability and in

response to the said representations, the appellant no. 4 requested

appellant no. 5 to arrange funds to the tune of Rs. 24.85 Lacs.

5. We shall refer to these communications in a greater detail in the

course of this order.

6. Notwithstanding the various communications, the amount was not

released in favour of the respondent on account of which a legal

notice was served upon the appellants by the respondent dated

10.02.2021 seeking release of the admitted liability along with

interest.

7. The case of the respondent before the learned Single Judge as

petitioner was that despite the admitted liability of Rs. 24.85 Lacs

towards him, the appellants did not release the amount in his favour

till the date of filing of the writ petition and even thereafter.

8. In paragraph No. 7 of the impugned order, the learned Single Judge

records the objections filed by the respondents (appellants herein)

in the following words "Objections on behalf of respondent nos. 1,

3, 4, 5 and 6 have been filed in which it has been stated that there is

no work order, technical sanction, administrative approval,

allotment order, work register, measurement book and geo tagged

photographs at three stages and further that due to non-availability

of funds, the claim of the petitioner is disputed one. It is also stated

that no tender was floated. It is further stated that the claim of the

petitioner is hopelessly time barred and the petitioner has a remedy

to file a civil suit."

9. Learned counsel for the appellants has argued that the impugned

order passed by the learned Single Judge is liable to be set aside on

two counts. Firstly, it is argued with great vehemence that a writ

petition could not have been filed and it ought to have been a civil

suit which had to be filed by the respondent to recover the amount

of Rs. 24.85 Lacs. The second argument put forth by the learned

counsel for the appellants is that the writ petition was hopelessly

time barred and was hit by laches as even applying the standard of

limitation for a civil suit, the writ petition was filed beyond the

period of three years from the date on which the cause of action

arose.

10. Learned counsel for the respondent has clarified that the cause of

action arose in favour of the respondent and against the appellants

for the first time in the year 2016 and thereafter, for the last time in

the year 2018 when he completed/repeated works.

11. According to learned counsel for the appellants that assuming 2018

to be the commencement of the cause of action to file a civil suit for

the alleged nonpayment of dues, the same came to an end in the

year 2021. It is pertinent to mention here that this writ petition has

been filed in the year 2021.

12. Learned counsel for the appellants has also referred to certain

judgments of the Delhi High Court in case titled M/s. Tirupati

Cement Products Vs. Delhi Jal Board & Ors. reported in 2020(4)

AD(Delhi) 302. This was a case where the Delhi High Court (which

has original jurisdiction) dismissed a civil suit on the ground of

limitation as the same had been filed beyond three years. With an

aid of this judgment and connecting it with the judgment of this

Court in case titled State of J & K & Ors. Vs. Constable Sanjeet

Kumar reported in 2012(IV) SLJ 1005 (HC), wherein at

Paragraph 10, this Court had referred and relied upon the judgment

passed by the Constitution Bench of the Supreme Court in State of

Madhya Pradesh & Anr. Vs. Bhailal Bhai reported in AIR 1964

SC 1006, wherein the Supreme Court held authoritatively that the

maximum period fixed for filing a suit before a Civil Court must

also be read as a „reasonable period' for filing the writ petition.

13. In that case, the Supreme Court held that the court may consider the

delay unreasonable, in a case to be assessed on the grounds of

laches, where the delay is unreasonable, even if it is less than

prescribed period of limitation for a civil action. The exposition of

law by the Supreme Court in this judgment passed by the

Constitution Bench is certainly not an indelible proposition of law

but must be applied in the facts and circumstances of a specific

case. The Supreme Court has held that where laches are to be

considered within a period less than the period mentioned under the

Limitation Act, the court may construe unreasonable delay based on

the conduct of the parties and the sum-totality of the circumstances

of that particular case. The contrary is also true. Where a party is

prevented from approaching the court on account of facts and

circumstances of a particular case which makes the delay

reasonable, in such a situation, laches can be condoned. Even

otherwise, there is a clear and unambiguous distinction between

limitation and laches. Limitation is a creature of statute and

therefore has to be strictly applied. Laches is a doctrine of equity

and while applying the same, what must weigh in the mind of the

court is that whether, the application of the same goes to advance

the cause of justice or put the adverse party to unreasonable

hardships.

14. Therefore, even it is assumed that the cause of action arose only

from 2016 and came to an end in the year 2019, even then, for

reasons to follow, that delay would be condonable. However, in the

specific facts and circumstances of this case, it has not been denied

that in 2016, the respondent carried out one set of work and he

again carried out works for the appellants in the year 2019. This

fact has not been denied.

15. Under the circumstances, the period of limitation would only expire

in the year 2021 which on the basis of facts also brings the petition

filed by the respondent before the learned Single Judge as not hit by

laches. As regards, the argument put forth by the learned counsel

for the appellants that civil suit was the appropriate remedy and in

the existence of the said alternate remedy, the writ petition could

not have been filed is also rejected as it is no longer res integra that

where the claim of the petitioner is undisputed by the respondents

and the same is an admitted liability, the petition is maintainable.

The other factor is that where no complicated question of fact is

involved and the liability can be verified from the pleadings itself,

the writ petition can be heard and sustained. Therefore, the second

argument is also rejected.

16. Learned counsel for the respondent on the other hand has argued

that the respondent has been made to run from pillar to post from

the year 2018. His admitted liability, despite his best efforts, has not

been paid by the appellants. In order to substantiate his argument,

he has drawn the attention of this Court to Page Nos. 48 to 53 of the

instant appeal which are letters issued by the office of the Executive

Engineer PMGSY Division Kishtwar and office of the Additional

District Development Commissioner (Chairman SOP/SDRF)

Kishtwar. Letters dated 07.03.2019, 10.10.2019 & 26.02.2020 have

been written by the office of the Executive Engineer PMGSY

Division Kishtwar to the office of the Additional District

Development Commissioner (Chairman SOP/SDRF) Kishtwar

requesting an expeditious release of Rs. 24.85 Lacs which has to be

paid to the respondent for repair of various roads which were

damaged due to torrential rains of March 2016, May 2016 and

February 2018, which were restored on "war footing" basis to allow

safe movement of vehicular traffic on these roads which was done

as per the direction of the District Administration and on account of

the pressure mounted by the general public and thereafter, requests

were made to the District Development Commissioner to release

Rs. 24.85 Lacs.

17. The three abovementioned letters once received by the office of the

District Development Commissioner, the District Development

Commissioner further addresses three letters to the Superintendent

Engineer PMGSY Circle Batote on 26.10.2019, 10.12.2019 &

14.03.2020 requesting the release of Rs. 24.85 Lacs for clearance of

the pending liability for restoration of the roads of the respondent. It

is even relevant to state that the letter dated 26.10.2019 has been

forwarded to the respondent herein/original petitioner. Likewise

also, the letters dated 10.12.2019 and 14.03.2020 also have been

marked to the respondent herein, by the office of the Additional

District Development Commissioner (Chairman SOP/SDRF)

Kishtwar. Thus, the period of limitation/laches, even if it is so, to be

applied strictly would commence from 14.03.2020 and end on

13.03.2023 and in this case, the original petition is filed on

19.04.2021, which is undisputed.

18. Under the circumstances, the arguments relating to laches is without

any substance and, therefore, rejected. This Court holds that the

respondent has been put to untold hardship from the year 2018

itself, where he has been compelled to run from pillar to post and

that, too, in vain for the release of his admitted dues.

19. The objections taken by the UT/appellants, as is reflected in

Paragraph 7 of the order passed by the learned Single Judge, is

grossly bureaucratic. While it is admitted that these works had to be

carried out on an emergency footing and also admitted that the

respondent herein/original petitioner, who has carried out these

works, it was callous indifference on the part of the UT to deprive

him of his rightful dues from 2018 till date.

20. Under the circumstances, this appeal is dismissed with exemplary

costs of Rs. 6.00 Lacs (Rs. 1.00 Lac for each year commencing

from 2018) to be paid by the appellants to the respondent, in

addition to the total admitted liability due to the respondent of Rs.

24.85 Lacs along with 6% interest imposed by the learned Single

Judge which was operative from the date of filing of the writ

petition.

21. However, it is made clear that if the dues of the respondent are not

paid to him within four weeks from the date of this order, the

respondent is entitled to file an application for contempt against the

appellants to enforce this order.

                                                  (Mohd. Yousuf Wani)                  (Atul Sreedharan)
                                                         Judge                               Judge
          JAMMU
          28.10.2024
          Manan



                                           Whether the order is speaking   :   Yes

                                           Whether the order is reportable :   No








 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter